MONTHYEARML24264A0232024-09-20020 September 2024 RAI TSTF-600, Rev. 0, Revise the Reactor Coolant System (RCS) Pressure Isolation Valve (PIV) Leakage Testing Frequency ML24249A1482024-09-11011 September 2024 Cover Letter for Final Traveler SE of TSTF 576, Revision 3, Revise Safety/Relief Valve Requirements ML24247A3162024-09-0606 September 2024 Cover Letter for Final Model SE of Traveler TSTF 592, Rev 2, Revise Automatic Depressurization System (ADS) Instrumentation Requirements ML24222A4002024-08-14014 August 2024 TSTF-602, Revise the Ventilation Filter Testing Program to Permit Alternate Challenge Agents, Acceptance Review Letter ML24106A2762024-08-0101 August 2024 Draft Safety Evaluation of Technical Specifications Task Force Traveler TSTF-576, Revision 3, Revise Safety/Relief Valve Requirements (EPID L -2019-PMP-0207) ML24207A1822024-07-25025 July 2024 TSTF-601, Extend Shield Building Completion Time After Refueling, Acceptance Review Letter ML24114A2572024-04-24024 April 2024 TSTF-599 Acceptance Review Letter ML24114A2652024-04-24024 April 2024 TSTF-597 Acceptance Review Letter ML23325A2132023-12-18018 December 2023 Cover Letter for Final Model SE of TSTF-591, Revise Risk Informed Completion Time (RICT) Program ML23262B2292023-09-21021 September 2023 Cover Letter Transmitting Final SE of TSTF-591, Revision 0, Revise Risk-Informed Completion Time (RICT) Program ML23124A2212023-09-11011 September 2023 Cover Letter for Final SEs of TSTF-589, Eliminate Automatic Diesel Generator (DG) Start During Shutdown ML23206A1242023-07-31031 July 2023 TSTF-584 Cover Letter for Final SE ML23205A2342023-07-0606 July 2023 Draft TSTF-601, Extend Shield Building Completion Time After Refueling ML23012A2812023-03-13013 March 2023 Draft SEs of TSTF-584, Eliminate Automatic RWCU System Isolation on SLC Initiation ML23059A3342023-02-28028 February 2023 TSTF-576 Open Issues Letter ML23010A2592023-01-11011 January 2023 Request for Additional Information Traveler TSTF-592, Revision 0, Revise Automatic Depressurization System (ADS) Instrumentation Requirements ML22272A5542022-10-0707 October 2022 Request for Additional Information Traveler TSTF-591, Revise Risk Informed Completion Time (RICT) Program TSTF-22-07, Transmittal of TSTF-592, Revision 0, Revise Automatic Depressurization System (ADS) Instrumentation Requirements2022-07-19019 July 2022 Transmittal of TSTF-592, Revision 0, Revise Automatic Depressurization System (ADS) Instrumentation Requirements ML22193A2372022-07-12012 July 2022 Request for Additional Information TSTF-589, Eliminate Automatic Diesel Generator Start During Shutdown TSTF-22-06, Technical Specifications Task Force - Request for a Workshop to Discuss the Interaction of Natural Phenomena Protection Design Features and Operability2022-07-0808 July 2022 Technical Specifications Task Force - Request for a Workshop to Discuss the Interaction of Natural Phenomena Protection Design Features and Operability ML22110A1712022-04-26026 April 2022 Acceptance for Review Regarding Traveler Tstf-584, Rev 0, Eliminate Automatic RWCU System Isolation on SLC Initiation TSTF-22-04, Technical Specifications Task Force - Transmittal of TSTF-591, Revision 0, Revise Risk Informed Completion Time (RICT) Program2022-03-22022 March 2022 Technical Specifications Task Force - Transmittal of TSTF-591, Revision 0, Revise Risk Informed Completion Time (RICT) Program ML21188A2782021-07-11011 July 2021 Cover Letter Transmitting Final SEs of CLIIP TSTF-580, Revision 1, Provide Exception from Entering Mode 4 with No Operable RHR (Residual Heat Removal) Shutdown Cooling TSTF-21-03, TSTF Response to NRC Questions on TSTF-576, Revision 0, Revise Safety/Relief Valve Requirements and Submittal of Revision 12021-06-23023 June 2021 TSTF Response to NRC Questions on TSTF-576, Revision 0, Revise Safety/Relief Valve Requirements and Submittal of Revision 1 ML21054A2512021-05-26026 May 2021 Cover Letter Transmitting Draft SEs of CLIIP TSTF-580, RHR Shutdown