ML100550497
ML100550497 | |
Person / Time | |
---|---|
Site: | Watts Bar |
Issue date: | 02/02/2010 |
From: | Tennessee Valley Authority |
To: | Office of Nuclear Reactor Regulation |
References | |
Download: ML100550497 (30) | |
Text
FQ (Z)
B 3.2.1 B 3.2 POWER DISTRIBUTION LIMITS B 3.2.1 Heat Flux Hot Channel Factor (FQ (Z))
BASES BACKGROUND The purpose of the limits on the values of FQ (Z) is to limit the local (i.e., pellet) peak power density. The value of FQ (Z) varies along the axial height (Z) of the core.
FQ (Z) is defined as the maximum local fuel rod linear power density divided by the average fuel rod linear power density, assuming nominal fuel pellet and fuel rod dimensions adjusted for uncertainty. Therefore, FQ (Z) is a measure of the peak fuel pellet power within the reactor core.
During power operation, the global power distribution is limited by LCO 3.2.3, "AXIAL FLUX DIFFERENCE (AFD)," and LCO 3.2.4, "QUADRANT POWER TILT RATIO (QPTR)," which are directly and continuously measured process variables. These LCOs, along with LCO 3.1.7, "Control Bank Insertion Limits," maintain the core limits on power distributions on a continuous basis.
FQ (Z) varies with fuel loading patterns, control bank insertion, fuel burnup, and changes in axial power distribution.
FQ (Z) is measured periodically using the Power Distribution Monitoring System (PDMS). These measurements are generally taken with the core at or near steady state conditions.
Using the measured three dimensional power distributions, it is possible to derive a measured value for FQ (Z). However, because this value represents a steady state condition, it does not include the variations in the value of FQ (Z) that are present during nonequilibrium situations, such as load following.
To account for these possible variations, the steady state value of FQ (Z) is adjusted by an elevation dependent factor that accounts for the calculated worst case transient conditions.
Core monitoring and control under nonsteady state conditions are accomplished by operating the core within the limits of the appropriate LCOs, including the limits on AFD, QPTR, and control rod insertion.
(continued)
Watts Bar - Unit 2 B 3.2-1 (developmental) B
FQ (Z)
B 3.2.1 BASES (continued)
APPLICABLE This LCO precludes core power distributions that violate the following fuel SAFETY design criteria:
ANALYSES
- a. During a loss of coolant accident (LOCA), the peak cladding temperature must not exceed 2200°F for small breaks, and there must be a high level of probability that the peak cladding temperature does not exceed 2200°F for large breaks (Ref. 1);
- b. During a loss of forced reactor coolant flow accident, there must be at least 95% probability at the 95% confidence level (the 95/95 DNB criterion) that the hot fuel rod in the core does not experience a departure from nucleate boiling (DNB) condition;
- c. During an ejected rod accident, the energy deposition to the fuel must not exceed 280 cal/gm (Ref. 2); and
- d. The control rods must be capable of shutting down the reactor with a minimum required SDM with the highest worth control rod stuck fully withdrawn (Ref. 3).
Limits on FQ (Z) ensure that the value of the initial total peaking factor assumed in the accident analyses remains valid. Other criteria must also be met (e.g., maximum cladding oxidation, maximum hydrogen generation, coolable geometry, and long term cooling). However, the peak cladding temperature is typically most limiting.
FQ (Z) limits assumed in the LOCA analysis are typically limiting relative to (i.e., lower than) the FQ (Z) limit assumed in safety analyses for other postulated accidents. Therefore, this LCO provides conservative limits for other postulated accidents.
FQ (Z) satisfies Criterion 2 of the NRC Policy Statement.
(continued)
Watts Bar - Unit 2 B 3.2-2 (developmental) A
FQ (Z)
B 3.2.1 BASES (continued)
LCO The Heat Flux Hot Channel Factor, FQ (Z), shall be limited by the following relationships:
CFQ FQ (Z) K(Z) for P > 0.5 P
CFQ FQ (Z) K(Z) for P 05 .
05 where: CFQ is the FQ(Z) limit at RTP provided in the COLR, K(Z) is the normalized FQ(Z) as a function of core height provided in the COLR, and THERMAL POWER P =
RTP The actual values of CFQ and K(Z) are given in the COLR; however, CFQ is normally a number on the order of 2.4, and K(Z) is a function that looks like the one provided in Figure B 3.2.1-1.
For Relaxed Axial Offset Control operation, FQ(Z) is approximated by FQC (Z) and FQW (Z). Thus, both FQC (Z) and FQW (Z) must meet the preceding limits on FQ (Z).
An FQC (Z) evaluation requires obtaining an incore power distribution measurement in MODE 1.
The measured value, FMQ(Z), of FQ(Z) is obtained from the incore power distribution measurement and then corrected for fuel manufacturing tolerances and measurement uncertainty.
(continued)
Watts Bar - Unit 2 B 3.2-3 (developmental) B
FQ (Z)
B 3.2.1 BASES LCO Using the PDMS to obtain the incore power distribution measurement:
(continued)
FCQ(Z) = 1.03 FMQ(Z) (1+UQ/100) where 1.03 is the factor that accounts for the fuel manufacturing tolerances and the factor (1+UQ/100), which accounts for measurement uncertainty, is calculated and applied automatically by the BEACON software (Ref. 4).
FQC (Z) is an approximation of the steady state FQ(Z).
The expression for FQW (Z) is:
FQW(Z) = FQC (Z) W(Z)/P for P > 0.5 FQW(Z) = FQC (Z) W(Z)/0.5 for P < 0.5 where W(Z) is a cycle dependent function that accounts for power distribution transients encountered during normal operation. W(Z) is included in the COLR.
The FQ (Z) limits define limiting values for core power peaking that precludes peak cladding temperatures above 2200°F during a small break LOCA, and assures with a high level of probability that the peak cladding temperature does not exceed 2200°F for large breaks (Ref. 1).
