MONTHYEARRS-09-133, Attachment 6, LaSalle, Unit 2, Nuclear Power Station Spent Fuel Storage Pool Criticality Safety Analysis with Neutron Absorbing Inserts and Without Boraflex2009-08-31031 August 2009
[Table View]Attachment 6, LaSalle, Unit 2, Nuclear Power Station Spent Fuel Storage Pool Criticality Safety Analysis with Neutron Absorbing Inserts and Without Boraflex Project stage: Request ML0931705992009-12-0202 December 2009 Request for Withholding Information from Public Disclosure by Letter Dated 10/5/09 Project stage: Withholding Request Acceptance ML1009802092010-04-26026 April 2010 Request for Additional Information Related to License Amendment Request Regarding the Use of Neutron Absorbing Inserts in Unit 2 Spent Fuel Pool Storage Racks Project stage: RAI ML1011904862010-05-0303 May 2010 Notice of Meeting with Exelon, LaSalle, Units 1 and 2, to Discuss Response to Request for Additional Information License Amendment Request Regarding the Use of Neutron Absorbing Inserts in Spent Fuel Pool Storage Racks Project stage: RAI ML1016502292010-06-10010 June 2010 Additional Information Supporting License Amendment Request Regarding the Use of Neutron Absorbing Inserts in Unit 2 Spent Fuel Pool Storage Racks Project stage: Other ML1016502862010-06-23023 June 2010 June 1, 2010, Summary of Meeting with Exelon Generation Co., LLC, on Responses to Request for Information License Amendment Request for the Use of Netco-SNAP-In Rack Inserts Project stage: RAI ML1028003592010-10-0707 October 2010 Notice of Public Meeting with Exelon Generation Company, LLC, Regarding LaSalle Netco Insert Request Project stage: Meeting ML1030004242010-10-28028 October 2010 Notice of Meeting with Exelon Genertion Company to Discuss the License Amendment Request to Allow Full Recovery of Spent Fuel Storage Rack Cells That Are Unusable Due to Boraflex Neutron Absorber Degradation Project stage: Meeting ML1030704842010-11-19019 November 2010 Summary of Public Meeting with Exelon Generation Company, LLC Regarding LaSalle Netco Insert Request Project stage: Meeting ML1030903782010-11-19019 November 2010 Licensee Handouts for LaSalle Meeting with Exelon to Discuss Netco Inserts Project stage: Meeting ML1032104992010-11-19019 November 2010 Request for Additional Information, Related to the Use of Neutron Absorbing Inserts Project stage: RAI RS-10-202, Additional Information Supporting License Amendment Request Re Use of Neutron Absorbing Inserts in Unit 2 Spent Fuel Pool Storage Racks2010-11-23023 November 2010 Additional Information Supporting License Amendment Request Re Use of Neutron Absorbing Inserts in Unit 2 Spent Fuel Pool Storage Racks Project stage: Request ML1034304232010-12-10010 December 2010 Request for Additional Information Related to the Use of Nuetron Absorbing Inserts Project stage: RAI RS-10-210, Additional Information Supporting License Amendment Request Regarding the Use of Neutron Absorbing Inserts in Unit 2 Spent Fuel Pool Storage Racks2010-12-14014 December 2010 Additional Information Supporting License Amendment Request Regarding the Use of Neutron Absorbing Inserts in Unit 2 Spent Fuel Pool Storage Racks Project stage: Request ML1034904622010-12-16016 December 2010 Notice of Meeting with Exelon Generation Company, LLC Regarding LaSalle Netco Insert Request Project stage: Meeting RS-10-216, Additional Information Supporting License Amendment Request Regarding the Use of Neutron Absorbing Inserts in Unit 2 Spent Fuel Pool Storage Racks2010-12-22022 December 2010 Additional Information Supporting License Amendment Request Regarding the Use of Neutron Absorbing Inserts in Unit 2 Spent Fuel Pool Storage Racks Project stage: Request ML1100503592010-12-29029 December 2010 NRC Meeting Slides for December 29, 2010, Public Conference Call with Exelon Generation Company Regarding LaSalle Netco Insert Request Project stage: Meeting ML1101300742011-01-11011 