MONTHYEARML24290A1102024-10-24024 October 2024 Notification of Licensed Operator Initial Examination 05000400/2025301 05000400/LER-2024-001-01, Automatic Reactor Trip Due to Main Generator Lock-Out2024-10-23023 October 2024 Automatic Reactor Trip Due to Main Generator Lock-Out IR 05000400/20240112024-09-10010 September 2024 NRC Inspection Report 05000400/2024011 IR 05000400/20240052024-08-26026 August 2024 Updated Inspection Plan for Shearon Harris Nuclear Power Plant, Unit 1 (Report 05000400-2024005) Rev 1 ML24059A4252024-08-14014 August 2024 Issuance of Amendment No. 202 Regarding Alignment of Certain Technical Specifications with Improved Standard Technical Specifications ML24213A0522024-08-0202 August 2024 Issuance of Amendment No. 201 to Extend Completion Time of Inoperable Reactor Coolant System Accumulator Using Consolidated Line Item Improvement Process ML24212A3412024-07-31031 July 2024 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000400/20240022024-07-29029 July 2024 – Integrated Inspection Report 05000400/2024002 ML24170A7312024-07-29029 July 2024 – Exemption from the Requirements of 10 CFR 50.55a(H)(2) Using the Risk-Informed Process for Evaluations Letter 05000400/LER-2024-001, Automatic Reactor Trip Due to Main Generator Lock-Out2024-07-22022 July 2024 Automatic Reactor Trip Due to Main Generator Lock-Out ML24183A0972024-07-12012 July 2024 ISFSI; Catawba 1, 2 & ISFSI; McGuire 1, 2 & ISFSI; Oconee 1, 2, 3 & ISFSI; Shearon Harris 1; H. B. Robinson 2 & ISFSI; and Radioactive Package Shipping Under 10 CFR 71 (71-266 & 71-345) – Review of QA Program Changes EPID L-2024-LLQ-0002 IR 05000400/20243022024-06-27027 June 2024 – NRC Operator Licensing Examination Approval 05000400/2024302 IR 05000400/20244012024-06-25025 June 2024 – Security Baseline Inspection Report05000400/2024401 ML24162A1372024-06-24024 June 2024 – Regulatory Audit Summary Related to the Review of Exemption Request from Certain Requirements in 10 CFR 50.55a(h)(2)(EPID L-2024-LLE-00040) ML24136A1382024-05-20020 May 2024 – Notification of an NRC Fire Protection Team Inspection (FPTI) (NRC Inspection Report 05000400/2024011) and Request for Information (RFI) ML24116A2592024-05-14014 May 2024 Staff Evaluation Related to Aging Management Plan and Inspection Plan for Reactor Vessel Internals ML24127A1592024-05-0808 May 2024 – Notification of Licensed Operator Initial Examination 05000400/2024302 IR 05000400/20240012024-05-0505 May 2024 Integrated Inspection Report 05000400/2024001 ML24100A0912024-04-10010 April 2024 Operator License Examination Report ML24058A2462024-03-18018 March 2024 – Supplemental Information Needed for Using the Risk-Informed Process for Evaluations for the Request for Exemption from Certain Requirements in 10 CFR 50.55a(h)(2) IR 05000400/20230062024-02-28028 February 2024 Annual Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2023006 ML24032A2632024-02-23023 February 2024 – Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0044 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) IR 05000400/20230042024-01-30030 January 2024 Integrated Inspection Report 05000400/2023004 ML23317A3462023-11-14014 November 2023 Duke Fleet - Correction Letter to License Amendment Nos. 312 & 340 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000400/20230032023-11-0909 November 2023 Integrated Inspection Report 05000400/2023003 ML23346A1322023-10-0606 October 2023 Communication from C-10 Research & Education Foundation Regarding NextEra Common Emergency Fleet Plan License Amendment Request and Related Documents Subsequently Published ML23234A1702023-10-0303 October 2023 Issuance of Amendment No. 199 Regarding Administrative Changes to the Renewed Facility Operating License and Technical Specifications ML23256A0882023-09-25025 September 2023 Issuance of Alternative to Steam Generator Welds ML23195A0782023-08-29029 August 2023 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000400/20230052023-08-23023 