ML070720181

From kanterella
Jump to navigation Jump to search
Errata Letter for IR 05000327-06-005, IR 05000328-06-005; IR 07200034-06-002; 10/01/2006 - 12/31/2006; Sequoyah Nuclear Plant, Units 1 & 2; Licensed Operator Requalification Program
ML070720181
Person / Time
Site: Sequoyah  Tennessee Valley Authority icon.png
Issue date: 02/22/2007
From: Widmann M
Reactor Projects Region 2 Branch 6
To: Singer K
Tennessee Valley Authority
References
IR-06-002, IR-06-005
Download: ML070720181 (32)


See also: IR 05000327/2006005

Text

February 22, 2007

Tennessee Valley Authority

ATTN: Mr. Karl W. Singer

Chief Nuclear Officer and

Executive Vice President

6A Lookout Place

1101 Market Street

Chattanooga, TN 37402-2801

SUBJECT:

ERRATA LETTER FOR SEQUOYAH NUCLEAR PLANT - NRC INTEGRATED

INSPECTION REPORT 05000327/2006005, 05000328/2006005 AND

07200034/2006002

Dear Mr. Singer:

On December 31, 2005, the United States Nuclear Regulatory Commission (NRC) completed

an inspection at your Sequoyah Nuclear Plant, Units 1 and 2. The above inspection report was

issued without three inspection findings and the closeout of four unresolved items which were

discussed in a conference call between Mr. R. Schin of this office and Mr. D. Kulisek and other

members of the your staff on December 20, 2006. The purpose of this letter is to include those

items in the inspection report and to ask that you replace the enclosed revised pages in your

original document.

The three additional inspection findings were of very low safety significance and were

determined to involve violations of NRC requirements. However, because of their very low

safety significance and because they are entered into your corrective action program, the NRC

is treating these findings as non-cited violations (NCVs) consistent with Section VI.A.1 of the

NRC Enforcement Policy. If you contest any of the additional NCVs in the enclosed revised

pages, you should provide a response within 30 days of the date of this errata letter, with the

basis for your denial, to the United States Nuclear Regulatory Commission, ATTN.: Document

Control Desk, Washington, D.C. 20555-0001; with copies to the Regional Administrator Region

II; the Director, Office of Enforcement, United States Nuclear Regulatory Commission,

Washington, D.C. 20555-0001; and the NRC Resident Inspector at the Sequoyah Nuclear

Plant.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter, its

enclosure, and your response, if any, will be available electronically for public inspection in the

NRC Public Document Room or from the Publicly Available Records (PARS) component of

TVA

2

NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

If you have any questions, please contact me at (404) 562-4550.

Sincerely,

/RA/

Malcolm T. Widmann, Chief

Reactor Projects Branch 6

Division of Reactor Projects

Docket Nos. 50-327, 50-328,72-034

License Nos. DPR-77, DPR-79

Enclosure:

Errata pages for Inspection Report 05000327/2006005 and 05000328/2006005

and 07200034/2006002

cc: w/encl: (See page 3)

_________________________

OFFICE

RII:DRP

RII:DRP

RII:DRS

SIGNATURE

/RA/

/RA/

/RA By MThomas for/

NAME

LGarner

MWidmann

CPayne

DATE

2/22/07

2/22/07

2/22/07

E-MAIL COPY?

YES

NO YES

NO YES

NO YES

NO YES

NO YES

NO

TVA

3

cc w/encl:

Ashok S. Bhatnagar

Senior Vice President

Nuclear Operations

Tennessee Valley Authority

Electronic Mail Distribution

Preston D. Swafford

Senior Vice President

Nuclear Support

Tennessee Valley Authority

Electronic Mail Distribution

Larry S. Bryant, Vice President

Nuclear Engineering &

Technical Services

Tennessee Valley Authority

Electronic Mail Distribution

Randy Douet

Site Vice President

Sequoyah Nuclear Plant

Electronic Mail Distribution

General Counsel

Tennessee Valley Authority

Electronic Mail Distribution

John C. Fornicola, General Manager

Nuclear Assurance

Tennessee Valley Authority

Electronic Mail Distribution

Glenn W. Morris, Manager

Licensing and Industry Affairs

Sequoyah Nuclear Plant

Tennessee Valley Authority

Electronic Mail Distribution

Beth A. Wetzel, Manager

Corporate Nuclear Licensing and

Industry Affairs

Tennessee Valley Authority

4X Blue Ridge

1101 Market Street

Chattanooga, TN 37402-2801

Robert H. Bryan, Jr., General Manager

Licensing and Industry Affairs

Sequoyah Nuclear Plant

Tennessee Valley Authority

4X Blue Ridge

1101 Market Street

Chattanooga, TN 37402-2801

David A. Kulisek, Plant Manager

Sequoyah Nuclear Plant

Tennessee Valley Authority

Electronic Mail Distribution

Lawrence E. Nanney, Director

TN Dept. of Environment & Conservation

Division of Radiological Health

Electronic Mail Distribution

County Mayor

Hamilton County Courthouse

Chattanooga, TN 37402-2801

Ann Harris

341 Swing Loop

Rockwood, TN 37854

James H. Bassham, Director

Tennessee Emergency Management

Agency

Electronic Mail Distribution

TVA

4

Letter to Karl W. Singer from Malcolm T. Widmann dated February 22, 2007

SUBJECT:

