Revised Schedule for Appendix K Measurement Uncertainty Recapture (MUR) Power Uprate Request - Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2
ML090130145
Person / Time
Site: Calvert Cliffs  Constellation icon.png
Issue date: 01/27/2009
From: Pickett D
Plant Licensing Branch 1
To: Spina J
Calvert Cliffs
Pickett D
References
TAC MD9554, TAC MD9555
Download: ML090130145 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 Mr. James A. Spina, Vice President Calvert Cliffs Nuclear Power Plant, Inc.

Calvert Cliffs Nuclear Power Plant 1650 Calvert Cliffs Parkway Lusby, MD 20657-4702

SUBJECT:

REVISED SCHEDULE FOR APPENDIX K MEASUREMENT UNCERTAINTY RECAPTURE (MUR) POWER UPRATE REQUEST - CALVERT CLIFFS NUCLEAR POWER PLANT, UNIT NOS. 1 AND 2 (TAC NOS. MD9554 AND MD9555)

Dear Mr. Spina:

By application dated August 29,2008, the Calvert Cliffs Nuclear Power Plant, Inc. (the licensee) submitted license amendment requests for Renewed Operating License Nos. DPR-53 and DPR-69 to increase the licensed core power for the Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2. Based on the implementation of more accurate feedwater flow measurement instrumentation, approval is being sought to increase the licensed core power by 1.38 percent from 2700 mega-watts thermal (MWt) to 2737 MWt.

In the application, the licensee requested that the Nuclear Regulatory Commission (NRC) develop a review schedule to support issuance of the license amendments by March 1, 2009.

The requested schedule is consistent with NRC goals of completing MUR power uprate reviews within 6 months following the staff's acceptance review. In order to meet this schedule, a verbal agreement was made between the NRC staff and the licensee that all requests for additional information (RAls) would be provided during the first week of November 2008 and the licensee would provide responses by December 31,2008.

By letter dated December 30, 2008, the licensee stated that they were unable to provide responses to all RAls "due to emergent plant related issues and the timing of the completion of the vendor testing and the vendor's flow uncertainty calculations." The licensee stated that they intend to provide responses to the remaining RAls by February 18, 2009, and requested a revised NRC completion date of April 20, 2009.

The NRC staff is disappointed that the licensee was not able to meet our expectations in responding to the RAls by the mutually agreed upon date of December 31,2008. The staff has set a high standard to industry by committing to complete reviews of MUR power uprates within 6 months following the staff's acceptance review. In order to meet this standard, the staff makes a diligent effort to make the necessary staff resources available. In taking these steps, it is expected that licensees will make every reasonable effort to meet their commitments and promptly notify the staff if they suspect otherwise.

The NRC staff acknowledges that the licensee provided a significant portion of the RAI responses by the agreed upon date. In consideration of this, the staff has chosen not to take more stringent actions such as termination or suspension of the amendment requests.

J. Spina

- 2 We understand that you intend to provide complete responses to the NRC staff's RAls by February 18, 2009. We urge you to take the appropriate steps to meet this date and keep the staff informed if additional delays are foreseen. However, we may not have the necessary expertise available to resume the review at that time. Higher priority outage requests for other dockets may result in the staff deferring work on the Calvert Cliffs MUR power uprate. As such, we may not be able to meet your requested completion date of April 20, 2009.

Please feel free to contact me at 301-415-1364 if you believe we have mischaracterized the ongoing review or if there are other mitigating circumstances such as the NRC staff's RAls were unreasonable, unexpected, or inconsistent with other docketed MUR reviews.

Sincerely,

~'-

v f Jt.Jlk Douglas V. Pickett, Senior Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-317 and 50-318 cc: Distribution via Listserv

J. Spina

- 2 We understand that you intend to provide complete responses to the NRC staff's RAls by February 18, 2009. We urge you to take the appropriate steps to meet this date and keep the staff informed if additional delays are foreseen. However, we may not have the necessary expertise available to resume the review at that time. Higher priority outage requests for other dockets may result in the staff deferring work on the Calvert Cliffs MUR power uprate. As such, we may not be able to meet your requested completion date of April 20, 2009.

Please feel free to contact me at 301-415-1364 if you believe we have mischaracterized the ongoing review or if there are other mitigating circumstances such as the NRC staff's RAls were unreasonable, unexpected, or inconsistent with other docketed MUR reviews.

Sincerely, IRA!

Douglas V. Pickett, Senior Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-317 and 50-318 cc: Distribution via Listserv Distribution:

PUBLIC RidsNrrLASLittle RidsOgcMailCenter Resource GDentel, R1 LPLI-1 r/f RidsNrrPMDPickett RidsAcrsAcnwMailCenter RidsNrrDpr RidsNrrDorlLpi-1 RidsNrrDprPgcb TAlexion, PGCB RidsNrrDorl ADAMS Accession No ML090130145 OFFICE LPLI-1/PM LPLI-1/LA PGCB/BC LPLI-1/BC NAME DPickett SLittie MMurphy MKowal DATE 01 123/09 01 121 109 01 123/09 01 127/09 OFFICIAL RECORD COpy