January 2011 Additional Information Supporting License Amendment Request Regarding the Use of Neutron Absorbing Inserts in Unit 2 Spent Fuel Pool Storage Racks Project stage: Request ML1100502552011-01-17017 January 2011 December 29, 2010, Summary of Public Conference Call with Exelon Generation Company, LLC, Regarding LaSalle Netco Insert Request Project stage: Other ML1101803312011-01-24024 January 2011 Proposed License Conditions Related to Use of Neutron Absorbers Project stage: Other RS-11-009, Additional Information Supporting License Amendment Request Regarding the Use of Neutron Absorbing Inserts in Unit 2 Spent Fuel Pool Storage Racks2011-01-24024 January 2011 Additional Information Supporting License Amendment Request Regarding the Use of Neutron Absorbing Inserts in Unit 2 Spent Fuel Pool Storage Racks Project stage: Request ML1102500512011-01-28028 January 2011 Issuance of Amendments Concerning Spent Fuel Neutron Absorbers Project stage: Approval RS-11-014, Additional Information Supporting License Amendment Request Regarding the Use of Neutron Absorbing Inserts in Unit 2 Spent Fuel Pool Storage Racks2011-01-28028 January 2011 Additional Information Supporting License Amendment Request Regarding the Use of Neutron Absorbing Inserts in Unit 2 Spent Fuel Pool Storage Racks Project stage: Request ML1104606172011-03-0404 March 2011 Request for Additional Inforamtion Related to the Use of Neutron Absorbing Inserts Project stage: Other RS-11-067, Response to Request for Additional Information Regarding Unit 2 Spent Fuel Pool Storage Racks2011-04-18018 April 2011 Response to Request for Additional Information Regarding Unit 2 Spent Fuel Pool Storage Racks Project stage: Response to RAI RS-11-109, Completion of License Condition 2.C.(30) Associated with Unit 2 Spent Fuel Pool Storage Racks2011-07-13013 July 2011 Completion of License Condition 2.C.(30) Associated with Unit 2 Spent Fuel Pool Storage Racks Project stage: Other RS-11-170, Completion of License Condition 2.C.(31) Associated with Unit 2 Spent Fuel Pool Storage Racks2011-10-20020 October 2011 Completion of License Condition 2.C.(31) Associated with Unit 2 Spent Fuel Pool Storage Racks Project stage: Other 2010-04-26 |
ML110050359 | |
Person / Time | |
---|---|
Site: | LaSalle ![]() |
Issue date: | 12/29/2010 |
From: | Division of Operating Reactor Licensing |
To: | |
Brown Eva, NRR/DORL, 415-2315 | |
Shared Package | |
ML110050347 | List: |
References | |
TAC ME2376, TAC ME2377 | |
Download: ML110050359 (12) | |
Similar Documents at LaSalle | |
---|---|
Category:Meeting Briefing Package/Handouts
MONTHYEARML24029A1742024-01-30030 January 2024
[Table view]Constellation Pre-Application January 30, 2024, Meeting Slides - Proposed Alternative to Utilize Code Case N-932, Alternative Requirements for Acceptance of Containment Base Metal Corrosion or Erosion ML23317A0712023-11-14014 November 2023 NRC Pre-Submittal Meeting on November 14th, 2023 - TSTF-591 and Selected 50.69 License Condition Updates (EPID L-2023-LLM-0098) (Slides) ML23255A1042023-08-11011 August 2023 Slides - Constellation - Pre-Application EP 9/18/2023 Draft CEG Presubmittal SG Performance Monitoring Plan Meeting Handout ML22311A5112022-11-0707 November 2022 Pool Swell License - Amendment Request ML21314A4472021-11-10010 November 2021 Slides for Presubmittial Meeting for Proposed Alternative to Adopt ASME Code Case N-921 to Extend the Inservice Inspection Interval ML21194A1582021-07-13013 July 2021 and Lasalle Nuclear Generating Stations 2020 Annual Assessment Meeting Slides ML21141A0102021-05-21021 May 2021 La Salle County Station, Units 1 and 2, May 27, 2021 Pre Submission Public Meeting Slides (EPID-L-2021-LRM-0052) ML20261G7322020-09-16016 September 2020 Pre-Submittal Slides Extend 120-month Isi/Ist Interval Under 50.55a ML20238B8662020-08-25025 August 2020 Hq Online EOC Slides ML20178A4202020-06-30030 