ERRATA: SEQUOYAH NUCLEAR PLANT - NRC INTEGRATED INSPECTION

REPORT 05000327/2006005, 05000328/2006005 AND 07200034/2006002

Distribution w/encl:

Bob Pascarelli, NRR

B. Moroney, NRR

C. Evans (Part 72 Only)

L. Slack, RII EICS

OE Mail (email address if applicable)

RIDSNRRDIRS

PUBLIC

TABLE OF CONTENTS

SUMMARY OF FINDINGS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2

REPORT DETAILS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3

REACTOR SAFETY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3

1R01

Adverse Weather Protection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4

1R02

Evaluations of Changes, Tests or Experiments . . . . . . . . . . . . . . . . . . . . . . . . . 4

1R04

Equipment Alignment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4

1R05

Fire Protection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4

1R07

Heat Sink Performance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5

1R08

Inservice Inspection (ISI) Activities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6

1R11

Licensed Operator Requalification Program . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9

1R12

Maintenance Effectiveness . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12

1R13

Maintenance Risk Assessments and Emergent Work Control . . . . . . . . . . . . . 12

1R15

Operability Evaluations

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13

1R17

Permanent Plant Modifications . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15

1R19

Post-Maintenance Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16

1R20

Refueling and Other Outage Activities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17

1R22

Surveillance Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19

1EP6

Drill Evaluation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19

RADIATION SAFETY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20

2OS1 Access Control To Radiologically Significant Areas . . . . . . . . . . . . . . . . . . . . . 20

OTHER ACTIVITIES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21

4OA2 Identification & Resolution of Problems . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21

4OA5 Other Activities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23

4OA6 Management Meetings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29

4OA7 Licensee Identified Violations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29

ATTACHMENT: SUPPLEMENTARY INFORMATION

Key Points of Contact . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . A-1

List of Items Opened, Closed, and Discussed . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . A-1

List of Documents Reviewed . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . A-3

List of Acronyms . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . A-14

Enclosure

U. S. NUCLEAR REGULATORY COMMISSION

REGION II

Docket Nos:

50-327, 50-328,72-034

License Nos:

DPR-77, DPR-79

Report No:

05000327/2006005 and 05000328/2006005 and

07200034/2006002

Licensee:

Tennessee Valley Authority (TVA)

Facility:

Sequoyah Nuclear Plant

Location:

Sequoyah Access Road

Soddy-Daisy, TN 37379

Dates:

October 1, 2006 - December 31, 2006

Inspectors:

J. Baptist, Acting Senior Resident Inspector

J. Diaz-Velez, Health Physicist (Section 2OS1)

F. Ehrhardt, Operations Engineer (Section 1R11.2)

L. Lake, Reactor Inspector (Section 1R08)

G. Laska, Senior Operations Examiner (Section 1R11.3)

D. Mas-Penaranda, Reactor Inspector (Sections 1R02, 1R17)

E. Michel, Reactor Inspector (Section 4OA5.3)

B. Miller, Reactor Inspector (Sections 1R08, 4OA5.2)

R. Moore, Senior Reactor Inspector (Section 4OA5.3)

S. Rose, Senior Operations Engineer (Section 1R11.3)

C. Smith Senior Reactor Inspector (Sections 1R02, 1R17)

M. Speck, Resident Inspector

C. Stancil, Resident Inspector (Section 1EP6)

Approved by:

M. Widmann, Chief

Reactor Projects Branch 6

Division of Reactor Projects

Enclosure

SUMMARY OF FINDINGS

IR 05000327/2006005, IR 05000328/2006005; IR 07200034/2006002; 10/01/2006 -

12/31/2006; Sequoyah Nuclear Plant, Units 1 & 2; Licensed Operator Requalification

Program.

The report covered a three-month period of inspection by resident inspectors and

announced inspections by 10 regional inspectors and one resident inspector from

another site. One NRC-identified Green finding, which was also a non-cited violation,

was identified. The significance of most findings is indicated by their color (Green,

White, Yellow, Red) using Inspection Manual Chapter (IMC) 0609, "Significance

Determination Process" (SDP). Findings for which the SDP does not apply may be

Green or be assigned a severity level after NRC management review. The NRC's

program for overseeing the safe operation of commercial nuclear power reactors is

described in NUREG-1649, "Reactor Oversight Process," Revision 3, dated July 2000.

A.

NRC-Identified and Self-Revealing Findings

Cornerstone: Mitigating Systems

Green. The inspectors identified a Green, non-cited violation (NCV) of 10 CFR 55.53,

Conditions of Licenses for failure to certify the qualifications and status of licensed

operators were current and valid prior to their resumption of license duties. Specific

aspects of the requalification program that were not valid included plant tours that were

not completed with another licensed operator and not completing all shift functions in

positions to which the individuals will be assigned. The licensee entered the finding into

the corrective action program as PER No.112004.

The finding is greater than minor because it is associated with the human performance

attribute of the Mitigating Systems Cornerstone that affects the cornerstone objective of

ensuring the availability, reliability, and capability of operators to respond to initiating

events to prevent undesirable consequences that could pose a potential risk to

operations. The finding was evaluated using the Operator Requalification Human

Performance Significance Determination Process. Under this SDP, record deficiencies

can be either minor or of very low safety significance (Green). This finding was

determined to be Green because it was related to the program for maintaining active

licenses and more than 20% of the records reviewed had deficiencies. (Section 1R11.3).