This LCO requires operation within the bounds assumed in the safety analyses. Calculations are performed in the core design process to confirm that the core can be controlled in such a manner during operation that it can stay within the LOCA FQ (Z) limits. If FQ (Z) cannot be maintained within the LCO limits, reduction of the core power is required.
Violating the LCO limits for FQ (Z) produces unacceptable consequences if a design basis event occurs while FQ (Z) is outside its specified limits.
APPLICABILITY The FQ (Z) limits must be maintained in MODE 1 to prevent core power distributions from exceeding the limits assumed in the safety analyses.
Applicability in other MODES is not required because there is either insufficient stored energy in the fuel or insufficient energy being transferred to the reactor coolant to require a limit on the distribution of core power.
(continued)
Watts Bar - Unit 2 B 3.2-4 (developmental) B
FQ (Z)
B 3.2.1 BASES ACTIONS A.1 Reducing THERMAL POWER by 1% RTP for each 1% by which FQC (Z) exceeds its limit, maintains an acceptable absolute power density.
FQC (Z) is FQM (Z) multiplied by a factor accounting for manufacturing tolerances and measurement uncertainties. FQM (Z) is the measured value of FQ (Z). The Completion Time of 15 minutes provides an acceptable time to reduce power in an orderly manner and without allowing the plant to remain in an unacceptable condition for an extended period of time.
A.2 A reduction of the Power Range Neutron Flux - High trip setpoints by
> 1% for each 1% by which FQC (Z) exceeds its limit, is a conservative action for protection against the consequences of severe transients with unanalyzed power distributions. The Completion Time of 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> is sufficient considering the small likelihood of a severe transient in this time period and the preceding prompt reduction in THERMAL POWER in accordance with Required Action A.1.
A.3 Reduction in the Overpower T trip setpoints by > 1% for each 1% by which FQC (Z) exceeds its limit, is a conservative action for protection against the consequences of severe transients with unanalyzed power distributions. The Completion Time of 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> is sufficient considering the small likelihood of a severe transient in this time period, and the preceding prompt reduction in THERMAL POWER in accordance with Required Action A.1.
A.4 Verification that FQC (Z) has been restored to within its limit, by performing SR 3.2.1.1 prior to increasing THERMAL POWER above the limit imposed by Required Action A.1, ensures that core conditions during operation at higher power levels are consistent with safety analyses assumptions.
(continued)
Watts Bar - Unit 2 B 3.2-5 (developmental) A
FQ (Z)
B 3.2.1 BASES ACTIONS B.1 (continued)
If it is found that the maximum calculated value of FQ (Z) that can occur during normal maneuvers, FQW (Z), exceeds its specified limits, there exists a potential for FQC (Z) to become excessively high if a normal operational transient occurs. Reducing the AFD limits by 1% for each 1% by which FQW (Z) exceeds its limit within the allowed Completion Time of 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />, restricts the axial flux distribution such that even if a transient occurred, core peaking factors are not exceeded.
C.1 If Required Actions A.1 through A.4 or B.1 are not met within their associated Completion Times, the plant must be placed in a mode or condition in which the LCO requirements are not applicable. This is done by placing the plant in at least MODE 2 within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />.
This allowed Completion Time is reasonable based on operating experience regarding the amount of time it takes to reach MODE 2 from full power operation in an orderly manner and without challenging plant systems.
SURVEILLANCE SR 3.2.1.1 and SR 3.2.1.2 are modified by a Note. The Note applies REQUIREMENTS during the first power ascension after initial fuel loading and a refueling. It states that THERMAL POWER may be increased until an equilibrium power level has been achieved at which a power distribution map can be obtained. This allowance is modified, however, by one of the Frequency conditions that requires verification that FQC (Z) and FQW (Z) are within their specified limits after a power rise of more than 10% RTP over the THERMAL POWER at which they were last verified to be within specified limits. Because FQC (Z) and FQW (Z) could not have previously been measured in this core, there is a second Frequency condition that requires determination of these parameters before exceeding 75% RTP.
This ensures that some determination of FQC (Z) and FQW (Z) is made at a lower power level at which adequate margin is available before going to 100% RTP. Also, this Frequency condition, together with the Frequency condition requiring verification of FQC (Z) and FQW (Z) following a power increase of more than 10%, ensures that they are verified as soon as RTP (or any other level for extended operation) is achieved.
(continued)
Watts Bar - Unit 2 B 3.2-6 (developmental) A
FQ (Z)
B 3.2.1 BASES SURVEILLANCE In the absence of these Frequency conditions, it is possible to increase REQUIREMENTS power to RTP and operate for 31 days without verification of FQC (Z) and (continued) FQW (Z). The Frequency condition is not intended to require verification of these parameters after every 10% increase in power level above the last verification. It only requires verification after a power level is achieved for extended operation that is 10% higher than that power at which FQ was last measured.
SR 3.2.1.1 Verification that FQC (Z) is within its specified limits involves increasing FQM (Z) to allow for manufacturing tolerance and measurement uncertainties in order to obtain FQC (Z). Specifically, FQM (Z) is the measured value of FQ (Z) obtained from the incore power distribution measurement.
Using the PDMS to obtain the incore power distribution measurement:
FCQ(Z) = 1.03 FMQ(Z) (1+UQ/100) where 1.03 is the factor that accounts for the fuel manufacturing tolerances and the factor (1+UQ/100), which accounts for measurement uncertainty, is calculated and applied automatically by the BEACON software (Ref. 4).
The limit with which FQC (Z) is compared varies inversely with power above 50% RTP and directly with a function called K(Z) provided in the COLR.
Performing this Surveillance in MODE 1 prior to exceeding 75% RTP ensures that the FQC (Z) limit is met when RTP is achieved, because peaking factors generally decrease as power level is increased.
If THERMAL POWER has been increased by > 10% RTP since the last determination of FQC (Z), another evaluation of this factor is required 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> after achieving equilibrium conditions at this higher power level (to ensure that FQC (Z) values are being reduced sufficiently with power increase to stay within the LCO limits).
