ML091120062

From kanterella
Jump to navigation Jump to search

Post Exam Comment Miscellaneous References (Folder 1)
ML091120062
Person / Time
Site: Millstone Dominion icon.png
Issue date: 03/31/2009
From:
Dominion Nuclear Connecticut
To: Caruso J
Operations Branch I
Hansell S
Shared Package
ML082600232 List:
References
50-336/09-301, TAC U01634, FOIA/PA-2011-0115 50-336/09-301
Download: ML091120062 (31)


Text

Q-35 (RO & I-SRO)

RO Question #2 The plant was operating at 100% power with all equipment in a normal alignment. Bus 24C is supplying Bus 24E. The "C" RBCCW Pump suddenly trips on fault. The Balance of Plant (BOP) operator starts the "B RBCCW Pump to supply Facility 2 and places the 'C' RBCCW Pump handswitch in Pull-To-Lock. NO other operator action is taken.

Then, a circuit failure in the Facility 2 ESAS Actuation Cabinet causes an inadvertent actuation of SIAS, CIAS, EBFAS and UV ALL plant systems and components function as designed (including those driven by the Facility 2 inadvertent actuation).

Which of the following correctly describes the condition of the RBCCW Pumps and Heat Exchanger TCVs based on the inadvertent ESAS actuation?

A The 'A' and 'B' RBCCW Pumps are running.

'A' heat exchanger TCV throttling on temperature.

This choice is technically correct.

'B' and 'C' heat exchanger TCVs full open. The following slides explain why.

B The 'A' and 'B' RBCCW Pumps are running.

'A' and 'B' heat exchanger TCVs throttling on temperature.

'C' heat exchanger TCVs full open.

C Only the 'A' RBCCW Pump is running This is the choice designated as

'A' heat exchanger TCV throttling on temperature.

'B' and 'C' heat exchanger TCVs full open. correct on the exam as given.

D Only the 'A' RBCCW Pump is running

'A' and 'B' heat exchanger TCVs throttling on temperature.

'C' heat exchanger TCVs full open.

Q-35 (RO & I-SRO)

The next three slides are pages from the Loss of RBCCW Abnormal Operating Procedure, AOP-2564 B RBCCW Pump SIAS/LNP Start Block Switch Explanation

Q-35 (RO & I-SRO)

Loss of RBCCW AOP-2564 Page 3, Step 1.2, Discussion Section Purpose and Function of the SIAS/LNP Block Switch

Q-35 (RO & I-SRO)

Loss of RBCCW AOP-2564 Page 15, Step 6.1 C RBCCW Pump Trip

Q-35 (RO & I-SRO)

Loss of RBCCW AOP-2564 Page 16, Step 6.1g C RBCCW Pump Trip, Start the B RBCCW Pump

Q-35 (RO & I-SRO)

The next slide is a page from the RBCCW System Normal Operating Procedure, OP-2330A Includes additional info on the SIAS/LNP Block Switch

Q-35 (RO & I-SRO)

RBCCW System Procedure, OP-2330A, Page 11, Step 4.2, Shifting From A RBCCW Pump to B RBCCW Pump Additional info on the SIAS/LNP Block Switch

Q-35 (RO & I-SRO)

B RBCCW Pump 4160 VAC Breaker on 24E The B RBCCW Pump SIAS/LNP is in Block Switch, located on the pump breaker cubicle front panel.

Shown in the BLOCK position.

BLOCK position RBCCW PUMP B SIAS/LNP START MANUALLY BLOCKED annunciator on C-06/7 will alarm when the B RBCCW Pump handswitch is NOT in Pull-To-Lock and this switch is in BLOCK.

