ML072840428

From kanterella
Jump to navigation Jump to search
IR 05000285-07-011, on 02/14/2007 - 09/18/2007; Fort Calhoun Station, Resident Report; Postmaintenance Testing, Identification and Resolution of Problems
ML072840428
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 10/10/2007
From: Howell A
NRC/RGN-IV/DRP
To: Ridenoure R
Omaha Public Power District
References
EA-07-194 IR-07-011
Download: ML072840428 (26)


See also: IR 05000285/2007011

Text

October 10, 2007

EA-07-194

R. T. Ridenoure

Vice President

Omaha Public Power District

Fort Calhoun Station FC-2-4 Adm.

P.O. Box 550

Fort Calhoun, NE 68023-0550

SUBJECT: FORT CALHOUN STATION NRC INSPECTION REPORT 05000285/2007011

Dear Mr. Ridenoure:

On September 18, 2007, the U.S. Nuclear Regulatory Commission (NRC) completed an

inspection at your Fort Calhoun Station. The enclosed inspection report documents the

inspection findings, which were discussed on September 18, 2007, with Mr. Tim Nellenbach,

Plant Manager, and other members of your staff. This report documents baseline inspection

activities related to Train A emergency diesel generator failures which occurred on

February 14, 2007, and February 16, 2007. Region IV management decided to document this

inspection in a separate report because the underlying performance deficiencies were complex

and the preliminary significance of associated findings appeared to be of greater than very low

safety significance. The inspection examined activities conducted under your license as they

relate to safety and compliance with the Commissions rules and regulations and with the

conditions of your license. The inspectors reviewed selected procedures and records, observed

activities, and interviewed personnel.

This report discusses a finding that appears to have Greater than Green (greater than very low)

safety significance. As described in Section 4OA2 of this report, contamination containing dust

and oil was found on the field flash relay auxiliary contact surfaces, which apparently caused

the February 14, 2007 emergency diesel generator failure. Our inspectors determined

that: (1) craftsmen were applying an unapproved wet lubricant to the auxiliary contact sliding

mechanisms, contrary to vendor recommendations and in the absence of procedural controls;

(2) that Fort Calhoun Station staff did not treat the February 14, 2007, emergency diesel

generator failure as a significant condition adverse to quality; and (3) actions in response to

applicable operating experience were not timely and did not prevent this condition from

occurring. These issues were assessed for safety significance based on the best available

information, including influential assumptions, using the applicable Significance Determination

Process (SDP). The NRC determined that preliminarily the above stated issues, which resulted

in two apparent violations, are cumulatively considered as one finding, which was determined to

have Greater than Green significance. The final resolution of this finding will convey the

increment in the importance to safety by assigning the corresponding color. This preliminary

finding has Greater than Green significance because the Train A emergency diesel generator

Omaha Public Power District

- 2 -

was unavailable for a significant period (between 14 and 28 days, depending on failure mode

assumptions). The primary assumptions associated with the preliminary SDP are documented

in Attachment 2 to this report.

The finding is associated with two apparent violations of NRC requirements and is being

considered for escalated enforcement action in accordance with the NRC Enforcement Policy.

The current Enforcement Policy is included on the NRCs Web site at

www.nrc.gov/about-nrc/regulatory/enforcement.html

Before we make a final decision on this matter, we are providing you an opportunity (1) to

present to the NRC your perspectives on the facts and assumptions, used by the NRC to arrive

at the finding and its significance, at a Regulatory Conference or (2) submit your position on the

finding to the NRC in writing. If you request a Regulatory Conference, it should be held within

30 days of the receipt of this letter and we encourage you to submit supporting documentation

at least one week prior to the conference in an effort to make the conference more efficient and

effective. If a Regulatory Conference is held, it will be open for public observation. If you

decide to submit only a written response, such submittal should be sent to the NRC within 30

days of the receipt of this letter. In either case, please provide the following additional

information:

Your position and justification for the applicable exposure time - whether the exposure

time should be 28 days (the full duration between surveillances) or 14 days (t/2) if the

exact time the diesel became inoperable was unknown.

Your own assessment of the increase in core damage frequency associated with the

Train A emergency diesel generator being unable to perform its safety function. Your

assessment should include a discussion of the contribution of internal and external

initiating events.

Your views on the origins of the oil and dust contaminants that were found on the

auxiliary contact surfaces.

These issues do not represent an immediate safety concern because of the corrective actions

you have taken. These actions involved inspecting and replacing, as necessary, vulnerable

auxiliary contacts in the emergency diesel generator control circuits.

Please contact Mr. Jeffrey Clark at (817) 860-8147 within 10 business days of the date of the

receipt of this letter to notify the NRC of your intentions. If we have not heard from you within

10 days, we will continue with our significance determination and enforcement decision and you

will be advised by separate correspondence of the results of our deliberations on this matter.

Since the NRC has not made a final determination in this matter, no Notice of Violation is being

issued for the inspection finding at this time. In addition, please be advised that the number

and characterization of apparent violations described in the enclosed inspection report may

change as a result of further NRC review.

Omaha Public Power District

- 3 -

In addition, this report documents one self-revealing finding of very low safety significance

(Green). This finding was determined to involve a violation of NRC requirements. However,

because of the very low safety significance and because it was entered into your corrective

action program, the NRC is treating this finding as a noncited violation (NCV), consistent with

Section VI.A.1 of the NRC Enforcement Policy. If you contest the violation or significance of the

NCV, you should provide a response within 30 days of the date of this inspection report, with

the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document

Control Desk, Washington, D.C. 20555-0001, with copies to the Regional Administrator, U.S.

Nuclear Regulatory Commission, Region IV, 611 Ryan Plaza Drive, Suite 400, Arlington, Texas

76011-4005; the Director, Office of Enforcement, U.S. Nuclear Regulatory Commission,

Washington, D.C. 20555-0001; and the NRC Resident Inspector at the Fort Calhoun Station

facility.

In accordance with 10 CFR Part 2.390 of the NRC's "Rules of Practice," a copy of this letter,

and its enclosure, will be available electronically for public inspection in the NRC Public

Document Room or from the Publicly Available Records component of NRCs document

system (ADAMS). ADAMS is accessible from the NRC Web site at

"http://www.nrc.gov/reading-rm/adams.html" (the Public Electronic Reading Room).

Sincerely,

/RA/ Tony Vegel for

Arthur T. Howell III, Director

Division of Reactor Projects

Docket: 50-285

License: DPR-40

Enclosure:

NRC Inspection Report 05000285/2007011

w/Attachment: Supplemental Information

cc w/Enclosure:

Joe l. McManis, Manager - Licensing

Omaha Public Power District

Fort Calhoun Station FC-2-4 Adm.