B.

Licensee-Identified Violations

A violation of very low safety significance, which was identified by the licensee, was

reviewed by the inspectors. Corrective actions taken or planned by the licensee have

been entered into the licensees corrective action program. This violation and corrective

action are listed in Section 4OA7.

Enclosure

29

performance indicator data submitted to the NRC to ensure it accurately reflected the

performance history of these systems.

b.

Findings and Observations

No findings of significance were identified. The licensee accurately documented the

baseline planned unavailability hours, the actual unavailability hours and the actual

unreliability information for the MSPI systems. No significant errors in the reported data

were identified, which resulted in a change to the indicated index color. No significant

discrepancies were identified in the MSPI basis document which resulted in: (1) a

change to the system boundary, (2) an addition of a monitored component, or (3) a

change in the reported index color.

.5

Institute of Nuclear Power Operations (INPO) Plant Assessment Report Review

a.

Inspection Scope

The inspectors reviewed the interim report for the INPO plant assessment report of

Sequoyah conducted in July 2006. The inspectors reviewed the report to ensure that

issues identified were consistent with the NRC perspectives of licensee performance

and if any significant safety issues were identified that required further NRC follow-up.

b. Findings

No findings of significance were identified.

4OA6 Meetings, Including Exit

.1

Exit Meeting Summary

On January 3, 2007, the resident inspectors presented the inspection results to

Mr. R. Douet and other members of his staff, who acknowledged the findings. The

inspectors asked the licensee whether any of the material examined during the

inspection should be considered proprietary. No proprietary information was identified.

4OA7 Licensee-Identified Violations

The following violation of very low safety significance (Green) was identified by the

licensee and is a violation of NRC requirements which meet the criteria of Section VI of

the NRC Enforcement Policy, NUREG-1600, for being dispositioned as an NCV.

TS 6.8.1 requires that written procedures shall be established, implemented, and

maintained covering the activities recommended in Appendix A of Regulatory

Guide 1.33, Revision 2, February 1978. Contrary to this, on November 28, 2006,

an AUO improperly implemented 0-GO-13,Reactor Coolant System Drain and

Fill Operations, Revision 54, Appendix AC by mispositioning an RCS loop 4 drain

valve. This revealed itself through the subsequent transfer of RCS inventory to

the Reactor Coolant Drain Tank and lowering of RCS pressurizer level. The

30

Enclosure

error was promptly corrected by operations staff and the event was identified in

the licensees corrective action program as PER 115534. This finding is of very

low safety significance because it did not challenge RCS inventory control by

exceeding available makeup capacity.

ATTACHMENT: SUPPLEMENTAL INFORMATION

Attachment

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee personnel

J. Adams, Boric Acid

D. Bodine, Chemistry/Environmental Manager

R. Bruno, Training Manager

R. Douet, Site Vice President

B. Dungan, Outage and Site Scheduling Manager

J. Epperson, Licensed Operator Requal Lead

J. Goulart, ISI

K. Jones, Site Engineering Manager

Z. Kitts, Licensing Engineer

D. Kulisek, Plant Manager

G. Morris, Licensing and Industry Affairs Manager

T. Niessen, Site Quality Manager

M. A. Palmer, Radiation Protection Manager

M. H. Palmer, Operations Manager

K. Parker, Maintenance and Modifications Manager

J. Proffitt, (Acting) Site Licensing Supervisor

J. Reisenbuechler, Operations Training Manager

R. Reynolds, Site Security Manager

N. Thomas, Licensing Engineer

S. Tuthill, Chemistry Operations Manager

J. Whitaker, ISI

K. Wilkes, Emergency Preparedness Manager

NRC personnel:

R. Bernhard, Region II, Senior Reactor Analyst

D. Pickett, Project Manager, Office of Nuclear Reactor Regulation

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

Opened and Closed

05000327,328/2006005-01

NCV

Failure to Certify Qualifications and Status

of Licensed Operators Were Current and

Valid (Section 1R11.3)

Opened

05000328/2006005-02

URI

Appendix R Manual Isolation Valve Failure

to Close Within the Required Time text

(Section 1R15)

Closed

05000327,328/2515/169

TI

Mitigating Systems Performance Index

Verification (Section 4OA5.4)

Attachment

A-2

Discussed

05000327, 328/2515/150

TI

Reactor Pressure Vessel Head and Vessel

Head Penetration Nozzles (NRC Order EA-

03-009) - Unit 2 (Section 4OA5.2)

05000327, 328/2515/166

TI

Pressurized Water Reactor Containment

Sump Blockage (NRC Generic Letter 2004-

02) - Unit 2 Section 4OA5.3)

