MONTHYEARML0824706232008-08-29029 August 2008 License Amendment Request: Appendix K Measurement Uncertainty Recapture - Power Uprate Request Project stage: Request ML0826703842008-09-24024 September 2008 Acceptance Review for Appendix K Measurement Uncertainty Recapture Application Project stage: Acceptance Review ML0827401442008-10-0303 October 2008 Request for Additional Information for License Amendment for Measurement Uncertainty Recapture Power Uprate- Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2 Project stage: RAI ML0828102202008-10-15015 October 2008 Request for Additional Information License Amendment for Measurement Uncertainty Recapture Power Uprate-Calvert Cliffs Nuclear Power Plant, Unit 1 and 2- Project stage: RAI ML0830400232008-11-0404 November 2008 Request for Additional Information License Amendment for Measurement Uncertainty Recapture Power Uprate-Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2 Project stage: RAI ML0831006242008-11-17017 November 2008 Request for Additional Information, License Amendment for Measurement Uncertainty Recapture Power Uprate Project stage: RAI ML0834300102008-12-0303 December 2008 Response to Request for Additional Information - License Amendment for Measurement Uncertainty Recapture Power Uprate Project stage: Response to RAI ML0834300122008-12-0303 December 2008 Bg&E Calculation CA00800, Total Loop Uncertainty Calculation for the Plant Computers Determination of Main Feedwater Pump Discharge Pressure, Revision 1 Project stage: Other ML0836500562008-12-29029 December 2008 Response to Request for Additional Information License Amendment for Measurement Uncertainty Recapture Power Uprate Project stage: Response to RAI ML0900203822008-12-29029 December 2008 Response to Request for Additional Information Measurement Uncertainty Recapture Power Uprate Project stage: Response to RAI ML0912401062008-12-30030 December 2008 Response to Request for Additional Information - License Amendment for Measurement Uncertainty Recapture Power Uprate Project stage: Response to RAI ML0901301452009-01-27027 January 2009 Revised Schedule for Appendix K Measurement Uncertainty Recapture (MUR) Power Uprate Request - Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2 Project stage: Other ML0905003982009-02-17017 February 2009 Response to Request for Additional Information on License Amendment for Measurement Uncertainty Recapture Power Uprate Project stage: Response to RAI ML0906307502009-02-18018 February 2009 Response to Request for Additional Information License Amendment for Measurement Uncertainty Recapture Power Uprate Project stage: Response to RAI ML0907705322009-03-24024 March 2009 Request for Additional Information License Amendment for Measurement Uncertainty Recapture Power Uprate - Calvert Cliffs Nuclear Power Plant, Units 1 & 2 - Project stage: RAI ML0907900242009-03-24024 March 2009 Request for Additional Information License Amendment for Measurement Uncertainty Recapture Power Uprate - Calvert Cliffs Nuclear Power Plant, Units 1 & 2 Project stage: RAI ML0906403082009-03-26026 March 2009 Request for Withholding Information from Public Disclosure for Calvert Cliffs Nuclear Power Plant Unit Nos. 1 and 2 (Tac Nos. MD9554 and MD955) Project stage: Withholding Request Acceptance ML0913101692009-05-0707 May 2009 Response to Request for Additional Information - License Amendment for Measurement Uncertainty Recapture Power Uprate Project stage: Response to RAI ML0916602902009-06-11011 June 2009 Revision to License Amendment for Measurement Uncertainty Recapture Power Uprate Project stage: Other ML0918802362009-07-0707 July 2009 Appendix K License Amendment Request Project stage: Other ML0918203662009-07-22022 July 2009 Amendment Regarding Measurement Uncertainty Recapture Power Uprate Project stage: Other 2008-09-24
[Table View] |
Text
From:
Pickett, Douglas Sent:
Tuesday, July 07, 2009 10:12 AM To:
'Furio, Patricia S' Cc:
Little, Sherri
Subject:
RE: Appendix K License Amendment Request Ms. Furio -
I consider your request to revise the implementation schedule for the Calvert Cliffs Unit No. 2 measurement uncertainty recapture power uprate to be appropriate and acceptable. I will document this email exchange as an official agency record and will make it publicly available in ADAMS.
Please contact me if you have any questions.
Douglas V. Pickett, Senior Project Manager Calvert Cliffs Nuclear Power Plant, R.E. Ginna Nuclear Power Plant U.S. Nuclear Regulatory Commission 301-415-1364 Email: douglas.pickett@nrc.gov From: Furio, Patricia S [1]
Sent: Tuesday, July 07, 2009 9:47 AM To: Pickett, Douglas
Subject:
Appendix K License Amendment Request As previously discussed, we would like to request a change to the implementation period for Unit 2 MUR power uprate due to the extended time required for resolution of various NRC questions about the license amendment request. The original requested timeframe required implementation on Unit 2 within 180 days of the end of the 2009 Unit 2 outage. We would like to revise this requested implementation timeframe to allow implementation within 180 days of issuance of the approved amendment request.
Please let me know if this change is not acceptable.
- Thanks, Pat Furio
>>> This e-mail and any attachments are confidential, may contain legal, professional or other privileged information, and are intended solely for the addressee. If you are not the intended recipient, do not use the information in this e-mail in any way, delete this e-mail and notify the sender. CEG-IP2 E-mail Properties Mail Envelope Properties ()
Subject:
RE: Appendix K License Amendment Request Sent Date: 07/07/2009 10:05:20 AM Received Date: 07/07/2009 10:11:00 AM From: Pickett, Douglas Created By: Douglas.Pickett@nrc.gov Recipients:
Patricia.Furio@constellation.com ('Furio, Patricia S')
Tracking Status: None Sherri.Little@nrc.gov (Little, Sherri)