June 26, 2007 Mr. Michael D. Wadley Site Vice President Prairie Island Nuclear Generating Plant Nuclear Management Company, LLC 1717 Wakonade Drive East Welch, MN 55089
SUBJECT:
PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNITS 1 AND 2 - ISSUANCE OF SECURITY PLAN REV. 1 CORRECTIONS (TAC NOS. MC8690 AND MC8691)
Dear Mr. Wadley:
By letter dated April 20, 2007, Nuclear Regulatory Commission (NRC) provided Nuclear Management Company, LLC, the approval for Revision 1 of the physical security plan (PSP),
training and qualification plan (T&QP), and safeguards contingency plan (SCP) for Prairie Island Nuclear Generating Plant, Units 1 and 2. The approval revised page 3 of the facility operating licenses to reflect Revision 1 of the combined set of security plans (security plan).
However, the changes to the licenses were incorrectly transmitted as amendments. In addition, the amendment nos. and the date of the letter were missing from the footer on the revised license pages, and Section 2.C(3) incorrectly listed Amendments 175 and 165 as latest amendment rather than Amendments 177 and 167 for Units 1 and 2, respectively. As a result, when Amendment Nos. 178 and 168 were issued on May 30, 2007, Revision 0 of the security plan was inadvertently reinstated. Thus, the enclosure to this letter provides the corrected license pages. These corrections are administrative license changes to the correct the errors introduced when conforming Facility Operating License Nos. DPR-42 and DPR-60 to NRC Orders EA-03-086 and EA-06-037.
Please replace the affected pages with the enclosed correct pages. We regret any inconvenience that may have been caused by this error. If you have any questions, please contact me at (301) 415-8371.
Sincerely,
/RA/
Mahesh L. Chawla, Project Manager Plant Licensing Branch III-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-282 and 50-306
Enclosure:
Replacement license pages cc w/encl: D. Axt, Security Manager, PINGP K. Riemer, Region III W. Smith, NSIR cc w/encl: See next page
June 26, 2007 Mr. Michael D. Wadley Site Vice President Prairie Island Nuclear Generating Plant Nuclear Management Company, LLC 1717 Wakonade Drive East Welch, MN 55089
SUBJECT:
PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNITS 1 AND 2 - ISSUANCE OF SECURITY PLAN REV. 1 CORRECTIONS (TAC NOS. MC8690 AND MC8691)
Dear Mr. Wadley:
By letter dated April 20, 2007, Nuclear Regulatory Commission (NRC) provided Nuclear Management Company, LLC, the approval for Revision 1 of the physical security plan (PSP),
training and qualification plan (T&QP), and safeguards contingency plan (SCP) for Prairie Island Nuclear Generating Plant, Units 1 and 2. The approval revised page 3 of the facility operating licenses to reflect Revision 1 of the combined set of security plans (security plan).
However, the changes to the licenses were incorrectly transmitted as amendments. In addition, the amendment nos. and the date of the letter were missing from the footer on the revised license pages, and Section 2.C(3) incorrectly listed Amendments 175 and 165 as latest amendment rather than Amendments 177 and 167 for Units 1 and 2, respectively. As a result, when Amendment Nos. 178 and 168 were issued on May 30, 2007, Revision 0 of the security plan was inadvertently reinstated. Thus, the enclosure to this letter provides the corrected license pages. These corrections are administrative license changes to the correct the errors introduced when conforming Facility Operating License Nos. DPR-42 and DPR-60 to NRC Orders EA-03-086 and EA-06-037.
Please replace the affected pages with the enclosed correct pages. We regret any inconvenience that may have been caused by this error. If you have any questions, please contact me at (301) 415-8371.
