MONTHYEARIR 05000272/20230042024-02-0505 February 2024 Integrated Inspection Report 05000272/2023004 and 05000311/2023004 ML24030A8752024-02-0101 February 2024 Operator Licensing Examination Approval IR 05000354/20230042024-02-0101 February 2024 Integrated Inspection Report 05000354/2023004 ML24009A1022024-01-26026 January 2024 Exemption from Select Requirements of 10 CF Part 73 (EPID L-2023-LLE-0045 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) IR 05000272/20234012024-01-22022 January 2024 Material Control and Accounting Program Inspection Report 05000272/2023401 and 05000311/2023401 IR 05000354/20234012024-01-22022 January 2024 Material Control and Accounting Program Inspection Report 05000354/2023401 ML23341A1372024-01-16016 January 2024 Issuance of Amendment No. 235 Revise Trip and Standby Auto-Start Logic Associated with Safety Related Heating, Ventilation and Air Conditioning ML24004A1542024-01-0808 January 2024 Notification of Conduct of a Fire Protection Team Inspection ML23307A1532023-12-15015 December 2023 NRC Investigation Report No. 1-2023-001 ML23335A1122023-12-15015 December 2023 Retest Schedule for Drywell to Suppression Chamber Vacuum Breakers LR-N23-0079, Special Report 23-02-00 Pursuant to the Requirements of Salem Unit 1 Technical Specification 3.3.3.7, Action 10, for the Unit 1 Main Steam Line Rad Monitor Inoperable for Greater than Seven Days2023-12-0707 December 2023 Special Report 23-02-00 Pursuant to the Requirements of Salem Unit 1 Technical Specification 3.3.3.7, Action 10, for the Unit 1 Main Steam Line Rad Monitor Inoperable for Greater than Seven Days LR-N23-0077, Loss of Coolant Accident Peak Cladding Temperature Margin Tracking - Annual Report 2023 & 30 Day Report for Salem Unit 1 Upflow Conversion2023-11-29029 November 2023 Loss of Coolant Accident Peak Cladding Temperature Margin Tracking - Annual Report 2023 & 30 Day Report for Salem Unit 1 Upflow Conversion ML23270C0072023-11-29029 November 2023 Notice of Proposed Amendment to Decommissioning Trust Agreement ML23324A3072023-11-17017 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000272/20230032023-11-13013 November 2023 Integrated Inspection Report 05000272/2023003 and 05000311/2023003 IR 05000354/20230032023-11-0707 November 2023 Integrated Inspection Report 05000354/2023003 LR-N23-0072, Core Operating Limits Report Cycle 302023-11-0101 November 2023 Core Operating Limits Report Cycle 30 IR 05000272/20234022023-10-12012 October 2023 and Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2023402, 05000272/2023402 and 05000311/2023402 (Cover Letter Only) IR 05000272/20230102023-10-12012 October 2023 Biennial Problem Identification and Resolution Inspection Report O5000272/2023010 and 05000311/2023010 LR-N23-0065, Submittal of 2023 Annual 10 CFR 50.46 Report2023-10-0202 October 2023 Submittal of 2023 Annual 10 CFR 50.46 Report LR-N23-0045, and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement2023-09-0808 September 2023 and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement ML23249A2612023-09-0606 September 2023 License Amendment Request to Modify the Salem and Hope Creek Exclusion Area Boundary IR 05000272/20230052023-08-31031 August 2023 Updated Inspection Plan for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2023005 and 05000311/2023005) IR 05000354/20230052023-08-31031 August 2023 Updated Inspection Plan for Hope Creek Generating Station (Report 05000354/2023005) ML23233A0762023-08-21021 August 2023 Requalification Program Inspection ML23192A8212023-08-14014 