Q-35 (RO & I-SRO)

RBCCW Heat Exchangers Temperature Control Valves (TCV)

Q-35 (RO & I-SRO)

Q-35 (RO & I-SRO)

SIAS on either facility will fail 2-SW-8.1B full open

Q-77/2 (I-SRO/SRO)

SRO Question #2 I-SRO Question #77 While performing a plant cooldown, the crew was about to place Shutdown Cooling (SDC) in service with "A" and "B" Reactor Coolant Pumps (RCPs) in service when Pressurizer Pressure Narrow Range Instrument, P-103-1, suddenly fails high.

Which of the following describes the impact of this failure and the action that the US must direct to stabilize the plant?

A The "A" Power Operated Relief Valve (PORV) will open and RCS pressure will rapidly lower.

Place the "A" LTOP switch to 'High',

g , close PORV Block Valve,, secure the "A" & "B RCPs,, and place SDC in service.

Correct Answer as given, which is believed to be invalid B The Facility 1 Safety Injection Tank (SIT) Outlet Valves will open causing the SITs to inject.

Override and close the SIT Outlet Valves and restore Pressurizer level to the desired setpoint.

C SDC Suction Isolation Valve, SI-652, will NOT open until the high pressure input is cleared.

Direct I&C to bypass or disconnect Pressurizer Pressure Narrow Range Instrument, P-103-1.

D The "B" Power Operated Relief Valve (PORV) will open and RCS pressure will rapidly lower.

Immediately place the associated PORV Block Valve to 'Close' and log into the LTOP Technical Specification LCO.

Q-77/2 (I-SRO/SRO)

Slide is from Reactor Coolant System L.P. RCS-00-C Pressurizer Pressure Instruments 2 transmitters (PT-103/103-1) provide signals to:

Low temperature over pressure protection.

Low range (0-1600 (0 1600 psia) indication on C03C03.

Indication of both on C-21 panel.

SDC suction valve interlock Prevent suction valve from opening with RCS >265 psia.

Alarm if on SDC and > 280 psia.

Auto opening of SIT isolation valves at 300 psia increasing.

Q-77/2 (I-SRO/SRO)

The next slide is a page from the Shutdown Cooling System Text, SDC-00-C Explanation of How P-103 & P-103-1 Effect SI-651 & SI-652

Q-77/2 (I-SRO/SRO)

Effect of P-103 & P-103-1 High Pressure (real or failed) with SI-651 & SI-652 CLOSED Effect of P-103 & P-103-1 High Pressure (real or failed) with SI-651 & SI-652 OPEN

Q-77/2 (I-SRO/SRO)

Alarm response for P-103-1 high and with SI-651 OPEN.

Loss of Shutdown Cooling Procedure, AOP-2572, is not referenced.

SI-651 will not open p until the failed instrument, P-103-1, is repaired or bypassed by I&C.

Q-77/2 (I-SRO/SRO)

Alarm response for P-103 high and with SI-652 OPEN.

Loss of Shutdown Cooling Procedure, AOP-2572, is not referenced.

SI-652 will not open p until the failed instrument, P-103, is repaired or bypassed by I&C.

Next Slide

Q-77/2 (I-SRO/SRO)

Cut-Away of P-103 RCS Pressure input to SI-652 OPEN permissive, from P&ID 25203-32008, Sh. 33 SI-652 can not be opened until the failed instrument, P-103, is repaired or bypassed by I&C.

Q-77/2 (I-SRO/SRO)

The next slide is a page from the Loss of Shutdown Cooling Abnormal Operating Procedure, AOP-2572 This is Thi i the th procedure d the th operators would normally use for guidance on the recovery of SDC as an RCS heat sink.

Q-77/2 (I-SRO/SRO)

Because there is no impact on the Shutdown Cooling System if P-103 or P-103-1 were to fail high with SI-651

& SI-652 OPEN, the Loss of Shutdown Cooling Procedure, AOP-2572, does not have guidance for this failure.

With SI-651 or SI-652 closed, SDC would not yet be in service. This scenario is addressed byy the Alarm Response Procedure (following slide).

