ML101880020

From kanterella
Jump to navigation Jump to search

Electronic Transmission, Draft Request for Additional Information Regarding Measurement Uncertainty Recapture Power Uprate
ML101880020
Person / Time
Site: Limerick  Constellation icon.png
Issue date: 07/08/2010
From: Peter Bamford
Plant Licensing Branch 1
To: Chernoff H
Plant Licensing Branch 1
Bamford, Peter J., NRR/DORL 415-2833
References
TAC ME3589, TAC ME3590
Download: ML101880020 (4)


Text

July 8, 2010 MEMORANDUM TO: Harold K. Chernoff, Chief Plant Licensing Branch I-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation FROM: Peter Bamford, Project Manager /ra/

Plant Licensing Branch I-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation

SUBJECT:

LIMERICK GENERATING STATION, UNITS 1 AND 2 - ELECTRONIC TRANSMISSION, DRAFT REQUEST FOR ADDITIONAL INFORMATION REGARDING MEASUREMENT UNCERTAINTY RECAPTURE POWER UPRATE (TAC NOS. ME3589 AND ME3590)

The attached draft request for additional information (RAI) was transmitted by electronic transmission on June 30, 2010, to Mr. Kevin Borton, at Exelon Generation Company, LLC (Exelon). This draft RAI was transmitted to facilitate the technical review being conducted by the Nuclear Regulatory Commission (NRC) staff and to support a conference call (if needed) with Exelon in order to clarify the licensees submittal. The draft RAI is related to Exelons submittal dated March 25, 2010, regarding Limerick Generating Station, Units 1 and 2, Measurement Uncertainty Recapture Power Uprate. The draft questions were sent to ensure that they were understandable, the regulatory basis was clear, and to determine if the information was previously docketed. Additionally, review of the draft RAI would allow Exelon to evaluate and agree upon a schedule to respond to the RAI. This memorandum and the attachment do not represent an NRC staff position.

Docket Nos. 50-352 and 50-353

Enclosure:

As stated

July 8, 2010 MEMORANDUM TO: Harold K. Chernoff, Chief Plant Licensing Branch I-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation FROM: Peter Bamford, Project Manager /ra/

Plant Licensing Branch I-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation

SUBJECT:

LIMERICK GENERATING STATION, UNITS 1 AND 2 - ELECTRONIC TRANSMISSION, DRAFT REQUEST FOR ADDITIONAL INFORMATION REGARDING MEASUREMENT UNCERTAINTY RECAPTURE POWER UPRATE (TAC NOS. ME3589 AND ME3590)

The attached draft request for additional information (RAI) was transmitted by electronic transmission on July 6, 2010, to Mr. Kevin Borton, at Exelon Generation Company, LLC (Exelon). This draft RAI was transmitted to facilitate the technical review being conducted by the Nuclear Regulatory Commission (NRC) staff and to support a conference call (if needed) with Exelon in order to clarify the licensees submittal. The draft RAI is related to Exelons submittal dated March 25, 2010, regarding Limerick Generating Station, Units 1 and 2, Measurement Uncertainty Recapture Power Uprate. The draft questions were sent to ensure that they were understandable, the regulatory basis was clear, and to determine if the information was previously docketed. Additionally, review of the draft RAI would allow Exelon to evaluate and agree upon a schedule to respond to the RAI. This memorandum and the attachment do not represent an NRC staff position.

Docket Nos. 50-352 and 50-353

Enclosure:

As stated DISTRIBUTION:

Public RidsNrrPMLimerick LPL1-2 R/F Accession No.: ML101880020

  • via memo OFFICE LPL1-2/PM CVIB/BC NAME PBamford MMitchell*

DATE 7/8/10 07/02/2010 OFFICIAL RECORD COPY

DRAFT REQUEST FOR ADDITIONAL INFORMATION LIMERICK GENERATING STATION, UNITS 1 AND 2 MEASUREMENT UNCERTAINTY RECAPTURE POWER UPRATE REQUEST DOCKET NOS. 50-352 AND 50-353 By letter dated March 25, 2010 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML100850380), Exelon Generation Company, LLC (Exelon, the licensee) submitted a license amendment request (LAR) proposing to revise the operating license and technical specifications (TSs) for Limerick Generating Station (LGS), Units 1 and 2.