August 2023 Updated Inspection Plan for Shearon Harris Nuclear Power Plant, Unit 1 (Report 05000400/2023005) ML23234A2542023-08-22022 August 2023 RQ Inspection Notification Letter IR 05000400/20234022023-07-26026 July 2023 Security Baseline Inspection Report 05000400/2023402 IR 05000400/20230022023-07-24024 July 2023 Integrated Inspection Report 05000400/2023002 IR 05000400/20234402023-07-17017 July 2023 Special Inspection Report 05000400/2023440 and Preliminary Greater than Green Finding and Apparent Violation Cover Letter 05000400/LER-2022-006-02, Auxiliary Feedwater Pump Inoperability2023-07-11011 July 2023 Auxiliary Feedwater Pump Inoperability IR 05000400/20243012023-05-15015 May 2023 – Notification of Licensed Operator Initial Examination 05000400/2024301 IR 05000400/20230012023-05-10010 May 2023 – Integrated Inspection Report 05000400 2023001 IR 05000400/20234042023-05-0404 May 2023 Cyber Security Inspection Report 05000400/2023404 ML23118A0762023-05-0101 May 2023 Approval for Use of Specific Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI ML23118A1392023-04-28028 April 2023 Submittal of Updated Final Safety Analysis Report (Amendment 65), Technical Specification Bases Revision, Report of Changes Pursuant to 10 CFR 50.59 and Summary of Commitment Changes IR 05000400/20234032023-04-0505 April 2023 Security Baseline Inspection Report 05000400/2023403 IR 05000400/20230102023-03-15015 March 2023 Comprehensive Engineering Team Inspection (CETI) Inspection Report 05000400/2023010 ML22332A4932023-03-10010 March 2023 William States Lee III 1 and 2 - Issuance of Amendments Regarding the Relocation of the Emergency Operations Facility 05000400/LER-1922-006-01, Auxiliary Feedwater Pump Inoperability2023-03-10010 March 2023 Auxiliary Feedwater Pump Inoperability IR 05000400/20220062023-03-0101 March 2023 Annual Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2022006 ML23033A5272023-02-0808 February 2023 Correction of Typographical Errors Incurred During Issuance of License Amendment No. 196 IR 05000400/20220042023-02-0707 February 2023 Integrated Inspection Report 05000400/2022004 05000400/LER-2022-007-01, Automatic Reactor Trip Due to Loss of Power from the a Auxiliary Bus2023-01-26026 January 2023 Automatic Reactor Trip Due to Loss of Power from the a Auxiliary Bus ML23020A1252023-01-23023 January 2023 Notification of Target Set Inspection and Request for Information (NRC Inspection Report 05000400/2023403) 05000400/LER-2022-006, Auxiliary Feedwater Pump Inoperability2022-12-20020 December 2022 Auxiliary Feedwater Pump Inoperability 2024-09-10
[Table view] |
Text
December 17, 2008 Mr. Chris L. Burton Vice President Shearon Harris Nuclear Power Plant, Unit 1 Carolina Power & Light Company P.O. Box 165, Mail Zone 1 New Hill, NC 27562-0165
SUBJECT:
ISSUANCE OF RENEWED FACILITY OPERATING LICENSE NO. NPF-63 FOR THE SHEARON HARRIS NUCLEAR POWER PLANT, UNIT 1
Dear Mr. Burton:
The U.S. Nuclear Regulatory Commission (NRC) has issued the Renewed Facility Operating License No. NPF-63, for the Shearon Harris Nuclear Power Plant (HNP), Unit 1. The NRC issued the renewed facility operating license based on the staffs review of your application dated November 14, 2006, as supplemented by letters submitted to the NRC through July 21, 2008. The technical specifications for HNP were not amended as a result of our review.
The technical basis for issuing the renewed license is set forth in NUREG-1916, Volumes 1 and 2, Safety Evaluation Report Related to the License Renewal of the Shearon Harris Nuclear Power Plant, Unit 1, published in August 2008. The results of the environmental reviews related to the issuance of the renewed license are given in NUREG-1437, Supplement 33, Generic Environmental Impact Statement for License Renewal of Nuclear Plants, Supplement 33, Regarding Shearon Harris Nuclear Power Plant, Unit 1, published in August 2008.
