Proposed Technical Specifications Change Supplement Re Operable Definition Modification for Air Handling Units While in Temporary 45-Day Allowed Outage Times
ML072681171
Person / Time
Site: Surry  Dominion icon.png
Issue date: 09/25/2007
From: Gerald Bichof
Virginia Electric & Power Co (VEPCO)
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
07-0109D
Download: ML072681171 (32)


Text

VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND, VIRGINIA 2326 1 September 25, 2007 U.S. Nuclear Regulatory Commission Serial No. 07-0109D Attention: Document Control Desk SPS-LICICGL R1 Washington, D.C. 20555 Docket Nos. 50-280, 281 License Nos. DPR-32, 37 VIRGINIA ELECTRIC AND POWER COMPANY SURRY POWER STATION UNITS 1 AND 2 PROPOSED TECHNICAL SPECIFICATIONS CHANGE SUPPLEMENT OPERABLE DEFINITION MODIFICATION FOR AIR HANDLING UNITS WHILE IN TEMPORARY 45-DAY ALLOWED OUTAGE TIMES In a letter dated February 26, 2007 (Serial No. 07-0109), Virginia Electric and Power Company (Dominion) requested amendments, in the form of changes to the Technical Specifications (TS) to Facility Operating License Numbers DPR-32 and DPR-37 for Surry Power Station Units 1 and 2, respectively. The proposed TS change would permit the use of temporary 45-day and 14-day allowed outage times (AOTs) to facilitate replacement of Main Control Room (MCR) and Emergency Switchgear Room (ESGR)

Air Conditioning System (ACS) chilled water piping. During activities to prepare for implementation of the chilled water piping replacement project and the proposed TS change, the need for an additional change to address a surveillance testing issue was recognized. Specifically, the operability requirements associated with the normal and emergency power supplies for the air handling units (AHUs) on the operating chilled water loop need to be modified while in the temporary 45-day AOTs during specific TS-required surveillance testing and related emergent corrective maintenance. This modification to the TS 1.O.D definition of OPERABLE will eliminate the need to enter the TS 3.23 action statements to restore AHU operability or to bring the unit to HOT SHUTDOWNICOLD SHUTDOWN conditions and will apply only during the temporary 45-day AOTs.

In addition, the NRC requested that Dominion revise the footnote to TS 3.23 in the February 26, 2007 proposed TS change request. Specifically, it was requested that the phrase "with an average planned out-of-service time of 90 days per 12-month period" be deleted from the footnote. This same phrase is also included in and is being deleted from the proposed TS 3.23 Basis change in the February 26, 2007 letter. The proposed revision to the TS 3.23 Basis change is included for the NRC's information.

A discussion of the proposed additional TS revision is provided in Attachment 1. The marked-up and proposed TS pages reflecting the proposed revision are provided in Attachments 2 and 3, respectively.

Serial No. 07-01090 Docket Nos. 50-280, 50-281 Page 2 of 3 The February 26, 2007 determination concluded that a significant hazards consideration does not exist with respect to the chilled water piping replacement TS change. The no significant hazards determination included in the February 26, 2007 letter has been reviewed with respect to the proposed additional revision, and it has been concluded that it remains applicable. Likewise, the environmental assessment included in the February 26, 2007 proposed TS change request concluded that the chilled water piping replacement TS change meets the criteria specified in 10 CFR 51.22 for a categorical exclusion from the requirements of 10 CFR 51.22 relative to requiring a specific environmental assessment or impact statement by the Commission. That environmental assessment has been reviewed with respect to the proposed additional revision, and it has been concluded that the existing environmental assessment remains applicable.

Furthermore, the supporting PRA analysis for the chilled water replacement TS change remains applicable and bounding. The proposed change has been reviewed and approved by the Station Nuclear Safety and Operating Committee.

Please include the proposed TS revision discussed herein as part of the ongoing NRC review of the proposed TS change provided in our February 26, 2007 submittal.

If you have any questions or require additional information, please contact Mr. Gary D. Miller at (804) 273-2771.

Sincerely, Gerald T. Bischof w

Vice President - Nuclear Engineering COMMONWEALTH OF VIRGINIA )

COUNTY OF HENRICO The foregoing document was acknowledged before me, in and for the County and Commonwealth aforesaid, today by Gerald T. Bischof, who is Vice President - Nuclear Engineering, of Virginia Electric and Power Company. He has affirmed before me that he is duly authorized to execute and file the foregoing document in behalf of that Company, and that the statements in the document are true to the best of his knowledge and belief.

Acknowledged before me the J 9 d a y of , 2007.

My Commission Expires: ,-,&dh 31 &?U/O Notary Public

Serial No. 07-0109D Docket Nos. 50-280, 50-281 Page 3 of 3 Attachments:

1. Discussion of Change
2. Marked-up Technical Specifications Pages
3. Proposed Technical Specifications Pages Commitments made in this letter: None.

cc: U.S. Nuclear Regulatory Commission Region II Sam Nunn Atlanta Federal Center 61 Forsyth Street, SW Suite 23 T85 Atlanta, Georgia 30303 State Health Commissioner Virginia Department of Health James Madison Building - 7thFloor 109 Governor Street Room 730 Richmond, Virginia 23219 Mr. S. P. Lingam NRC Project Manager - Surry U. S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike Mail Stop 8G9A Rockville, Maryland 20852 Mr. R. A. Jervey NRC Project Manager - North Anna U. S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike Mail Stop 8G9A Rockville, Maryland 20852 Mr. R. Reyes NRC Senior Resident Inspector Surry Power Station

Attachment 1 Discussion of Change Operable Definition Modification for Air Handling Units While in Temporary 45-day Allowed Outage Times Surry Power Station Units 1 and 2 Virginia Electric and Power Company (Dominion)

Serial No. 07-0109D Docket Nos. 50-280150-281 Attachment 1 DISCUSSION OF CHANGE 1.0 Introduction Letter Serial No. 07-0109, dated February 26, 2007, transmitted proposed Technical Specifications (TS) revisions regarding the use of temporary 45-day and 14-day allowed outage times (AOTs) to permit the replacement of Main Control Room (MCR) and Emergency Switchgear Room (ESGR) Air Conditioning System (ACS) chilled water piping. During the activities to prepare for implementation of the chilled water piping replacement project and TS change, it was recognized that, during specific TS-required surveillance testing, resultant inoperability of the air handling units (AHUs) on the operating chilled water loop will require entry into an action statement to restore AHU operability within one hour or bring the unit to HOT SHUTDOWN (HSD) conditions within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and be in COLD SHUTDOWN (CSD) in the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.

Therefore, an additional TS change is requested to modify the operability requirements associated with the normal and emergency power supplies for the AHUs on the operating chilled water loop while in the temporary 45-day AOTs during specific TS-required surveillance testing and related emergent corrective maintenance. This modification to the TS 1.O.D definition of OPERABLE will eliminate the need to enter the action statement to restore AHU operability or to bring the unit to HSDICSD conditions.