Attachment

LIST OF ACRONYMS

AFW

auxiliary feedwater

ANSI

American National Standards Institute

AOP

abnormal operating procedures

ARC

alternate repair criteria

ASME

American Society of Mechanical Engineers

ATWS

anticipated transient without scram

AUO

auxiliary unit operator

BACC

boric acid corrosion control

BMV

bare metal visual

CCP

cooling charging pump

CCPIT

cooling charging pump injection tank

CFR

Code of Federal Regulations

CR

condition report

CRDM

control rod drive mechanism

CVCS

chemical volume control system

DCN

design change notice

ECCS

emergency core cooling system

ECT

eddy current testing

EDY

effective degradation years

ERCW

essential raw cooling water

ETSS

examination technique specifications sheet

FCV

flow control valve

FE

functional evaluation

FME

foreign material exclusion

FOSAR

foreign object search and recovery

HR

high radiation

HUT

holdup tank

INPO

Institute of Nuclear power Operations

ISFSI

independent spent fuel storage installation

ISI

inservice inspection

LHRA

locked high radiation area

MRP

materials reliability program

MSPI

mitigating systems performance index

NCV

non-cited violation

NDE

non-destructive examination

NRC

U.S. Nuclear Regulatory Commission

ODSCC

outer diameter stress corrosion cracking

OPDP

operations department procedure

PAR

publically available records

PER

problem evaluation report

PER

protective action recommendation

PORV

power-operated relief valve

PWSCC

primary water stress corrosion cracking

RCP

reactor coolant pump

RCS

reactor coolant system

RHR

residual heat removal

RP

radiation protection

Attachment

A-15

RPVH

reactor pressure vessel head

RTP

rated thermal power

RWP

radiation work permit

RWST

refueling water storage tank

SDP

significance determination process

SER

safety evaluation report

SG

steam generator

SI

safety injection

SI

surveillance instructions

SSC

structure, system, or component

TDAFP

turbine driven auxiliary feedwater pump

TI

temporary instruction

TS

technical specification

TVA

Tennessee Valley Authority

UFSAR

updated final safety analysis report

UHI

upper head injection

URI

unresolved item

UT

ultrasonic testing

WOs

work orders

Enclosure

U. S. NUCLEAR REGULATORY COMMISSION

REGION II

Docket Nos:

50-327, 50-328,72-034

License Nos:

DPR-77, DPR-79

Report No:

05000327/2006005 and 05000328/2006005 and

07200034/2006002

Licensee:

Tennessee Valley Authority (TVA)

Facility:

Sequoyah Nuclear Plant

Location:

Sequoyah Access Road

Soddy-Daisy, TN 37379

Dates:

October 1, 2006 - December 31, 2006

Inspectors:

J. Baptist, Acting Senior Resident Inspector

J. Diaz-Velez, Health Physicist (Section 2OS1)

F. Ehrhardt, Operations Engineer (Section 1R11.2)

L. Lake, Reactor Inspector (Section 1R08)

G. Laska, Senior Operations Examiner (Section 1R11.3)

D. Mas-Penaranda, Reactor Inspector (Sections 1R02, 1R17)

E. Michel, Reactor Inspector (Section 4OA5.3)

B. Miller, Reactor Inspector (Sections 1R08, 4OA5.2)

R. Moore, Senior Reactor Inspector (Section 4OA5.3)

S. Rose, Senior Operations Engineer (Section 1R11.3)

R. Schin, Senior Reactor Inspector (Sections 4OA5.5 - 4OA5.8)

C. Smith Senior Reactor Inspector (Sections 1R02, 1R17)

M. Speck, Resident Inspector

C. Stancil, Resident Inspector (Section 1EP6)

Approved by:

M. Widmann, Chief

Reactor Projects Branch 6

Division of Reactor Projects

Enclosure

TABLE OF CONTENTS

SUMMARY OF FINDINGS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2a

REPORT DETAILS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3

REACTOR SAFETY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3

1R01

Adverse Weather Protection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4

1R02

Evaluations of Changes, Tests or Experiments . . . . . . . . . . . . . . . . . . . . . . . . . 4

1R04

Equipment Alignment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4

1R05

Fire Protection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4

1R07

Heat Sink Performance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5

1R08

Inservice Inspection (ISI) Activities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6

1R11

Licensed Operator Requalification Program . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9

1R12

Maintenance Effectiveness . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12

1R13

Maintenance Risk Assessments and Emergent Work Control . . . . . . . . . . . . . 12

1R15

Operability Evaluations

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13

1R17

Permanent Plant Modifications . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15

1R19

Post-Maintenance Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16

1R20

Refueling and Other Outage Activities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17

1R22

Surveillance Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19

1EP6

Drill Evaluation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19

RADIATION SAFETY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20

2OS1 Access Control To Radiologically Significant Areas . . . . . . . . . . . . . . . . . . . . . 20

OTHER ACTIVITIES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21

4OA2 Identification & Resolution of Problems . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21

4OA5 Other Activities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23

4OA6 Management Meetings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 38

4OA7 Licensee Identified Violations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 38

ATTACHMENT: SUPPLEMENTARY INFORMATION

Key Points of Contact . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . A-1

List of Items Opened, Closed, and Discussed . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . A-1

List of Documents Reviewed . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . A-3

List of Acronyms . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . A-14

Enclosure

SUMMARY OF FINDINGS

IR 05000327/2006005, IR 05000328/2006005; IR 07200034/2006002; 10/01/2006 -

12/31/2006; Sequoyah Nuclear Plant, Units 1 & 2; Licensed Operator Requalification

Program.