August 2023 and Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Issuance of Amendment Nos. 234, 347, and 329 Revise Technical Specifications to Delete Meteorological Tower Location IR 05000272/20230022023-08-0909 August 2023 Integrated Inspection Report 05000272/2023002 and 05000311/2023002 LR-N23-0055, Special Report 272/23-01-00, Pursuant to the Requirements of Technical Specification 3.3.3.1, Action 23, for the Vent Noble Gas Rad Monitor Inoperable for Greater than Seven Days2023-08-0303 August 2023 Special Report 272/23-01-00, Pursuant to the Requirements of Technical Specification 3.3.3.1, Action 23, for the Vent Noble Gas Rad Monitor Inoperable for Greater than Seven Days IR 05000354/20230022023-08-0303 August 2023 Integrated Inspection Report 05000354/2023002 and Independent Spent Fuel Storage Installation Inspection Report 07200048/2023001 IR 05000354/20230102023-08-0303 August 2023 Biennial Problem Identification and Resolution Inspection Report 05000354/2023010 LR-N23-0052, Retest Schedule for Drywell to Suppression Chamber Vacuum Breakers Per Technical Specification 4.6.2.12023-07-31031 July 2023 Retest Schedule for Drywell to Suppression Chamber Vacuum Breakers Per Technical Specification 4.6.2.1 LR-N23-0054, In-Service Inspection Activities2023-07-26026 July 2023 In-Service Inspection Activities LR-N23-0042, Spent Fuel Cask Registration2023-07-12012 July 2023 Spent Fuel Cask Registration LR-N23-0046, Emergency Plan Document Revisions Implemented June 28, 20232023-07-10010 July 2023 Emergency Plan Document Revisions Implemented June 28, 2023 LR-N23-0005, License Amendment Request to Amend Technical Specifications (TS) 6.8.4.f for Permanent Extension of Type a and Type C Leak Rate Test Frequencies2023-06-23023 June 2023 License Amendment Request to Amend Technical Specifications (TS) 6.8.4.f for Permanent Extension of Type a and Type C Leak Rate Test Frequencies ML23139A1472023-06-0505 June 2023 Relief Request Associated with Fourth Interval In-service Inspection Limited Examinations of Weld Coverage ML23096A1842023-05-0909 May 2023 Issuance of Amendment No. 328 Revise and Relocate Reactor Coolant System Pressure and Temperature Limits and Pressurizer Overpressure Protection System Limits to Pressure and Temperature Limits Report IR 05000272/20230012023-05-0303 May 2023 Integrated Inspection Report 05000272/2023001 and 05000311/2023001 ML23081A4662023-05-0202 May 2023 Issuance of Amendment Nos. 346 and 327 Revise Technical Specifications to Extend Allowable Outage Time for Inoperable Emergency Diesel Generator IR 05000272/20233012023-05-0101 May 2023 Initial Operator Licensing Examination Report 05000272/2023301 and 05000311/2023301 ML23121A1412023-05-0101 May 2023 Senior Reactor and Reactor Operator Initial License Examinations IR 05000354/20230112023-05-0101 May 2023 Commercial Grade Dedication Report 05000354/2023011 LR-N23-0035, 2022 Annual Radioactive Effluent Release Report (ARERR)2023-04-27027 April 2023 2022 Annual Radioactive Effluent Release Report (ARERR) LR-N23-0034, 2022 Annual Radiological Environmental Operating Report (AREOR) - Salem Nuclear Generating Station, Unit Nos. 1 and 2 and Hope Creek Generating Station2023-04-27027 April 2023 2022 Annual Radiological Environmental Operating Report (AREOR) - Salem Nuclear Generating Station, Unit Nos. 1 and 2 and Hope Creek Generating Station LR-N23-0033, Core Operating Limits Report Cycle 272023-04-26026 April 2023 Core Operating Limits Report Cycle 27 IR 05000354/20230012023-04-26026 April 2023 