Cooling System - Hot Shutdown ML21106A2452021-04-20020 April 2021 Cover Letter Transmitting Final Model SE of TSTF 554, Revision 1, Revise Reactor Coolant Leakage Requirements ML21098A2422021-04-14014 April 2021 Cover Letter for Final SEs of TSTF-577, Revision 1, Revised Frequencies for Steam Generator Tube Inspections ML21068A4012021-03-24024 March 2021 Cover Letter for Draft SEs TSTF 577, Revision 1, Revised Frequencies for Steam Generator Tube Inspections TSTF-21-01, Transmittal of TSTF-580, Revision 1, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2021-01-26026 January 2021 Transmittal of TSTF-580, Revision 1, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling ML20322A3612020-12-18018 December 2020 TSTF-554 Cover Letter for Final SE ML20308A6562020-11-0606 November 2020 Request for Additional Information Traveler TSTF-577, Revision 0, Revised Frequencies for Steam Generator Tube Inspections ML20168A3962020-10-30030 October 2020 Cover Letter Transmitting Draft SE of TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements ML20265A1152020-10-0909 October 2020 Cover Letter Transmitting Model SE of TSTF-582 and TSTF-583-T ML20133J8832020-07-29029 July 2020 Letter Transmitting Draft SE of Traveler TSTF-582, Revision 0, RPV WIC Enhancements TSTF-20-04, Technical Specifications Task Force - Transmittal of TSTF-577, Revision 0, Revised Frequencies for Steam Generator Tube Inspections2020-06-0808 June 2020 Technical Specifications Task Force - Transmittal of TSTF-577, Revision 0, Revised Frequencies for Steam Generator Tube Inspections ML20133J8152020-05-13013 May 2020 Letter Transmitting Revised Final SE of Traveler TSTF-564, Revision 2, Safety Limit MCPR, Using the Consolidated Line Item Improvement Process ML20132A1832020-05-11011 May 2020 Request for Additional Information TSTF-576, Revision 0, Revised Safety/Relief Valve Requirement TSTF-20-01, Transmittal of TSTF-IG-20-02, Guidance on Evaluating One-Time Surveillance Frequency Changes Under the Surveillance Frequency Control Program (TSTF-425M SFCP)2020-04-0909 April 2020 Transmittal of TSTF-IG-20-02, Guidance on Evaluating One-Time Surveillance Frequency Changes Under the Surveillance Frequency Control Program (TSTF-425M SFCP) TSTF-19-14, Technical Specifications Task Force - TSTF Response to NRC Questions on TSTF-582, RPV WIC Enhancements2020-02-12012 February 2020 Technical Specifications Task Force - TSTF Response to NRC Questions on TSTF-582, RPV WIC Enhancements TSTF-19-11, TSTF Response to NRC Questions on TSTF-554, Revise Reactor Coolant Leakage Requirements2020-01-16016 January 2020 TSTF Response to NRC Questions on TSTF-554, Revise Reactor Coolant Leakage Requirements ML19325C4362019-12-17017 December 2019 Cover Letter Transmitting Final SEs of Traveler TSTF-568, Revision 2, Revise Applicability of BWR/4 TS 3.6.2.5 and TS 3.6.3.2 TSTF-19-09, Technical Specifications Task Force - Transmittal of TSTF-576, Revision 0, Revise Safety/Relief Valve Requirements2019-12-13013 December 2019 Technical Specifications Task Force - Transmittal of TSTF-576, Revision 0, Revise Safety/Relief Valve Requirements ML19323E9282019-12-10010 December 2019 Cover Letter Transmitting Final SEs of Traveler TSTF-541, Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position TSTF-19-13, Technical Specifications Task Force - Updated TSTF Membership and Distribution2019-12-0303 December 2019 Technical Specifications Task Force - Updated TSTF Membership and Distribution TSTF-19-12, TSTF Comments on Draft Safety Evaluations for Traveler TSTF-541, Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position.2019-11-0505 November 2019 TSTF Comments on Draft Safety Evaluations for Traveler TSTF-541, Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position. TSTF-19-10, Transmittal of Errata Changes to TSTF-541, Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position2019-08-28028 August 2019 Transmittal of Errata Changes to TSTF-541, Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position