Sincerely,
/RA/
Mahesh L. Chawla, Project Manager Plant Licensing Branch III-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-282 and 50-306
Enclosure:
Replacement license pages cc w/encl: D. Axt, Security Manager, PINGP K. Riemer, Region III W. Smith, NSIR cc w/encl: See next page DISTRIBUTION: ( w/o enclosure):
PUBLIC LPLIII-1 R/F RidsNrrPMMChawla RidsNrrLATHarris RidsNrrDorlLple RidsOgcRp AFrazier, NSIR WSmith, NSIR DDorman KRiner, NSIR SMorris, NSIR DHuyck, NSIR ADAMS Accession Number: ML071180002 Pkg: ML071180005 OFFICE LPL3-1/PM LPL3-1/LA NSIR/DSP/RSB/SS NSIR/DSP/RSB/TL OGC LPL3-1/(A)BC NAME MChawla THarris WSmith AFrazier JZorn TTate PM for DATE 6/26/07 6/26/07 5/09/07 5/09/07 6 /25/ 07 6/26/ 07 OFFICIAL RECORD COPY
Prairie Island Nuclear Generating Plant, Units 1 and 2 cc:
Jonathan Rogoff, Esquire Vice President, Counsel & Secretary Nuclear Management Company, LLC 700 First Street Hudson, WI 54016 Manager, Regulatory Affairs Prairie Island Nuclear Generating Plant Nuclear Management Company, LLC 1717 Wakonade Drive East Welch, MN 55089 Manager - Environmental Protection Division Minnesota Attorney Generals Office 445 Minnesota St., Suite 900 St. Paul, MN 55101-2127 U.S. Nuclear Regulatory Commission Resident Inspector's Office 1719 Wakonade Drive East Welch, MN 55089-9642 Regional Administrator, Region III U.S. Nuclear Regulatory Commission Suite 210 2443 Warrenville Road Lisle, IL 60532-4351 Administrator Goodhue County Courthouse Box 408 Red Wing, MN 55066-0408 Commissioner Minnesota Department of Commerce 85 7th Place East, Suite 500 St. Paul, MN 55101-2198 Tribal Council Prairie Island Indian Community ATTN: Environmental Department 5636 Sturgeon Lake Road Welch, MN 55089 Nuclear Asset Manager Xcel Energy, Inc.
414 Nicollet Mall, R.S. 8 Minneapolis, MN 55401 Michael B. Sellman President and Chief Executive Officer Nuclear Management Company, LLC 700 First Street Hudson, MI 54016 Craig G. Anderson Senior Vice President, Group Operations Nuclear Management Company, LLC 700 First Street Hudson, WI 54016 November 2005
NUCLEAR MANAGEMENT COMPANY, LLC DOCKET NO. 50-282 PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNIT 1 ADMINISTRATIVE LICENSE CHANGE TO FACILITY OPERATING LICENSE License No. DPR-42 1.
The Nuclear Regulatory Commission (the Commission) has found that:
A.
When the Commission issued EA-03-086, the Order requiring compliance with the revised design bases threat, (DBT Order) on April 29, 2003, the Commission determined that conforming administrative license changes to facility operating licenses (FOLs) were required to ensure implementation of the DBT Order requirements and the FOLs were consistent. A supplemental set of adversary characteristics of the DBT was provided to all power reactor licenses in Order EA-06-037 Updated Adversary Characteristic Order, dated March 20, 2006. Therefore, an administrative license change to FOL No. DPR-42 is being made to incorporate the reference to the revised Physical Security Plan, Safeguards Contingency and Plan, and Training and Qualification Plan required by both DBT Orders, that complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commissions rules and regulations set forth in 10 CFR Chapter I; B.
The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C.
There is reasonable assurance (i) that the activities authorized by this administrative license change can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; D.
The issuance of this administrative license change will not be inimical to the common defense and security or to the health and safety of the public; and E.
The issuance of this administrative license change is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.
2.
Accordingly, the FOL is changed as indicated in the attachment.
3.
This administrative license change is effective as of the date of its issuance and shall be implemented upon issuance.
FOR THE NUCLEAR REGULATORY COMMISSION
/RA Patrick Milano for/
Travis L. Tate, Acting Chief Plant Licensing Branch III-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
Attachment:
Changes to the Facility Operating License Date of Issuance: June 26, 2007
NUCLEAR MANAGEMENT COMPANY, LLC DOCKET NO. 50-306 PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNIT 2 ADMINISTRATIVE LICENSE CHANGE TO FACILITY OPERATING LICENSE License No. DPR-60 1.
The Nuclear Regulatory Commission (the Commission) has found that:
A.
When the Commission issued EA-03-086, the Order requiring compliance with the revised design bases threat, (DBT Order) on April 29, 2003, the Commission determined that conforming administrative license changes to facility operating licenses (FOLs) were required to ensure implementation of the DBT Order requirements and the FOLs were consistent. A supplemental set of adversary characteristics of the DBT was provided to all power reactor licenses in Order EA-06-037 Updated Adversary Characteristic Order, dated March 20, 2006. Therefore, an administrative license change to FOL No. DPR-60 is being made to incorporate the reference to the revised Physical Security Plan, Safeguards Contingency and Plan, and Training and Qualification Plan required by both DBT Orders, that complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commissions rules and regulations set forth in 10 CFR Chapter I; B.
The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C.
There is reasonable assurance (i) that the activities authorized by this administrative license change can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; D.
The issuance of this administrative license change will not be inimical to the common defense and security or to the health and safety of the public; and E.
The issuance of this administrative license change is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.
2.
Accordingly, the FOL is changed as indicated in the attachment.
3.
This administrative license change is effective as of the date of its issuance and shall be implemented upon issuance.