P.O. Box 550

Fort Calhoun, NE 68023-0550

David J. Bannister

Site Director - Fort Calhoun Station

Omaha Public Power District

Fort Calhoun Station FC-1-1 Plant

P.O. Box 550

Fort Calhoun, NE 68023-0550

Omaha Public Power District

- 4 -

James R. Curtiss

Winston & Strawn

1700 K Street NW

Washington, DC 20006-3817

Chairman

Washington County Board of Supervisors

P.O. Box 466

Blair, NE 68008

Julia Schmitt, Manager

Radiation Control Program

Nebraska Health & Human Services

Dept. of Regulation & Licensing

Division of Public Health Assurance

301 Centennial Mall, South

P.O. Box 95007

Lincoln, NE 68509-5007

Melanie Rasmussen

Bureau of Radiological Health

Iowa Department of Public Health

Lucas State Office Building, 5th Floor

321 East 12th Street

Des Moines, IA 50319

Omaha Public Power District

- 5 -

Electronic distribution by RIV:

Regional Administrator (EEC)

DRP Director (ATH)

DRS Director (DDC)

DRS Deputy Director (RJC1)

Senior Resident Inspector (JDH1)

Resident Inspector (LMW1)

Branch Chief, DRP/E (JAC)

Senior Project Engineer, DRP/E (GDR)

Team Leader, DRP/TSS (CJP)

RITS Coordinator (MSH3)

OEMail

G. M. Vasquez, RIV

V. L. Dricks, RIV

W. M. Maier, RIV

M. a. Ashley, NRR

J. Wray, OE

Only inspection reports to the following:

DRS STA (DAP)

D. Pelton, OEDO RIV Coordinator (DLP)

ROPreports

FCS Site Secretary (BMM)

SUNSI Review Completed: GDR ADAMS: G Yes No Initials: GDR

G Publicly Available G Non-Publicly Available G Sensitive G Non-Sensitive

R:\\_REACTORS\\_FCS\\2007\\FCS 2007-011_gdr.wpd

RIV:SPE:DRP/E

RI:DRP/E

SPE:DRP/E

C:DRS/EB1

C:DRS/OB

GDReplogle

LMWilloughby

JDHanna

WBJones

ATGody

/RA/

E-GDReplogle

T-GDReplogle

/RA/

MEMurphy for

09/28/07

09/28/07

10/02/07

09/26/07

09/26/07

C:DRS/EB2

SRA:DRS

ACES

C:DRP/E

D:DRS

LJSmith

RLBywater

GMVasquez

JAClark

DDChamberlain

/RA/

/RA/

GDReplogle for

09/27/07

10/ /07

09/30/07

10/02/07

10/02/07

D:DRP

ATHowell

AVegel for

10/10/07

OFFICIAL RECORD COPY

T=Telephone E=E-mail F=Fax

Enclosure

-1-

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

Docket:

50-285

License:

DPR-40

Report:

05000285/2007011

Licensee:

Omaha Public Power District

Facility:

Fort Calhoun Station

Location:

Fort Calhoun Station FC-2-4 Adm.

P.O. Box 399, Highway 75 - North of Fort Calhoun

Fort Calhoun, Nebraska

Dates:

February 16, 2007 through September 18, 2007

Inspectors:

J. Hanna, Senior Resident Inspector

L. Willoughby, Resident Inspector

G. Replogle, Senior Project Engineer

Reactor Analyst

R. Bywater, Senior Reactor Analyst

Branch Chief

Jeff Clark, Chief, Project Branch E

Division of Reactor Projects

Approved By:

Arthur T. Howell, Director

Division of Rector Projects

Enclosure

-2-

SUMMARY OF FINDINGS

IR 05000285/2007011; 02/14/2007 - 09/18/2007; Fort Calhoun Station, Resident Report;

Postmaintenance Testing, Identification and Resolution of Problems.

The report covered a 31 week period of inspection by a senior resident inspector, a resident

inspector and a senior project engineer. One Green noncited violation and two apparent

violations of significance were identified. The significance of most findings is indicated by their

color (Green, White, Yellow, or Red) using Inspection Manual Chapter 0609, Significance

Determination Process. Findings for which the significance determination process does not

apply may be Green or be assigned a severity level after NRC management review. The

NRC's program for overseeing the safe operation of commercial nuclear power reactors is

described in NUREG-1649, Reactor Oversight Process, Revision 3, dated July 2000.

A.

NRC-Identified Findings and Self-Revealing Findings

Cornerstone: Mitigating Systems

Green. A self-revealing Green noncited violation of Technical Specification 5.8.1.a

(Procedures) was identified for an inadequate postmaintenance testing procedure.

Craftsmen had replaced the field flash relay auxiliary contacts (following a previous field

flash failure on February 14, 2007) and had misaligned the contact assembly during

installation. Postmaintenance testing was inadequate because it did not verify that the

contacts properly repositioned to the closed position following the surveillance test.

When the emergency diesel generator was started two days later, for a normal

surveillance test, the field did not flash because the contacts were stuck open.

This finding was greater than minor because the finding was associated with the

mitigating systems cornerstone objective (procedure quality attribute) to ensure the

availability, reliability, and capability of systems that respond to initiating events to

prevent undesirable consequences. The exposure time for this performance deficiency

was approximately 60 hours6.944444e-4 days <br />0.0167 hours <br />9.920635e-5 weeks <br />2.283e-5 months <br />. Using the Manual Chapter 0609, Appendix A,

Determining the Significance of Reactor Inspection Findings for At-Power Situations,

Phase 1 screening worksheet, the inspectors determined that the finding was of very

low safety significance (Green) because it was not: 1) a design or qualification

deficiency; 2) a loss of system safety function; 3) an actual loss of safety function for

greater than its technical specification allowed outage time; 4) a loss of safety function

of a non-technical specification train; or 5) a seismic, flooding or severe weather related

finding. The finding had crosscutting aspects in the human performance area,

specifically the resource attribute (H.2(c)) in that a complete and accurate test

instruction was not provided to test the 2CR auxiliary relay contacts (Section 1R19).

TBD. The inspectors identified an apparent violation of 10 CFR 50, Appendix B,

Criterion XVI (Corrective Actions), with two examples, for the failure to: 1) treat the

February 14, 2007, emergency diesel generator failure as a significant condition

adverse to quality; and 2) promptly identify and correct a significant condition adverse to

quality (high resistance on field flash circuit contacts) after determining that similar

operating experience was applicable. In addition, a contributor to the inoperable

Enclosure

-3-

emergency diesel generator included the failure to revisit the diesel generator operability

evaluation in response to the applicable operating experience. Overall, the licensee

responded to various problems in isolation and did not adopt a corrective action process

that maintained emergency diesel generator reliability and availability.

This apparent violation was greater than minor because it affected the mitigating

systems cornerstone objective (equipment performance attribute), to ensure the

availability, reliability, and capability of systems that respond to initiating events to

prevent undesirable consequences. For the preliminary significance determination, the

inspectors used a 14 day exposure time, which was half the time period between the

last successful surveillance and the February 14, 2007, failure. However, this exposure

time could increase to 28 days if the NRC determines the failure was caused by contact

binding, versus contamination. Using the NRC Inspection Manual Chapter 0609,

Appendix AProperty "Inspection Manual Chapter" (as page type) with input value "NRC Inspection Manual 0609,</br></br>Appendix A" contains invalid characters or is incomplete and therefore can cause unexpected results during a query or annotation process., Determining the Significance of Reactor Inspection Findings for At-Power

Situations, significance determination process, a Region IV senior reactor analyst

determined that the finding was potentially Greater than Green. The finding had

crosscutting aspects in the area of problem identification and resolution, operating

experience component, because the licensee failed to institutionalize relevant operating

experience in a reasonable time (P.2(b)) (Section 4OA2.1).