In addition, the NRC requested that Dominion revise the footnote to TS 3.23 in the February 26, 2007 proposed TS change request. Specifically, it was requested that the phrase "with an average planned out-of-service time of 90 days per 12-month period" be deleted from the footnote. This same phrase is also included in and is being deleted from the proposed TS 3.23 Basis change in the February 26, 2007 letter. The proposed revision to the TS 3.23 Basis change is included for the NRC's information.

The proposed additional TS revision has been reviewed, and it has been determined that the change has no adverse safety impact. Furthermore, the no significant hazards determination included in the February 26, 2007 letter remains applicable with respect to the proposed additional TS revision. Likewise, the environmental assessment included in the February 26, 2007 letter has been reviewed with respect to the proposed revision, and it has been concluded that the existing environmental assessment remains applicable as well.

2.0 Discussion of Change As noted above, the Surry TS change request associated with the MCR and ESGR ACS chilled water piping replacement, which was transmitted by our February 26, 2007 letter, permits the use of temporary 45-day and 14-day AOTs to facilitate the piping replacement. That TS change request included a supporting probabilistic risk assessment (PRA) analysis with Tier 2 Equipment Unavailability Restrictions for Units 1 and 2. Emergency diesel generators (EDGs) 1, 2, and 3 were included in the restriction Page 1 of 10

Serial No. 07-0109D Docket Nos. 50-280150-281 Attachment 1 list with a Note that states: "Required surveillance testing and preventive maintenance will be performed. Surveillance testing and preventive maintenance scheduled during the temporary AOTs will be evaluated with respect to being rescheduled outside the .

AOTs. . . . Elective maintenance will not be performed, . . . ."

During the activities to prepare for implementation of the chilled water piping replacement project and the TS change, it was recognized that, when one of the chilled water loops is out of service for replacement and during the TS-required surveillances that render an EDG inoperable, TS action statement entry for AHU inoperability on the operating chilled water loop also results, due to inoperability of the AHU's emergency power source. This is because the Surry TS l.O.D definition of OPERABLE requires that both the normal and emergency electrical power sources be capable of performing their related support functions. In addition, because the redundant AHUs on the out of service loop are inoperable due the replacement of that loop, the provisions of TS 3.0.2 cannot be used. When a component is determined to be inoperable solely because either its emergency or normal power source is inoperable, TS 3.0.2 allows the component to be considered OPERABLE provided its corresponding normal or emergency power source is OPERABLE and its redundant component(s) is OPERABLE. Figure 2 from Attachment 4 in the February 26, 2007 letter is included for reference (at the end of this attachment); this figure illustrates AHU location in each chilled water loop and emergency power source (identified in parentheses). Since no provision was included in the chilled water piping replacement TS change to address the impact of the TS-required surveillances rendering an EDG inoperable during the piping replacement AOTs, the resultant AHU inoperability and the applicable TS requirements are as follows:

With Chilled Water Loop A out of service for replacement (1-VS-AC-1, 1-VS-AC-7, 2-VS-AC-7, and 2-VS-AC-9 inoperable):

J EDG 1 (1H) surveillance - no additional AHU inoperability and no AHU TS action statement entry required J EDG 2 (2H) surveillance VS-AC-6 and 2-VS-AC-8 inoperable; TS 3.23.C.2.c.l entry required on Units 1 and 2 J EDG 3 (1Jl2J) surveillance VS-AC-2 and 1-VS-AC-6 inoperable; TS 3.23.C.2.a.4 entry required on Unit 1 0 With Chilled Water Loop C out of service for replacement (1-VS-AC-2, I-VS-AC-6, 2-VS-AC-6, and 2-VS-AC-8 inoperable):

J EDG 1 (1H) surveillance - I-VS-AC-1 and 1-VS-AC-7 inoperable; TS 3.23.C.2.c.l entry required on Units 1 and 2 J EDG 2 (2H) surveillance - no additional AHU inoperability and no AHU TS action statement entry required J EDG 3 (1Jl2J) surveillance VS-AC-7 and 2-VS-AC-9 inoperable; TS 3.23.C.2.b.4 entry required on Unit 2 Page 2 of 10

Serial No. 07-0109D Docket Nos. 50-280150-281 Attachment 1 The referenced TS requirements are as follows:

With more than two Unit 1 or Unit 2 AHUs inoperable, TS 3.23.C.2.a.4 and TS 3.23.C.2.b.4 require restoration of operability of at least one AHU in each air conditioning zone on the respective unit within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> or bring the unit to HSD within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and be in CSD in the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.

Whenever both units are above CSD, with one or two AHUs on each unit powered from an H bus inoperable, TS 3.23.C.2.c.l requires restoration of operability of the inoperable AHU(s) on one unit within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> or bring both units to HSD within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and be in CSD in the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.

As noted above, the chilled water piping replacement TS change request indicated that surveillance testing scheduled during the temporary AOTs will be evaluated with respect to being rescheduled outside the AOTs. The preparation effort for the TS change request included an evaluation of surveillances. However, during implementation planning activities for the chilled water piping replacement, it was recognized that certain monthly and quarterly surveillances will need to be performed during the temporary 45-day AOTs. These surveillances render an EDG inoperable and, in turn, result in AHU inoperability. The surveillances of concern are monthly EDG surveillances (during which an EDG is declared inoperable for 3 to 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />), monthly Consequence Limiting Safeguards (CLS) logic surveillances (during which EDG 3 is declared inoperable for less than one hour), and quarterly EDG surveillances (during which an EDG is declared inoperable for 5 to 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />). The identified time periods of EDG inoperability for these surveillances are worst case times. The following surveillances that render an EDG inoperable will be conducted during Phase Ill of the piping replacement (chilled water loop C out of service for replacement). The associated AHU TS action statement entry is also identified:

J Two EDG 1 monthly surveillances - AHU TS action statement on Units 1 and 2 J Two EDG 2 monthly surveillances - no AHU TS action statement on either unit J EDG 3 monthly surveillance - AHU TS action statement on Unit 2 J Two Unit 1 CLS logic monthly surveillances - AHU TS action statement on Unit 2 J Unit 2 CLS logic monthly surveillance - AHU TS action statement on Unit 2 The surveillances that will be conducted and the associated AHU TS action statement entry during Phase IV (chilled water loop A out of service for replacement) are:

J EDG 1 monthly surveillance - no AHU TS action statement on either unit J EDG 1 quarterly surveillance - no AHU TS action statement on either unit J EDG 2 monthly surveillance - AHU TS action statement on Units 1 and 2 J EDG 3 monthly surveillance - AHU TS action statement on Unit 1 J EDG 3 quarterly surveillance - AHU TS action statement on Unit 1 J Unit 1 CLS logic monthly surveillance - AHU TS action statement on Unit 1 J Two Unit 2 CLS logic monthly surveillances - AHU TS action statement on Unit 1

Serial No. 07-0109D Docket Nos. 50-280150-281 Attachment 1 The need to perform the monthly and quarterly surveillances listed above during the temporary 45-day AOTs is based upon the current chilled water piping replacement project schedule.