June 2020 NEI Slides for June 30, 2020, Public Meeting on COVID-19 Response ML20170B0212020-06-23023 June 2020 NRC Pre-Submittal Meeting Byron Unit 2 One-Time Deferral of Reactor Pressure Vessel Head Penetration Nozzle (Rpvhpn) Inspections ML20169A5592020-06-16016 June 2020 Steam Generator License Amendment Request Pre-Submittal Meeting (NRC) - Byron Unit 2 LAR for One-Time Deferral of Steam Generator Inspections (Rev 1) ML20163A6552020-06-16016 June 2020 6-16-20 Byron Unit 2 Steam Generator License Amendment Request Pre-Submittal Meeting (NRC) - Byron Unit 2 LAR for One-Time Deferral of Steam Generator Inspections ML19318F9512019-11-20020 November 2019 Presentation Slides for November 20, 2019, Pre-Application Meeting - Request for Revision to Quality Assurance Program Internal Audit Frequency ML19161A2572019-06-0404 June 2019 BWR Fleet Msv/Srv - Testing Frequency Relief Request NRC Pre-Application Meeting June 4, 2019 ML19151A6602019-05-31031 May 2019 BWR Fleet Mssv/Srv Testing Frequency Relief Request NRC Pre-Application Meeting June 4, 2019 ML19022A2002019-01-23023 January 2019 Request for Use of ASME Code Case N-879 for Exelon Nuclear Power Plants ML18347B3142018-12-19019 December 2018 Bwrvip/Asme Relief Request Discussion December 19, 2018 ML18334A2162018-11-30030 November 2018 Presentation Slides: Exelon BWR MSIV (Boiling-Water Reactor - Main Steam Isolation Valve) Leakage Optimization for NRC Pre-Submittal Meeting of December 6, 2018 ML18319A1272018-11-19019 November 2018 Slides for 11/19/18 Public Meeting - Exelon Fleet LAR for Common Language for TS 5.7 High Radiation Areas ML18054B3592018-02-27027 February 2018 Slide: NRC Pre-Submittal Meeting for Exelon Fleet LAR to Relocate TS Unit Staff Qualification ANSI Requirements to the QATR, February 27, 2018, Profile Info: Submitted by Frank Mascitelli ML17142A2382017-05-25025 May 2017 OEDO-17-00280 - Briefing Package for Drop-In Visit on June 9, 2017, by Senior Management of Exelon Generation Company, LLC with Chairman Svinicki, Commissioner Baran, and Commissioner Burns ML16194A0062016-07-12012 July 2016 Pre-Application Meeting Presentation Regarding LaSalle County Station License Amendment Request for Revision of Suppression Pool Swell Design Analysis ML16077A1562016-03-22022 March 2016 Fleet: Pre-application Teleconference with Exelon to Discuss a Potential License Amendment Request Regarding Operating Training Standards ML16077A3492016-03-17017 March 2016 NRC Briefing Slides for LaSalle Dseis Public Meeting March 22, 2016 ML16075A3292016-03-16016 March 2016 OEDO-16-00165 - Briefing Package for Drop-In Visit on March 23, 2016, by Senior Management of Exelon Generation Company, LLC with the NRC Executive Director for Operations ML15062A3642015-03-0303 March 2015 Environmental Scoping Briefing for March 10th Meetings ML15058A6322015-02-27027 February 2015 LSCS Scoping Briefing Prepared 2-27-15 for March 10th Meeting ML13212A3372013-07-31031 July 2013 NRC NEI-01-01 Meeting Presentation on 7/31/13 Digital I&C Meeting NEI 01-01, NRC NEI-01-01 Meeting Presentation on 7/31/13 Digital I&C Meeting2013-07-31031 July 2013 NRC NEI-01-01 Meeting Presentation on 7/31/13 Digital I&C Meeting ML13211A3782013-07-30030 July 2013 7/31/2013 NRC Public Meeting Presentation on NEI 01-01 NEI 01-01, 7/31/2013 NRC Public Meeting Presentation on NEI 01-012013-07-30030 July 2013 7/31/2013 NRC Public Meeting Presentation on NEI 01-01 ML13164A3792013-06-24024 June 2013 Summary of Public Meeting with Exelon Generation Company, LLC, Regarding the Proposed Extended Power Uprate License Amendment Request for LaSalle County Station, Units 1 and 2 ML12159A2662012-06-11011 June 2012 County Generating Station Pre-Application Meeting Extended Power Uprate: Replacement Steam Dryers. June 11, 2012 ML12130A0442012-06-0707 June 2012 Summary of Public Meeting with Exelon Generation Company, LLC, Regarding Proposed