Technical Specification Task Force (TSTF) Traveler 363, Revision 0, Revise Topical Report References in Its 5.6.5, COLR
ML093100498
Person / Time
Site: Technical Specifications Task Force
Issue date: 12/11/2009
From: Rosenberg S
NRC/NRR/DPR/PSPB
To:
Technical Specifications Task Force
References
Download: ML093100498 (3)


Text

December 11, 2009 Technical Specifications Task Force 11921 Rockville Pike, Suite 100 Rockville, MD 20852

SUBJECT:

TECHNICAL SPECIFICATIONS TASK FORCE TRAVELER TSTF-363, REVISION 0, REVISE TOPICAL REPORT REFERENCES IN ITS 5.6.5, COLR

Dear TSTF Members,

The NRC staff issued a letter to the Technical Specifications Task Force (TSTF) on November 2, 2009 (Agencywide Documents Access and Management System (ADAMS)

Accession No. ML092151016), regarding TSTF Travelers TSTF-363, Revision 0, TSTF-408, Revision 1, and TSTF-419, Revision 0 (ADAMS Accession Nos. ML040630088, ML011630261, and ML012690234, respectively). These Travelers involve the relocation of Topical Report revisions and date citations from the Technical Specifications (TSs) to the Core Operating Limits Report and the Pressure and Temperature Limits Report.

This letter clarifies the letter and enclosure dated November 2, 2009. The agency has not finalized our position on this issue with regard to these travelers. The NRC staff is working with the TSTF to resolve concerns in this area. While the NRC staff and TSTF resolve concerns related to this matter, there may be significant delays in the review of license amendment requests implementing Travelers TSTF-363, Revision 0, TSTF-408, Revision 1, and TSTF-419, Revision 0.

The NRC staff is interested in meeting with the TSTF, to discuss concerns associated with Travelers TSTF-363, Revision 0, TSTF-408, Revision 1, and TSTF-419, Revision 0. It was discussed during the November 4, 2009, meeting, that a possible meeting time would be in January 2009. Please contact Michelle Honcharik at 301-415-1157 to schedule the meeting.

Sincerely,

/RA By Tom Blount For/

Stacey L. Rosenberg, Chief Special Projects Branch Division of Policy and Rulemaking Office of Nuclear Reactor Regulation Project No. 753 cc: See next page

ML040630088, ML011630261, and ML012690234, respectively). These Travelers involve the relocation of Topical Report revisions and date citations from the Technical Specifications (TSs) to the Core Operating Limits Report and the Pressure and Temperature Limits Report.

This letter clarifies the letter and enclosure dated November 2, 2009. The agency has not finalized our position on this issue with regard to these travelers. The NRC staff is working with the TSTF to resolve concerns in this area. While the NRC staff and TSTF resolve concerns related to this matter, there may be significant delays in the review of license amendment requests implementing Travelers TSTF-363, Revision 0, TSTF-408, Revision 1, and TSTF-419, Revision 0.

The NRC staff is interested in meeting with the TSTF, to discuss concerns associated with Travelers TSTF-363, Revision 0, TSTF-408, Revision 1, and TSTF-419, Revision 0. It was discussed during the November 4, 2009, meeting, that a possible meeting time would be in January 2009. Please contact Michelle Honcharik at 301-415-1157 to schedule the meeting.

Sincerely,

/RA By Tom Blount For/

Stacey L. Rosenberg, Chief Special Projects Branch Division of Policy and Rulemaking Office of Nuclear Reactor Regulation Project No. 753 cc: See next page DISTRIBUTION:

PUBLIC RidsOgcMailCenter RidsNrrDorlLpl1-2 John Hughey PSPB Reading File RidsAcrsAcnwMailCen RidsNrrDirsItsb Matthew Mitchell RidsNrrDpr ter RidsNrrDciCvib Gregory Cranston RidsNrrDprPspb RidsNrrDirs RidsNrrDssSrxb Benjamin Parks RidsNrrPMMHoncharik RidsNrrDe SRosenberg Tai Huang RidsNrrLADBaxley RidsNrrDorl (Hardcopy)

ADAMS Accession No.: ML093100498 NRR-106 OFFICE PSPB/LA PSPB/PM SRXB/BC ITSB/BC DORL/BC PSPB/BC NAME DBaxley (CHawes for) MHoncharik GCranston RElliott HChernoff SRosenberg (MHamm for)

DATE 11/18/09 12/11/09 12/11/09 12/11/09 12/11/09 12/11/09 Technical Specifications Task Force Project No. 753 Technical Specifications Task Force 11921 Rockville Pike Suite 100 Rockville, MD 20852 Attention: Donald Hoffman Telephone: 301-984-4400 E-mail: donaldh@excelservices.com Kenneth Schrader Diablo Canyon Power Plant Building 104/5/21A P.O. Box 56 Avila Beach, CA 93424 Telephone: 805-545-4328 E-mail: kjse@pge.com John Messina First Energy Nuclear Operating Company 76 South Main Street Mail Stop: Akron-GO-14 Akron, OH 44308 Telephone: 330-384-5878 E-mail: jmessina@firstenergycorp.com Thomas Raidy Southern California Edison Mail Stop D-3-E P.O. Box 128 San Clemente, CA 92672 Telephone: 949-368-7582 E-mail: Tom.Raidy@sce.com Wendy E. Croft Exelon Nuclear 200 Exelon Way, Suite 340 Kennett Square, PA 19348 Telephone: 610-765-5726 E-mail: Wendi.Croft@exeloncorp.com Brian Mann EXCEL Services Corporation 11921 Rockville Pike, Suite 100 Rockville, MD 20852 Telephone: 301-984-4400 E-mail: brianm@excelservices.com 4/22/09