Integrated Inspection Report 05000354/2023001 LR-N23-0010, License Amendment Request Revision of Technical Specification (TS) to Delete TS Section 5.5 - Meteorological Tower Location2023-04-21021 April 2023 License Amendment Request Revision of Technical Specification (TS) to Delete TS Section 5.5 - Meteorological Tower Location LR-N23-0009, License Amendment Request (LAR) to Revise the Hope Creek Trip and Standby Auto-start Logic Associated with Safety Related Heating, Ventilation and Air Conditioning (HVAC) Trains2023-04-18018 April 2023 License Amendment Request (LAR) to Revise the Hope Creek Trip and Standby Auto-start Logic Associated with Safety Related Heating, Ventilation and Air Conditioning (HVAC) Trains ML23087A1492023-04-17017 April 2023 NRC to PSEG Salem, Transmittal of the National Marine Fisheries Service'S March 24, 2023, Biological Opinion GAR-2020-02842 Concerning Salem and Hope Creek 2024-02-05
[Table view] |
Text
October 15, 2009 Mr. Thomas Joyce President and Chief Nuclear Officer PSEG Nuclear LLC P.O. Box 236 Hancocks Bridge, NJ 08038
SUBJECT:
NOTICE OF INTENT TO PREPARE AN ENVIRONMENTAL IMPACT STATEMENT AND CONDUCT SCOPING PROCESS FOR LICENSE RENEWAL FOR THE SALEM NUCLEAR GENERATING STATION UNITS 1 AND 2, AND THE HOPE CREEK GENERATING STATION
Dear Mr. Joyce:
The U.S. Nuclear Regulatory Commission staff (NRC or the staff) has received your applications dated August 18, 2009, for the renewal of the Operating Licenses DPR-70, DPR-75, and NPF-57 for Salem Nuclear Generating Station (SALEM) Units 1 and 2, and Hope Creek Generating Station (HCGS), respectively. In support of each application and in accordance with Title 10 of the Code of Federal Regulations (10 CFR) Part 51 and 10 CFR Part 54, Public Service Enterprise Group Nuclear, LLC (PSEG Nuclear) and Exelon Generation Company, LCC (EGC) also submitted environmental reports (ER) for SALEM and HCGS. This letter provides information related to the staffs environmental reviews of the applications.
The NRC has prepared a notice of intent advising the public that the NRC intends to gather information necessary to prepare a plant-specific supplement to the Commissions Generic Environmental Impact Statement for License Renewal of Nuclear Plants, (NUREG-1437) related to the review of the applications for the renewal of the SALEM and HCGS operating licenses. Enclosed is a copy of the Notice of Intent, which have been forwarded to the Office of the Federal Register for publication.
Pursuant to 10 CFR 51.28, PSEG Nuclear and EGC are invited to participate in the environmental scoping process. As discussed in the enclosed notice, the staff is providing the public with the opportunity to participate in two environmental scoping meetings to be held Thursday, November 5, 2009. The meetings will be held at Salem County Emergency Services Building, 135 Cemetery Road, Woodstown, New Jersey 08098. The first session will be held in the afternoon, and the second session, covering the same subjects, will be held in the evening.
The NRC will present an overview of the environmental review process and will describe how the process will be implemented for the review of the SALEM and HCGS license renewal applications.
A separate NRC meeting notice with a more detailed agenda is forthcoming. You will be provided a copy of that notice.
In the interim, should you have any questions regarding the scoping meeting, please contact the NRCs Environmental Project Manager, Mr. Eccleston, at 301-415-8537 or by e-mail at charles.eccleston@nrc.gov.