Extended Power Uprate License Amendment Request for LaSalle County Station, Units 1 and 2 ML1209306162012-04-0202 April 2012 Enclosure - 04/04/2012 Exelon Nuclear Meeting Presentation LaSalle Count Station Pre-Application Meeting Extended Power Uprate. ML1209006542012-03-30030 March 2012 Slides for April 4 Public Meeting on LaSalle Extended Power Uprate ML1208701402012-03-27027 March 2012 Licensee Slides for Exelon Fleet Pre-Submittal Public Meeting 4-10-12 Licensed Operator Eligibility Requirements LAR ML1208806542012-03-27027 March 2012 Non-Proprietary Slides for LaSalle Prnm Meeting ML1200303212012-01-19019 January 2012 12/7/2011 - Summary of Public Meeting with Exelon Regarding the Proposed Extended Power Uprate License Amendment Request for LaSalle, Units 1 and 2 ML13014A1002011-09-12012 September 2011 Sprinkler Clogging LaSalle Exelon - Presentation During September 2011 NEI Fire Protection Information Forum RS-11-096, Intent to Submit License Amendment Request to Install Power Range Neutron Monitor (Prnm) in Accordance with Interim Staff Guidance, Digital I & C-ISG-062011-06-0707 June 2011 Intent to Submit License Amendment Request to Install Power Range Neutron Monitor (Prnm) in Accordance with Interim Staff Guidance, Digital I & C-ISG-06 ML1100502552011-01-17017 January 2011 December 29, 2010, Summary of Public Conference Call with Exelon Generation Company, LLC, Regarding LaSalle Netco Insert Request ML1100503592010-12-29029 December 2010 NRC Meeting Slides for December 29, 2010, Public Conference Call with Exelon Generation Company Regarding LaSalle Netco Insert Request ML1030903782010-11-19019 November 2010 Licensee Handouts for LaSalle Meeting with Exelon to Discuss Netco Inserts ML1030704842010-11-19019 November 2010 Summary of Public Meeting with Exelon Generation Company, LLC Regarding LaSalle Netco Insert Request ML1032601422010-11-10010 November 2010 Handouts for November 10, 2010 Public Conference Call with Exelon Regarding LaSalle Insert Request ML0919803632009-08-20020 August 2009 Summary of Licensing Counterparts Meeting with Exelon Generation Company, to Discuss Licensing Practices and Processes ML0917502262009-07-0707 July 2009 Summary of Pre-Application Meeting with Exelon Generation Company, License Amendment Request for LaSalle and Limerick Measurement Uncertainty Recapture Power Uprates ML0911102662009-04-16016 April 2009 LaSalle Summary Meeting Slides 2024-01-30 Category:Slides and Viewgraphs MONTHYEARML24029A1742024-01-30030 January 2024
[Table view]Constellation Pre-Application January 30, 2024, Meeting Slides - Proposed Alternative to Utilize Code Case N-932, Alternative Requirements for Acceptance of Containment Base Metal Corrosion or Erosion ML23317A0712023-11-14014 November 2023 NRC Pre-Submittal Meeting on November 14th, 2023 - TSTF-591 and Selected 50.69 License Condition Updates (EPID L-2023-LLM-0098) (Slides) ML23255A1042023-08-11011 August 2023 Slides - Constellation - Pre-Application EP 9/18/2023 Draft CEG Presubmittal SG Performance Monitoring Plan Meeting Handout NEI 99-01, Slides - Constellation - Pre-Application EP 2/23/2023 Meeting Slides2023-02-21021 February 2023 Slides - Constellation - Pre-Application EP 2/23/2023 Meeting Slides ML22311A5112022-11-0707 November 2022 Pool Swell License - Amendment Request ML21314A4472021-11-10010 November 2021 Slides for Presubmittial Meeting for Proposed Alternative to Adopt ASME Code Case N-921 to Extend the Inservice Inspection Interval ML21194A1582021-07-13013 July 2021 and Lasalle Nuclear Generating Stations 2020 Annual Assessment Meeting Slides ML21162A3322021-06-11011 June 2021 BWR Fleet Relief Request Associated with RPV Instrument Nozzle Repairs ML21141A0102021-05-21021 May 2021 La Salle County Station, Units 1 and 2, May 27, 2021 Pre Submission Public Meeting Slides (EPID-L-2021-LRM-0052) ML20261G7322020-09-16016 September 2020 Pre-Submittal