MONTHYEARRS-09-133, Attachment 6, LaSalle, Unit 2, Nuclear Power Station Spent Fuel Storage Pool Criticality Safety Analysis with Neutron Absorbing Inserts and Without Boraflex2009-08-31031 August 2009 Attachment 6, LaSalle, Unit 2, Nuclear Power Station Spent Fuel Storage Pool Criticality Safety Analysis with Neutron Absorbing Inserts and Without Boraflex Project stage: Request ML0928102792009-10-0505 October 2009 License Amendment Regarding the Use of Neutron Absorbing Inserts in Unit 2 Spent Fuel Pool Storage Racks Project stage: Other ML0931705992009-12-0202 December 2009 Request for Withholding Information from Public Disclosure by Letter Dated 10/5/09 Project stage: Withholding Request Acceptance ML1009802092010-04-26026 April 2010 Request for Additional Information Related to License Amendment Request Regarding the Use of Neutron Absorbing Inserts in Unit 2 Spent Fuel Pool Storage Racks Project stage: RAI ML1011904862010-05-0303 May 2010 Notice of Meeting with Exelon, LaSalle, Units 1 and 2, to Discuss Response to Request for Additional Information License Amendment Request Regarding the Use of Neutron Absorbing Inserts in Spent Fuel Pool Storage Racks Project stage: RAI ML1016502292010-06-10010 June 2010 Additional Information Supporting License Amendment Request Regarding the Use of Neutron Absorbing Inserts in Unit 2 Spent Fuel Pool Storage Racks Project stage: Request ML1016103942010-06-10010 June 2010 E-mail Response to Eeeb AST RAI on June 10, 2010 Project stage: Request ML1016502862010-06-23023 June 2010 June 1, 2010, Summary of Meeting with Exelon Generation Co., LLC, on Responses to Request for Information License Amendment Request for the Use of Netco-SNAP-In Rack Inserts Project stage: RAI ML1028003592010-10-0707 October 2010 Notice of Public Meeting with Exelon Generation Company, LLC, Regarding LaSalle Netco Insert Request Project stage: Meeting ML1030004242010-10-28028 October 2010 Notice of Meeting with Exelon Genertion Company to Discuss the License Amendment Request to Allow Full Recovery of Spent Fuel Storage Rack Cells That Are Unusable Due to Boraflex Neutron Absorber Degradation Project stage: Meeting ML1032104992010-11-19019 November 2010 Request for Additional Information, Related to the Use of Neutron Absorbing Inserts Project stage: RAI ML1030704842010-11-19019 November 2010 Summary of Public Meeting with Exelon Generation Company, LLC Regarding LaSalle Netco Insert Request Project stage: Meeting ML1030903782010-11-19019 November 2010 Licensee Handouts for LaSalle Meeting with Exelon to Discuss Netco Inserts Project stage: Meeting RS-10-202, Additional Information Supporting License Amendment Request Re Use of Neutron Absorbing Inserts in Unit 2 Spent Fuel Pool Storage Racks2010-11-23023 November 2010 Additional Information Supporting License Amendment Request Re Use of Neutron Absorbing Inserts in Unit 2 Spent Fuel Pool Storage Racks Project stage: Request ML1034304232010-12-10010 December 2010 Request for Additional Information Related to the Use of Nuetron Absorbing Inserts Project stage: RAI RS-10-210, Additional Information Supporting License Amendment Request Regarding the Use of Neutron Absorbing Inserts in Unit 2 Spent Fuel Pool Storage Racks2010-12-14014 December 2010 Additional Information Supporting License Amendment Request Regarding the Use of Neutron Absorbing Inserts in Unit 2 Spent Fuel Pool Storage Racks Project stage: Request ML1034904622010-12-16016 December 2010 Notice of Meeting with Exelon Generation Company, LLC Regarding LaSalle Netco Insert Request Project stage: Meeting RS-10-216, Additional Information Supporting License Amendment Request Regarding the Use of Neutron Absorbing Inserts in Unit 2 Spent Fuel Pool Storage