TBD. The inspectors identified an apparent violation of Technical Specification 5.8.1.a

(Procedures) for failing to establish a procedure for proper lubrication of the auxiliary

contact sliding mechanism, an activity that affected the performance of the emergency

diesel generator. As a result, craftsmen used an unapproved wet lubricant on the

emergency diesel generator field flash relay auxiliary contact sliding mechanisms, which

was contrary to vendor recommendations, without a procedure that directed the action.

The lubricant was the most likely contributor to oil and dust contamination on the

auxiliary contact surfaces, which apparently caused the emergency diesel generator

failure on February 14, 2007. In addition, a contributor to the apparent violation included

the failure to properly implement the Reliability Centered Maintenance Program.

This finding was greater than minor because it affected the mitigating systems

cornerstone objective (procedure quality attribute), to ensure the availability, reliability,

and capability of systems that respond to initiating events to prevent undesirable

consequences. For the preliminary significance determination, the inspectors used a 14

day exposure time, which was half the time period between the last successful

surveillance and the February 14, 2007, failure. However, this exposure time could

increase to 28 days if the NRC determines the failure was caused by contact binding,

versus contamination. Using the NRC Inspection Manual Chapter 0609, Appendix A,

Determining the Significance of Reactor Inspection Findings for At-Power Situations,

significance determination process, a Region IV senior reactor analyst determined that

the finding was potentially Greater than Green. The finding had crosscutting aspects in

the area of human performance, resources component, in that the licensee failed to

provide a procedure to control a safety related maintenance activity (H.2(c))

(Section 4OA2.2).

Enclosure

-4-

REPORT DETAILS

1.

REACTOR SAFETY

Cornerstones: Initiating Events, Mitigating Systems, and Barrier Integrity

1R19

Post-Maintenance Testing (71111.19)

a.

Inspection Scope

The inspectors selected the below listed risk significant post-maintenance test activity.

The inspectors: (1) reviewed the applicable licensing basis and/or design-basis

documents to determine the safety functions; (2) evaluated the safety functions that may

have been affected by the maintenance activity; and (3) reviewed the test procedure to

ensure it adequately tested the safety function that may have been affected. The

inspectors reviewed test data to verify that acceptance criteria were met.

February 14, 2007, Work Order 263000-02, Replace the Auxiliary Contacts on

the 2CR Starter

Documents reviewed by the inspectors are listed in the attachment.

The inspectors completed one sample.

b.

Findings

Introduction. A self-revealing Green noncited violation of Technical Specification 5.8.1.a

(Procedures) was identified for an inadequate postmaintenance testing procedure.

Craftsmen had replaced the field flash relay auxiliary contacts (following a previous field

flash failure on February 14, 2007) and had misaligned the contact assembly during

installation. Postmaintenance testing was inadequate because it did not verify that the

contacts properly repositioned to the closed position following the surveillance test.

When the emergency diesel generator was started two days later, for a normal

surveillance, the field did not flash because the contacts were stuck open.

Description. When an emergency diesel generator first starts, a control circuit must

energize the generator field flash circuit in order to ensure proper electric generator

operation. A vital component in the field flash circuit is the field flash relay (2CR relay)

and its auxiliary contacts (2CR contacts). The contacts must be in the closed position to

enable the initial field flash but open when the field flash circuit is no longer needed. At

the end of a surveillance run, the contacts must be in their normally closed position to

support flashing the field during the next emergency diesel generator start. If the

contacts fail open, the emergency diesel generator is inoperable.

Following a Train A emergency diesel field flash failure on February 14, 2007, the

licensee found that the field flash relay auxiliary contacts had failed (this failure is

discussed in Section 4OA2 of this report). For this particular failure, high electrical

resistance across the auxiliary contacts likely caused the malfunction. Craftsmen

Enclosure

-5-

replaced the auxiliary contacts and performed postmaintenance testing in accordance

with Work Order 00263000-02. During the postmaintenance test, the emergency diesel

generator started and developed the required voltage. Operators returned the

emergency diesel generator to service. The licensee did not recognize, at the time, that

the field flash relay auxiliary contacts were stuck in the open position or that the

emergency diesel generator was inoperable.

On February 16, 2007, the licensee performed a surveillance of the Train A emergency

diesel generator and the generator field again failed to flash. The licensee found the

stuck open contacts and determined craftsmen had inadvertently misaligned the

contacts during installation, which caused the assembly to bind. The licensees root

cause analysis determined that the postmaintenance test was inadequate because it

failed to verify that the field flash relay auxiliary contacts had returned to their normally

closed position.

Analysis. The failure to perform an adequate postmaintenance test following safety

related work was a performance deficiency. This finding was greater than minor

because the finding was associated with the mitigating systems cornerstone objective

(procedure quality attribute) to ensure the availability, reliability, and capability of

systems that respond to initiating events to prevent undesirable consequences. The

exposure time for this performance deficiency was approximately 60 hours6.944444e-4 days <br />0.0167 hours <br />9.920635e-5 weeks <br />2.283e-5 months <br />. Using the

Manual Chapter 0609, Appendix A, Determining the Significance of Reactor Inspection

Findings for At-Power Situations, Phase 1 screening worksheet, the inspectors

determined that the finding was of very low safety significance (Green) because it was

not: 1) a design or qualification deficiency; 2) a loss of system safety function; 3) an

actual loss of safety function for greater than its technical specification allowed outage

time; 4) a loss of safety function of a non-technical specification train; or 5) a seismic,

flooding or severe weather related finding. The finding had crosscutting aspects in the

human performance area, specifically the resource attribute (H.2(c)) in that a complete

and accurate test instruction was not provided to test the 2CR auxiliary relay contacts.

Enforcement. Fort Calhoun Technical Specification 5.8.1.a states, in part, Written

procedures... shall be established, implemented and maintained covering the following

activities... The applicable procedures recommended in Regulatory Guide 1.33,

Revision 2, Appendix A, 1978. Regulatory Guide 1.33, Revision 2, Appendix A, 1978,

Section 8b(1)(q), recommends, in part, specific procedures for surveillance tests,

including "emergency power tests. The licensee performed postmaintenance testing of

the emergency diesel generator in accordance with Work Order 00263000-02. Contrary

to the above, as of February 16, 2007, the field flash relay postmaintenance test

procedure, an emergency power test procedure, was not adequate to satisfy this

requirement because the postmaintenance test failed to verify that the auxiliary contacts

were properly installed. Since this finding was of very low safety significance and was

documented in the licensees corrective action program as Condition

Reports 2007-00745 and 2007-00756, this violation is being treated as a noncited

violation (NCV), consistent with Section VI.A of the NRC Enforcement Policy

(NCV 05000285/2007011-01), Inadequate Emergency Diesel Generator

Postmaintenance Test.