The Frequency of 31 EFPD is adequate to monitor the change of power distribution with core burnup because such changes are slow and well controlled when the plant is operated in accordance with the Technical Specifications (TS).
(continued)
Watts Bar - Unit 2 B 3.2-7 (developmental) B
FQ (Z)
B 3.2.1 BASES SURVEILLANCE SR 3.2.1.2 REQUIREMENTS (continued) The nuclear design process includes calculations performed to determine that the core can be operated within the FQ (Z) limits. Because incore power distribution measurements are taken at or near steady state conditions, the variations in power distribution resulting from normal operational maneuvers are not present in the incore power distribution measurement data. These variations are, however, conservatively calculated by considering a wide range of unit maneuvers in normal operation. The maximum peaking factor increase over steady state values, calculated as a function of core elevation, Z, is called W(Z).
Multiplying the measured total peaking factor, FQC(Z), by W(Z) and by dividing by P gives the maximum FQ(Z) calculated to occur in normal operation, FQW(Z). Scaling the W(Z) factors by 1/P accounts for the possibility that reactor power may be increased prior to the next FQ surveillance (Ref. 5).
The limit with which FQW (Z) is compared varies inversely with power and directly with the function K(Z) provided in the COLR.
The W(Z) curve is provided in the COLR for discrete core elevations.
Incore power distribution measurement results are typically calculated at 30 to 75 core elevations. FQW (Z) evaluations are not applicable for the following axial core regions, measured in percent of core height:
- a. Lower core region, from 0 to 10% inclusive; and
- b. Upper core region, from 90 to 100% inclusive.
The top and bottom 10% of the core are excluded from the evaluation because of the difficulty of making a precise measurement in these regions.
This Surveillance has been modified by a Note that may require that more frequent surveillances be performed. If FQW (Z) is evaluated and found to be within its limit, an evaluation of the expression below is required to account for any increase to FQM (Z) that may occur and cause the FQ (Z) limit to be exceeded before the next required FQ (Z) evaluation.
Watts Bar - Unit 2 B 3.2-8 (developmental) B
FQ (Z)
B 3.2.1 BASES SURVEILLANCE SR 3.2.1.2 (continued)
REQUIREMENTS If the two most recent FQ (Z) evaluations show an increase in the expression maximum over z FQC (Z)
K(Z) it is required to meet the FQ (Z) limit with the last FQW (Z) increased by the appropriate factor specified in the COLR, or to evaluate FQ (Z) more frequently, each 7 EFPD. These alternative requirements prevent FQ (Z) from exceeding its limit for any significant period of time without detection.
Performing the Surveillance in MODE 1 prior to exceeding 75% RTP ensures that the FQ (Z) limit is met when RTP is achieved, because peaking factors are generally decreased as power level is increased.
FQ (Z) is verified at power levels > 10% RTP above the THERMAL POWER of its last verification, 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> after achieving equilibrium conditions to ensure that FQ (Z) is within its limit at higher power levels.
The Surveillance Frequency of 31 EFPD is adequate to monitor the change of power distribution with core burnup. The Surveillance may be done more frequently if required by the results of FQ (Z) evaluations.
The Frequency of 31 EFPD is adequate to monitor the change of power distribution because such a change is sufficiently slow, when the plant is operated in accordance with the TS, to preclude adverse peaking factors between 31 day surveillances.
Watts Bar - Unit 2 B 3.2-9 (developmental) A
FQ (Z)
B 3.2.1 BASES REFERENCES 1. Title 10, Code of Federal Regulations, Part 50.46, "Acceptance Criteria for Emergency Core Cooling Systems for Light Water Nuclear Power Reactors."
- 2. Regulatory Guide 1.77, Rev. 0, "Assumptions Used for Evaluating a Control Rod Ejection Accident for Pressurized water Reactors,"
May 1974.
- 3. Title 10, Code of Federal Regulations, Part 50, Appendix A, "General Design Criteria for Nuclear Power Plants," GDC 26, "Reactivity Control System Redundancy and Capability."
- 4. WCAP-12472-P-A, BEACON Core Monitoring and Operations Support System, August 1994, (Addendum 2, April 2002).
- 5. Westinghouse Technical Bulletin (TB) 08-4, FQ Surveillance at Part Powers, July 15, 2008.
Watts Bar - Unit 2 B 3.2-10 (developmental) B
FQ (Z)
B 3.2.1 BASES CORE HEIGHT
- For core height of 12 feet Figure B 3.2.1-1 (page 1 of 1)
K(Z) - Normalized FQ (Z) as a Function of Core Height Watts Bar - Unit 2 B 3.2-11 (developmental) A
FNH B 3.2.2 B 3.2 POWER DISTRIBUTION LIMITS
( )
B 3.2.2 Nuclear Enthalpy Rise Hot Channel Factor F H N
BASES BACKGROUND The purpose of this LCO is to establish limits on the power density at any point in the core so that the fuel design criteria are not exceeded and the accident analysis assumptions remain valid. The design limits on local (pellet) and integrated fuel rod peak power density are expressed in terms of hot channel factors. Control of the core power distribution with respect to these factors ensures that local conditions in the fuel rods and coolant channels do not challenge core integrity at any location during either normal operation or a postulated accident analyzed in the safety analyses.
FNH is defined as the ratio of the integral of the linear power along the fuel rod with the highest integrated power to the average integrated fuel rod power. Therefore, FNH is a measure of the maximum total power produced in a fuel rod.
FNH is sensitive to fuel loading patterns, bank insertion, and fuel burnup.
FNH typically increases with control bank insertion and typically decreases with fuel burnup.
FNH is not directly measurable but is inferred from an incore power distribution measurement obtained with the Power Distribution Monitoring System (PDMS). Specifically, the results of the three dimensional incore power distribution measurement are analyzed by a computer to determine FNH. This factor is calculated at least every 31 EFPD. However, during power operation, the global power distribution is monitored by LCO 3.2.3, "AXIAL FLUX DIFFERENCE (AFD)," and LCO 3.2.4, "QUADRANT POWER TILT RATIO (QPTR)," which address directly and continuously measured process variables.