Sincerely,
/RA/
Bo M. Pham, Chief Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-272, 50-311, 50-354 Enclosures As stated cc w/encls: See next page
Package (ML092740417), Letter (ML092740412), FRN (ML092740421)
OFFICE LA:DLR PM:DLR:RPB2 PM:DLR:RPB1 PM:DLR:RPB1 OGC NAME SFigueroa N.Ferrer C.Eccleston D.Ashley BHarris DATE 10/6/09 10/8/09 10/9/09 10/14/09 10/14/09 OFFICE BC:DLR:RPB1 AME B. Pham DATE 10/15/09
Letter to PSEG Nuclear from B. Pham, dated October 15, 2009 DISTRIBUTION:
SUBJECT:
NOTICE OF INTENT TO PREPARE AN ENVIRONMENTAL IMPACT STATEMENT AND CONDUCT SCOPING PROCESS FOR LICENSE RENEWAL FOR THE SALEM NUCLEAR GENERATING STATION UNITS 1 AND 2, AND THE HOPE CREEK GENERATING STATION HARD COPY:
DLR RF E-MAIL:
PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RdsNrrDlrRer1 Resource RidsNrrDlrRer2 Resource RidsOgcMailCenter Resource
DPelton DAshley JRobinson REnnis MModes, RI DKern, RI JBrand, RI RConte, RI RBellamy, RI PBamford, RI MMcLaughlin, RI
Hope Creek Generating Station and Salem Nuclear Generating Station, Unit Nos. 1 and 2 cc:
Mr. Thomas Joyce Mr. James Mallon President and Chief Nuclear Officer Manager - Licensing PSEG Nuclear LLC PSEG Nuclear One Alloway Creek Neck Road P.O. Box 236 Hancocks Bridge, NJ 08038 Hancocks Bridge, NJ 08038 Mr. Dennis Winchester Mr. Jeffrie J. Keenan, Esquire Vice President - Nuclear Assessment Manager - Licensing PSEG Nuclear PSEG Nuclear LLC P.O. Box 236 One Alloway Creek Neck Road Hancocks Bridge, NJ 08038 Hancocks Bridge, NJ 08038 Mr. Robert Braun Mr. Michael Gaffney Site Vice President - Salem Manager - Hope Creek Regulatory PSEG Nuclear LLC Assurance One Alloway Creek Neck Road PSEG Nuclear LLC Hancocks Bridge, NJ 08038 One Alloway Creek Neck Road Hancocks Bridge, NJ 08038 Mr. George Barnes Site Vice President - Hope Creek Mr. Steven Mannon PSEG Nuclear Manager - Salem Regulatory Assurance P.O. Box 236 P.O. Box 236 Hancocks Bridge, NJ 08038 Hancocks Bridge, NJ 08038 Mr. Carl Fricker Township Clerk Vice President - Operations Support Lower Alloways Creek Township PSEG Nuclear LLC Municipal Building, P.O. Box 157 One Alloway Creek Neck Road Hancocks Bridge, NJ 08038 Hancocks Bridge, NJ 08038 Mr. Paul Bauldauf, P.E., Asst. Director Mr. George Gellrich Radiation Protection Programs Plant Manager - Salem NJ Department of Environmental PSEG Nuclear Protection and Energy, CN 415 P.O. Box 236 Trenton, NJ 08625-0415 Hancocks Bridge, NJ 08038 Mr. Brian Beam Mr. Larry Wagner Board of Public Utilities Site Vice President - Hope Creek 2 Gateway Center, Tenth Floor PSEG Nuclear LLC Newark, NJ 07102 One Alloway Creek Neck Road Hancocks Bridge, NJ 08038 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406
Hope Creek Generating Station and Salem Nuclear Generating Station, Unit Nos. 1 and 2 cc:
Senior Resident Inspector Mr. Ali Fakhar Salem Nuclear Generating Station Manager, License Renewal U.S. Nuclear Regulatory Commission PSEG Nuclear LLC Drawer 0509 One Alloway Creek Neck Road Hancocks Bridge, NJ 08038 Hancocks Bridge, NJ 08038 Mr. Michael Gallagher Mr. William Mattingly Vice President - License Renewal Projects Manager - Salem Regulatory Assurance Exelon Nuclear LLC PSEG Nuclear LLC 200 Exelon Way One Alloway Creek Neck Road Kennett Square, PA 19348 Hancocks Bridge, NJ 08038 Mr. Ed Eilola Mr. Earl R. Gage Plant Manager - Salem Salem County Administrator PSEG Nuclear LLC Administration Building One Alloway Creek Neck Road 94 Market Street Hancocks Bridge, NJ 08038 Salem, NJ 08079 Mr. Larry Wagner Senior Resident Inspector Plant Manager - Hope Creek Hope Creek Generating Station PSEG Nuclear LLC U.S. Nuclear Regulatory Commission One Alloway Creek Neck Road Drawer 0509 Hancocks Bridge, NJ 08038 Hancocks Bridge, NJ 08038 Mr. Paul Davison Director - Nuclear Oversight PSEG Nuclear LLC One Alloway Creek Neck Road Hancocks Bridge, NJ 08038 Ms. Christine Neely Director - Regulator Affairs PSEG Nuclear LLC One Alloway Creek Neck Road Hancocks Bridge, NJ 08038