ML072990208

From kanterella
Jump to navigation Jump to search

Response to Generic Letter 96-06 Assurance of Equipment Operability and Containment Integrity During Design-basis Accident Conditions
ML072990208
Person / Time
Site: Oconee  Duke Energy icon.png
Issue date: 12/06/2007
From: Olshan L
NRC/NRR/ADRO/DORL/LPLII-1
To: Brandi Hamilton
Duke Power Co
Olshan L N, NRR/DORL, 415-1419
References
TAC M96840, TAC M96841, TAC M96842
Download: ML072990208 (6)


Text

December 6, 2007 Mr. Bruce H. Hamilton Vice President, Oconee Site Duke Power Company LLC 7800 Rochester Highway Seneca, SC 29672

SUBJECT:

OCONEE NUCLEAR STATION, UNITS 1, 2, AND 3, - RESPONSE TO GENERIC LETTER 96-06 ASSURANCE OF EQUIPMENT OPERABILITY AND CONTAINMENT INTEGRITY DURING DESIGN-BASIS ACCIDENT CONDITIONS (TAC NOS. M96840, M96841, and M96842)

Dear Mr. Hamilton:

On September 30, 1996, the U. S. Nuclear Regulatory Commission (NRC) issued Generic Letter (GL) 96-06, Assurance of Equipment Operability and Containment Integrity During Design-Basis Accident Conditions, (Agencywide Documents Access and Management System (ADAMS)

Accession No. 9609250096). In GL 96-06, the NRC staff expressed concerns that cooling water systems serving the containment air coolers may (1) be exposed to the hydrodynamic effects of waterhammer during either a loss-of-coolant accident or a main steam line break or (2) experience two-phase flow conditions during these postulated accidents. The NRC staff also expressed concern that thermally-induced overpressurization of isolated water-filled piping sections in containment could jeopardize the ability of accident mitigating systems to perform their safety functions and could also lead to a breach of containment integrity via bypass leakage. The NRC staff requested that the licensees assess these concerns, take certain actions as appropriate, and provide certain information to the NRC staff within specified times.

Duke Energy, the licensee for Oconee Nuclear Station Units 1, 2, and 3 (ONS) provided responses to GL 96-06 in letters dated October 29, 1996 (Accession No. 9611040090), January 28, 1997 (Accession No. 9702110158), April 15, 1997 (Accession No. 9704210201), June 30, 1997 (Accession No. 9707090108), August 1, 1997 (Accession No. 9708070324), May 28, 1998 (Accession No. 9806020059), September 22, 1998 (Accession No. 9809290222), December 17, 1998 (Accession No. 9812240142), March 23, 1999 (Accession No. 9903300338), December 15, 1999 (ADAMS Accession No. ML993610085), July 26, 2002 (ADAMS Accession No. ML022190445), September 30, 2002 (ADAMS Accession No. ML022820013), March 24, 2003 (ADAMS Accession No. ML030920448), September 29, 2003 (ADAMS Accession No. ML032810326), May 10, 2006 (ADAMS Accession No. ML061380548), and February 14, 2007 (ADAMS Accession No. ML070610328).

During the course of evaluating the GL 96-06 waterhammer issue, the licensee also submitted Licensee Event Report (LER)97-002 reporting waterhammer vulnerabilities that were identified.

Revision 2 of the LER, dated September 14, 1998, was the final update.

B. Hamilton Waterhammer and Two-Phase Flow Subsequent to the issuance of GL 96-06, the Electric Power Research Institute (EPRI) developed an analytical methodology for evaluating the consequences of GL 96-06 waterhammer events as documented in EPRI Technical Reports 1003098 and 1006456 (previously EPRI Report TR-113594). The EPRI methodology was approved by the NRC in a safety evaluation dated April 3, 2002, and is included as an Appendix of the EPRI Technical Reports. Section 3.3 of the staffs safety evaluation identified additional information that licensees who choose to use the EPRI methodology were required to provide in order to: a) confirm that the EPRI methodology was properly applied and that plant-specific risk considerations were consistent with the EPRI risk perspective, b) justify any proposed exceptions to the EPRI methodology, and c) address the GL 96-06 two-phase flow issue.