The report covered a three-month period of inspection by resident inspectors and

announced inspections by 11 regional inspectors and one resident inspector from

another site. Four NRC-identified Green findings, which were also non-cited violations,

were identified. The significance of most findings is indicated by their color (Green,

White, Yellow, Red) using Inspection Manual Chapter (IMC) 0609, "Significance

Determination Process" (SDP). Findings for which the SDP does not apply may be

Green or be assigned a severity level after NRC management review. The NRC's

program for overseeing the safe operation of commercial nuclear power reactors is

described in NUREG-1649, "Reactor Oversight Process," Revision 3, dated July 2000.

A.

NRC-Identified and Self-Revealing Findings

Cornerstone: Mitigating Systems

Green. The inspectors identified a Green, non-cited violation (NCV) of 10 CFR 55.53,

Conditions of Licenses for failure to certify the qualifications and status of licensed

operators were current and valid prior to their resumption of license duties. Specific

aspects of the requalification program that were not valid included plant tours that were

not completed with another licensed operator and not completing all shift functions in

positions to which the individuals will be assigned. The licensee entered the finding into

the corrective action program as PER No.112004.

The finding is greater than minor because it is associated with the human performance

attribute of the Mitigating Systems Cornerstone that affects the cornerstone objective of

ensuring the availability, reliability, and capability of operators to respond to initiating

events to prevent undesirable consequences that could pose a potential risk to

operations. The finding was evaluated using the Operator Requalification Human

Performance Significance Determination Process. Under this SDP, record deficiencies

can be either minor or of very low safety significance (Green). This finding was

determined to be Green because it was related to the program for maintaining active

licenses and more than 20% of the records reviewed had deficiencies. (Section 1R11.3).

Green. The inspectors identified a non-cited violation of Unit 1 License Condition 16,

Fire Protection, and Unit 2 License Condition 13, Fire Protection, for failure to protect

certain equipment that was required for safe shutdown from fire damage. The

licensees Safe Shutdown Analysis for a fire in the Unit 1 480V Board Room 1B (Fire

Area FAA-095) relied on the fire not damaging at least two of the three Unit 1 battery

chargers located in the room plus one of the two Unit 1 inverters and one of the two

Unit 2 inverters located in the room. However, the battery chargers and inverters were

not separated or protected from fire damage as required by the License Conditions and

Fire Protection Program. The licensee entered the issue into the corrective action

program.

2b

Enclosure

This finding is of greater than minor safety significance because it affected the

objectives of the Mitigating Systems Cornerstone of Reactor Safety. It affected the

availability and reliability of systems that mitigate initiating events to prevent undesirable

consequences and also involved a lack of required fire barriers or separation for

equipment relied upon for safe shutdown following a fire. The finding is of very low

safety significance because of the low frequency of fires that could damage two of the

three Unit 1 battery chargers, both Unit 1 inverters, or both Unit 2 inverters that were

located in the Unit 1 480V Board Room 1B concurrent with a failure of the sprinkler

system. (Section 4OA5.5)

Green. The inspectors identified a non-cited violation of Unit 1 License Condition 16,

Fire Protection, and Unit 2 License Condition 13, Fire Protection, for failure to protect

certain electrical cables for safe shutdown equipment from fire damage. The power

cables to Unit 1 vital inverter 1-II and Unit 2 vital inverter 2-II were routed through the

north end of the Unit 1 480V Board Room 1B (Fire Area FAA-095) without protection or

separation from fire damage as required by the License Conditions and Fire Protection

Program. The licensee entered the issue into the corrective action program and revised

the fire procedure to add local manual operator actions to mitigate the effects of fire

damage to the cables of concern.

This finding is of greater than minor safety significance because it affected the

objectives of the Mitigating Systems Cornerstone of Reactor Safety. It affected the

availability and reliability of systems that mitigate initiating events to prevent undesirable

consequences and also involved a lack of required fire barriers or separation for

equipment relied upon for safe shutdown following a fire. The finding is of very low

safety significance because of the low frequency of fires that could damage the cables

of concern and also damage the redundant safe shutdown equipment. (Section

4OA5.6)

Green. The inspectors identified a non-cited violation of Unit 2 License Condition 13,

Fire Protection, for failure to maintain adequate lighting in the Unit 2 main steam valve

vault room to support time-critical operator actions required for post-fire safe shutdown.

The licensee entered the issue into the corrective action program and replaced the light

bulbs to restore the room lighting.

This finding is of greater than minor safety significance because it affected the

objectives of the Mitigating Systems Cornerstone of Reactor Safety. It affected the

availability and reliability of systems that mitigate initiating events to prevent undesirable

consequences. The finding is of very low safety significance because of the low

frequency of fires that could lead to core damage if the operator actions in the Unit 2

main steam valve vault room were not performed in a timely manner. (Section 4OA5.7)

B.

Licensee-Identified Violations

A violation of very low safety significance, which was identified by the licensee, was

reviewed by the inspectors. Corrective actions taken or planned by the licensee have

been entered into the licensees corrective action program. The violation and corrective

actions are listed in Section 4OA7.

29

Enclosure

performance indicator data submitted to the NRC to ensure it accurately reflected the

performance history of these systems.

b.

Findings and Observations

No findings of significance were identified. The licensee accurately documented the

baseline planned unavailability hours, the actual unavailability hours and the actual

unreliability information for the MSPI systems. No significant errors in the reported data

were identified, which resulted in a change to the indicated index color. No significant

discrepancies were identified in the MSPI basis document which resulted in: (1) a

change to the system boundary, (2) an addition of a monitored component, or (3) a

change in the reported index color.