The COLR provides peaking factor limits that ensure that the design basis value of the departure from nucleate boiling (DNB) is met for normal operation, operational transients, and any transient condition arising from events of moderate frequency. The DNB design basis precludes DNB for the hottest fuel rod in the core. All DNB limited transient events are assumed to begin with an FNH value that satisfies the LCO requirements.
(continued)
Watts Bar - Unit 2 B 3.2-12 (developmental) B
FNH B 3.2.2 BASES BACKGROUND Operation outside the LCO limits may produce unacceptable (continued) consequences if a DNB limiting event occurs. The DNB design basis ensures that there is no overheating of the fuel that results in possible cladding perforation with the release of fission products to the reactor coolant.
APPLICABLE Limits on FNH preclude core power distributions that exceed the following SAFETY fuel design limits:
ANALYSES
- a. There must be at least 95% probability at the 95% confidence level (the 95/95 DNB criterion) that the hottest fuel rod in the core does not experience a DNB condition;
- b. During a loss of coolant accident (LOCA), the peak cladding temperature (PCT) must not exceed 2200°F for small breaks, and there must be a high level of probability that the peak cladding temperature does not exceed 2200°F for large breaks (Ref. 3);
- c. During an ejected rod accident, the energy deposition to the fuel must not exceed 280 cal/gm (Ref. 1); and
- d. Fuel design limits required by GDC 26 (Ref. 2) for the condition when control rods must be capable of shutting down the reactor with a minimum required SDM with the highest worth control rod stuck fully withdrawn.
For transients that may be DNB limited, FNH is a significant core parameter. The limits on FNH ensure that the DNB design basis is met for normal operation, operational transients, and any transients arising from events of moderate frequency. The DNB design basis is met by limiting the minimum local DNB heat flux ratio to a value which satisfies the 95/95 criterion for the DNB correlation used. Refer to the Bases for the Reactor Core Safety Limits, B 2.1.1, for a discussion of the applicable DNBR limits. The W-3 Correlation with a DNBR limit of 1.3 is applied in the heated region below the first mixing vane grid. In addition, the W-3 DNB correlation is applied in the analysis of accident conditions where the system pressure is below the range of the WRB-2M correlation for RFA-2 fuel with IFMs. For system pressures in the range of 500 to 1000 psia, the W-3 correlation DNBR limit is 1.45 instead of 1.3.
Application of these criteria provides assurance that the hottest fuel rod in the core does not experience a DNB.
(continued)
Watts Bar - Unit 2 B 3.2-13 (developmental) B
FNH B 3.2.2 BASES APPLICABLE The allowable FNH limit increases with decreasing power level. This SAFETY functionality in FNH is included in the analyses that provide the Reactor ANALYSES Core Safety Limits (SLs) of SL 2.1.1. Therefore, any DNB events in (continued) which the calculation of the core limits is modeled implicitly use this variable value of FNH in the analyses. Likewise, all transients that may be DNB limited are assumed to begin with an initial FNH as a function of power level defined by the COLR limit equation.
The LOCA safety analyses that verify the acceptability of the resulting peak cladding temperature (Ref. 3) model FNH as well as the Nuclear Heat Flux Hot Channel Factor (FQ(Z)).
The fuel is protected in part by Technical Specifications, which ensure that the initial conditions assumed in the safety and accident analyses remain valid. The following LCOs ensure this: LCO 3.2.3, "AXIAL FLUX DIFFERENCE (AFD)," LCO 3.2.4, "QUADRANT POWER TILT RATIO (QPTR)," LCO 3.1.7, "Control Bank Insertion Limits," LCO 3.2.2, "Nuclear Enthalpy Rise Hot Channel Factor (FNH)," and LCO 3.2.1, "Heat Flux Hot Channel Factor (FQ(Z))."
FNH and FQ(Z) are measured periodically using the PDMS (Ref. 4).
Measurements are generally taken with the core at, or near, steady state conditions. Core monitoring and control under transient conditions (Condition 1 events) are accomplished by operating the core within the limits of the LCOs on AFD, QPTR, and Bank Insertion Limits.
FNH satisfies Criterion 2 of the NRC Policy Statement.
LCO FNH shall be maintained within the limits of the relationship provided in the COLR.
The FNH limit identifies the coolant flow channel with the maximum enthalpy rise. This channel has the least heat removal capability and thus the highest probability for a DNB.
The limiting value of FNH, described by the equation contained in the COLR, is the design radial peaking factor used in the unit safety analyses.
(continued)
Watts Bar - Unit 2 B 3.2-14 (developmental) B
FNH B 3.2.2 BASES LCO A power multiplication factor in this equation includes an additional (continued) margin for higher radial peaking from reduced thermal feedback and greater control rod insertion at low power levels. The limiting value of FNH is allowed to increase 0.3% for every 1% RTP reduction in THERMAL POWER.
APPLICABILITY The FNH limits must be maintained in MODE 1 to preclude core power distributions from exceeding the fuel design limits for DNBR and PCT.
Applicability in other MODES is not required because there is either insufficient stored energy in the fuel or insufficient energy being transferred to the coolant to require a limit on the distribution of core power. Specifically, the design bases events that are sensitive to FNH in other MODES (MODES 2 through 5) have significant margin to DNB, and therefore, there is no need to restrict FNH in these MODES.
ACTIONS A.1.1 With FNH exceeding its limit, the unit is allowed 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> to restore FNH to within its limits. This restoration may, for example, involve realigning any misaligned rods or reducing power enough to bring FNH within its power dependent limit. When the FNH limit is exceeded, the DNBR limit is not likely violated in steady state operation, because events that could significantly perturb the FNH value (e.g., static control rod misalignment) are considered in the safety analyses. However, the DNBR limit may be violated if a DNB limiting event occurs. Thus, the allowed Completion Time of 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> provides an acceptable time to restore FNH to within its limits without allowing the plant to remain in an unacceptable condition for an extended period of time.