The licensee indicated in letters dated May 28, 1998, March 23, 1999 and December 15, 1999, that further action to address the waterhammer and two-phase flow issues would be deferred pending completion of the EPRI initiative (referred to above). Upon completion of the EPRI initiative and as requested by NRC letter dated May 2, 2002 (ADAMS Accession No. ML0211906450), the licensee provided additional information related to using the EPRI methodology in letters dated September 30, 2002, and March 24, 2003. Based on the results of the waterhammer analyses that were completed, the licensee determined that two modifications to the low pressure service water system for ONS were warranted in order to resolve the waterhammer vulnerabilities that exist. The first modification would prevent drainage of the reactor building cooling units (RBCUs) and the reactor coolant pump (RCP) bearing oil and motor air coolers supply and discharge lines and the second modification would physically separate in containment the reactor building auxiliary cooling unit (RBACU) lines and coolers from the RBCU lines and coolers. The specific details associated with these modifications were discussed in of the September 30, 2002, letter and implementation schedules were discussed in letters dated September 29, 2003, May 10, 2006, and February 14, 2007. In the May 10, 2006, letter the licensee determined that NRC review and approval was required before the drain down prevention modification could be implemented and that additional time would be required in order to allow for preparation and NRC approval of a license amendment request. The most recent letter indicated that the modifications associated with the RBACUs have been completed, and established a commitment to complete the remaining (drain down prevention) modification during the Fall 2008, Spring 2009, and Fall 2009 outages for ONS. The licensee also indicated in the September 29, 2003, letter that more detailed thermal-hydraulic analyses are being developed to ensure final resolution of the waterhammer concerns.

In addition to the waterhammer analysis that was completed, the licensee also completed a risk assessment and addressed the GL 96-06 two-phase flow issue thereby satisfying the conditions that were stipulated by the NRC for using the EPRI methodology. The plant-specific risk assessment was discussed in the licensees September 30, 2002, and March 24, 2003, letters.

The additional information requested by the NRC staff in a letter dated June 17, 1998, (Accession No. ML9806180264) for addressing the two-phase flow issue was provided in Enclosure A of the licensees March 24, 2003, letter.

While the licensees waterhammer evaluation was not entirely consistent with the EPRI methodology (primarily due to nonconservative closure velocity assumptions), the information that was provided in the September 30, 2002, and March 24, 2003, letters indicates that these

B. Hamilton analyses were performed to support continued plant operation pending the implementation of plant modifications that would either prevent or significantly reduce the severity of GL 96-06 waterhammer events. In light of the risk considerations that were discussed, the licensee felt that the analyses were adequate to support interim operation while plant modifications were being completed. The NRC staff agrees that the licensees resolution of the GL 96-06 waterhammer issue is acceptable in the interim, recognizing that: the modifications to separate the RBACUs have been completed on all three Oconee units; the licensee has established a firm commitment to complete the remaining (drain down prevention) modifications in accordance with the schedule provided in the February 14, 2007, letter; and a license amendment request (ADAMS Accession No. ML072920449) has been submitted by the licensee in order to implement the plant modifications that remain to be completed.

The licensee discussed the risk considerations that are partially credited for using the EPRI methodology in the September 30, 2002, and March 24, 2003, letters. In particular, it is the NRC staffs understanding that the licensee did not identify any inconsistencies between the plant specific risk assessment that was performed for ONS and the one that was completed by EPRI.

However, the staff notes that the licensee indicated that the pipe failure probability is most likely less than the EPRI value of 1.0E-2 based on plant-specific column closure waterhammer testing that has been completed. The NRC staff considers the licensees risk assessment to be acceptable.