The question did not intend to solicit operator actions outside of written procedural guidance.

Q-98/23 (I-SRO/SRO)

SRO Question #23 I-SRO Question #98 A Fuel Handling Accident has occurred inside Containment as evidenced by several Containment process and area radiation monitors rising or in alarm. All personnel were immediately evacuated.

In order to limit personnel exposure, per AOP-2577 (Fuel Handling Accident), the Shift Manager must ensure which of the following are performed?

A The Containment (Outage) Equipment Hatch must be closed no more than 30 minutes after the event. Correct Answer as given B Containment Purge Valves, AC-4, 5, 6, and 7 must be closed no more than 50 minutes after the event.

C The Transfer Tube Isolation Valve, RW-280, must be closed no more than 50 minutes after the event.

D One train of CRACS must be operating in Recirculation mode no more than 30 minutes after the event. Suggested Additional Correct Answer

Q-98/23 (I-SRO/SRO)

The next three slides are excerpts from the Alternate Source Term presentation given in License Operator Requalification Training (LORT) that all License Upgrade candidates attended.

Tech. Spec. Changes -

Alternate Source Term Cycle 07-6 Operator Training C07601

Q-98/23 (I-SRO/SRO)

Tech. Spec. Changes -

Alternate Source Term Partial implementation overview Done in Sept. - Nov. 2004 Initial changes g to allow relaxation of CTMT and SFP closure during outages.

Change calculated doses due to FHA in CTMT or SFP Change times for isolating and going to recirc.

in CR Changes due to a cask drop in SFP

Q-98/23 (I-SRO/SRO)

Tech. Spec. Changes -

Alternate Source Term Full implementation phase overview Done 08/29/07 Implement Reg. Guide 1.183 as basis for source term.

Allow a consistent Design Basis for all accident dose assessments.

Allow more Cont. Room In-leakage Allow more CTMT by-pass leakage Allow more RWST valve backleakage (IST)

Increased Pri.-to-Sec. Leakrate limit Re-define Dose Equivalent I-131 Allow more time, (1 hr), for Cont. Rm. Isolation & recirc.

Allow more time for termination of CS (4 hrs)

Q-98/23 (I-SRO/SRO)

Tech. Spec. Changes -

Alternate Source Term Technical Specification Basis Changes

Q-98/23 (I-SRO/SRO)

The next slide is page 21 from the Unit 2 EOP Users Guide Procedure, OP-2260 OP-2260 contains information that explains what changed to alter the correct choice for Question #98.

Q-98/23 (I-SRO/SRO)

The is a page from the Unit 2 EOP Users Guide Procedure, OP-2260 Change #3 was made to accommodate the change in the Alternate Source Term.

Q-98/23 (I-SRO/SRO)

The next three slides are excerpts from the Fuel Handling Accident Abnormal Operating Procedure, AOP-2577 AOP-2577 contains information used to develop the original question.

The following slides also explain what changed to alter the correct choice.

Q-98/23 (I-SRO/SRO)

Excerpts from the Fuel Handling Accident Abnormal Operating Procedure, AOP-2577 Information used to develop the original question.

Information that changed in Administrative Requirements, but has not yet been changed in AOP-2577.

Q-98/23 (I-SRO/SRO)

Excerpts from the Fuel Handling Accident Abnormal Operating Procedure, AOP-2577 Procedure use guidelines dictate that, due to the order of the steps in the procedure, the action to place CRACS in recirculation mode must be started before the action to close the Containment Equipment Hatch (VERIFY Containment Closure established).

Additional procedural guidance given in Step 3.6, next slide.

Q-98/23 (I-SRO/SRO)

Excerpts from the Fuel Handling Accident Abnormal Operating Procedure, AOP-2577 Some Examinees felt that the order of the procedure steps implies that the actions directed before the Containment Closure step must be started within any existing time limit for the action to VERIFY Containment Closure is established (original correct answer to the question).