Condition A is modified by a Note that requires that Required Actions A.2 and A.3 must be completed whenever Condition A is entered. Thus, if power is not reduced because this Required Action is completed within the 4 hour4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> time period, Required Action A.2 nevertheless requires another measurement and calculation of FNH within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> in accordance with SR 3.2.2.1.
However, if power is reduced below 50% RTP, Required Action A.3 requires that another determination of FNH must be done prior to exceeding 50% RTP, prior to exceeding 75% RTP, and within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> after reaching or exceeding 95% RTP. In addition, Required Action A.2 is performed if power ascension is delayed past 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.
(continued)
Watts Bar - Unit 2 B 3.2-15 (developmental) A
FNH B 3.2.2 BASES ACTIONS A.1.2.1 and A.1.2.2 (continued)
If the value of FNH is not restored to within its specified limit either by adjusting a misaligned rod or by reducing THERMAL POWER, the alternative option is to reduce THERMAL POWER to < 50% RTP in accordance with Required Action A.1.2.1 and reduce the Power Range Neutron Flux-High to 55% RTP in accordance with Required Action A.1.2.2. Reducing RTP to < 50% RTP increases the DNB margin and does not likely cause the DNBR limit to be violated in steady state operation. The reduction in trip setpoints ensures that continuing operation remains at an acceptable low power level with adequate DNBR margin. The allowed Completion Time of 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> for Required Action A.1.2.1 is consistent with those allowed for in Required Action A.1.1 and provides an acceptable time to reach the required power level from full power operation without allowing the plant to remain in an unacceptable condition for an extended period of time. The Completion Times of 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> for Required Actions A.1.1 and A.1.2.1 are not additive.
The allowed Completion Time of 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> to reset the trip setpoints per Required Action A.1.2.2 recognizes that, once power is reduced, the safety analysis assumptions are satisfied and there is no urgent need to reduce the trip setpoints. This is a sensitive operation that may inadvertently trip the Reactor Protection System.
A.2 Once the power level has been reduced to < 50% RTP per Required Action A.1.2.1, an incore power distribution measurement (SR 3.2.2.1) must be obtained and the measured value of FNH verified not to exceed the allowed limit at the lower power level. The unit is provided 20 additional hours to perform this task over and above the 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> allowed by either Action A.1.1 or Action A.1.2.1. The Completion Time of 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> is acceptable because of the increase in the DNB margin, which is obtained at lower power levels, and the low probability of having a DNB limiting event within this 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> period. Additionally, operating experience has indicated that this Completion Time is sufficient to obtain the incore power distribution measurement, perform the required calculations, and evaluate FNH.
(continued)
Watts Bar - Unit 2 B 3.2-16 (developmental) B
FNH B 3.2.2 BASES (continued)
ACTIONS A.3 (continued)
Verification that FNH is within its specified limits after an out of limit occurrence ensures that the cause that led to the FNH exceeding its limit is corrected, and that subsequent operation proceeds within the LCO limit. This Action demonstrates that the FNH limit is within the LCO limits prior to exceeding 50% RTP, again prior to exceeding 75% RTP, and within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> after THERMAL POWER is 95% RTP.
This Required Action is modified by a Note that states that THERMAL POWER does not have to be reduced prior to performing this Action.
B.1 When Required Actions A.1.1 through A.3 cannot be completed within their required Completion Times, the plant must be placed in a mode in which the LCO requirements are not applicable. This is done by placing the plant in at least MODE 2 within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />. The allowed Completion Time of 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> is reasonable, based on operating experience regarding the time required to reach MODE 2 from full power conditions in an orderly manner and without challenging plant systems.
SURVEILLANCE SR 3.2.2.1 REQUIREMENTS The value of FNH is determined by using the PDMS to obtain an incore power distribution measurement. A data reduction computer program then calculates the maximum value of FNH from the measured flux distributions. The measured value of FNH must be multiplied by a factor to account for measurement uncertainty before making comparisons to the FNH limit.
When the PDMS is used to obtain the incore power distribution measurement, the factor (1+UH/100) is calculated and applied automatically by the BEACON software (References 4 and 5).
After the initial fuel loading and each refueling, FNH must be determined in MODE 1 prior to exceeding 75% RTP. This requirement ensures that FNH limits are met at the beginning of each fuel cycle.
The 31 EFPD Frequency is acceptable because the power distribution changes relatively slowly over this amount of fuel burnup. Accordingly, this Frequency is short enough that the FNH limit cannot be exceeded for any significant period of operation.
Watts Bar - Unit 2 B 3.2-17 (developmental) B
FNH B 3.2.2 BASES (continued)
REFERENCES 1. Regulatory Guide 1.77, Rev. 0, "Assumptions Used for Evaluating a Control Rod Ejection Accident for Pressurized Water Reactors,"
May 1974.
- 2. Title 10, Code of Federal Regulations, Part 50, Appendix A, "General Design Criteria for Nuclear Power Plants," GDC 26, "Reactivity Control System Redundancy and Capability."
- 3. Title 10, Code of Federal Regulations, Part 50.46, "Acceptance Criteria for Emergency Core Cooling Systems for Light Water Nuclear Power Reactors."
- 4. WCAP-12472-P-A, BEACON Core Monitoring and Operations Support System, August 1994.
- 5. WCAP-12472-P-A, BEACON Core Monitoring and Operations Support System, Addendum 2, April 2002.
Watts Bar - Unit 2 B 3.2-18 (developmental) B
AFD B 3.2.3 B 3.2 POWER DISTRIBUTION LIMITS B 3.2.3 AXIAL FLUX DIFFERENCE (AFD)
BASES BACKGROUND The purpose of this LCO is to establish limits on the values of the AFD in order to limit the amount of axial power distribution skewing to either the top or bottom of the core. By limiting the amount of power distribution skewing, core peaking factors are consistent with the assumptions used in the safety analyses. Limiting power distribution skewing over time also minimizes the xenon distribution skewing, which is a significant factor in axial power distribution control.