Enclosure

-6-

4.

OTHER ACTIVITIES

4OA2 Identification and Resolution of Problems (71152)

Selected Issue Follow-up Inspection

a.

Inspection Scope

The inspectors selected the below listed issue for an in-depth review. The inspectors

considered the following during the review of the licensee's actions: 1) complete and

accurate identification of the problem in a timely manner; 2) evaluation and disposition

of operability/reportability issues; 3) consideration of extent of condition, generic

implications, common cause, and previous occurrences; 4) classification and

prioritization of the resolution of the problem; 5) identification of root and contributing

causes of the problem; 6) identification of corrective actions; and 7) completion of

corrective actions in a timely manner.

C

February 14, 2007, Train A emergency diesel generator field flash failure

Documents reviewed by the inspectors are listed in the attachment.

The inspectors completed one sample.

b.

Findings

The following two apparent violations are equal contributors to the emergency diesel

generator failure. These apparent violations support one finding of potentially Greater

than Green significance. The NRC will document final enforcement and significance in

future correspondence.

.1

Inadequate Corrective Actions for Emergency Diesel Generator Failure

Introduction. The inspectors identified an apparent violation of 10 CFR 50, Appendix B,

Criterion XVI (Corrective Actions), with two examples, for the failure to: 1) treat the

February 14, 2007, emergency diesel generator failure as a significant condition

adverse to quality; and 2) promptly identify and correct a significant condition adverse to

quality (high resistance on field flash circuit contacts) after determining that similar

operating experience was applicable. In addition, a contributor to the inoperable

emergency diesel generator included the failure to revisit the diesel generator operability

evaluation in response to the applicable operating experience. Overall, the licensee

responded to various problems in isolation and did not adopt a corrective action process

that maintained emergency diesel generator reliability and availability.

Description. When an emergency diesel generator first starts, a control circuit must

energize the generator field flash circuit at 750 rpm in order to ensure proper electric

generator operation. A vital component in the field flash circuit is the field flash relay

(2CR relay) and its auxiliary contacts (2CR contacts). Prior to the 750 rpm engine

speed, the 2CR contacts are in their normally closed position. At 750 rpm the circuit is

Enclosure

-7-

energized and the generator field is flashed. When generator voltage is sufficient, the

generator voltage regulator can control the generator field, thus the field flash circuit is

no longer needed. The field flash circuit is then disabled by energizing the 2CR relay,

which opens the 2CR contacts. The relay is then de-energized and the contacts return

to their normally closed position, ready for the next emergency diesel generator start.

The generator will fail to develop adequate voltage if the field flash circuit does not

function as designed. Two potential failure modes include excessive resistance across

the 2CR contacts (due to surface contamination or oxidation) and mechanical binding of

the contacts in the stuck open position.

On February 14, 2007, during the monthly Train A emergency diesel generator

surveillance, the generator field failed to flash at the required 750 rpm. The licensee

determined that a malfunction of the 2CR auxiliary contacts had caused the field flash

failure.

Inadequate Corrective Actions for February 14, 2007 Failure: On April 30, 2007, the

inspectors identified that the licensee had failed to treat the February 14, 2007,

unsuccessful emergency diesel generator run as a significant condition adverse to

quality and had subsequently failed to take required actions.

A failed emergency diesel generator is a significant condition adverse to quality. For

significant conditions adverse to quality, 10 CFR 50, Appendix B, Criterion XVI

(Corrective Actions) requires the licensee to identify the cause for the failure and to take

actions to preclude repetition. While the licensee did enter the problem into their

corrective action program as Condition Report 200700725 and replaced the 2CR

auxiliary contacts, it failed to identify the cause for the failure or to specify actions to

preclude repetition. This is the first example of an apparent violation fo 10 CFR 50,

Appendix B, Criterion XVI.

Root Cause: In response to the inspectors concerns, the licensee performed a root

cause assessment and sent the failed auxiliary contacts to an independent laboratory

for analysis. The root cause determined that high contact electrical resistance caused

the failure. The licensee had measured contact electrical resistance immediately

afterwards and noted that the as-found resistance varied between 10 and 300 Ohms (on

numerous different measurement attempts). The resistance should have been 0 Ohms.

The licensee determined that as little as 11 Ohms of resistance was sufficient to cause

circuit failure.

An independent laboratory provided a formal report to the licensee entitled Failure

Analysis of GE CR105 X 300 Auxiliary Contact Assemblies, dated July, 2007. The

laboratory found contaminants on the contact surfaces. The contamination was a

combination of oil and dust, which likely came from the operating environment. The

report speculated that some of the oil could have come from the fingers of individuals

who had handled the contacts. However, the report later dismissed this possibility by

stating that some of the contaminants were caked on the surface.

The laboratory cautioned that the reliability of the results was affected by mishandling of

the auxiliary contacts prior to their arrival at the lab. The report stated that the as-found

Enclosure

-8-

condition of the contacts was disturbed and that the auxiliary contacts had been

disassembled and then reassembled in an inappropriate manner. The inspectors

determined that the contacts were mishandled following the diesel failure because the

licensee had not recognized the problems significance and had failed to follow

reasonable protocols for the control and handling of the failed component. Nonetheless,

based on pictures of the contact surfaces, showing spots of contamination, and

electrical resistance readings, the inspectors agreed that the circuit failure was likely

caused by the dust and oil surface contamination. However, neither the inspectors nor

the licensee could conclusively exclude the possibility that the contacts had stuck in the

open position following the previous surveillance (28 days earlier).

Inadequate Response to Applicable Industry Operating Experience: The

inspectors found that the licensee had failed to promptly identify a significant condition

adverse to quality in response to applicable operating experience. Fort Calhoun entered

operating experience associated with an emergency diesel generator failure - dirty field

flash relay contacts - into their Operating Experience System on May 19, 2006 (Fort

Calhoun Operating Experience Number 2007-6767). High resistance across K2 (field

flash interrupt) contacts caused the diesel generator to fail its surveillance test. The K2

contacts serve the same function as the Fort Calhoun 2CR contacts.

The licensee failed to properly evaluate emergency diesel generator operability in

response to the operating experience. Fort Calhoun personnel wrote Condition

Report 200602614. dated June 21, 2006, to evaluate the operating experience. The

operability determination did not challenge operability because, at the time, Operations

did not know if the operating experience applied to Fort Calhoun. Engineering

determined that the operating experience was applicable to Fort Calhoun on September

16, 2006, but did not revisit operability, they just updated the condition report. The

failure to revisit operability when additional information was identified was inconsistent

with NRC RIS 2005-20, Part 9900 Technical Guidance: Operability Determinations and

Functionality Assessments for Resolution of Degraded or Nonconforming Conditions

Adverse to Quality or Safety. Specifically, this document states, in part:

Reviewing the performance of SSCs [structures systems and components] and

ensuring their operability is a continual [emphasis added] process. Potential

degraded or nonconforming conditions of SSCs may be discovered during many

activities:... j. Operational event reviews.