Slides Extend 120-month Isi/Ist Interval Under 50.55a ML20238B8662020-08-25025 August 2020 Hq Online EOC Slides ML20178A4202020-06-30030 June 2020 NEI Slides for June 30, 2020, Public Meeting on COVID-19 Response ML20170B0212020-06-23023 June 2020 NRC Pre-Submittal Meeting Byron Unit 2 One-Time Deferral of Reactor Pressure Vessel Head Penetration Nozzle (Rpvhpn) Inspections ML20163A6552020-06-16016 June 2020 6-16-20 Byron Unit 2 Steam Generator License Amendment Request Pre-Submittal Meeting (NRC) - Byron Unit 2 LAR for One-Time Deferral of Steam Generator Inspections ML20169A5592020-06-16016 June 2020 Steam Generator License Amendment Request Pre-Submittal Meeting (NRC) - Byron Unit 2 LAR for One-Time Deferral of Steam Generator Inspections (Rev 1) ML18347B3142018-12-19019 December 2018 Bwrvip/Asme Relief Request Discussion December 19, 2018 ML18334A2162018-11-30030 November 2018 Presentation Slides: Exelon BWR MSIV (Boiling-Water Reactor - Main Steam Isolation Valve) Leakage Optimization for NRC Pre-Submittal Meeting of December 6, 2018 ML18319A1272018-11-19019 November 2018 Slides for 11/19/18 Public Meeting - Exelon Fleet LAR for Common Language for TS 5.7 High Radiation Areas ML18054B3592018-02-27027 February 2018 Slide: NRC Pre-Submittal Meeting for Exelon Fleet LAR to Relocate TS Unit Staff Qualification ANSI Requirements to the QATR, February 27, 2018, Profile Info: Submitted by Frank Mascitelli ML17339A1812017-12-0707 December 2017 NRC Hq Pre-Submittal LaSalle CSCS LAR 12-7-2017 Final ML16194A0062016-07-12012 July 2016 Pre-Application Meeting Presentation Regarding LaSalle County Station License Amendment Request for Revision of Suppression Pool Swell Design Analysis ML16077A1562016-03-22022 March 2016 Fleet: Pre-application Teleconference with Exelon to Discuss a Potential License Amendment Request Regarding Operating Training Standards ML16077A3492016-03-17017 March 2016 NRC Briefing Slides for LaSalle Dseis Public Meeting March 22, 2016 ML15062A3642015-03-0303 March 2015 Environmental Scoping Briefing for March 10th Meetings ML15058A6322015-02-27027 February 2015 LSCS Scoping Briefing Prepared 2-27-15 for March 10th Meeting ML13212A3372013-07-31031 July 2013 NRC NEI-01-01 Meeting Presentation on 7/31/13 Digital I&C Meeting NEI 01-01, NRC NEI-01-01 Meeting Presentation on 7/31/13 Digital I&C Meeting2013-07-31031 July 2013 NRC NEI-01-01 Meeting Presentation on 7/31/13 Digital I&C Meeting ML13211A3782013-07-30030 July 2013 7/31/2013 NRC Public Meeting Presentation on NEI 01-01 NEI 01-01, 7/31/2013 NRC Public Meeting Presentation on NEI 01-012013-07-30030 July 2013 7/31/2013 NRC Public Meeting Presentation on NEI 01-01 ML13164A3792013-06-24024 June 2013 Summary of Public Meeting with Exelon Generation Company, LLC, Regarding the Proposed Extended Power Uprate License Amendment Request for LaSalle County Station, Units 1 and 2 ML12200A3652012-07-27027 July 2012 County Station UHS Pre-Application Mtg 6-28-12 - Final ML12188A5122012-07-0606 July 2012 IEMA HAB Lessons Learned_rev1 ML12159A2662012-06-11011 June 2012 County Generating Station Pre-Application Meeting Extended Power Uprate: Replacement Steam Dryers. June 11, 2012 ML12130A0442012-06-0707 June 2012 Summary of Public Meeting with Exelon Generation Company, LLC, Regarding Proposed Extended Power Uprate License Amendment Request for LaSalle County Station, Units 1 and 2 ML1209306162012-04-0202 April 2012 Enclosure - 04/04/2012 Exelon Nuclear Meeting Presentation LaSalle Count Station Pre-Application Meeting Extended Power Uprate. ML1209006542012-03-30030 March 2012 Slides for April 4 Public Meeting on LaSalle Extended Power Uprate ML1208701402012-03-27027 March 2012 Licensee Slides for Exelon Fleet Pre-Submittal Public Meeting 4-10-12 Licensed Operator Eligibility Requirements LAR ML1208806542012-03-27027 March 2012 Non-Proprietary Slides for LaSalle Prnm Meeting