July 22, 2008 Mr. David A. Christian President and Chief Nuclear Officer Virginia Electric and Power Company Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711
SUBJECT:
MILLSTONE POWER STATION, UNIT NOS. 2 AND 3 - REQUEST FOR ADDITIONAL INFORMATION (RAI) REGARDING CONTROL ROOM HABITABILITY PROGRAM AMENDMENT REQUEST (TAC NOS. MD6115 AND MD6116)
Dear Mr. Christian:
By letter to the Nuclear Regulatory Commission (NRC) dated July 13, 2007, as supplemented by letters dated December 7, 2007, March 5, 2008, March 25, 2008, June 9, 2008 and June 26, 2008, Dominion Nuclear Connecticut, Inc. (DNC) submitted the proposed license amendment request for Millstone Power Station, Unit Nos. 2 and 3 to modify the Technical Specification (TS) requirements related to control room envelope habitability consistent with NRC-approved Technical Specification Task Force Traveler (TSTF) -448, Control Room Habitability, revision 3. The NRC staff has reviewed the request submitted by DNC and has identified a need for additional information as set forth in the enclosure.
The draft questions were sent to Mr. William Bartron, from your staff, to ensure that the questions were understandable, the regulatory basis for the questions was clear, and to determine if the information was previously docketed. On July 15, 2008, Mr. Gary Johnson, from your staff, indicated that DNC understands the issues and plans to submit a response by August 4, 2008. Please note that if you do not respond to this letter within this agreed response time or provide an acceptable alternate date in writing, we may reject your application for amendment under the provisions of Title 10 of the Code of Federal Regulations, Section 2.108.
If you have any questions, please contact me at (301) 415-3204.
Sincerely,
/ra/
John D. Hughey, Project Manager Plant Licensing Branch I-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-336 and 50-423
Enclosure:
RAI cc w/encl: See next page
July 22, 2008 Mr. David A. Christian President and Chief Nuclear Officer Virginia Electric and Power Company Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711
SUBJECT:
MILLSTONE POWER STATION, UNIT NOS. 2 AND 3 - REQUEST FOR ADDITIONAL INFORMATION (RAI) REGARDING CONTROL ROOM HABITABILITY PROGRAM AMENDMENT REQUEST (TAC NOS. MD6115 AND MD6116)
Dear Mr. Christian:
By letter to the Nuclear Regulatory Commission (NRC) dated July 13, 2007, as supplemented by letters dated December 7, 2007, March 5, 2008, March 25, 2008, June 9, 2008 and June 26, 2008, Dominion Nuclear Connecticut, Inc. (DNC) submitted the proposed license amendment request for Millstone Power Station, Unit Nos. 2 and 3 to modify the Technical Specification (TS) requirements related to control room envelope habitability consistent with NRC-approved Technical Specification Task Force Traveler (TSTF) -448, Control Room Habitability, revision 3. The NRC staff has reviewed the request submitted by DNC and has identified a need for additional information as set forth in the enclosure.
The draft questions were sent to Mr. William Bartron, from your staff, to ensure that the questions were understandable, the regulatory basis for the questions was clear, and to determine if the information was previously docketed. On July 15, 2008, Mr. Gary Johnson, from your staff, indicated that DNC understands the issues and plans to submit a response by August 4, 2008. Please note that if you do not respond to this letter within this agreed response time or provide an acceptable alternate date in writing, we may reject your application for amendment under the provisions of Title 10 of the Code of Federal Regulations, Section 2.108.
If you have any questions, please contact me at (301) 415-3204.
Sincerely,
/ra/
John D. Hughey, Project Manager Plant Licensing Branch I-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-336 and 50-423
Enclosure:
RAI cc w/encl: See next page DISTRIBUTION:
PUBLIC LPL1-2 R/F RidsNrrDorlLpl1-2 RidsNrrPMJHughey RidsNrrLAABaxter RidsRgn1MailCenter RidsAcrsAcnwMailCenter RidsOgcRp RDennig, NRR ADAMS Accession No. ML081930974 OFFICE LPL1-2/PM LPL1-2/LA SCVB/BC LPL1-2/BC NAME JHughey ABaxter RDennig HChernoff DATE 07/21/2008 07/21/2008 07/22/2008 7/22/2008 Official Record Copy
Millstone Power Station, Unit Nos. 2 and 3 cc:
Lillian M. Cuoco, Esquire Senior Counsel Dominion Resources Services, Inc.
Building 475, 5th Floor Rope Ferry Road Waterford, CT 06385 Edward L. Wilds, Jr., Ph.D.
Director, Division of Radiation Department of Environmental Protection 79 Elm Street Hartford, CT 06106-5127 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 First Selectmen Town of Waterford 15 Rope Ferry Road Waterford, CT 06385 Charles Brinkman, Director Washington Operations Nuclear Services Westinghouse Electric Company 12300 Twinbrook Pkwy, Suite 330 Rockville, MD 20852 Senior Resident Inspector Millstone Power Station c/o U.S. Nuclear Regulatory Commission P. O. Box 513 Niantic, CT 06357 Mr. J. W. "Bill" Sheehan Co-Chair NEAC 19 Laurel Crest Drive Waterford, CT 06385 Ms. Nancy Burton 147 Cross Highway Redding Ridge, CT 00870 Mr. Evan W. Woollacott Co-Chair Nuclear Energy Advisory Council 128 Terrys Plain Road Simsbury, CT 06070 Mr. Joseph Roy Director of Operations Massachusetts Municipal Wholesale Electric Company P.O. Box 426 Ludlow, MA 01056 Mr. William D. Bartron Licensing Supervisor Dominion Nuclear Connecticut, Inc.
Building 475, 5th Floor Roper Ferry Road Waterford, CT 06385 Mr. J. Alan Price Site Vice President Dominion Nuclear Connecticut, Inc.
Building 475, 5th Floor Rope Ferry Road Waterford, CT 06385 Mr. Chris L. Funderburk Director, Nuclear Licensing and Operations Support Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711
Enclosure MILLSTONE POWER STATION, UNIT NOS. 2 AND 3 PROPOSED TECHNICAL SPECIFICATION CHANGE:
CONTROL ROOM HABITABILITY REQUEST FOR ADDITIONAL INFORMATION Dominion Nuclear Connecticut, Inc. (DNC) provided a supplement dated March 5, 2008, to its submittal dated July 13, 2007, (Agencywide Documents Access and Management System (ADAMS) Accession Nos. ML080660650 and ML071970463). In the response to NRC request for additional information question 1 (RAI 1), DNC stated that Millstone Power Station, Unit No. 2 (MPS2) conducts preventative maintenance and surveillance tests in lieu of a pressurization test to ensure that the MPS2 Control Room Envelope (CRE) boundary can perform its safety function. The response also noted that any criteria not met while performing these activities are documented and resolved in accordance with the MPS Corrective Action Program. The Nuclear Regulatory Commission (NRC) staff requests that the following information be provided in addition to the response provided to RAI 1 in the March 5, 2008, supplement.
RAI 1.a)
How will the MPS2 Technical Specification (TS) 6.27 description of the Control Room Habitability Program and associated License Condition incorporate the corrective action program and associated trending into a periodic assessment of the MPS2 CRE boundary? (The proposed text for MPS2 TS 6.27.d does not contain this information.)
RAI 1.b)
At what frequency will the periodic assessment of the MPS2 CRE boundary integrity be performed? What is the basis for this frequency?