An additional revision to the chilled water piping replacement TS change request is proposed to address the AHU TS action statement entry. The proposed revision is a footnote modifying the TS 1.O.D definition of OPERABLE as it applies to the normal and emergency power supplies for the AHUs under these specific conditions. The proposed footnote states: "For the purpose of performing Technical Specification-required surveillances that render an emergency diesel generator inoperable and completing any related emergent corrective maintenance within the TS 3.16.6.1 allowed outage time, the definition of OPERABLE for the air handling units on the operating chilled water loop is modified to require the normal or emergency electrical power source to be capable of performing its related support function. This footnote shall only apply during the temporary 45-day allowed outage times to permit replacement of the Main Control Room and Emergency Switchgear Room Air Conditioning System chilled water piping.

This proposed modification of the definition of OPERABLE will allow the AHUs to not be declared inoperable due to EDG inoperability and, thus, will eliminate the need to enter TS 3.23.C.2.a.4, TS 3.23.C.2.b.4, and TS 3.23.C.2.c.l.

The proposed revision is acceptable for the following reasons:

The modified OPERABLE definition for the AHUs will be applied for a very short duration during each of the two temporary 45-day AOTs. During Phase Ill, the duration of EDG inoperability (i.e., planned unavailability to perform TS-required surveillances) will be approximately 15 hours1.736111e-4 days <br />0.00417 hours <br />2.480159e-5 weeks <br />5.7075e-6 months <br />. Similarly during Phase IV, the duration will be approximately 17 hours1.967593e-4 days <br />0.00472 hours <br />2.810847e-5 weeks <br />6.4685e-6 months <br />.

During the monthly and quarterly EDG surveillances conducted during the temporary 45-day AOTs, the other EDGs that are not rendered inoperable by the surveillance testing will be identified as protected equipment in accordance with the Operations Department's Protected Equipment Program. This Program was discussed in the February 26, 2007 letter, which transmitted the chilled water piping replacement TS change.

In the event that related emergent EDG corrective maintenance is identified during a required surveillance, the EDG will be restored to service within the 7-day AOT in TS 3.16.B.1 or the reactor shall be brought to HSD within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and CSD within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.

Consistent with the current work planning practice regarding switchyard control, switchyard work will be coordinated with plant work, unit conditions, and testing activities such that an unnecessary risk to the station is not created. Furthermore, switchyard activities that could potentially affect the availability of the offsite power supply will be prohibited during TS-required surveillances that render an EDG inoperable conducted during the temporary 45-day AOTs.

The supporting PRA analysis for the chilled water replacement TS change included in letter Serial No. 07-0109, as well as the PRA information in the associated RAI responses (References 2, 3 and 4), has been reviewed with respect to this additional Page 4 of 10

Serial No. 07-0109D Docket Nos. 50-280150-281 Attachment 1 revision. It has been determined that the supporting PRA analysis and the RAI responses remain applicable and bounding.

It should be noted that the modified OPERABLE definition for the AHUs requiring the normal or (versus and) emergency electrical power source is consistent with the NUREG-1431/Westinghouse Improved Standard TS definition of OPERABLE.

In addition, the NRC requested that Dominion make a minor revision to the footnote to TS 3.23 in the February 26, 2007 proposed TS change request. Specifically, it was requested that the phrase "with an average planned out-of-service time of 90 days per 12-month period" be deleted from the footnote. An associated revision to the TS 3.23 Basis change in the February 26, 2007 letter is also needed to delete the same phrase.

3.0 Specific Revisions The chilled water piping replacement TS change request in the February 26, 2007 letter included the following Operating License (OL) Condition Item Q for each unit:

Q. As discussed in the footnote to Technical Specifications 3.23.C.2.a.l and 3.23.C.2.b.1, the use of temporary 45-day and 14-day allowed outage times to permit replacement of the Main Control Room and Emergency Switchgear Room Air Conditioning System chilled water piping shall be in accordance with the basis, risk evaluation, equipment unavailability restrictions, and compensatory actions provided in the licensee's submittal dated February 26, 2007 (Serial No. 07-0109).

Subsequently, the Units 1 and 2 OLs were revised to include an OL Condition Q titled Mitigation Strategy. Thus, the OL Condition Q in the February 26, 2007 letter is renumbered as OL Condition R and is revised to include the following italicized text:

R. As discussed in the footnote to Technical Specifications 3.23.C.2.a.l and 3.23.C.2.b.1, the use of temporary 45-day and 14-day allowed outage times to permit replacement of the Main Control Room and Emergency Switchgear Room Air Conditioning System chilled water piping shall be in accordance with the basis, risk evaluation, equipment unavailability restrictions, and compensatory actions provided in the licensee's submittal dated February 26, 2007 (Serial No. 07-0109) and in the associated supplemental transmittals. As discussed in the footnote to the Technical Specification 1.0.D definition of OPERABLE, the definition of OPERABLE for the air handling units on the operating chilled water loop is modified to require the normal or emergency electrical power source during the temporary 45-day allowed outage times, as discussed in the licensee's submittal dated (DATE) (Serial No. 07-01090).

NOTE: The associated supplemental transmittals referred to by the phrase "and in the associated supplemental transmittals" added in the Operating License Condition R for each unit are References 2 through 7, as well as this transmittal.

Page 5 of 10

Serial No. 07-01090 Docket Nos. 50-280150-281 Attachment 1 The TS I.O.D definition of OPERABLE is:

A system, subsystem, train, component, or device shall be operable or have operability when it is capable of performing its specified function(s). Implicit in this definition shall be the assumption that all necessary attendant instrumentation, controls, normal and emergency electrical power sources, cooling or seal water, lubrication or other auxiliary equipment that are required for the system, train, component, or device to perform its function(s) are also capable of performing their related support function(s). . . .

The TS l.O.D definition of OPERABLE is modified by adding an asterisk in the phrase normal and* emergency electrical power sources with the following footnote:

  • For the purpose of performing Technical Specification-required surveillances that render an emergency diesel generator inoperable and completing any related emergent corrective maintenance within the TS 3.76.B.1 allowed outage time, the definition of OPERABLE for the air handling units on the operating chilled water loop is modified to require the normal or emergency electricalpower source to be capable of performing its related support function. This footnote shall only apply during the temporary 45-day allowed outage times to permit replacement of the Main Control Room and Emergency Switchgear Room Air Conditioning System chilled water piping.

The chilled water piping replacement TS change request in the February 26, 2007 letter included a footnote to TSs 3.23.C.2.a.l and 3.23.C.2.b.l. In response to the NRC request that Dominion revise the footnote to delete the phrase "with an average planned out-of-senlice time of 90 days per 12-month p e r i o d this phrase is being deleted from the footnote, as noted below.