.5

(Closed) Unresolved Item (URI) 05000327,328/2005011-01, Reliance on 20-foot

Separation Zones for Fire Protection in Unit 1 480V Board Room 1B

a.

Inspection Scope

This in-office review followed up on URI 05000327,328/2005011-01, which had been

opened for NRC review of the licensing basis regarding use of 20-foot separation zones,

as specified in Appendix R,Section III.G.2 of 10 CFR 50, to protect safe shutdown

equipment from fire damage and the potential for the identified condition to adversely

affect safe shutdown.

b.

Findings

Introduction. A Green non-cited violation (NCV) of Unit 1 License Condition 16, Fire

Protection, and Unit 2 License Condition 13, Fire Protection, was identified for failure to

protect certain equipment that was required for safe shutdown from fire damage. The

licensees Safe Shutdown Analysis for a fire in the Unit 1 480V Board Room 1B (Fire

Area FAA-095) relied on the fire not damaging at least two of the three Unit 1 battery

chargers located in the room plus one of the two Unit 1 inverters and one of the two

Unit 2 inverters located in the room. However, the battery chargers and inverters were

not separated or protected from fire damage as required by the License Conditions and

Fire Protection Program.

Description. As described in Inspection Report (IR) 05000327,328/2005011, the NRC

had identified that the battery chargers and inverters in the Unit 1 480V Board Room 1B

(Fire Area FAA-095) were not separated or protected from fire damage as required by

10 CFR 50, Appendix R, Section III.G.2. One method prescribed by III.G.2 was

separation of equipment of redundant trains by a horizontal distance of more than 20

feet with no intervening combustibles or fire hazards. In addition, III.G.2 required that

fire detectors and an automatic fire suppression system be installed in the fire area.

The licensee had relied on 20-foot separation zones between each of the three Unit 1

battery chargers located in the room, a 20-foot separation zone between the two Unit 1

inverters located in the room, and a 20-foot separation zone between the two Unit 2

inverters located in the room. However, each 20-foot separation zone was not free of

intervening combustibles or fire hazards as required in that each 20-foot zone contained

30

Enclosure

energized 480V motor control centers (MCCs), nonqualified electrical cables in open

trays, and other electrical equipment including inverters. The MCCs, inverters, and non-

qualified cables in trays represented both ignition sources (fire hazards) and

combustibles in the form of insulated wires.

IR 05000327,328/2005011 also described the NRC-approved Deviation #11 to 10 CFR 50, Appendix R, Section III.G.2, regarding 20-foot separation zones in the auxiliary

building. (The Unit 1 480V Board Room 1B was located in the auxiliary building.)

Deviation #11 allowed 20-foot separation zones with intervening combustibles in the

form of cable trays provided that: 1) the cables had fuse and breaker coordination to

minimize the potential for fires initiating from cable faults and 2) extra sprinklers were

installed to compensate for cable trays partially blocking any sprinklers. The electrical

cables that were in open trays in the 20-foot separation zones in Unit 1 480V Board

Room 1B had sprinklers installed above and alongside them and the cables had fuse

and breaker coordination. The 480V MCCs that were in the 20-foot separation zones

also had sprinklers installed above them; however, the MCCs were not included in an

approved Deviation. Also, the MCCs represented much more significant ignition

sources (fire hazards) than the cable trays. In addition, some of the other electrical

equipment that was in one 20-foot separation zone (inverters in the 20-foot zone

between battery chargers on the south end of the room ) had no sprinklers above them.

After further in-office review of the licensing basis, the inspectors determined that strict

compliance with Appendix R to 10 CFR 50 is not a current requirement for Sequoyah

Units 1 and 2. Appendix R states that it applies to licensed nuclear power electric

generating stations that were operating prior to January 1, 1979. However, Sequoyah

Units 1 and 2 received their operating licenses after January 1, 1979. Prior to 1997, the

Sequoyah Unit 1 and Unit 2 License Conditions for Fire Protection had required that

TVA shall comply with Sections III.G, III.J, III.l, and III.O of Appendix R of 10 CFR 50,

except where the NRC has approved deviations. However, the Unit 1 and Unit 2

License Conditions for Fire Protection were changed in 1997 to no longer specifically

require compliance with Appendix R. The current License Conditions for Fire Protection

allow the licensee to make changes to the fire protection program if the changes do not

adversely affect post-fire safe shutdown.

During the inspection that is documented in IR 05000327,328/2005011, licensee

engineers had written an evaluation stating that the presence of MCCs and inverters in

the 20-foot separation zones in Unit 1 480V Board Room 1B did not adversely affect

safe shutdown and were acceptable as installed because there were sprinklers above

the cable trays and MCCs. However, after further in-office and onsite review, the

inspectors determined that the arrangement of MCCs with open cable trays directly

above them in the room created the potential for a fire initiating in an MCC section to

quickly involve cable trays, grow large enough to damage all of the equipment in the

room, and consequently to adversely affect safe shutdown. While there were sprinklers

above the MCCs and cable trays that could potentially extinguish a fire before it became

large, they were in a cross-zone preaction-type system that had a potential to fail. The

sprinkler piping was normally dry. Supplying water into the sprinkler piping involved

activation of at least two smoke detectors from different zones in the room and then

automatic opening of a valve in the fire water system. If the cross-zone detector circuit

31

Enclosure

failed or the automatic valve failed, then all of the sprinklers in the room would fail to

deliver water. The inspectors determined that the presence of 480V MCCs and

inverters (with open cable trays above them) in the 20-foot separation zones did not

comply with the approved Fire Protection Program and that this nonconforming

condition did adversely affect safe shutdown. Consequently, this condition represented

a violation of the Unit 1 and Unit 2 License Conditions for Fire Protection. When

informed of this determination, the licensee promptly entered the condition into the

corrective action program in Problem Evaluation Report (PER) 116718.