The licensee addressed the GL 96-06 two-phase flow considerations in letters dated January 28, 1997, and March 24, 2003. The licensees analyses appeared to address primarily heat transfer considerations, but did not address fatigue and erosion concerns relative to those areas that experience two-phase flow. Because erosion and fatigue are longer term effects, the NRC staff considers the licensees response to be acceptable in the interim pending completion of the plant modifications that remain for resolving the GL 96-06 waterhammer issue (referred to above).

Based on a review of the information that was provided and as discussed above, the NRC staff is satisfied that the licensee has adequately addressed the GL 96-06 waterhammer and two-phase flow issues for ONS for continued interim operation pending implementation of the remaining (drain down prevention) plant modifications that must be completed. This conclusion was reached recognizing that the licensee has completed the necessary RBACU separation modifications and has established a firm commitment and schedule and has submitted a license amendment request for completing the remaining plant modifications.

While the NRC staff is satisfied with the licensees resolution of the GL 96-06 waterhammer and two-phase flow issues in the interim while plant modifications are being completed, a detailed quantitative assessment of the licensees waterhammer and two-phase flow analyses was not performed and a review of the licensees use and application of computer codes for performing these analyses was not performed. Consequently, these areas could be the subject of future NRC audit or inspection activities.

Thermal Overpressurization In letters dated January 28, April 15, and June 30, 1997, and December 17, 1998, the licensee provided responses to the issue of thermally-induced pressurization of piping runs penetrating the containment.

B. Hamilton In its response of January 28, 1997, the licensee identified 28 piping penetrations (total for all three units) and one piping segment in the decay heat drop line of each unit which were susceptible to thermally-induced pressurization. In this submittal, the licensee also determined that all of the identified penetrations and piping segments were operable. In the December 17, 1998, response, the licensee provided the necessary long-term actions and identified several additional penetrations that were susceptible to thermally-induced pressurization. For all three units, the licensee identified a total of 36 penetrations that required installation of a relief valve, 6 penetrations that required installation of leak off lines with check valves, 4 penetrations that were required to be cut, capped, and abandoned, and 3 penetrations that were required to have administrative controls to drain the lines prior to power operation. For the three decay heat drop lines, the licensee identified that administrative controls were required to partially drain the lines prior to power operation. The licensee's evaluation determined that all other piping segments penetrating containment were not susceptible to thermally-induced pressurization.

Based on this information, the NRC staff has concluded that the licensee has provided an acceptable resolution for the issue of thermally-induced pressurization of piping runs penetrating the containment for ONS.

Conclusion Based on the information discussed above, and the licensees License Amendment Request for Low Pressure Service Water Reactor Building Waterhammer Prevention System Modification to Mitigate Waterhammers Described in Generic Letter 96-06 and Associated Technical Specifications, submitted on October 16, 2007 (ADAMS Accession No. ML072920449), the NRC staff considers your response to GL 96-06 to be complete, subject to future NRC inspection activities as indicated above.

This completes our activity on TAC Nos. M96840, M96841, and M96842. If you have questions regarding this letter, please contact me at (301) 415-1419.

Sincerely,

/RA/

Leonard Olshan, Project Manager Plant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos.: 50-269, 50-270, and 50-287 Cc: See next page

In its response of January 28, 1997, the licensee identified 28 piping penetrations (total for all three units) and one piping segment in the decay heat drop line of each unit which were susceptible to thermally-induced pressurization. In this submittal, the licensee also determined that all of the identified penetrations and piping segments were operable. In the December 17, 1998, response, the licensee provided the necessary long-term actions and identified several additional penetrations that were susceptible to thermally-induced pressurization. For all three units, the licensee identified a total of 36 penetrations that required installation of a relief valve, 6 penetrations that required installation of leak off lines with check valves, 4 penetrations that were required to be cut, capped, and abandoned, and 3 penetrations that were required to have administrative controls to drain the lines prior to power operation. For the three decay heat drop lines, the licensee identified that administrative controls were required to partially drain the lines prior to power operation. The licensee's evaluation determined that all other piping segments penetrating containment were not susceptible to thermally-induced pressurization.