  • For the purpose of replacing Main Control Room (MCR) and Emergency Switchgear Room (ESGR) Air Conditioning System chilled water piping, temporary 45-day and 14-day allowed outage times (AOTs) are provided. The basis for and the risk evaluation of the temporary AOTs, as well as equipment unavailability restrictions and compensatory actions, are provided in the licensee's submittal dated February 26, 2007 (Serial No. 07-0109). Four entries into the temporary AOTs are permitted in a 24-month time span wiCk 3:: 9 4 -

d 3 .- The 24-month time frame begins upon entry into the first temporary AOT. The four entries accommodate replacement of I) the chilled water loop C piping in the ESGR and the MCR (45-day AOT), 2) the chilled water loop A piping in the ESGR and the MCR (45-day AOT), 3) the chilled water piping in the Mechanical Equipment Room #3 (MER-3) associated with chiller 1-VS-E-4A (14-day AOT), and 4) the chilled water piping in MER-3 associated with chiller 1-VS-E-4C (14-day AOT).

Upon completion of the work associated with the fourth temporary AOT, this footnote is no longer applicable.

Page 6 of 10

Serial No. 07-01090 Docket Nos. 50-280150-281 Attachment 1 The chilled water piping replacement TS change request also included a paragraph to be added to the TS 3.23 Basis. Consistent with the NRC-requested footnote revision, the phrase "with an average planned out-of-sewice time of 90 days per 12-month period is also being deleted from the TS Basis revision, as noted below.

The exterior surface of the MCR and ESGR ACS chilled water piping located in the ESGR, the MCR, and MER-3 is exhibiting general corrosion. For the purpose of replacing the MCR and ESGR ACS chilled water piping, temporary 45-day and 14-day allowed outage times. (AOTs) are provided, as discussed in the footnote to Technical Specifications 3.23.C.2.a.l and 3.23.C.2.b.l. The basis for and the risk evaluation of the temporary AOTs, as well as equipment unavailability restrictions and compensatory actions, are provided in the licensee's submittal dated February 26, 2007 (Serial No. 07-0109). Four entries into the temporary AOTs are permitted in a 24-month time span 0 4 3 .- The 24-month time frame begins upon entry into the first temporary AOT. The four entries accommodate replacement of 1) the chilled water loop C piping in the ESGR and the MCR (45-day AOT), 2) the chilled water loop A piping in the ESGR and the MCR (45-day AOT), 3) the chilled water piping in MER-3 associated with chiller 1-VS-E-4A (14-day AOT), and 4) the chilled water piping in MER-3 associated with chiller 1-VS-E-4C (14-day AOT). Upon completion of the work associated with the fourth temporary AOT, the footnote is no longer applicable.

4.0 No Significant Hazards Consideration The no significant hazards determination included in the February 26, 2007 letter for the chilled water piping replacement TS change request stated the following:

1. Does the proposed license amendment involve a siqnificant increase in the probability or consequences of an accident previously evaluated?

The proposed change has been evaluated using the risk-informed processes described in Regulatory Guide (RG) 1.174, "An Approach for Using Probabilistic Risk Assessment in Risk-Informed Decisions on Plant-Specific Changes to the Licensing Basis, and RG 1.177, "An Approach for Plant-Specific, Risk-Informed Decision Making: Technical Specifications." The risk associated with the proposed change was found to be "small" and therefore acceptable.

In addition, the proposed change does not affect the initiators of analyzed events or the assumed mitigation of accident or transient events. During the temporary 45-day and 14-day AOT entries, equipment availability restrictions will restrict or limit the out-of-service time of risk significant plant equipment due to surveillance testing, preventive maintenance, and elective maintenance. In addition, during the replacement activities, compensatory actions will be in place to ensure the availability of chilled water or to provide backup cooling. Therefore, the ACS will Page 7 of 10

Serial No. 07-01090 Docket Nos. 50-280150-281 Attachment 1 continue to perform its required function. As a result, the proposed change to the Surry TS does not involve any significant increase in the probability or the consequences of any accident or malfunction of equipment important to safety previously evaluated since neither accident probabilities nor consequences are being affected by this proposed change.

2. Does the proposed license amendment create the possibilitv of a new or different kind of accident from any accident previouslv evaluated?

The proposed change does not involve a change in the methods used to respond to plant transients. There is no alteration to the parameters within which the plant is normally operated or in the setpoints, which initiate protective or mitigative actions.

The MCR and ESGR ACS will continue to perform its required function. This is assured by the planned implementation of compensatory actions, including provisions for backup cooling. Consequently, no new failure modes are introduced by the proposed change. Therefore, the proposed Surry TS change does not create the possibility of a new or different kind of accident or malfunction of equipment important to safety from any previously evaluated.

3. Does the proposed amendment involve a siqnificant reduction in a marqin of safetv?

Margin of safety is established through the design of the plant structures, systems, and components, the parameters within which the plant is operated, and the establishment of the setpoints for the actuation of equipment relied upon to respond to an accident or transient event. The proposed change does not affect the ability of the MCR and ESGR ACS to perform its required function. This is assured by the planned implementation of compensatory actions, including provisions for backup cooling. Furthermore, the proposed change has been evaluated using the risk-informed processes described in Regulatory Guide (RG) 1.174, "An Approach for Using Probabilistic Risk Assessment in Risk-Informed Decisions on Plant-Specific Changes to the Licensing Basis," and RG 1.177, "An Approach for Plant-Specific, Risk-Informed Decision Making: Technical Specifications." The risk associated with the proposed change was found to be acceptably small. Therefore, the proposed change to the Surry TS does not involve a significant reduction in a margin of safety.

The February 26, 2007 determination concluded that a significant hazards consideration does not exist with respect to the chilled water piping replacement TS change. The no significant hazards determination included in the February 26, 2007 letter has been reviewed with respect to this proposed additional TS revision, and it has been concluded that it remains applicable.

5.0 Environmental Assessment The environmental assessment included in the February 26, 2007 proposed TS change request concluded that the chilled water piping replacement TS change meets the Page 8 of 10

Serial No. 07-0109D Docket Nos. 50-280150-281 Attachment 1 criteria specified in 10 CFR 51.22 for a categorical exclusion from the requirements of 10 CFR 51.22 relative to requiring a specific environmental assessment or impact statement by the Commission. That environmental assessment has been reviewed with respect to this proposed additional TS revision and it has been concluded that the existing environmental assessment remains applicable.