The inspectors determined that the subsequent engineering response and related

corrective actions were not timely. Engineers determined that the operating experience

was applicable to Fort Calhoun on September 16, 2006, but waited until

January 30, 2007, to make a recommendation for a functional test. The due date for

procedure changes was June 15, 2007. The inspectors noted that checking the

resistance across the auxiliary contacts could have been performed in a few minutes.

In addition, the inspectors determined that the licensees response to the subject

operating experience was not reasonable because:

Enclosure

-9-

The operating experience was directly applicable to Fort Calhoun Station.

Fort Calhoun had documented instances of unexpected high resistance readings

on 2CR and 3CR auxiliary contacts. In 1989 and 1990, FCS wrote Work Orders

892492, 900235, and 900485 that documented higher than expected contact

resistance on the Train B emergency diesel generator 2CR and 3CR auxiliary

contacts. The 3CR auxiliary contacts are exactly the same component

(manufacturer and model number) as the 2CR contacts. In response to this

problem, the licensee replaced the affected Train B auxiliary contacts. The Train

A auxiliary contacts were not replaced.

The field flash circuit was particularly sensitive to high resistance across the 2CR

contacts. As little as 11 Ohms could cause field flash circuit failure (similar to the

operating experience description).

The 2CR auxiliary contacts had been in service for many years.

The licensee did not establish a periodic preventive maintenance task to check

contact condition or electrical resistance.

This is the second example of an apparent violation of 10 CFR 50, Appendix B,

Criterion XVI.

Analysis. The failure to treat the February 14, 2007, emergency diesel generator failure

as a significant condition adverse to quality and the failure to promptly identify a

significant condition adverse to quality in response to applicable operating experience

were performance deficiencies. These concerns were greater than minor because they

affected the mitigating systems cornerstone objective (equipment performance

attribute), to ensure the availability, reliability, and capability of systems that respond to

initiating events to prevent undesirable consequences. For the preliminary significance

determination, the inspectors used a 14-day exposure time, which was half the time

period between the last successful surveillance and the February 14, 2007, failure.

However, this exposure time could increase to 28 days if the NRC determines the failure

was caused by contact binding, versus contamination. Using the NRC Inspection

Manual Chapter 0609, Appendix A, Determining the Significance of Reactor Inspection

Findings for At-Power Situations, significance determination process Phase 1 screening

worksheet, the finding screened to a Phase 2 significance determination because the

Train A emergency diesel generator was inoperable for greater than the Technical

Specification allowed outage time. A Region IV senior reactor analyst performed a

Phase 2 significance determination and found the finding was potentially Greater than

Green. The senior reactor analyst performed a preliminary Phase 3 significance

determination, which is included as Attachment 2 to this report. The finding had

crosscutting aspects in the area of problem identification and resolution, operating

experience component, because the licensee failed to institutionalize relevant operating

experience in a reasonable time (P.2(b)).

Enforcement. 10 CFR 50, Appendix B, Criterion XVI (Corrective Actions) states, in part,

Measures shall be established to assure that conditions adverse to quality, such as

failures... [and] deficiencies are promptly identified and corrected. In the case of

Enclosure

-10-

significant conditions adverse to quality, the measures shall assure that the cause of the

condition is determined and corrective action taken to preclude repetition. Contrary to

the above, as of April 30, 2007, the licensee failed to take measures to assure that the

cause of the February 14, 2007, Train A emergency diesel generator failure (a

significant condition adverse to quality) was determined and corrective actions taken to

preclude repetition. In addition, prior to February 14, 2007, the licensee failed to

promptly identify and correct a significant condition adverse to quality, in that the

licensee had determined that operating experience associated with an emergency

diesel generator failure was applicable to Fort Calhoun but failed to promptly identify the

same significant condition at this station. The licensee captured this finding in their

corrective action program as Condition Report 200700725. This is an apparent violation

pending completion of a final significance determination, AV 05000285/20070011-02,

Inadequate Emergency Diesel Generator Corrective Measures.

.2

Failure to Have Procedure for Work on Safety Related Components

Introduction. The inspectors identified an apparent violation of Technical Specification 5.8.1.a (Procedures) for failing to establish a procedure for proper lubrication of the

auxiliary contact sliding mechanism, an activity that affected the performance of the

emergency diesel generator. As a result, craftsmen used an unapproved wet lubricant

on the emergency diesel generator field flash relay auxiliary contact sliding

mechanisms, which was contrary to vendor recommendations, without a procedure that

directed the action. The lubricant was the most likely contributor to oil and dust

contamination on the auxiliary contact surfaces, which apparently caused the

emergency diesel generator failure on February 14, 2007. In addition, a contributor to

the apparent violation included the failure to properly implement the Reliability Centered

Maintenance Program.

Description. The inspectors identified that craftsmen were applying a wet lubricant

(Molykote 55M) to the 2CR auxiliary contact sliding surfaces without an approved

procedure that directed the action. The independent laboratory found a wet lubricant on

the auxiliary contacts sliding surfaces. The licensee had informed the laboratory that

the lubricant was most likely Molykote 55M. This lubricant was the most likely

contributor to oil found on the contact surfaces because oil tends to migrate and the

lubricant was in the closest proximity to the contact surfaces.

The auxiliary contact vendor, General Electric (GE), had recommended against using a

wet lubricant, such as Molykote 55M, because it would attract dirt and foreign material

and could cause auxiliary contact binding. While the licensee had written a letter to GE,

asking for permission to use Molykote 55M, the licensee was unable to find a response

from GE that accepted the practice. More recently, the licensee contacted GE and was

informed that the vendor still did not approve of wet lubricants on the auxiliary contact

sliding mechanisms.

Plant craftsmen informed the inspectors that they always used Molykote 55M on

auxiliary contacts in the plant. The inspectors asked the licensee to provide the

procedure that directed and approved this action. The licensee was unable to provide

an appropriate instruction. The licensee believes that fossil unit workers had started the

informal lubrication practice and permanent plant workers continued it.

Enclosure

-11-

By failing to establish a procedure for this activity, the licensee bypassed other

processes, such as 10 CFR 50.59, that could have identified potential adverse

unintended consequences - such as the increase in the probability of malfunction of

equipment important to safety.

Failure to Follow Reliability Centered Maintenance Program: As a contributing

cause, the licensee determined that their Reliability Centered Maintenance program was

inadequate. The licensee had planned to change to a new program, which would

effectively correct the problem.

The inspectors found that the program was adequate, but the licensee had failed to

properly implement the program. For example, PBD-13, Preventive Maintenance,

Revision 4 states, in part:

The reliability centered maintenance methodology consists of a series of orderly

steps to systematically identify functional subsystems for a system, identify

components required to satisfy the function, and then determine credible failure

modes for each item and the effects that these failure modes would have on

equipment operation.

