Inspection / Activity Plan Page 1 of 2 09/01/2010 13:28:47 Report 22 09/01/2010 - 12/31/2011 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Oconee OL EXAM
- INITIAL EXAM - PREP 5
1 OCONEE/OCTOBER 2010 EXAM AT POWER FACILITIES V23339 10/04/2010 10/05/2010 OL EXAM
- INITIAL EXAM WEEK 3
1 OCONEE/OCTOBER 2010 EXAM AT POWER FACILITIES V23339 10/25/2010 10/29/2010 EB3ISI
- UNIT 3 INSERVICE INSPECTION 1
3 IP Inservice Inspection Activities - PWR 7111108P 11/01/2010 11/05/2010 EB3TI172
- RCS DISSIMILAR METAL BUTT WELDS 1
3 IP Reactor Coolant System Dissimiliar Metal Butt Welds 2515/172 11/01/2010 11/05/2010 EB3SGISI
- UNIT 3 SG INSERVICE INSPECTION 1
3 IP Inservice Inspection Activities - PWR 7111108P 11/08/2010 11/12/2010 OL RQ
- REQUAL INSPECTION 2
1, 2, 3 IP Licensed Operator Requalification Program 7111111B 02/28/2011 03/04/2011 EB3ISI
- UNIT 1 INSERVICE INSPECTION 1
1 IP Inservice Inspection Activities - PWR 7111108P 04/11/2011 04/15/2011 OL EXAM
- INITIAL EXAM PREP 4
1 OCONEE/APRIL 2011 EXAM AT POWER FACILITIES V23348 04/11/2011 04/15/2011 EB3SGISI
- UNIT 1 SG INSERVICE INSPECTION 1
1 IP Inservice Inspection Activities - PWR 7111108P 04/18/2011 04/22/2011 OL EXAM
- INIITIAL EXAM WEEK 4
1 OCONEE/APRIL 2011 EXAM AT POWER FACILITIES V23348 05/02/2011 05/06/2011 EB2-TFPI
- 805 TFPI 6
1, 2, 3 IP Fire Protection [Triennial]
7111105T 06/27/2011 07/01/2011 1, 2, 3 IP Fire Protection [Triennial]
7111105T 07/11/2011 07/15/2011 CDBI
- COMPONENT DESIGN BASES INSPECTION 9
1, 2, 3 IP Component Design Bases Inspection 7111121 08/15/2011 08/19/2011 1, 2, 3 IP Component Design Bases Inspection 7111121 08/29/2011 09/02/2011 1, 2, 3 IP Component Design Bases Inspection 7111121 09/12/2011 09/16/2011 1, 2, 3 IP Component Design Bases Inspection 7111121 09/26/2011 09/30/2011 PSB1EP
- EMERGENCY PREPAREDNESS INSPECTION 1
1, 2, 3 IP Alert and Notification System Testing 7111402 08/22/2011 08/26/2011 1, 2, 3 IP Emergency Preparedness Organization Staffing and Augmentation System 7111403 08/22/2011 08/26/2011 1, 2, 3 IP Emergency Action Level and Emergency Plan Changes 7111404 08/22/2011 08/26/2011 1, 2, 3 IP Correction of Emergency Preparedness Weaknesses and Deficiencies 7111405 08/22/2011 08/26/2011 1, 2, 3 IP Performance Indicator Verification 71151 08/22/2011 08/26/2011 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Enclosure
Inspection / Activity Plan Page 2 of 2 09/01/2010 13:28:47 Report 22 09/01/2010 - 12/31/2011 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Oconee OL EXAM
- INITIAL EXAM PREP 4
1 OCONEE/OCTOBER 2011 EXAM AT POWER FACILITIES V23361 09/26/2011 09/30/2011 OL EXAM
- INITIAL EXAM WEEK 3
1 OCONEE/OCTOBER 2011 EXAM AT POWER FACILITIES V23361 10/17/2011 10/21/2011 PSB1-RP
- RP OCCUPATIONAL WEEK 1 3
1, 2, 3 IP Radiological Hazard Assessment and Exposure Controls 71124.01 10/24/2011 10/28/2011 1, 2, 3 IP Occupational ALARA Planning and Controls 71124.02 10/24/2011 10/28/2011 1, 2, 3 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 10/24/2011 10/28/2011 1, 2, 3 IP Occupational Dose Assessment 71124.04 10/24/2011 10/28/2011 1, 2, 3 IP Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation 71124.08 10/24/2011 10/28/2011 1, 2, 3 IP Performance Indicator Verification 71151 10/24/2011 10/28/2011 PSB1-TI
- TI-179 NSTS VERIFICATION 3
1, 2, 3 IP Verification of Licensee Responses to NRC Requirement for Inventories of Materials Tracked in NSTS 2515/179 10/24/2011 10/28/2011 1, 2, 3 IP Verification of Licensee Responses to NRC Requirement for Inventories of Materials Tracked in NSTS 2515/179 11/14/2011 11/18/2011 EB3 ISI
- UNIT 2 IN-SERVICE INSPECTION 1
2 IP Inservice Inspection Activities - PWR 7111108P 10/31/2011 11/04/2011 EB3SGISI
- UNIT 2 SG INSERVICE INSPECTION 1
2 IP Inservice Inspection Activities - PWR 7111108P 11/07/2011 11/11/2011 PSB1-RP
- RP OCCUPATIONAL WEEK 2 4
1, 2, 3 IP Radiological Hazard Assessment and Exposure Controls 71124.01 11/14/2011 11/18/2011 1, 2, 3 IP Occupational ALARA Planning and Controls 71124.02 11/14/2011 11/18/2011 1, 2, 3 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 11/14/2011 11/18/2011 1, 2, 3 IP Occupational Dose Assessment 71124.04 11/14/2011 11/18/2011 1, 2, 3 IP Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation 71124.08 11/14/2011 11/18/2011 1, 2, 3 IP Performance Indicator Verification 71151 11/14/2011 11/18/2011 PB7-PI&R
- PROBLEM IDENTIFICATION AND RESOLUTION 5
1, 2, 3 IP Identification and Resolution of Problems 71152B 11/28/2011 12/02/2011 1, 2, 3 IP Identification and Resolution of Problems 71152B 12/12/2011 12/16/2011 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.