6.0 Conclusion The proposed additional TS revision discussed herein modifies the operability requirements for the normal and emergency power supplies for the AHUs on the operating chilled water loop during specific TS-required surveillance testing and related emergent corrective maintenance to eliminate the need to enter the AHU TS action statement. This additional proposed TS revision has been reviewed with respect to the chilled water piping replacement TS change request. The supporting PRA analysis for the chilled water piping replacement TS change included in letter Serial No. 07-0109, as well as the PRA information in the associated RAI responses (References 2 through 7),

has been reviewed with respect to this additional proposed TS revision. It has been determined that the supporting PRA analysis and the RAI responses remain applicable and bounding. Thus, the risk associated with the chilled water piping replacement TS change, including the proposed additional TS revision discussed in this letter, has been determined to be acceptably small. In addition, this proposed additional TS revision includes the NRC requested change to delete the phrase "with an average planned out-of-service time of 90 days per 12-month period" from the footnote to TS 3.23, as well as from the TS 3.23 Basis revision, in the February 26, 2007 proposed additional TS change request. The Station Nuclear Safety and Operating Committee (SNSOC) has reviewed this proposed TS revision, and it has been concluded that this additional revision does not have an adverse impact on safety, does not involve a significant hazards consideration, and will not endanger the health and safety of the public.

7.0 References

1. Letter Serial No. 07-0109, dated February 26, 2007, Proposed TS Change -

Temporary 45-day and 14-day AOTs to Replace MCR and ESGR ACS Chilled Water Piping

2. Letter Serial No. 07-0381, dated May 31, 2007, Proposed TS Change - Temporary 45-day and 14-day AOTs to Replace MCR and ESGR ACS Chilled Water Piping -

Response to NRC Request for Additional lnformation

3. Letter Serial No. 07-0443, dated June 28, 2007, Proposed TS Change - Temporary 45-day and 14-day AOTs to Replace MCR and ESGR ACS Chilled Water Piping -

Response to NRC Request for Additional lnformation Page 9 of 10

Serial No. 07-0109D Docket Nos. 50-280150-281 Attachment 1

4. Letter Serial No. 07-0443A, dated July 20, 2007, Proposed TS Change -Temporary 45-day and 14-day AOTs to Replace MCR and ESGR ACS Chilled Water Piping -

Response to NRC Request for Additional lnformation

5. Letter Serial No. 07-0109A, dated April 5, 2007, Proposed TS Change - Temporary 45-day and 14-day AOTs to Replace MCR and ESGR ACS Chilled Water Piping -

Response to NRC Request for Additional lnformation

6. Letter Serial No. 07-0109Bl dated May 14, 2007, Proposed TS Change - Temporary 45-day and 14-day AOTs to Replace MCR and ESGR ACS Chilled Water Piping -

Additional lnformation Regarding MCR Heatup

7. Letter Serial No. 07-0109C, dated July 13, 2007, Proposed TS Change -Temporary 45-day and 14-day AOTs to Replace MCR and ESGR ACS Chilled Water Piping -

Additional lnformation Regarding Backup Cooling Supply Flow Page 10 of 10

MER-1 CHILLED MER-1 CHILLED WATER BACKUP WATER BACKUP RETURN SUPPLY AIR HANDLING UNIT (TYP)

SUPPLY FROM LOOP A I LOOP C MER-5 CHILLERS E-40,4E l2JIl H.1 HI (1JI2J) ( 1J12H)

Note: This figure illustrates a typical valve alignment for the Chilled Water System.

The actual valve alignment is dependent CHILLED WATER upon the specific equipment in operation.

EXISTING MCR I ESGR CHILLED WATER SYSTEM FIGURE 2 I 1 RETURN TO MER.5 CHILLERS

~ 6 3 9 E-4D.4E (2JIlH.lH)

Attachment 2 Marked-up Technical Specifications Pages Operable Definition Modification for Air Handling Units While in Temporary 45-day Allowed Outage Times NOTE: The document from which the marked-up pages were excerpted is identified on each page. The revisions from this TS change request are denoted by arrows in the right margin. Notes are included to clarify other changes on the marked-up pages.

Surry Power Station Units 1 and 2 Virginia Electric and Power Company (Dominion)

The Updated Final Safety Analysis Report supplement as revised on July 25, October 1, November 4, and December 2,2002, shall be included in the next scheduled update to the licensee's Updated Final Safety Analysis Report required by 10 CFR 50.71(e)(4), following the issuance of this renewed license. Until that update is complete, the licensee may make changes to the programs described in such supplement without prior Commission approval, provided that the licensee evaluates each such change pursuant to the criteria set forth in 10 CFR 50.59, and otherwise complies with the requirements in that section.

Q. Mitigation Strateav L Develop and maintain strategies for addressing large fires and explosions and that include the following key areas:

(1) Fire fighting response strategy with the following elements:

8D

a. Pre-defined coordinated fire response strategy and guidance
b. Assessment of mutual aid fire fighting assets
c. Designated staging areas for equipment and materials
d. Command and control
e. Training of response personnel (2) Operations to mitigate fuel damage considering the following:
a. Protection and use of personnel assets
b. Communications

/I

c. Minimizing fire spread
d. Procedures for implementing integrated fire response strategy )I
e. Identification of readily-available pre-staged equipment
f. Training on integrated fire response strategy u1
g. Spent fuel pool mitigation measures (1 (3) Actions to minimize release to include consideration of:

1

a. Water spray scrubbing
b. Dose to onsite responders W

1 N s f - R ~ LICEUSE O M D I ~ I O 'i7. ~J

4. This renewed license is effective as of the date of issuance and shall expire at midnight on May 25,2032.

FOR THE NUCLEAR REGULATORY COMMISSION Samuel J. Coiiins, Director Office of Nuclear Reactor Regulation

Attachment:

Appendix A, Technical Specifications Date of Issuance: March 20, 2003 SURRY - UNIT 1 Renewed License No. DPR-32

(2) The Updated Final Safety Analysis Report supplement as revised on July 25, October 1, November 4, and December 2,2002, shall be included in the next scheduled update to the licensee's Updated Final Safety Analysis Report required by 10 CFR 50.71 (e)(4), following the issuance of this renewed license. Until that update is complete, the licensee may make changes to the programs described in such supplement without prior Commission approval, provided that the licensee evaluates each such change pursuant to the criteria set forth in 10 CFR 50.59, and otherwise complies with the requirements in that section.

4. $. As discussed in the footnote to Technical Specifications 3.23.C.2.a.l and 3.23.C.2.b.1, the use of temporary 45-day and 14-day allowed outage times to permit replacement of the Main Control Room and Emergency Switchgear Room Air Conditioning System chilled water piping shall be in accordance with the basis, risk evaluation, equipment unavailability restrictions, and compensatory actions provided in the licensee's submittal dated February 26, 2007 (Serial No. 07-0109X(

I ~ S E R T A A S P A R T oG LICE~JSE c o d D ~ m o UR.

4. This renewed license is effective as of the date of issuance, and shall expire at midnight on May 25, 2032.

FOR THE NUCLEAR REGULATORY COMMISSION Samuel J. Collins, Director Office of Nuclear Reactor Regulation

Attachment:

Appendix A, Technical Specifications Date of Issuance: March 20, 2003 SURRY - UNIT 1

P. Updated Final Safetv Analysis Report (1) The Updated Final Safety Analysis Report supplement submitted pursuant to 10 CFR 54.21 (d), as revised on July 25, 2002, October 1, 2002, November 4, 2002, and December 2, 2002 describes certain future inspection activities to be completed before the period of extended operation. The licensee shall complete these activities no later than January 29, 2013, and shall notify the NRC in writing when implementation of these activities is complete and can be verified by NRC inspection.