Racks2010-12-22022 December 2010 Additional Information Supporting License Amendment Request Regarding the Use of Neutron Absorbing Inserts in Unit 2 Spent Fuel Pool Storage Racks Project stage: Request ML1100503592010-12-29029 December 2010 NRC Meeting Slides for December 29, 2010, Public Conference Call with Exelon Generation Company Regarding LaSalle Netco Insert Request Project stage: Meeting ML1101300742011-01-11011 January 2011 Additional Information Supporting License Amendment Request Regarding the Use of Neutron Absorbing Inserts in Unit 2 Spent Fuel Pool Storage Racks Project stage: Request ML1100502552011-01-17017 January 2011 December 29, 2010, Summary of Public Conference Call with Exelon Generation Company, LLC, Regarding LaSalle Netco Insert Request Project stage: Other ML1101803312011-01-24024 January 2011 Proposed License Conditions Related to Use of Neutron Absorbers Project stage: Other RS-11-009, Additional Information Supporting License Amendment Request Regarding the Use of Neutron Absorbing Inserts in Unit 2 Spent Fuel Pool Storage Racks2011-01-24024 January 2011 Additional Information Supporting License Amendment Request Regarding the Use of Neutron Absorbing Inserts in Unit 2 Spent Fuel Pool Storage Racks Project stage: Request RS-11-014, Additional Information Supporting License Amendment Request Regarding the Use of Neutron Absorbing Inserts in Unit 2 Spent Fuel Pool Storage Racks2011-01-28028 January 2011 Additional Information Supporting License Amendment Request Regarding the Use of Neutron Absorbing Inserts in Unit 2 Spent Fuel Pool Storage Racks Project stage: Request ML1102500512011-01-28028 January 2011 Issuance of Amendments Concerning Spent Fuel Neutron Absorbers Project stage: Approval ML1104606172011-03-0404 March 2011 Request for Additional Inforamtion Related to the Use of Neutron Absorbing Inserts Project stage: Other RS-11-067, Response to Request for Additional Information Regarding Unit 2 Spent Fuel Pool Storage Racks2011-04-18018 April 2011 Response to Request for Additional Information Regarding Unit 2 Spent Fuel Pool Storage Racks Project stage: Response to RAI RS-11-109, Completion of License Condition 2.C.(30) Associated with Unit 2 Spent Fuel Pool Storage Racks2011-07-13013 July 2011 Completion of License Condition 2.C.(30) Associated with Unit 2 Spent Fuel Pool Storage Racks Project stage: Other ML1120301262011-08-0404 August 2011 Closure of Spent Fuel Pool Neutron Absorbers Inserts Project stage: Other RS-11-170, Completion of License Condition 2.C.(31) Associated with Unit 2 Spent Fuel Pool Storage Racks2011-10-20020 October 2011 Completion of License Condition 2.C.(31) Associated with Unit 2 Spent Fuel Pool Storage Racks Project stage: Other 2010-04-26
[Table View] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 June 23, 2010 LICENSEE:
Exelon Generation Company, LLC FACILITY:
LaSalle County Station, Units 1 and 2
SUBJECT:
SUMMARY
OF JUNE 1,2010, MEETING WITH EXELON GENERATION COMPANY, LLC, ON RESPONSES TO REQUEST FOR INFORMATION RE: LICENSE AMENDMENT REQUEST FOR THE USE OF NETCO-SNAP-IN RACK INSERTS (TAC NO. ME2376 AND ME2377)
On June 1, 2010, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Exelon Generation Company, LLC (EGC, licensee) at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland. The purpose of the meeting was to discuss the draft request for additional information (RAI) responses related to license amendment request submitted on October 5,2009 (Agencywide Documents Access and Management System (ADAMS) Package No. ML092810278), regarding the use of neutron absorbing inserts in the LaSalle county Station (LSCS), Unit 2, spent fuel pool storage racks. A list of attendees is provided as Enclosure 1.