Renewed Facility Operating License No. NPF-63 expires at midnight on October 24, 2046. contains the Renewed Facility Operating License No. NPF-63 and attachments, Appendix B - Environmental Protection Plan, and Appendix C - Antitrust Conditions.
C. Burton Enclosure 2 is a copy of the related Federal Register notice of issuance of the renewed license.
The original has been sent to the Office of the Federal Register for publication. If you have any questions regarding this issue, please feel free to contact me at 301-415-3137 or by e-mail at maurice.heath@nrc.gov.
Sincerely,
/RA/
Maurice Heath, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-400
Enclosures:
- 1. Renewed Facility Operating License No. NPF-63
- 2. Federal Register Notice cc: See next page (w/o Attachments to Renewed Operating License)
(PKG.) ML083120248, (LTR.) ML083110495, (LIC.) ML083120237, (FRN) ML083120243, (App. A. & B.) ML052860283 *concurred via e-mail OFFICE PM:RPB1:DLR LA:DLR Tech Editor* PM:DORL:LPLII-2 BC:DORL:LPLII-2 NAME MHeath YEdmonds HSpencer MVaaler TBoyce w/comments DATE 12/10/08 12/11/08 11/17/08 11/10/08 11/12/08 OFFICE BC:RPB1:DLR D:DLR OGC nlo D:NRR PM:RPB1:DLR NAME DPelton BHolian DRoth ELeeds MHeath DATE 12/10/08 12/10/08 12/9/08 12/17/08 12/17/08 Shearon Harris Nuclear Power Plant, Unit 1 cc:
Mr. J. Paul Fulford, Manager Mr. Kelvin Henderson Performance Evaluation and Plant General Manager Regulatory Affairs PEB 5 Shearon Harris Nuclear Power Plant Progress Energy Carolinas, Inc.
Progress Energy Carolinas, Inc. P.O. Box 1551 P.O. Box 165, Mail Zone 3 Raleigh, NC 27602-1551 New Hill, NC 27562-0165 Mr. Chris L. Burton David T. Conley Director of Site Operations Associate General Counsel II - Shearon Harris Nuclear Power Plant Legal Department Progress Energy Carolinas, Inc.
Progress Energy Service Company, LLC P.O. Box 165, Mail Zone 1 P.O. Box 1551 New Hill, NC 27562-0165 Raleigh, NC 27602-1551 Mr. Robert P. Gruber Resident Inspector/Harris NPS Executive Director c/o U.S. Nuclear Regulatory Commission Public Staff NCUC 5421 Shearon Harris Road 4326 Mail Service Center New Hill, NC 27562-9998 Raleigh, NC 27699-4326 Ms. Margaret A. Force Chairman of the North Carolina Assistant Attorney General Utilities Commission State of North Carolina P.O. Box 29510 P.O. Box 629 Raleigh, NC 27626-0510 Raleigh, NC 27602 Mr. Tony Gurley, Chair Public Service Commission Board of County Commissioners State of South Carolina of Wake County P.O. Drawer 11649 P. O. Box 550 Columbia, SC 29211 Raleigh, NC 27602 Ms. Beverly Hall, Section Chief Mr. Carl Thompson, Chair Division of Radiation Protection Board of County Commissioners N.C. Department of Environment of Chatham County and Natural Resources P.O. Box 87 3825 Barrett Drive Pittsboro, NC 27312 Raleigh, NC 27609-7721
Shearon Harris Nuclear Power Plant, Unit 1 cc:
Mr. Thomas J. Natale, Manager Support Services Shearon Harris Nuclear Power Plant Progress Energy Carolinas, Inc.
P.O. Box 165, Mail Zone 1 New Hill, NC 27562-0165 Mr. David H. Corlett, Supervisor Licensing/Regulatory Programs Shearon Harris Nuclear Power Plant Progress Energy Carolinas, Inc.
P.O. Box 165, Mail Zone 1 New Hill, NC 27562-0165 Mr. John H. ONeill, Jr.
Pillsbury Winthrop Shaw Pittman, LLP 2300 N Street, NW Washington, DC 20037-1128