Relaxed Axial Offset Control (RAOC) methodology is a calculational procedure that defines the allowed operational space of the AFD versus THERMAL POWER. The AFD limits are selected by considering a range of axial xenon distributions that may occur as a result of large variations of the AFD. Subsequently, power peaking factors and power distributions are examined to ensure that the loss of coolant accident (LOCA), loss of flow accident, and anticipated transient limits are met. Violation of the AFD limits invalidate the conclusions of the accident and transient analyses with regard to fuel cladding integrity.
Although the RAOC defines limits that must be met to satisfy safety analyses, typically an operating scheme, Constant Axial Offset Control (CAOC), is used to control axial power distribution in day to day operation (Ref. 1). CAOC requires that the AFD be controlled within a narrow tolerance band around a burnup dependent target to minimize the variation of axial peaking factors and axial xenon distribution during unit maneuvers.
The CAOC operating space is typically smaller and lies within the RAOC operating space. Control within the CAOC operating space constrains the variation of axial xenon distributions and axial power distributions.
RAOC calculations assume a wide range of xenon distributions and then confirm that the resulting power distributions satisfy the requirements of the accident analyses.
(continued)
Watts Bar - Unit 2 B 3.2-19 (developmental) A
AFD B 3.2.3 BASES (continued)
APPLICABLE The AFD is a measure of the axial power distribution skewing to either the SAFETY top or bottom half of the core. The AFD is sensitive to many core related ANALYSES parameters such as control bank positions, core power level, axial burnup, axial xenon distribution, and, to a lesser extent, reactor coolant temperature and boron concentration.
The allowed range of the AFD is used in the nuclear design process to confirm that operation within these limits produces core peaking factors and axial power distributions that meet safety analysis requirements.
The RAOC methodology (Ref. 2) establishes a xenon distribution library with tentatively wide AFD limits. One dimensional axial power distribution calculations are then performed to demonstrate that normal operation power shapes are acceptable for the LOCA and loss of flow accident, and for initial conditions of anticipated transients. The tentative limits are adjusted as necessary to meet the safety analysis requirements.
The limits on the AFD ensure that the Heat Flux Hot Channel Factor (FQ(Z)) is not exceeded during either normal operation or in the event of xenon redistribution following power changes. The limits on the AFD also restrict the range of power distributions that are used as initial conditions in the analyses of Condition 2, 3, or 4 events. This ensures that the fuel cladding integrity is maintained for these postulated accidents. The most important Condition 4 event is the LOCA. The most important Condition 3 event is the loss of flow accident. The most important Condition 2 events are uncontrolled bank withdrawal and boration or dilution accidents.
Condition 2 accidents simulated to begin from within the AFD limits are used to confirm the adequacy of the Overpower T and Overtemperature T trip setpoints.
The limits on the AFD satisfy Criterion 2 of the NRC Policy Statement.
(continued)
Watts Bar - Unit 2 B 3.2-20 (developmental) A
AFD B 3.2.3 BASES (continued)
LCO The shape of the power profile in the axial (i.e., the vertical) direction is largely under the control of the operator through the manual operation of the control banks or automatic motion of control banks. The automatic motion of the control banks is in response to temperature deviations resulting from manual operation of the Chemical and Volume Control System to change boron concentration or from power level changes.
Signals are available to the operator from the Nuclear Instrumentation System (NIS) excore neutron detectors (Ref. 3). Separate signals are taken from the top and bottom detectors. The AFD is defined as the difference in normalized flux signals between the top and bottom excore detectors in each detector well. For convenience, this flux difference is converted to provide flux difference units expressed as a percentage and labeled as % flux.
The AFD limits are provided in the COLR. Figure B 3.2.3-1 shows typical RAOC AFD limits. The AFD limits for RAOC do not depend on the target flux difference. However, the target flux difference may be used to minimize changes in the axial power distribution.
Violating this LCO on the AFD could produce unacceptable consequences if a Condition 2, 3, or 4 event occurs while the AFD is outside its specified limits.
APPLICABILITY The AFD requirements are applicable in MODE 1 greater than or equal to 50% RTP when the combination of THERMAL POWER and core peaking factors are of primary importance in safety analysis.
For AFD limits developed using RAOC methodology, the value of the AFD does not affect the limiting accident consequences with THERMAL POWER < 50% RTP and for lower operating power MODES.
ACTIONS A.1 As an alternative to restoring the AFD to within its specified limits, Required Action A.1 requires a THERMAL POWER reduction to
< 50% RTP. This places the core in a condition for which the value of the AFD is not important in the applicable safety analyses. A Completion Time of 30 minutes is reasonable, based on operating experience, to reach 50% RTP without challenging plant systems.
(continued)
Watts Bar - Unit 2 B 3.2-21 (developmental) A
AFD B 3.2.3 BASES (continued)
SURVEILLANCE SR 3.2.3.1 REQUIREMENTS The AFD is monitored on an automatic basis using the unit process computer, which has an AFD monitor alarm. The computer determines the 1 minute average of each of the OPERABLE excore detector outputs and provides an alarm message immediately if the AFD for two or more OPERABLE excore channels is outside its specified limits.
This Surveillance verifies that the AFD, as indicated by the NIS excore channel, is within its specified limits and is consistent with the status of the AFD monitor alarm. With the AFD monitor alarm inoperable, the AFD is monitored every hour to detect operation outside its limit. The Frequency of 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> is based on operating experience regarding the amount of time required to vary the AFD, and the fact that the AFD is closely monitored. With the AFD monitor alarm OPERABLE, the Surveillance Frequency of 7 days is adequate considering that the AFD is monitored by a computer and any deviation from requirements is alarmed.
REFERENCES 1. WCAP-8385 (Proprietary), "Power Distribution Control and Load Following Procedures," Westinghouse Electric Corporation, September 1974.
- 2. R. W. Miller et al., "Relaxation of Constant Axial Offset Control:
FQ Surveillance Technical Specification," WCAP-10216-P-A, June 1983.