The licensee presented information in response to the RAls sent to the licensee on April 26, 2010 (ADAMS Accession No. ML100980209). A large portion of the meeting was closed to the public because of the proprietary nature of the responses. The licensee submitted their formal responses to the RAls on June 10, 2010 (ADAMS Package No. ML101650228). The non proprietary version can be found in ADAMS (ADAMS Accession No. ML101650229 and ML101650230).
Members of the public were not in attendance. Public Meeting Feedback forms were not received.
Please direct any inquiries to me at 301-415-3719, or Cameron.goodwin@nrc.gov.
~d~
Cameron Goodwin, Project Manager Plant Licensing Branch 111-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-373 and 50-374
Enclosure:
List of Attendees cc w/encl: Distribution via Listserv
LIST OF ATTENDEES JUNE 1, 2010, MEETING WITH EXELON GENERATION COMPANY, LLC ON RESPONSES TO REQUEST FOR INFORMATION RE: LICENSE AMENDMENT REQUEST FOR THE USE OF NETCO-SNAP-IN RACK INSERTS EXELON Darin Benyak Ken Nicely Steve Shields Philip Hansett Jill Fisher Adam Levin NRC Cameron Goodwin Tony Ulses Tony Nakanishi KentWood Christine Lipa Don Mueller (ORNL)
AREVA Ed Fowles Alan Maginnis ENCLOSURE
June 23, 2010 LICENSEE:
Exelon Generation Company, LLC FACILITY:
LaSalle County Station, Units 1 and 2
SUBJECT:
SUMMARY
OF JUNE 1,2010, MEETING WITH EXELON GENERATION COMPANY, LLC, ON RESPONSES TO REQUEST FOR INFORMATION RE: LICENSE AMENDMENT REQUEST FOR THE USE OF NETCO-SNAP-IN RACK INSERTS (TAC NO. ME2376 AND ME2377)
On June 1, 2010, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Exelon Generation Company, LLC (EGC, licensee) at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland. The purpose of the meeting was to discuss the draft request for additional information (RAI) responses related to license amendment request submitted on October 5, 2009 (Agencywide Documents Access and Management System (ADAMS) Package No. ML092810278), regarding the use of neutron absorbing inserts in the LaSalle county Station (LSCS), Unit 2, spent fuel pool storage racks. A list of attendees is provided as Enclosure 1.
The licensee presented information in response to the RAls sent to the licensee on April 26, 2010 (ADAMS Accession No. ML100980209). A large portion of the meeting was closed to the public because of the proprietary nature of the responses. The licensee submitted their formal responses to the RAls on June 10,2010 (ADAMS Package No. ML101650228). The non proprietary version can be found in ADAMS (ADAMS Accession No. ML101650229 and ML101650230).
Members of the public were not in attendance. Public Meeting Feedback forms were not received.
Please direct any inquiries to me at 301-415-3719, or Cameron.goodwin@nrc.gov.
IRA!
Cameron Goodwin, Project Manager Plant Licensing Branch 111-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-373 and 50-374
Enclosure:
List of Attendees cc w/encl: Distribution via Listserv DISTRIBUTION:
PUBLIC RidsNrrLA THarris Resource KWood, NRR LPL3-2 r/f RidsOgcRp Resource TUlses, NRR RidsAcrsAcnw_MailCTR Resource RidsRgnXMailCenter Resource SBagley, EDO Region 3 RidsNrrDorlLpl3-2Resource CSteger, NRR RidsNrrPMLaSalie Resource TNakanishi, NRR ADAMS Accession no.
Meeting Notice ML101190486 Meeting Summary ML101650286 NRC-001 OFFICE DORULPL3-2/PM DORULPL3-2/LA DORULPL3-2/BC DORULPL3-2/PM NAME CGoodwin THarris RCarlson CGoodwin DATE 06/12/10 06/17/10 06/21/10 06/23/10 OFFICIAL RECORD COpy