(2) The Updated Final Safety Analysis Report supplement as revised on July 25, 2002, October 1, 2002, November 4,2002, and December 2,2002, shall be included in the next scheduled update to the Updated Final Safety Analysis Report required by 10 CFR 50.71(e)(4), following the issuance of this renewed license. Until that update is complete, the licensee may make changes to the programs described in such supplement without prior Commission approval, provided that the licensee evaluates each such change pursuant to the criteria set forth in 10 CFR 50.59 and otherwise complies with the requirements in that section.

Q. Mitigation Strategy I Develop and maintain strategies for addressing large fires and explosions and that include the following key areas:

(1) Fire fighting response strategy with the following elements:

a. Pre-defined coordinated fire response strategy and guidance
b. Assessment of mutual aid fire fighting assets
c. Designated staging areas for equipment and materials
d. Command and control
e. Training of response personnel (2) Operations to mitigate fuel damage considering the following:
a. Protection and use of personnel assets
b. Communications
c. Minimizing fire spread
d. Procedures for implementing integrated fire response strategy
e. Identification of readily-available pre-staged equipment
f. Training on integrated fire response strategy
g. Spent fge! pos! mitigation measures (3) Actions to minimize release to include consideration of:
a. Water spray scrubbing
b. Dose to onsite responders cY IdSf3R-f LlCEr\lSE W N D I T ~ O ~K. )

SURRY - UNIT 2 Renewed License No. DPR-37

P. Updated Final Safety Analysis Report (1) The Updated Final Safety Analysis Report supplement submitted pursuant to 10 CFR 54.21 (d), as revised on July 25, 2002, October 1, 2002, November 4, 2002, and December 2,2002 describes certain future inspection 9 activities to be completed before the period of extended operation. The E%,

d 0

licensee shall complete these activities no later than January 29, 2013, and (3 L 0 shall notify the NRC in writing when implementation of these activities is complete and can be verified by NRC inspection. 23 (2) The Updated Final Safety Analysis Report supplement as revised on July 25, 2002, October 1, 2002, November 4, 2002, and December 2, 2002, shall be included in the next scheduled update to the Updated Final Safety G

Analysis Report required by 10 CFR 50.71 (e)(4), following the issuance of this J renewed license. Until that update is complete, the licensee may make changes to the programs described in such supplement without prior Commission approval, provided that the licensee evaluates each such change pursuant to the criteria set forth in 10 CFR 50.59 and otherwise complies with the requirements in that section.

. 6 AS discussed in the footnote to Technical Specifications 3.23.C.2.a.l and 3.23.C.2.b.1, the use of temporary 45-day and 14-day allowed outage times to permit replacement of the Main Control Room and Emergency Switchgear Room Air Conditioning System chilled water piping shall be in accordance with the basis, risk evaluation, equipment unavailability restrictions, and compensatory actions provided in the licensee's submittal dated February 26, 2007 (Serial No. 07-0109)%

INSERT A A.S P A R T O F LICGblSE m b l ~ l ~ iI?. ~n)

4. This renewed license is effective as of the date of issuance, and shall expire at midnight on January 29, 2033.

FOR THE NUCLEAR REGULATORY COMMISSION Samuel J. Collins, Director Office of Nuclear Reactor Regulation

Attachment:

Appendix A, Technical Specifications Date of Issuance: March 20, 2003 SURRY - UNIT 2

INSERT A - add to Units 1 and 2 Operating License Condition R:

and in the associated supplemental transmittals. As discussed in the footnote to the Technical Specification 1.O.D definition of OPERABLE, the definition of OPERABLE for the air handling units on the operating chilled water loop is modified to require the normal or (versus and) emergency electrical power source during the temporary 45-day allowed outage times, as discussed in the licensee's submittal dated (DATE) (Serial No.

07-0109D).

When the neutron chain reaction is self-sustaining and keff = 1.O.

6. POWER OPERATION When the reactor is critical and the neutron flux power range instrumentation indicates greater than 2% of rated power.

Any operation involving movement of core components when the vessel head is unbolted or removed.

A system, subsystem, train, component, or device shall be operable or have operability when it is capable of performing its specified function(s).

Implicit in this definition shall be the assumption that all necessary attendant instrumentafion, controls, normal and'cemergency electrical 1t power sources, cooling or seal water, lubrication or other auxiliary equipment that are required for the system, subsystem, train, component or device to perform its function(s) are also capable of performing their ,

related support function(s). The system or component shall be considered to have this capability when: (1) it satisfies the limiting conditions for operation defined in Section 3, and (2) it has been tested periodically in accordance with Section 4 and meets its performance requirements.

E. PROTECTIVE lNSTRUMENTATlON LOGIC An arrangement of components and modules as required to getleiate a slisgk proledive action digitai signai when required by a unit condition. An analog channel loses its identity when single action signals are combined.

  • INSERT B AS MuTI~OTE It-Amendment Nos.

INSERT B - insert as a footnote to the TS 1.O.D definition of OPERABLE :