Preventive Maintenance Basis (PM Basis) - the PM Basis identifies and justified

the PM program on a component [emphasis added] level.

Predictive (Condition Monitoring) Activities - activities that analyze equipment

performance to detect and develop trends so that appropriate corrective actions

can be taken before [emphasis added] the equipment is no longer capable of

performing its intended function...

Preventive Maintenance Standards are developed for each major component

type. Preventive Maintenance Standards include: normal preventive

maintenance to be performed; its frequency and basis; failure mechanisms, their

causes, and preventive maintenance that could be performed on that type of

component; site specific component failure information for that component type;

and recommendations, requirements, and industry operating experience.

Appendix D to PBD-13 specifies, in part, that a comprehensive PM program be

developed because single failures can not be tolerated for risk significant

structures systems and components.

Contrary to the above, for the 2CR relays (with attached 2CR auxiliary contacts):

1.

For the field flash function, the licensee identified the subsystem required to

support the function but failed to determine credible failure modes for each item

or the effects that these failure modes would have on equipment operation.

Consequently, no meaningful preventive maintenance or condition monitoring

was performed.

Enclosure

-12-

2.

No PM Basis was identified and justified on a component [emphasis added] level

basis for the 2CR auxiliary contacts (or the circuit that contained the contacts).

3.

Predictive Maintenance activities were not specified to analyze equipment

performance to detect and develop trends so that appropriate corrective actions

could be taken before [emphasis added] the equipment was no longer capable

of performing its intended function.

4.

A comprehensive preventive maintenance activity was not established for these

risk significant components.

The inspectors noted that the licensee had performed evaluations for other relays and

their associated contacts. The failure modes included dirty contacts. This is a

contributor to the apparent violation. However, failing to establish preventive

maintenance to preclude relay failures meant that the licensee had essentially

implemented a run to failure, then fix approach for these components.

Analysis. The failure to provide a technical specification required procedure to control

the application of lubricants on safety related components was a performance

deficiency. This finding was greater than minor because it affected the mitigating

systems cornerstone objective (procedure quality attribute), to ensure the availability,

reliability, and capability of systems that respond to initiating events to prevent

undesirable consequences. For the preliminary significance determination, the

inspectors used a 14-day exposure time, which was half the time period between the

last successful surveillance and the February 14, 2007, failure. However, this exposure

time could increase to 28 days if the NRC determines the failure was caused by contact

binding, versus contamination. Using the NRC Inspection Manual Chapter 0609,

Appendix AProperty "Inspection Manual Chapter" (as page type) with input value "NRC Inspection Manual 0609,</br></br>Appendix A" contains invalid characters or is incomplete and therefore can cause unexpected results during a query or annotation process., Determining the Significance of Reactor Inspection Findings for At-Power

Situations, significance determination process Phase 1 screening worksheet, the

finding screened to a Phase 2 significance determination because the Train A

emergency diesel generator was inoperable for greater than the technical specification

allowed outage time. A Region IV senior reactor analyst performed a Phase 2

significance determination and found the finding was potentially Greater than Green.

The senior reactor analyst performed a preliminary Phase 3 significance determination,

which is included as Attachment 2 to this report. The finding had crosscutting aspects

in the area of human performance, resources component, in that the licensee failed to

provide a procedure to control a safety related maintenance activity (H.2(c)).

Enforcement. Fort Calhoun Technical Specification 5.8.1.a states, in part, Written

procedures... shall be established, implemented and maintained covering the following

activities... The applicable procedures recommended in Regulatory Guide 1.33,

Revision 2, Appendix A, 1978. Regulatory Guide 1.33, Revision 2, Appendix A, 1978,

Section 9, recommends procedures for Maintenance that can affect the performance of

safety-related equipment. Contrary to the above, the licensee failed to provide a written

procedure for maintenance that could affect the performance of safety-related auxiliary

contacts, in that craftsmen were applying lubrication to safety-related auxiliary contact

sliding mechanisms without a procedure or other written instruction. The licensee

captured this finding in their corrective action program as Condition Report 2007-2911.

This is an apparent violation pending completion of a final significance determination,

Enclosure

-13-

AV 05000285/20070011-03, Failure to Provide Procedure for Safety Related

Maintenance Activities.

4OA6 Meetings, Including Exit

On September 18, 2007, the Senior Resident Inspector presented the inspection

findings to Mr. Tim Nellenbach, Plant Manager, and other members of the licensees

staff. The licensee acknowledged the findings. The inspector confirmed that proprietary

information was not provided or examined during the inspection.

ATTACHMENTS: 1. SUPPLEMENTAL INFORMATION

2. PRELIMINARY SIGNIFICANCE DETERMINATION

Attachment 1

A1-1

Attachment 1

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee Personnel

D. Bannister, Acting Site Director

G. Cavanaugh, Supervisor, Regulatory Compliance

M. Frans, Manager, System Engineering

H. Faulhaber, Division Manager, Engineering

M. Ferm, Manager, Shift Operations

D. Guinn, Licensing Engineer

D. Lakin, Manager, Corrective Action Program

J. McManis, Manager, Licensing

T. Nellenbach, Plant Manager

R. Johansan, Manager, Maintenance

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

Opened

05000285/2007011-02

AV

Inadequate Emergency Diesel Generator

Corrective Measures (Section 4OA2.1)05000285/2007011-03

AV

Failure to Provide Procedure for Safety Related

Maintenance Activities (Section 4OA2.2)

Opened and Closed

05000285/2007011-01

NCV

Inadequate Emergency Diesel Generator

Postmaintenance Test (Section 1R19)

LIST OF DOCUMENTS REVIEWED

Section 1R19: Post-Maintenance Testing

Work Order 263000-02, Replace the Aux Contacts on the 2CR Starter

Drawing B120C11509, Schematic Diagram Field Flashing Control, Sheet 1, Revision 9

Root Cause Analysis Report, Emergency Diesel Generator #1 (Unknown Inoperability - 2/14/07 to

2/16/07)

Condition Reports 200700756, 200700725, 200700745, and 200700875

Attachment 1

A1-2

Section 4OA2: Other Activities (Identification and Resolution of Problems (71152))

Procedures

SO-R-2, Condition Reporting and Corrective Action, Revision 34

MM-ST-DG-0001, Diesel Generator DG-1 Inspection, Revisions 56 and 57

OP-ST-DG-0001, Diesel Generator 1 Check, Revision 53

PBD-13, Preventive Maintenance, Revision 4

PED-SEI-13, Preventive maintenance Program - Technical Basis, Revision 11

Drawings

B120C11509, Schematic Diagram Field Flashing Control, Sheet 1, Revision 9

B120C11509, Schematic Diagram Field Flashing Control, Sheet 2, Revision 3

44D302335, 1 Phase Full Wave SCR Static Exciter, Sheet 2, Revision 6

B120F11503, emergency Generators Control Cabinets AI-133A & AI-133B, Sheet 3,

Revision 13

Maintenance Work Orders

900485, 892492, 892951, 263000-02

Condition Reports

2007-2227, 2007-2712, 2007-2911, 2007-2912, 200700725, 200700745, 200700756, 200700875