Analysis. This finding is of greater than minor safety significance because it affected the

objectives of the Mitigating Systems Cornerstone of Reactor Safety. The finding

affected the availability and reliability of systems that mitigate initiating events to prevent

undesirable consequences and also involved a lack of required fire barriers for

equipment relied upon for safe shutdown following a fire. The finding is of very low

significance because of the low frequency of fires that could quickly grow large enough

to damage all of the equipment in the room, concurrent with a failure of the sprinkler

system.

The finding affected fire protection, so the Fire Protection Significance Determination

Process (SDP) (NRC Manual Chapter 0609, Appendix F) analysis was used. Because

the finding affected post-fire safe shutdown, represented a high degradation, and had a

duration of more than 30 days, the Fire Protection SDP Phase 1 analysis screened to

Phase 2. In the Phase 2 analysis, the same fire scenarios that affected this finding also

affected the finding described in the following Section 4OA5.6, so they were analyzed

together. In the Phase 2 analysis, about 40 of the 480V motor control center (MCC)

vertical sections in the room with multiple open cable trays directly above them could

initiate a fire that could create a hot gas layer that could damage everything in the room

before the fire brigade would arrive, if the automatic sprinkler system failed. With a

sprinkler system failure probability of 0.05, the finding screened to greater than Green

and an SDP Phase 3 was needed. In the Phase 3 analysis, two NRC Senior Reactor

Analysts conducted onsite inspection of the physical arrangement of target cables and

ignition sources and used more advanced analytical methods than those used in the

SDP Phase 2 analysis. The SDP Phase 3 analysis concluded the finding was of very

low safety significance (Green) because of the low frequency of fires that could quickly

grow large enough to damage all of the equipment in the room, concurrent with a failure

of the sprinkler system.

Enforcement. The Unit 1 and Unit 2 License Conditions for Fire Protection (16 and 13,

respectively) require that TVA implement and maintain in effect all provisions of the

approved fire protection program referenced in the Sequoyah Nuclear Plants Final

Safety Analysis Report and as approved in NRC Safety Evaluation Reports (SERs),

including the SERs contained in NUREG-011, Supplement 1, and NUREG-1232,

Volume 2. The License Conditions also state that TVA may make changes to the

approved fire protection program without prior approval by the Commission only if those

changes would not adversely affect the ability to achieve and maintain safe shutdown in

the event of a fire.

The SERs in NUREG-011 and NUREG-1232 accepted the Sequoyah fire protection

program based on meeting the criteria of Appendix A to BTP 9.5-1 and Sections III.G,

III.J, III.l, and III.O of Appendix R. BTP 9.5-1 and Section III.G of Appendix R require

32

Enclosure

that where cables or equipment that could prevent operation or cause maloperation of

systems necessary to achieve and maintain hot shutdown conditions are located within

the same fire area outside of primary containment, the cables shall be separated from

circuits of redundant trains or protected from fire damage by one of three specified

means.

Contrary to the above requirements, the Unit 1 battery chargers, Unit 1 inverters, and

Unit 2 inverters in Unit 1 480V Board Room 1B (Fire Area FAA-095) were not separated

from circuits of redundant trains or protected from fire damage by one of the three

specified means and thus could adversely affect safe shutdown. These electrical

components that were relied on for safe shutdown during a fire in Unit 1 480V Board

Room 1B had been unprotected for many years. Because this failure to protect safe

shutdown components is of very low safety significance and has been entered into the

licensees corrective action program as PER 116718, this violation is being treated as an

NCV, consistent with Section VI.A of the NRC Enforcement Policy. It is identified as

NCV 05000327,328/2006005-03 Inadequate 20-foot Separation Zones for Fire

Protection in Unit 1 480V Board Room 1B . URI 05000327,328/2005011-01 is closed.

.6

(Closed) Unresolved Item (URI) 05000327,328/2005011-02, Unprotected Power Cables

to Vital Inverters in the Unit 1 480V Board Room 1B

a.

Inspection Scope

This in-office review followed up on URI 05000327,328/2005011-02, which had been

opened for NRC review of the licensing basis regarding use of local manual operator

actions instead of physical protection or separation of cables as required by 10 CFR 50,

Appendix R,Section III.G.2.

b.

Findings

Introduction. A Green NCV of Unit 1 License Condition 16, Fire Protection, and Unit 2

License Condition 13, Fire Protection, was identified for failure to protect certain

electrical cables for safe shutdown equipment from fire damage. The alternating current

(AC) power cables to Unit 1 vital inverter 1-II and Unit 2 vital inverter 2-II were routed

through the north end of the Unit 1 480V Board Room 1B (Fire Area FAA-095) without

protection or separation from fire damage as required by the License Conditions and

Fire Protection Program.