ML19176A1892019-08-14014 August 2019 Cover Letter Transmitting Final Safety Evaluations of Traveler TSTF-569, Revision 2, Revise Response Time Testing Definition TSTF-19-03, Request for Fee Exemption for TSTF-554, Revision 0, Revise Reactor Coolant Leakage Requirements - Letter2019-07-0808 July 2019 Request for Fee Exemption for TSTF-554, Revision 0, Revise Reactor Coolant Leakage Requirements - Letter TSTF-19-08, Draft of Traveler TSTF-582, Revision 0, RPV WIC Enhancements.2019-07-0303 July 2019 Draft of Traveler TSTF-582, Revision 0, RPV WIC Enhancements. TSTF-19-06, TSTF Comments on Draft Safety Evaluations for Traveler TSTF-569, Revision 1, Revise Response Time Testing Definition2019-06-25025 June 2019 TSTF Comments on Draft Safety Evaluations for Traveler TSTF-569, Revision 1, Revise Response Time Testing Definition 2024-09-06
[Table view] |
Text
November 2, 2009 Technical Specification Task Force 11921 Rockville Pike, Suite 100 Rockville, MD 20852
SUBJECT:
TECHNICAL SPECIFICATION TASK FORCE (TSTF) TRAVELER 363, REVISION 0, REVISE TOPICAL REPORT REFERENCES IN ITS 5.6.5, COLR
Dear TSTF Members,
TSTF Traveler 363, Revision 0, Revise Topical Report References in ITS [Improved Technical Specifications] 5.6.5, COLR [Core Operating Limits Report], (Agencywide Documents Access and Management System (ADAMS) Accession No. ML040630088) relocates Topical Report revisions and date citations from the TSs to the COLR. Similarly, TSTF Traveler 408, Revision 1, and TSTF Traveler 419, Revision 0, relocate Topical Report revisions and date citations from the TSs to the Pressure and Temperature Limits Report (ADAMS Accession Nos. ML011630261 and ML012690234, respectively). The NRC staff has identified concerns associated with these TSTF Travelers as discussed in the attached Enclosure.
The NRC staff requests a meeting with the members of the TSTF, to discuss approval and continued use of TSTF Travelers 363, Revision 0, 408, Revision 1, and 419, Revision 0. Please contact Michelle Honcharik at 301-415-1157 to schedule the meeting.
Sincerely,
/RA by McCoppin for/
Stacey L. Rosenberg, Chief Special Projects Branch Division of Policy and Rulemaking Office of Nuclear Reactor Regulation Project No. 753
Enclosure:
As stated cc w/encl: See next page
ML092151016
- Indicates Email Conc. NRR-106 OFFICE PSPB/LA PSPB/PM SRXB/BC ITSB/BC DORL/BC PSPB/BC NAME DBaxley MHoncharik* GCranston RElliott HChernoff SRosenberg (CHawes for) (w/comments)
DATE 8/4/09 11/2/09 10/27/09 11/2/09 10/22/09 11/2/09 Technical Specifications Task Force Project No. 753 Technical Specifications Task Force 11921 Rockville Pike Suite 100 Rockville, MD 20852 Attention: Donald Hoffman Telephone: 301-984-4400 E-mail: donaldh@excelservices.com Kenneth Schrader Diablo Canyon Power Plant Building 104/5/21A P.O. Box 56 Avila Beach, CA 93424 Telephone: 805-545-4328 E-mail: kjse@pge.com John Messina First Energy Nuclear Operating Company 76 South Main Street Mail Stop: Akron-GO-14 Akron, OH 44308 Telephone: 330-384-5878 E-mail: jmessina@firstenergycorp.com Thomas Raidy Southern California Edison Mail Stop D-3-E P.O. Box 128 San Clemente, CA 92672 Telephone: 949-368-7582 E-mail: Tom.Raidy@sce.com Wendy E. Croft Exelon Nuclear 200 Exelon Way, Suite 340 Kennett Square, PA 19348 Telephone: 610-765-5726 E-mail: Wendi.Croft@exeloncorp.com Brian Mann EXCEL Services Corporation 11921 Rockville Pike, Suite 100 Rockville, MD 20852 Telephone: 301-984-4400 E-mail: brianm@excelservices.com 4/22/09
Technical Specification Task Force Traveler 363, Revision 0, Revise Topical Report References in ITS 5.6.5, COLR Generic Letter (GL) 88-16, Removal of Cycle Specific Parameter Limits from Technical Specifications, provides guidance for licensees to relocate reactor physics parameters from the Technical Specifications (TS) to a licensee controlled document referred to as the Core Operating Limits Report (COLR) and add a listing of approved methodologies to the TS.