ML1200303212012-01-19019 January 2012 12/7/2011 - Summary of Public Meeting with Exelon Regarding the Proposed Extended Power Uprate License Amendment Request for LaSalle, Units 1 and 2 ML13014A1002011-09-12012 September 2011 Sprinkler Clogging LaSalle Exelon - Presentation During September 2011 NEI Fire Protection Information Forum ML11201A2132011-07-20020 July 2011 Summary of Public Meeting to Discuss Exelon'S Plans for Implementing an Electronic Document Control System (Edocs) for Use by NRC Inspectors with U.S. Nuclear Regulatory Commission (NRC) Region III Staff ML1100502552011-01-17017 January 2011 December 29, 2010, Summary of Public Conference Call with Exelon Generation Company, LLC, Regarding LaSalle Netco Insert Request ML1100503592010-12-29029 December 2010 NRC Meeting Slides for December 29, 2010, Public Conference Call with Exelon Generation Company Regarding LaSalle Netco Insert Request ML1030704842010-11-19019 November 2010 Summary of Public Meeting with Exelon Generation Company, LLC Regarding LaSalle Netco Insert Request ML1030903782010-11-19019 November 2010 Licensee Handouts for LaSalle Meeting with Exelon to Discuss Netco Inserts ML1032601422010-11-10010 November 2010 Handouts for November 10, 2010 Public Conference Call with Exelon Regarding LaSalle Insert Request ML0929400522009-10-22022 October 2009 Meeting Power Uprate Meeting Slides ML0917502262009-07-0707 July 2009 Summary of Pre-Application Meeting with Exelon Generation Company, License Amendment Request for LaSalle and Limerick Measurement Uncertainty Recapture Power Uprates ML0911102662009-04-16016 April 2009 LaSalle Summary Meeting Slides ML0909005022009-04-0909 April 2009 Meeting Summary of Pre-application Meeting with Exelon on License Amendment Request for Automatic Depressurization System for LaSalle 2024-01-30 |
Text
Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Nuclear Regulatory Commission December 29, 2010 1
Introduction - Charles Norton Application Status - Eva Brown Path Forward - Eva Brown Outstanding Concerns - Kent Wood 2
Charles Norton Project Manager Division of Operating Reactor Licensing 3
Eva Brown Senior Project Manager Division of Operating Reactor Licensing 4
October 5, 2009 submittal [ML092810278]
November 12, 2009 Acceptance Review Complete
[ML093160531]
Requests for Additional Information April 26, 2010 [ML100980209]
June 2, 2010 e-mail [ML101540001]
November 19, 2010 [ML103210499]
December 10, 2010 [ML103430423]
Supplements June 10, 2010 [ML101650229]
November 23, 2010 [ML103270566]
December 14, 2010 [ML103490098]
December 22, 2010 [ML103570025]
5
Public Meetings January 29, 2009 Pre-application March 18, 2009 Pre-application June 1, 2010 Discuss RAI Responses October 21, 2010 Discuss support for outage November 10, 2010 Licensee proposal for outage December 29, 2010 Discuss status and path forward beyond outage 6
NRC Review to be completed in two parts Outage + 120 Full campaign Outage (L2R13)
Three Spent fuel casks loaded Possibility of two more?
Spring 2011 refueling outage Pool reconfiguration L2R13+120 days Full campaign Licensee proposed completion December 31, 2014 Outstanding technical issues 7
Relies heavily on engineering judgment and loading of spent fuel casks November 10, 2010 proposal November 23, 2010 supplement December 14, 2010 supplement December 22, 2010 supplement NRC staff technical review Completion scheduled January 28, 2011 Partial review License conditions 8
NETCO Inserts completion Original date was 2016 Current proposed 2014 NRC technical concerns Technical Evaluation completion Schedule indeterminate Additional Information Needed 9
Kent Wood Reactor Systems Engineer Division of Safety Systems 10
Biases and Uncertainties Code Validation Analysis Assumptions Non-conservatisms Degradation Modeling Uniform Thinning Random Localized Dissolution B-10 Self Shielding Accidents Miss-Loading Seismic 11