This LAR proposes to implement an increase of approximately 1.65% in rated thermal power from the currently licensed thermal power limit of 3458 megawatts thermal. The increase would be based on the improved thermal power measurement accuracy, which would be achieved through the utilization of the Cameron International (formerly Caldon) CheckPlusTM leading edge flowmeter (LEFM) ultrasonic flow measurement instrumentation. The application also proposes a modification to the standby liquid control system (SLCS). The Nuclear Regulatory Commission (NRC) staff has been reviewing the submittal and has determined that additional information is needed to complete its review.

1. The LAR, Attachment 6, Section 3.2.1, Fracture Toughness, requires additional information. Appendix G to 10 CFR Part 50, Fracture Toughness Requirements, states that reactor vessel (RV) beltline materials must maintain upper-shelf energy (USE) throughout the life of the RV of no less than 50 ft-lbs unless it is demonstrated in a manner approved by the Director, Office of Nuclear Reactor Regulation, that lower values of Charpy USE will provide margins of safety against fracture equivalent to those required by Appendix G of Section XI of the American Society of Mechanical Engineers (ASME) Code. The submittal states that the minimum USE for LGS, Unit 1 is 24 ft-lbs at 32 effective full power years (EFPY) for low pressure coolant injection (LPCI) nozzle forging Q2Q35W, and is 25 ft-lbs for LGS, Unit 2 at 32 EFPY for LPCI nozzle forging Q2Q33W, and therefore Equivalent Margin Analyses (EMAs) were performed for the limiting RV beltline plate, weld and nozzle forging materials. The licensee states that NEDO-32205-A, Rev. 1, 10 CFR 50 Appendix G Equivalent Margin Analysis for Low Upper Shelf Energy in BWR/2 through BWR/6 Vessels, was used with a bounding peak fluence of 1.9 x 1018 n/cm2 (E > 1.0 MeV) to evaluate the vessel against the requirements of 10 CFR Part 50, Appendix G. In NEDO-32205-A, Rev. 1, the materials addressed in the analysis included: SA302 Grade B and Grade B Modified low allow steel plate, SA533 Grade B Class 1 low alloy steel plate, Shielded Metal Arc Welds, Electroslag Welds, Submerged Arc Welds (SAW) made with non-Linde 80 flux, and SAW with Linde 80 flux. The nozzle materials were not included in the NEDO-32205-A, Rev. 1 analysis. Therefore, the staff does not find the application of NEDO-32205-A, Rev. 1 acceptable for demonstrating compliance with Appendix G to 10 CFR Part 50 for LGS, Units 1 and 2 nozzle materials. The methodology contained in NEDO-32205-A, Rev. 1, is applicable only to the materials Enclosure

DRAFT analyzed in the report. For all RV beltline materials with USE values below 50 ft-lbs at 32 EFPY, the licensee must submit analyses to demonstrate that the lower values of Charpy USE will provide margins of safety against fracture equivalent to those required by Appendix G of Section XI of the ASME Code.

2. The current thermal licensed power (CTLP) pressure-temperature (P-T) curves, contained in Pressure-Temperature Curves for PECO Energy Company Limerick 1 (GE-NE-B11-00836-00-01, Rev. 0), and Pressure-Temperature Curves for PECO Energy Company Limerick 2 (GE-NE-B11-00836-00-02, Rev. 0), did not include analysis of the water level instrumentation nozzles within the RV beltline region. Provide a technical basis to support the statement in Attachment 6, Section 3.2.1, Fracture Toughness, that the water level instrumentation nozzle that occurs within the RV beltline region is bounded by the CTLP P-T curves.
3. Initial property values for RV beltline materials are not consistent with the values previously submitted in response to Generic Letter 92-01, Rev. 1, Reactor Vessel Structural Integrity, and P-T curve submittals for LGS, Units 1 and 2 in GE-NE-B11-00836-00-01 and GE-NE-B11-00836-00-02, respectively. Provide a comprehensive listing of the RV beltline materials, including the heat number for each RV beltline plate or forging and the heat number of wire and flux lot number used to fabricate each RV beltline weld; the chemical composition, in particular the weight in percent of copper and nickel for each RV beltline material; and the unirradiated reference temperature for each RV beltline material, and the method of determining the unirradiated reference temperature from the Charpy and drop weight tests.