Similarly, GL 96-03, Relocation of The Pressure Temperature Limit Curves and Low Temperature Overpressure Protection System Limits, provides guidance for relocating reactor coolant system (RCS) pressure and temperature limits from the TS to a licensee controlled document referred to as the Pressure and Temperature Limits Report (PTLR).
GL 88-16 and GL 96-03 relocated the numerical values in TS Limiting Condition of Operations and added approved methodologies for calculating operating limits. This approach was considered to be acceptable so long as the Administrative Controls TS for the COLR or PTLR continued to provide a direct link to the specific methodology used to calculate the values previously listed in the TS. This arrangement would allow the actual values, previously listed in the TS, to be consistently reproduced and controlled. The guidance in GL 88-16 and GL 96-03 specifies the inclusion of Topical Report number, title, or other NRC approval document, and date in the TS for those parameters relocated to the COLR/PTLR. This approach links a particular parameter relocated to the COLR/PTLR to the specific analytical methodology that calculates the parameter. Reference to a specific revision of a methodology in the TS was deemed equivalent to listing a particular parameter in the TS that is calculated by the methodology.
Technical Specification Task Force (TSTF) Traveler 363, Revision 0, February 22, 2000, Revise Topical Report References in ITS [Improved Technical Specification] 5.6.5, COLR,1 relocates Topical Report revisions and date citations from the TS to the COLR. Consistent with TSTF Traveler 363, Revision 0, TSTF Traveler 408, Revision 1, May 2, 2001, Relocation of LTOP [Low-Temperature Overpressure Protection] Enable Temperature and PORV [Power Operated Relief Valve] Lift Setting to the PTLR2 and TSTF Traveler 419, Revision 0, May 2, 2001, Revise PTLR Definition and References in ISTS 5.6.6, RCS PTLR3 include relocation of Topical Report revisions and date citations from the TSs to the PTLR.
Removal of the Topical Report revision numbers or approval dates from the TS in accordance with the subject TSTF Travelers does not provide a direct link to specific TS numerical values relocated to the COLR/PTLR, since there is no reference to a specific methodology. The TSTF Travelers modify the TS removing reference to specific documents and, in effect, allow reference to a range of methodologies represented by various Topical Report revisions. Since the criterion contained in Title 10 of the Code of Federal Regulations Section 50.59(c)(2)(viii) allows licensees to use previously NRC-approved methodologies. This approach is not equivalent to listing a specific parameter in the TS. Therefore, the NRC staff has determined that relaxation of TS Topical Report documentation from the guidance provided in GL 88-16 and GL 96-03 was not appropriate. Therefore, the NRC staff no longer supports the position reflected in TSTF Travelers 363, Revision 0, 408, Revision 1, and 419, Revision 0.
1 Agencywide Documents Access and Management System (ADAMS) Accession No. ML040630088.
2 ADAMS Accession No. ML011630261.
3 ADAMS Accession No. ML012690234.
ENCLOSURE