Miscellaneous

Control Room Logs, Day Shift, 01-17-2007

Control Room Logs, Day Shift, 02-14-2007

Control Room Logs, Night Shift, 02-14-2007

Control Room Logs, Day Shift, 02-16-2007

Control Room Logs, Night Shift, 02-16-2007

Shift Manager Logs, Night Shift, 02-16-2007

Southwest Research Institute Failure Analysis of GE CR105 X 300 Auxiliary Contact Assemblies

dated July 2007

Root Cause Analysis Report, Emergency Diesel Generator DG-1 Field Flash Functional Failure

(2/14/2007)

NUREG/CR-5762, Comprehensive Aging Assessment of Circuit Breakers and Relays

(ML0412805681)

TD G080.2800, Instruction Manual for Static Exciter Regulator for AC Generators, Revision 1

TD G100.0490, Instruction Manual for AC Synchronous Generators, Revision 0

Attachment 1

A1-3

TD G080.4350, Renewal Parts Magnetic Motor Starters NEMA Size 3

TD G080.3500, NEMA Size 3 CR105 Magnetic Contactors, CR106 Magnetic Starters

LIST OF ACRONYMS

AV

Apparent Violation

CFR

Code of Federal Regulations

NCV

noncited violation

NRC

Nuclear Regulatory Commission

Attachment 2

A2-1

Attachment 2

Preliminary Significance Determination

Significance Determination Basis for Apparent Violations, February 14, 2007 Failure

Reactor Inspection for IE, MS, BI Cornerstones

a.

Phase 1 Screening Logic, Results and Assumptions

In accordance with NRC Inspection Manual Chapter 0612, Appendix B, "Issue Screening,"

the inspectors determined that: 1) the failure to identify the cause and specify corrective

actions to preclude repetition for a significant condition adverse to quality; 2) the

application of a lubricant on the auxiliary contacts without an approved procedure; 3) the

failure to promptly identify and correct a significant condition adverse to quality, that was

identified through operating experience reviews; 4) the failure to revisit operability in

response to new adverse operating experience; and 5) the failure to implement the

Reliability Centered Maintenance program were performance deficiencies. This finding

was determined to be greater than minor because the condition affected the

availability/reliability the Train A emergency diesel generator and thus affected the

Equipment Performance attribute under the Mitigating Systems cornerstone.

The last known successful test of Train A emergency diesel generator occurred 28 days

prior to the February 14, 2007, failure. Because the exact failure mode could not be

determined the exposure time was assumed to be one half the time since the last know

successful performance of the diesel generator or 14 days. In accordance with NRC

Inspection Manual Chapter 0609, Appendix A, Determining the Significance of Reactor

Inspection Findings for At-Power Situations, dated March 23, 2007, the inspectors

conducted a significance determination process (SDP) Phase 1 screening and determined

that the finding resulted in loss of the safety function of Train A emergency diesel

generator for greater than the Technical Specification allowed outage time. Consequently,

a Phase 2 SDP risk significance estimation was required.

b.

Phase 2 Estimation

Internal Events and Large Early Release Frequency (LERF)

The inspectors and a RIV senior reactor analyst (SRA) performed a Phase 2 evaluation

using the Risk-Informed Inspection Notebook for Fort Calhoun Power Station,

Revision 2.01, (SDP Phase 2 Notebook) and its associated "Phase 2 Pre-solved Table."

The last successful surveillance test of Train A emergency diesel generator was performed

on January 17, 2007, and the test failure was on February 14, 2007. The inspectors could

not determine with certainty when the EDG became non-functional. Therefore, in

accordance with the SDP Usage Rule for exposure time, a "T/2" exposure time of 14 days

was assumed. A 14-day exposure time is represented as a "3 - 30 day" exposure category

in the SDP Phase 2 evaluation.

Attachment 2

A2-2

The inspectors determined that after an emergency start of Train A emergency diesel

generator during a loss of offsite power (LOOP), operators would not be capable of

diagnosing and correcting the problem with the field flash relay. Therefore, recovery was

not credited.

The Train A emergency diesel generator was identified as a target in the Phase 2 pre-

solved table so it could be used directly to assess the finding. The pre-solved table

identified that the finding was "CDF-dominant." Therefore, no additional review was

required for LERF consideration. For a 3 - 30 day exposure time, the pre-solved table

identified that the significance of the finding was White with respect to CDF. The dominant

sequence (with an equivalent risk contribution of 6) involved a station blackout (LOOP with

failure of the EDGs), and failure to recover offsite power in 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> (LOOP - EAC - REC8).

External Events

Neither the Fort Calhoun SDP Phase 2 Notebook, nor the pre-solved table includes

screening capability for external events or other initiating events. Because the risk

contribution of the finding due to internal events was Greater than Green, the SRA

conducted additional review for external event contribution. Experience has shown, using

the Risk-Informed Inspection Notebooks, that accounting for external initiators could result

in increasing the risk significance of an inspection finding by as much as one order of

magnitude. The SRA determined that the most efficient method of accounting for external

initiators was to use the guidance provided in IMC 0609, Appendix A, Attachment 3, "User

Guidance for Screening of External Events Risk Contributions."

Screening of Fire Risk Contributions

The finding affected Train A emergency diesel generator, which was not in the protected

train of the post-fire safe shutdown path. Ordinarily, this would result in the finding being

screened from further consideration for fire-risk contribution using IMC 0609, Appendix A,

Attachment 3. However, the licensee's probabilistic safety assessment staff informed the

analyst that there were some fire areas where Train A emergency diesel generator was

credited. These fire areas included fires in the upper electrical penetration room, the lower

electrical penetration room, and for any fire scenario involving a LOOP with the loss of the

4160 V Bus 1A4 or the EDG-2. The risk contribution of these fire areas is addressed in the

Section C.

Screening of Seismic Risk Contributions

The analyst determined the finding did not immediately screen out as insignificant due to

seismic risk contribution. This was because Train A emergency diesel generator was on

the licensee's IPEEE list of equipment addressed in their seismic margins approach to

seismic risk contribution, it was used to mitigate the consequences of a loss of AC power

during a seismic event, and the exposure time of the finding was greater than 3 days.

Therefore, the analyst continued the evaluation using the guidance in the Risk Assessment

Standardization Project (RASP) External Events Handbook.

The analyst estimated the seismic contribution using the "Seismic Event Modeling and

Seismic Risk Quantification Handbook" of the RASP External Events Handbook. For Fort

Attachment 2

A2-3

Calhoun Station, the frequency of a seismically-induced LOOP event was estimated as

1.06E-4/year. The SPAR model estimate of the failure-to-run of EDG-2 was 2.068E-2.

Therefore the estimated CDF of a seismically-induced LOOP with a random failure of

DG-2 for a 14-day exposure period was in the high E-8/year range. The seismic risk

contribution of the finding was insignificant relative to the internal events result.