- 3. Watts Bar FSAR, Section 7.7, "Control Systems."
Watts Bar - Unit 2 B 3.2-22 (developmental) A
AFD B 3.2.3 BASES Figure B 3.2.3-1 TYPICAL AXIAL FLUX DIFFERENCE Acceptable Operation Limits as a Function of RATED THERMAL POWER Watts Bar - Unit 2 B 3.2-23 (developmental) A
QPTR B 3.2.4 B 3.2 POWER DISTRIBUTION LIMITS B 3.2.4 QUADRANT POWER TILT RATIO (QPTR)
BASES BACKGROUND The QPTR limit ensures that the gross radial power distribution remains consistent with the design values used in the safety analyses. Precise radial power distribution measurements are made during startup testing, after refueling, and periodically during power operation.
The power density at any point in the core must be limited so that the fuel design criteria are maintained. Together, LCO 3.2.3, "AXIAL FLUX DIFFERENCE (AFD)," LCO 3.2.4, and LCO 3.1.7, "Control Rod Insertion Limits," provide limits on process variables that characterize and control the three dimensional power distribution of the reactor core. Control of these variables ensures that the core operates within the fuel design criteria and that the power distribution remains within the bounds used in the safety analyses.
APPLICABLE This LCO precludes core power distributions that violate the following fuel SAFETY design criteria:
ANALYSES
- a. During a large break loss of coolant accident, the peak cladding temperature must not exceed 2200°F (Ref. 1);
- b. During a loss of forced reactor coolant flow accident, there must be at least 95% probability at the 95% confidence level (the 95/95 departure from nucleate boiling (DNB) criterion) that the hot fuel rod in the core does not experience a DNB condition;
- c. During an ejected rod accident, the energy deposition to the fuel must not exceed 280 cal/gm (Ref. 2); and
- d. The control rods must be capable of shutting down the reactor with a minimum required SDM with the highest worth control rod stuck fully withdrawn (Ref. 3).
The LCO limits on the AFD, the QPTR, the Heat Flux Hot Channel Factor (FQ(Z)), the Nuclear Enthalpy Rise Hot Channel Factor (FNH), rod group alignment, sequence, overlap, and control bank insertion are established to preclude core power distributions that exceed the safety analyses limits.
(continued)
Watts Bar - Unit 2 B 3.2-24 (developmental) B
QPTR B 3.2.4 BASES APPLICABLE The QPTR limits ensure that FNH and FQ(Z) remain below their limiting SAFETY values by preventing an undetected change in the gross radial power ANALYSES distribution.
(continued)
In MODE 1, the FNH and FQ(Z) limits must be maintained to preclude core power distributions from exceeding design limits assumed in the safety analyses.
The QPTR satisfies Criterion 2 of the NRC Policy Statement.
LCO The QPTR limit of 1.02, at which corrective action is required, provides a margin of protection for both the DNB ratio and linear heat generation rate contributing to excessive power peaks resulting from X-Y plane power tilts. A limiting QPTR of 1.02 can be tolerated before the margin for uncertainty in FQ(Z) and (FNH) is possibly challenged.
APPLICABILITY The QPTR limit must be maintained in MODE 1 with THERMAL POWER
> 50% RTP to prevent core power distributions from exceeding the design limits.
Applicability in MODE 1 50% RTP and in other MODES is not required because there is either insufficient stored energy in the fuel or insufficient energy being transferred to the reactor coolant to require the implementation of a QPTR limit on the distribution of core power. The QPTR limit in these conditions is, therefore, not important. Note that the FNH and FQ(Z) LCOs still apply, but allow progressively higher peaking factors at 50% RTP or lower.
ACTIONS A.1 With the QPTR exceeding its limit, a power level reduction of 3% RTP for each 1% by which the QPTR exceeds 1.00 is a conservative tradeoff of total core power with peak linear power. The Completion Time of 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> allows sufficient time to identify the cause and correct the tilt. Note that the power reduction itself may cause a change in the tilted condition.
(continued)
Watts Bar - Unit 2 B 3.2-25 (developmental) A
QPTR B 3.2.4 BASES ACTIONS A.2 (continued)
After completion of Required Action A.1, the QPTR Alarm may still be in its alarmed state. As such, any additional changes in the QPTR are detected by requiring a check of the QPTR once per 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> thereafter.
If the QPTR continues to increase, THERMAL POWER has to be reduced accordingly. A 12-hour Completion Time is sufficient because any additional change in QPTR would be relatively slow.
A.3 The peaking factors FNH and FQ(Z) are of primary importance in ensuring that the power distribution remains consistent with the initial conditions used in the safety analyses. Performing SRs on FNH and FQ(Z) within the Completion Time of 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> ensures that these primary indicators of power distribution are within their respective limits.
A Completion Time of 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> takes into consideration the rate at which peaking factors are likely to change, and the time required to stabilize the plant and perform an incore power distribution measurement. If these peaking factors are not within their limits, the Required Actions of these Surveillances provide an appropriate response for the abnormal condition. If the QPTR remains above its specified limit, the peaking factor surveillances are required each 7 days thereafter to evaluate FNH and FQ(Z) with changes in power distribution. Relatively small changes are expected due to either burnup and xenon redistribution or correction of the cause for exceeding the QPTR limit.
A.4 Although FNH and FQ(Z) are of primary importance as initial conditions in the safety analyses, other changes in the power distribution may occur as the QPTR limit is exceeded and may have an impact on the validity of the safety analysis. A change in the power distribution can affect such reactor parameters as bank worths and peaking factors for rod malfunction accidents. When the QPTR exceeds its limit, it does not necessarily mean a safety concern exists. It does mean that there is an indication of a change in the gross radial power distribution that requires an investigation and evaluation that is accomplished by examining the incore power distribution. Specifically, the core peaking factors and the quadrant tilt must be evaluated because they are the factors that best characterize the core power distribution. This re-evaluation is required to ensure that, before increasing THERMAL POWER to above the limit of Required Action A.1, the reactor core conditions are consistent with the assumptions in the safety analyses.