  • For the purpose of performing Technical Specification-required surveillances that render an emergency diesel generator inoperable and completing any related emergent corrective maintenance within the TS 3.16.B. 1 allowed outage time, the definition of OPERABLE for the air handling units on the operating chilled water loop is modified to require the normal or emergency electrical power source to be capable of performing its related support function. This footnote shall only apply during the temporary 45-day allowed outage times to permit replacement of the Main Control Room and Emergency Switchgear Room Air Conditioning System chilled water piping.
2. Air Handling Units (AHUs)
a. Unit 1 air handling units, 1-VS-AC-1 , 1-VS-AC-2, 1-VS-AC-6, and 1-VS-AC-7, must be OPERABLE whenever Unit 1 is above COLD SHUTDOWN.
1. If either any single Unit 1 AHU or two Unit 1 AHUs on the same chilled water loop (1-VS-AC- 1 and 1-VS-AC-7 or 1-VS-AC-2 and 1-VS-AC-6)* become inoperable, restore operability of the one inoperable AHU or two inoperable AHUs within seven (7) days or bring Unit 1 to HOT SHUTDOWN within the next six (6) hours and be in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.
2. If two Unit 1 AHUs on different chilled water loops and in different air conditioning zones (1-VS-AC-1 and 1-VS-AC-6 or 1-VS-AC-2 and 1-VS-AC-7) become inoperable, restore operability of the two inoperable AHUs within seven (7) days or bring Unit 1 to HOT SHUTDOWN within the next six (6) hours and be in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.
3. If two Unit 1 AHUs in the same air conditioning zone (I-VS-AC-1 and 1-VS-AC-2 or 1-VS-AC-6 and 1-VS-AC-7) become inoperable, restore operability of at least one Unit 1 AHU in each air conditioning zone (1-VS-AC-1 or 1-VS-AC-2 and 1-VS-AC-6 or 1-VS-AC-7) within one (1) hour or bring Unit 1 to HOT SHUTDOWN within the next six (6) hours and be in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.
4. If more than two Unit 1 AHUs become inoperable, restore operability of at least one Unit 1 AHU in each air conditioning zone (1-VS-AC-1 or 1-VS-AC-2 and 1-VS-AC-6 or I-VS-AC-7) within one (1) hour or bring Unit 1 to HOT SHUTDOWN within the next six (6) hours and be in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.
b. Unit 2 air handling units, 2-VS-AC-8, 2-VS-AC-9, 2-VS-AC-6, and 2-VS-AC-7 must be OPERABLE whenever Unit 2 is above COLD SHUTDOWN.
1. If either any single Unit 2 AHU or two Unit 2 AHUs on the same chilled water loop (2-VS-AC-7 and 2-VS-AC-9 or 2-VS-AC-6 and 2-VS-AC-8)* become inoperable, restore operability of the one inoperable AHU or two inoperable AHUs within seven (7) days or bring Unit 2 to HOT SHUTDOWN within the next six (6) hours and be in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.
  • For the purpose of replacing Main Control Room (MCR) and Emergency Switchgear Room (ESGR) Air Conditioning System chilled water piping, temporary 45-day and 14-day allowed outage times (AOTs) are provided. The basis for and the risk evaluation of the temporary AOTs, as well as equipment unavailability restrictions and compensatory actions, are provided in the licensee's submittal dated February 26,2007 (Serial No. 07-0109). Four entries into the temporary AOTs are permitted in a 24-month time *,naps The 24-month time frame begins upon entry into the first temporary AOT. The four entries accommodate replacement of I) the chilled water loop C piping in the ESGR and the MCR (45-day AOT), 2) the chilled water loop A piping in the ESGR and the MCR (45-day AOT), 3) the chilled water piping in the Mechanical Equipment Room #3 (MER-3) associated with chiller 1-VS-E-4A (14-day AOT), and 4) the chilled water piping in MER-3 associated with chiller 1-VS-E4C (14-day AOT). Upon completion of the work associated with the fourth temporary AOT, this footnote is no longer applicable.

Amendment Nos.

The exterior surface of the MCR and ESGR ACS chilled water piping located in the ESGR, the MCR, and MER-3 is exhibiting general corrosion. For the purpose of replacing the MCR and ESGR ACS chilled water piping, temporary 45-day and 14-day allowed outage times (AOTs) are provided, as discussed in the footnote to Technical Specifications 3.23.C.2.a.1 and 3.23.C.2.b.l. The basis for and the risk evaluation of the temporary AOTs, as well as equipment unavailability restrictions and compensatory actions, are provided in the licensee's submittal dated February 26, 2007 (Serial No. 07-0109). Four entries into the temporary AOTs are permitted in a 24-month time

  • , naps

. . The 24-month time frame begins upon entry into the first temporary AOT. The four entries accommodate replacement of I ) the chilled water loop C piping in the ESGR and the MCR (45-day AOT), 2) the chilled water loop A piping in the ESGR and the MCR (45-day AOT), 3) the chilled water piping in MER-3 associated with chiller 1-VS-E-4A (14-day AOT), and 4) the chilled water piping in MER-3 associated with chiller I-VS-E-4C (14-day AOT). Upon completion of the work associated with the fourth temporary AOT, the footnote is no longer applicable.

Amendment Nos.

Attachment 3 Proposed Technical Specifications Pages Operable Definition Modification for Air Handling Units While in Temporary 45-day Allowed Outage Times NOTE: The typed pages reflect two sets of revision bars in the right margin. The inner revision bars (closer to the text) identify the revisions from the TS change request i n letter Serial No. 07-0109. The outer revision bars (closer to the edge of the page) identify the revisions from this TS change request.

Surry Power Station Units 1 and 2 Virginia Electric and Power Company (Dominion)

(2) The Updated Final Safety Analysis Report supplement as revised on July 25, October 1, November 4, and December 2,2002, shall be included in the next scheduled update to the licensee's Updated Final Safety Analysis Report required by 10 CFR 50.71 (e)(4), following the issuance of this renewed license. Until that update is complete, the licensee may make changes to the programs described in such supplement without prior Commission approval, provided that the licensee evaluates each such change pursuant to the criteria set forth in 10 CFR 50.59, and otherwise complies with the requirements in that section.

Q. Mitigation Strategy Develop and maintain strategies for addressing large fires and explosions and that include the following key areas:

(1) Fire fighting response strategy with the following elements:

a. Predefined coordinated fire response strategy and guidance
b. Assessment of mutual aid fire fighting assets
c. Designated staging areas for equipment and materials
d. Command and control
e. Training of response personnel (2) Operations to mitigate fuel damage considering the following:
a. Protection and use of personnel assets
b. Communications
c. Minimizing fire spread
d. Procedures for implementing integrated fire response strategy
e. Identification of readily-available pre-staged equipment
f. Training on integrated fire response strategy
g. Spent fuel pool mitigation measures (3) Actions to minimize release to include consideration of:
a. Water spray scrubbing
b. Dose to onsite responders SURRY - UNIT I Renewed License No. DPR-32

As discussed in the footnote to Technical Specifications 3.23.C.2.a.l and 3.23.C.2.b.1, the use of temporary 45-day and 14-day allowed outage times to permit replacement of the Main Control Room and Emergency Switchgear Room Air Conditioning System chilled water piping shall be in accordance with the basis, risk evaluation, equipment unavailability restrictions, and compensatory actions provided in the licensee's submittal dated February 26, 2007 (Serial No. 07-0109) and in the associated supplemental transmittals. As discussed in the footnote to the Technical Specification 1.O.D definition of OPERABLE, the definition of OPERABLE for the air handling units on the operating chilled water loop is modified to require the normal or (versus and) emergency electrical power source during the temporary 45-day allowed outage times, as discussed in the licensee's submittal dated (DATE) (Serial No. 07-0109D).

4. This renewed license is effective as of the date of issuance and shall expire at midnight on May 25,2032.

FOR THE NUCLEAR REGULATORY COMMISSION Samuel J. Collins, Director Office of Nuclear Reactor Regulation

Attachment:

Appendix A, Technical Specifications Date of Issuance: March 20, 2003 SURRY - UNIT 1 Renewed License No. DPR-32

R. As discussed in the footnote to Technical Specifications 3.23.C.2.a.l and 3.23.C.2.b.1, the use of temporary 45-day and 14-dayallowed outage times to permit replacement of the Main Control Room and Emergency Switchgear Room Air Conditioning System chilled water piping shall be in accordance with the basis, risk evaluation, equipment unavailability restrictions, and compensatory actions provided in the licensee's submittal dated February 26, 2007 (Serial No. 07-0109) and in the associated supplemental transmittals. As discussed in the footnote to the Technical Specification 1.O.D definition of OPERABLE, the definition of OPERABLE for the air handling units on the operating chilled water loop is modified to require the normal or (versus and) emergency electrical power source during the temporary 45-day allowed outage times, as discussed in the licensee's submittal dated (DATE) (Serial No. 07-07090).