Screening of Flood Risk Contributors

Using IMC 0609, Appendix A, Attachment 3, Table 3.1, "Plant Specific Flood Scenarios

and Initiator Frequencies," the analyst determined that Train A emergency diesel generator

was not a structure, system, or component identified as critical to avoiding core damage for

any flood scenario of significance. Therefore, flood risk contribution was screened out

from further consideration.

Estimation of External Event Risk Contributions

Based on the screening of external event risk contributions described above, the analyst

concluded the total risk contribution from external events (other than fire) resulting from the

finding was not significant. Further assessment was necessary with respect to fire-risk

contribution.

c.

Validation of Phase 2 SDP Results

The SRA used the NRC's simplified plant analysis risk (SPAR) model for Fort Calhoun

Station, Revision 3.31, dated April 10, 2006, to estimate the increase in risk associated

with the finding due to internal initiating events. Average test and maintenance and

"winter" raw water success criteria were assumed. A cutset truncation of 1.0E-12 was

used.

Consistent with the Phase 2 SDP evaluation, the SRA used a 14-day exposure time and

the observed failure of Train A emergency diesel generator was modeled as a failure-to-

start basic event.

The SRA noted that an influential assumption in the analysis would be whether the finding

resulted in a random, independent, or common-cause failure of the Train A emergency

diesel generator field flash relay. Guidance in the RASP Handbook states that if the cause

of the failure cannot be determined to be independent, or common-cause related, that the

cause should be assumed to be random in the analysis. Additionally, the RASP Handbook

states that a component failure can be considered independent when the cause is well

understood and there is no possibility (probability = 0.0) that the same circumstances exist

in other components in the common-cause component group.

At the conclusion of the inspection, the licensee had not definitively ruled out the potential

for common-cause failure to be a consideration in its root cause assessment work. Some

evidence indicated that the Train A emergency diesel generator field flash relay failure may

have been independent based on differences in the age of the relays and past

maintenance practices. However, the SRA considered that there must be at least some

possibility that the same circumstances resulting in the Train A emergency diesel generator

failure could exist in EDG-2.

Attachment 2

A2-4

Consistent with guidance in the RASP Handbook, including the NRC document, "Common-

Cause Failure Analysis in Event Assessment, (June 2007)", the SRA modeled the

condition by adjusting the following basic events in the SPAR model:

EPS-DGN-FS-1A = TRUE

EPS-DGN-FR-1A = 1.0

EPS-DGN-CF-RUN = FALSE

The SPAR baseline CDF was 1.69E-5/year. The evaluation case for the above change set

resulted in a CDF of 2.40E-4/year. The dominant core damage sequence was a LOOP,

followed by failure EDG-2, failure to maintain reactor coolant system subcooling, and

failure to recover an EDG or offsite power within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />.

The change in CDF (CDF) was:

CDF = CDFcase - CDFbase

= 2.40E-4/year - 1.69E-5/year = 2.23E-4/year.

Therefore, the total change in core damage frequency over the exposure time that was

related to this finding was calculated as:

CDF = 2.23E-4/year ÷ 365 days/year * 14 days = 8.56E-6 over the period.

This result was consistent with the White Phase 2 SDP result. Therefore, the analyst

considered the White Phase 2 SDP result to be validated for the risk contribution resulting

from internal initiating events.

Potential Risk Contribution due to LERF,

The dominant core damage sequences evaluated in the Phase 2 SDP evaluation did not

involve a potential for containment bypass. Therefore, using the guidance of IMC 0612,

Appendix HProperty "Inspection Manual Chapter" (as page type) with input value "NRC Inspection Manual 0612,</br></br>Appendix H" contains invalid characters or is incomplete and therefore can cause unexpected results during a query or annotation process., "Containment Integrity Significance Determination Process," the finding

screened from further consideration with respect to LERF. The analyst concluded that the

significance of the finding obtained from the CDF assessment was sufficient to

characterize its risk significance and no further LERF-related evaluation was necessary.

Estimation of Risk Contribution from Fire and Total Risk Contribution of Finding

Using information provided by the licensee from its own fire analysis work, the analyst

performed a simplified estimate of the total risk contribution (including fire events) using the

internal events SPAR model result. The licensee estimated that for a finding resulting in

unavailability of the Train A emergency diesel generator, approximately 33 percent of the

total core damage frequency resulted from fire events.

Therefore, for a 14-day exposure period, the total risk contribution of the finding for internal

initiating events and external initiating events combined could result in a CDF in the low

E-5 range.

Attachment 2

A2-5

d.

Licensees Preliminary Risk Evaluation

The licensee's probabilistic safety assessment (PSA) staff provided the analyst with

preliminary insights from its own risk assessment of the Train A emergency diesel

generator failure. The licensee first performed its assessment assuming Train A

emergency diesel generator was out of service for maintenance, which did not address the

concern discussed above addressing adjustments for potential common-cause failure. The

licensee's baseline model CDF, which also includes seismic initiators, was 1.87E-5/year.

The evaluation case CDF with Train A emergency diesel generator in maintenance was

7.54E-5/year, resulting in a CDF of 2.2E-6/year over the 14-day exposure period.

The licensee provided additional information after consideration of fire scenarios and

consideration of common cause failure to start of EDG-2. The new model added the

existing licensees existing Revision 7 PRA model to an upgraded fire model taken from

the Individual Plant Examination of External Events (IPEEE). An example of an upgrade in

the fire model obtained from the IPEEE was that the probability of circuit failure resulting

from a hot short was increased from the IPEEE original value of 0.06 to a revised value of

0.6.

In the revised model, which now included internal events, internal flood, seismic, and fire,

the baseline CDF with random failures of the EDGs and nominal common cause failure,

was 4.08E-5/year. With Train A emergency diesel generator failed, and a change in the

probability of EDG-2 failure due to common cause increasing similar to the SPAR model

calculation, the resulting evaluation case CDF was 1.75E-4/year. This resulted in a CDF

of 5.14E-6/year over the 14-day exposure period.

The dominant fire initiating event was a fire in the EDG-2 room, with subsequent failure of

EDG-2, hot short-induced failure of offsite power to its associated vital bus, and failure of

offsite power to the other train with the already failed Train A emergency diesel generator.

Core damage sequences involving this initiator represented 13 percent of the total

contribution to CDF.

e.

Conclusion

The Phase 2 analysis of the significance of the finding, validated with use of the NRC

SPAR model, resulted in a determination that the significance was at least of low-to-

moderate safety significance (White). However, this conclusion was dependent on the

influential assumption of a 14-day exposure time. Additionally, external initiating events

were known to be a potentially significant contributor to the overall significance of the

finding. Although the licensees preliminary results had been discussed, the licensee had

not completed its own final analysis of the significance of the finding by the conclusion of

the inspection. Pending completion of this analysis and review by the NRC staff, the

analyst considered the significance of the inspection finding best characterized as Greater

than Green.