(continued)
Watts Bar - Unit 2 B 3.2-26 (developmental) B
QPTR B 3.2.4 BASES ACTIONS A.5 (continued)
If the QPTR has exceeded the 1.02 limit and a re-evaluation of the safety analysis is completed and shows that safety requirements are met, the excore detectors are recalibrated to show a QPTR of 1.0 prior to increasing THERMAL POWER to above the limit of Required Action A.1.
This is done to detect any subsequent significant changes in QPTR.
Required Action A.5 is modified by a Note that states that the QPTR is not zeroed out until after the re-evaluation of the safety analysis has determined that core conditions at RTP are within the safety analysis assumptions (i.e., Required Action A.4). This Note is intended to prevent any ambiguity about the required sequence of actions.
A.6 Once the flux tilt is zeroed out (i.e., Required Action A.5 is performed), it is acceptable to return to full power operation. However, as an added check that the core power distribution at RTP is consistent with the safety analysis assumptions, Required Action A.6 requires verification that FQ(Z) and FNH are within their specified limits within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> of reaching RTP.
As an added precaution, if the core power does not reach RTP within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, but is increased slowly, then the peaking factor surveillances must be performed within 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> of the time when the ascent to power was begun. These Completion Times are intended to allow adequate time to increase THERMAL POWER to above the limit of Required Action A.1, while not permitting the core to remain with unconfirmed power distributions for extended periods of time.
Required Action A.6 is modified by a Note that states that the peaking factor surveillances may only be done after the excore detectors have been calibrated to show zero tilt (i.e., Required Action A.5). The intent of this Note is to have the peaking factor surveillances performed at operating power levels, which can only be accomplished after the excore detectors are calibrated to show zero tilt and the core returned to power.
(continued)
Watts Bar - Unit 2 B 3.2-27 (developmental) A
QPTR B 3.2.4 BASES ACTIONS B.1 (continued)
If Required Actions A.1 through A.6 are not completed within their associated Completion Times, the unit must be brought to a MODE or condition in which the requirements do not apply. To achieve this status, THERMAL POWER must be reduced to < 50% RTP within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />. The allowed Completion Time of 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> is reasonable, based on operating experience regarding the amount of time required to reach the reduced power level without challenging plant systems.
SURVEILLANCE SR 3.2.4.1 REQUIREMENTS SR 3.2.4.1 is modified by two Notes. Note 1 allows QPTR to be calculated with three power range channels if THERMAL POWER is
< 75% RTP and the input from one power range neutron flux channel is inoperable. Note 2 allows performance of SR 3.2.4.2 in lieu of SR 3.2.4.1 if more than one input from power range neutron flux channels are inoperable.
This Surveillance verifies that the QPTR, as indicated by the Nuclear Instrumentation System (NIS) excore channels, is within its limits. The Frequency of 7 days when the QPTR alarm is OPERABLE is acceptable because of the low probability that this alarm can remain inoperable without detection.
When the QPTR alarm is inoperable, the Frequency is increased to 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />. This Frequency is adequate to detect any relatively slow changes in QPTR, because for those changes of QPTR that occur quickly (e.g., a dropped rod), there typically are other indications of abnormality that prompt a verification of core power tilt.
SR 3.2.4.2 This Surveillance is modified by a Note, which states that it is required only when the input from one or more power range neutron flux channels are inoperable and the THERMAL POWER is 75% RTP.
(continued)
Watts Bar - Unit 2 B 3.2-28 (developmental) A
QPTR B 3.2.4 BASES SURVEILLANCE SR 3.2.4.2 (continued)
REQUIREMENTS With an NIS power range channel inoperable, tilt monitoring for a portion of the reactor core becomes degraded. Large tilts are likely detected with the remaining channels, but the capability for detection of small power tilts in some quadrants is decreased. Performing SR 3.2.4.2 at a Frequency of 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> provides an accurate alternative means for ensuring that any tilt remains within its limits.
For the purpose of monitoring the QPTR when the input from one or more power range neutron flux channels is inoperable, incore power distribution measurement information is used to confirm that the normalized symmetric power distribution is consistent with the indicated QPTR and the reference normalized symmetric power distribution. The incore power distribution measurement information can be used to generate an incore tilt. This tilt can be compared to the reference incore tilt to generate an incore QPTR. Therefore, incore QPTR can be used to confirm that excore QPTR is within limits.
The incore power distribution measurement information can be obtained from an OPERABLE Power Distribution Monitoring System (PDMS) (Ref.
4).
The reference normalized symmetric power distribution is available from the last incore power distribution measurement information used to calibrate the excore axial offset. The reference incore power distribution measurement information is obtained from an OPERABLE PDMS.
With the input from one or more power range neutron flux channels inoperable, the indicated QPTR may be changed from the value indicated with all four channels OPERABLE. To confirm that no change in tilt has actually occurred, which might cause the QPTR limit to be exceeded, the normalized quadrant tilt is compared against the reference normalized quadrant tilt. Nominally, quadrant tilt from the surveillance should be within 2% of the tilt shown by the reference incore power distribution measurement information.
REFERENCES 1. Title 10, Code of Federal Regulations, Part 50.46, "Acceptance Criteria for Emergency Core Cooling Systems for Light Water Nuclear Power Reactors."
Watts Bar - Unit 2 B 3.2-29 (developmental) B
QPTR B 3.2.4 BASES
- 2. Regulatory Guide 1.77, Rev. 0, "Assumptions Used for Evaluating a Control Rod Ejection Accident for Pressurized Water Reactors,"
May 1974.
- 3. Title 10, Code of Federal Regulations, Part 50, Appendix A, "General Design Criteria for Nuclear Power Plants," GDC 26, "Reactivity Control System Redundancy and Capability."
- 4. WCAP-12472-P-A, BEACON Core Monitoring and Operations Support System, August 1994 (Addendum 2, April 2002).
Watts Bar - Unit 2 B 3.2-30 (developmental) B