Based on this information, the NRC staff has concluded that the licensee has provided an acceptable resolution for the issue of thermally-induced pressurization of piping runs penetrating the containment for ONS.

Conclusion Based on the information discussed above, and the licensees License Amendment Request for Low Pressure Service Water Reactor Building Waterhammer Prevention System Modification to Mitigate Waterhammers Described in Generic Letter 96-06 and Associated Technical Specifications, submitted on October 16, 2007 (ADAMS Accession No. ML072920449), the NRC staff considers your response to GL 96-06 to be complete, subject to future NRC inspection activities as indicated above.

This completes our activity on TAC Nos. M96840, M96841, and M96842. If you have questions regarding this letter, please contact me at (301) 415-1419.

Sincerely,

/RA/

Leonard Olshan, Project Manager Plant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos.: 50-269, 50-270, and 50-287 Cc: See next page DISTRIBUTION:

PUBLIC RidsNrrDORL RidsNrrDORLLpl2-1 RidsNrrLAMOBrien LPL2-1 Reading RidsNrrPMLOlshan RidsOgcRp RidsRgn2MailCenter RidsNrrDprPgcb RidsNrrDssSbpb RIdsNrrDeEemb RidsAcrsAcnwMailCenter RidsNrrRgn2MailCenter JWilson, NRR ACCESSION NUMBER: ML072990208 OFFICE LPL2-1/PM PGCB/BC SBPB/BC EMCB/BC LPL2-1/BC NAME LOlshan MMurphy DHarrison KManoly EMarinos DATE 10 / 26 / 07 12/4/07 11 / 15 / 07 11 / 19 /07 12/6/07 OFFICIAL RECORD COP

Oconee Nuclear Station, Units 1, 2, and 3 cc:

Mr. Bruce H. Hamilton Vice President, Oconee Site Duke Power Company LLC 7800 Rochester Highway Seneca, SC 29672 Ms. Lisa F. Vaughn Associate General Counsel and Managing Attorney Duke Energy Carolinas, LLC 526 South Church Street - EC07H Charlotte, North Carolina 28202 Manager, LIS NUS Corporation 2650 McCormick Dr., 3rd Floor Clearwater, FL 34619-1035 Senior Resident Inspector U.S. Nuclear Regulatory Commission 7812B Rochester Highway Seneca, SC 29672 Mr. Henry Porter, Director Division of Radioactive Waste Management Bureau of Land and Waste Management Dept. of Health and Env. Control 2600 Bull St.

Columbia, SC 29201-1708 Mr. Michael A. Schoppman Framatome ANP 1911 North Ft. Myer Dr.

Suite 705 Rosslyn, VA 22209 Mr. B. G. Davenport Regulatory Compliance Manager Oconee Nuclear Site Duke Energy Corporation ON03RC 7800 Rochester Highway Seneca, SC 29672 Mr. Leonard G. Green Assistant Attorney General NC Department of Justice P.O. Box 629 Raleigh, NC 27602 Mr. R. L. Gill, Jr.

Manager - Nuclear Regulatory Issues and Industry Affairs Duke Power Company LLC 526 S. Church St.

Mail Stop EC05P Charlotte, NC 28202 Division of Radiation Protection NC Dept of Environment, Health, & Natural Resources 3825 Barrett Dr.

Raleigh, NC 27609-7721 Mr. Peter R. Harden, IV VP-Customer Relations and Sales Westinghouse Electric Company 6000 Fairview Road 12th Floor Charlotte, NC 28210 Mr. Henry Barron Group Vice President, Nuclear Generation and Chief Nuclear Officer P.O. Box 1006-EC07H Charlotte, NC 28201-1006 Mr. Charles Brinkman Director, Washington Operations Westinghouse Electric Company 12300 Twinbrook Parkway, Suite 330 Rockville, MD 20852 Ms. Kathryn B. Nolan Senior Counsel Duke Energy Carolinas, LLC 526 South Church Street - EC07H Charlotte, NC 28202