March 31, 2008 Mr. Thomas J. Shortell Manager Training Constellation Energy Group Nine Mile Point Nuclear Station, Units 1 & 2 450 Lake Road Oswego, NY 13126
SUBJECT:
NRC OPERATOR LICENSING INITIAL EXAM RESULTS (NINE MILE POINT NUCLEAR STATION, UNIT 2)
(COVER LETTER PUBLICALLY AVAILABLE, ENCLOSURES WITHHELD FROM PUBLIC)
Dear Mr. Shortell:
The purpose of this letter is to inform you of the individual examination results for your applicants on the initial written examination conducted on March 17, 2008, and the walk-through (overall) and/or simulator operating tests administered March 10 - 14, 2008 at your facility. This meets the intent of Section E.1 of the Examination Standards (ES 501) in Supplement 1, of NUREG-1021, AOperator Licensing Examinations Standards for Power Reactors.@ Nine individuals were administered the examination and eight passed. However, we will not issue one license until you certify in writing that the applicant has acquired all of the training and experience for which he was previously granted a waiver This information is considered proprietary" in accordance with 10 CFR 2.390 and it supplements the information contained in the related examination report for your facility which will be issued shortly.
is the completed ES-501-2, Power Plant Licensing Examination Results Summary, and is a summary of overall examination results.
contains the individual results ES-303-1 and 303-2, Operator License Examination Report, for the applicants. Contained therein are the deficiencies noted for each applicant. In accordance with your Systems Approach to Training (SAT) Program, we expect that you will review these results and provide appropriate remedial training for the individual independent of the overall pass status. The applicants have authorized the release of this information to your facility by signing Block 19A of NRC Form 398.
is a copy of the licenses.
T.
Thank you for your cooperation in this matter. Please refer any questions you have to me at (610) 337-5046.
Sincerely,
/RA/
Samuel L. Hansell, Jr., Chief Operations Branch Division of Reactor Safety Docket No. 50-220 License No. DPR-63
Enclosures:
- 1. ES-501-2, Power Plant Licensing Examination Results Summary
- 2. ES-303-1 and 303-2, Individual Examination Results
- 3. Licenses cc with Enclosure 3:
Mr. Keith J. Polson, Vice President
Thank you for your cooperation in this matter. Please refer any questions you have to me at (610) 337-5046.
Sincerely,
/RA/
Samuel L. Hansell, Jr., Chief Operations Branch Division of Reactor Safety Docket No. 50-220 License No. DPR-63
Enclosures:
- 1. ES-501-2, Power Plant Licensing Examination Results Summary
- 2. ES-303-1 and 303-2, Individual Examination Results
- 3. Licenses cc with Enclosure 3:
Mr. Keith J. Polson, Vice President Distribution: w/o enclosures:
Master Exam File SUNSI Review Complete: slh (Reviewer=s Initials)
ADAMS PACKAGE NO.: ML073040288 DOCUMENT NAME: G:\\DRS\\Operations Branch\\DANTONIO\\Exam 08-NMP2 Mar 08 (U01740)\\ExamNotificationLtr.doc After declaring this document AAn Official Agency Record,@ it will without enclosures be released to the Public.
OFFICE RI/DRS/OB RI/DRS/OB RI/DRS/OB NAME CJBixler/CJB JMDAntonio/JMD SLHansell/SLH DATE 03/28/08 03/ 31 /08 03/ 31 /08 OFFICIAL RECORD COPY