4. This renewed license is effective as of the date of issuance and shall expire at midnight on January 29,2033.

FOR THE NUCLEAR REGULATORY COMMISSION Samuel J. Collins, Director Office of Nuclear Reactor Regulation

Attachment:

Appendix A, Technical Specifications Date of Issuance: March 20, 2003 SURRY - UNIT 2 Renewed License No. DPR-37

5. REACTOR CRITICAL When the neutron chain reaction is self-sustaining and keff = 1.O.
6. POWER OPERATION When the reactor is critical and the neutron flux power range instrument2 indicates greater than 2% of rated power.
7. REFUELING OPERATION Any operation involving movement of core components when the vessel head is unbolted or removed.

D. OPERABLE A system, subsystem, train, component, or device shall be operable or have operability when it is capable of performing its specified function(s). Implicit in this definition shall be the assumption that all necessary attendant instrumentation, controls, normal and* emergency electrical power sources, cooling or seal water, lubrication or other auxiliary equipment that are required for the system, subsystem, train, component or device to perform its function(s) are also capable of performing their related support function(s). The system or component shall be considered to have this capability when: (1) it satisfies the limiting conditions for operation defined in Section 3, and (2) it has been tested periodically in accordance with Section 4 and meets its performance requirements.

E. PROTECTIVE INSTRUMENTATION LOGIC

1. ANALOG CHANNEL An arrangement of components and modules as required to generate a single protective action digital signal when required by a unit condition. An analog channel loses its identity when single action signals are combined.
  • For the purpose of performing Technical Specification-required surveillances that render an emergency diesel generator inoperable and completing any related emergent corrective maintenance within the TS 3.16.B. 1 allowed outage time, the definition of OPERABLE for the air handling units on the operating chilled water loop is modified to require the normal or emergency electrical power source to be capable of performing its related support function. This footnote shall only apply during the temporary 45-day allowed outage times to permit replacement of the Main Control Room and Emergency Switchgear Room Air Conditioning System chilled water piping.

Amendment Nos.

2. Air Handling Units (AHUs)
a. Unit 1 air handling units, 1-VS-AC- 1, 1-VS-AC-2, 1-VS-AC-6, and I -VS-AC-7, must be OPERABLE whenever Unit 1 is above COLD SHUTDOWN.
1. If either any single Unit 1 AHU or two Unit 1 AHUs on the same chilled water loop (1-VS-AC- 1 and 1-VS-AC-7 or 1-VS-AC-2 and 1-VS-AC-6)" become inoperable, restore operability of the one inoperable AHU or two inoperable AHUs within seven (7) days or bring Unit 1 to HOT SHUTDOWN within the next six (6) hours and be in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.
2. If two Unit 1 AHUs on different chilled water loops and in different air conditioning zones (1-VS-AC-I and 1-VS-AC-6 or 1-VS-AC-2 and I -VS-AC-7) become inoperable, restore operability of the two inoperable AHUs within seven (7) days or bring Unit 1 to HOT SHUTDOWN within the next six (6) hours and be in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.
3. If two Unit 1 AHUs in the same air conditioning zone (I-VS-AC-1 and 1-VS-AC-2 or 1 -VS-AC-6 and 1-VS-AC-7) become inoperable, restore operability of at least one Unit 1 AHU in each air conditioning zone (I -VS-AC- 1 or 1-VS-AC-2 and 1-VS-AC-6 or 1-VS-AC-7) within one (1) hour or bring Unit 1 to HOT SHUTDOWN within the next six (6) hours and be in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.
4. If more than two Unit 1 AHUs become inoperable, restore operability of at least one Unit 1 AHU in each air conditioning zone (1-VS-AC- 1 or 1-VS-AC-2 and I -VS-AC-6 or 1 -VS-AC-7) within one (I) hour or bring Unit 1 to HOT SHUTDOWN within the next six (6) hours and be in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.
b. Unit 2 air handling units, 2-VS-AC-8, 2-VS-AC-9, 2-VS-AC-6, and 2-VS-AC-7 must be OPERABLE whenever Unit 2 is above COLD SHUTDOWN.
1. If either any single Unit 2 AHU or two Unit 2 AHUs on the same chilled water loop (2-VS-AC-7 and 2-VS-AC-9 or 2-VS-AC-6 and 2-VS-AC-8)" become inoperable, restore operability of the one inoperable AHU or two inoperable AHUs within seven (7) days or bring Unit 2 to HOT SHUTDOWN within the next six (6) hours and be in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.
  • For the purpose of replacing Main Control Room (MCR) and Emergency Switchgear Room (ESGR) Air Conditioning System chilled water piping, temporary 45-day and 14-day allowed outage times (AOTs) are provided. The basis for and the risk evaluation of the temporary AOTs, as well as equipment unavailability restrictions and compensatory actions, are provided in the licensee's submittal dated February 26, 2007 (Serial No. 07-0109). Four entries into the temporary AOTs are permitted in a 24-month time span. The 24-month time frame begins upon entry into the first temporary AOT. The four entries accommodate replacement of 1) the chilled water loop C piping in the ESGR and the MCR (45-day AOT), 2) the chilled water loop A piping in the ESGR and the MCR (45-day AOT), 3) the chilled water piping in the Mechanical Equipment Room #3 (MER-3) associated with chiller 1-VS-E-4A (14-day AOT), and 4) the chilled water piping in MER-3 associated with chiller 1-VS-E-4C (14-day AOT). Upon completion of the work associated with the fourth temporary AOT, this footnote is no longer applicable.

Amendment Nos.

The exterior surface of the MCR and ESGR ACS chilled water piping located in the ESGR, the MCR, and MER-3 is exhibiting general corrosion. For the purpose of replacing the MCR and ESGR ACS chilled water piping, temporary 45-day and 14-day allowed outage times (AOTs) are provided, as discussed in the footnote to Technical Specifications 3.23.C.2.a.1 and 3.23.C.2.b.l. The basis for and the risk evaluation of the temporary AOTs, as well as equipment unavailability restrictions and compensatory actions, are provided in the licensee's submittal dated February 26, 2007 (Serial No. 07-0109). Four entries into the temporary AOTs are permitted in a 24-month time span. The 24-month time frame begins upon entry into the first temporary AOT. The four entries accommodate replacement of 1) the chilled water loop C piping in the ESGR and the MCR (45-day AOT), 2) the chilled water loop A piping in the ESGR and the MCR (45-day AOT), 3) the chilled water piping in MER-3 associated with chiller 1-VS-E-4A (14-day AOT), and 4) the chilled water piping in MER-3 associated with chiller 1-VS-E-4C (14-day AOT). Upon completion of the work associated with the fourth temporary AOT, the footnote is no longer applicable.

Amendment Nos.