FOR THE NUCLEAR REGULATORY COMMISSION
/RA Patrick Milano for/
Travis L. Tate, Acting Chief Plant Licensing Branch III-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
Attachment:
Changes to the Facility Operating License Date of Issuance: June 26, 2007
CHANGES TO FACILITY OPERATING LICENSE NOS. DPR-42 AND DPR-60 DOCKET NOS. 50-282 AND 50-306 Replace the following pages of Facility Operating License Nos. DPR-42 and DPR-60 with the attached revised pages. The changed areas are identified by a marginal line.
REMOVE INSERT DPR-42, License Page 3 DPR-42, License Page 3 DPR-60, License Page 3 DPR-60, License Page 3 (4)
Pursuant to the Act and 10 CFR Parts 30, 40, and 70, NMC to receive, possess and use in amounts as required any byproduct, source or special nuclear material without restriction to chemical or physical form, for sample analysis or instrument and equipment calibration or associated with radioactive apparatus or components; (5)
Pursuant to the Act and 10 CFR Parts 30 and 70, NMC to possess but not separate, such byproduct and special nuclear materials as may be produced by the operation of the facility; (6)
Pursuant to the Act and 10 CFR Parts 30 and 70, NMC to transfer byproduct materials from other job sites owned by Northern States Power Company for the purpose of volume reduction and decontamination.
C.
This amended license shall be deemed to contain and is subject to the conditions specified in the following Commission regulations in 10 CFR Chapter l: Part 20, Section 30.34 of Part 30, Sections 50.54 and 50.59 of Part 50, and Section 70.32 of Part 70; is subject to all applicable provisions of the Act and to the rules, regulations, and orders of the Commission now or hereafter in effect; and is subject to the additional conditions specified or incorporated below:
(1)
Maximum Power Level NMC is authorized to operate the facility at steady state reactor core power levels not in excess of 1650 megawatts thermal.
(2)
Technical Specifications The Technical Specifications contained in Appendix A, as revised through Amendment No. 178, are hereby incorporated in the license. NMC shall operate the facility in accordance with the Technical Specifications.
(3)
Physical Protection NMC shall fully implement and maintain in effect all provisions of the Commission-approved physical security, guard training and qualification, and safeguards contingency plans including amendments made pursuant to provisions of the Miscellaneous Amendments and Search Requirements revisions to 10 CFR 73.55 (51 FR 27817 and 27822) and to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The combined set of plans, which contains Safeguards Information protected under 10 CFR 73.21, is entitled: "Prairie Island Nuclear Generating Plant Security Plan, Training and Qualification Plan, Safeguards Contingency Plan, and Independent Spent Fuel Storage Installation Security Program," Revision 1, submitted by letters dated October 18, 2006, and January 10, 2007.
Unit 1 Amendment No. 178 Revised by letter dated June 26, 2007 (5)
Pursuant to the Act and 10 CFR Parts 30 and 70, NMC to possess but not separate, such byproduct and special nuclear materials as may be produced by the operation of the facility; (6)
Pursuant to the Act and 10 CFR Parts 30 and 70, NMC to transfer byproduct materials from other job sites owned by Northern States Power Company for the purposes of volume reduction and decontamination.
C.
This amended license shall be deemed to contain and is subject to the conditions specified in the following Commission regulations in 10 CFR Chapter l: Part 20, Section 30.34 of Part 30, Sections 50.54 and 50.59 of Part 50, and Section 70.32 of Part 70; is subject to all applicable provisions of the Act and to the rules, regulations, and orders of the Commission now or hereafter in effect; and is subject to the additional conditions specified or incorporated below:
(1)
Maximum Power Level NMC is authorized to operate the facility at steady state reactor core power levels not in excess of 1650 megawatts thermal.
(2)
Technical Specifications The Technical Specifications contained in Appendix A, as revised through Amendment No. 168, are hereby incorporated in the license. NMC shall operate the facility in accordance with the Technical Specifications.
(3)
Physical Protection NMC shall fully implement and maintain in effect all provisions of the Commission-approved physical security, guard training and qualification, and safeguards contingency plans including amendments made pursuant to provisions of the Miscellaneous Amendments and Search Requirements revisions to 10 CFR 73.55 (51 FR 27817 and 27822) and to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The combined set of plans, which contains Safeguards Information protected under 10 CFR 73.21, is entitled:
'Prairie Island Nuclear Generating Plant Security Plan, Training and Qualification Plan, Safeguards Contingency Plan, and Independent Spent Fuel Storage Installation Security Program," Revision 1, submitted by letters dated October 18, 2006, and January 10, 2007.
Unit 2 Amendment No. 168 Revised by letter dated June 26, 2007