Description. As described in IR 05000327,328/2005011, the NRC had identified that the

licensee had failed to adequately protect the AC power cables to Unit 1 vital inverter 1-II

and Unit 2 vital inverter 2-II in the north end of the Unit 1 480V Board Room 1B (Fire

Area FAA-095) from fire damage. When informed of this condition, the licensee

promptly entered the issue into their corrective action program in PER 91841 and

revised the fire procedure to add local manual operator actions to mitigate the effects of

fire damage to the cables of concern. However, this licensee corrective action relied on

local manual operator actions instead of using physical protection or separation of the

cables as required by 10 CFR 50, Appendix R, Section III.G.2

After further review of the licensing basis, the inspectors determined that strict

compliance with Appendix R to 10 CFR 50 is not a current requirement for Sequoyah

33

Enclosure

Units 1 and 2. Appendix R states that it applies to licensed nuclear power electric

generating stations that were operating prior to January 1, 1979. However, Sequoyah

Units 1 and 2 received their operating licenses after January 1, 1979. Prior to 1997, the

Sequoyah Unit 1 and Unit 2 License Conditions for Fire Protection had required that

TVA shall comply with Sections III.G, III.J, III.l, and III.O of Appendix R of 10 CFR 50,

except where the NRC has approved deviations. However, the Unit 1 and Unit 2

License Conditions for Fire Protection were changed in 1997 to no longer specifically

require compliance with Appendix R. The current License Conditions for Fire Protection

allow the licensee to make changes to the fire protection program if the changes do not

adversely affect post-fire safe shutdown. Consequently, since the added local manual

operator actions did not adversely affect safe shutdown, the licensee could rely on them

as corrective action for the identified condition.

The inspectors determined that the licensees failure to protect the AC power cables to

Unit 1 vital inverter 1-II and Unit 2 vital inverter 2-II in the north end of the Unit 1 480V

Board Room 1B (Fire Area FAA-095) from fire damage was not in compliance with the

License Conditions for Fire Protection and the licensees approved fire protection

program, which included design criteria described in 10 CFR 50, Appendix R, Section

III.G.2 and NRC Branch Technical Position (BTP) 9.5-1. Further, this condition

adversely affected post-fire safe shutdown in that it created the potential for one fire to

damage equipment that was relied on for safe shutdown during that fire.

Analysis. This finding is of greater than minor safety significance because it affected the

objectives of the Mitigating Systems Cornerstone of Reactor Safety. The finding

affected the availability and reliability of systems that mitigate initiating events to prevent

undesirable consequences and also involved a lack of required fire barriers for

equipment relied upon for safe shutdown following a fire. The finding is of very low

significance because of the low frequency of fires that could damage the cables of

concern and also damage the redundant safe shutdown equipment which is located in

the same fire area.

The finding affected fire protection, so the Fire Protection Significance Determination

Process (SDP) (NRC Manual Chapter 0609, Appendix F) analysis was used. Because

the finding affected post-fire safe shutdown, represented a high degradation, and had a

duration of more than 30 days, the Fire Protection SDP Phase 1 analysis screened to

Phase 2. In the Phase 2 analysis, the same fire scenarios that affected this finding also

affected the finding described in the above Section 4OA5.5, so they were analyzed

together. In the Phase 2 analysis, about 40 of the 480V motor control center (MCC)

vertical sections in the room with multiple open cable trays directly above them could

initiate a fire that could create a hot gas layer that could damage everything in the room

before the fire brigade would arrive, if the automatic sprinkler system failed. With a

sprinkler system failure probability of 0.05, the finding screened to greater than Green

and an SDP Phase 3 was needed. In the Phase 3 analysis, two NRC Senior Reactor

Analysts conducted onsite inspection of the physical arrangement of target cables and

ignition sources and used more advanced analytical methods than those used in the

SDP Phase 2 analysis. The SDP Phase 3 analysis concluded the finding was of very

low safety significance (Green) because of the low frequency of fires that could damage

the cables of concern and also damage the redundant safe shutdown equipment which

is located in the same fire area.

34

Enclosure

Enforcement. The Unit 1 and Unit 2 License Conditions for Fire Protection (16 and 13,

respectively) require that TVA implement and maintain in effect all provisions of the

approved fire protection program referenced in the Sequoyah Nuclear Plants Final

Safety Analysis Report and as approved in NRC Safety Evaluation Reports (SERs),

including the SERs contained in NUREG-011, Supplement 1, and NUREG-1232,

Volume 2. The License Conditions also state that TVA may make changes to the

approved fire protection program without prior approval by the Commission only if those

changes would not adversely affect the ability to achieve and maintain safe shutdown in

the event of a fire.

The SERs in NUREG-011 and NUREG-1232 accepted the Sequoyah fire protection

program based on meeting the criteria of Appendix A to BTP 9.5-1 and Sections III.G,

III.J, III.l, and III.O of Appendix R. BTP 9.5-1 and Section III.G of Appendix R require

that where cables or equipment that could prevent operation or cause maloperation of

systems necessary to achieve and maintain hot shutdown conditions are located within

the same fire area outside of primary containment, the cables shall be separated from

circuits of redundant trains or protected from fire damage by one of three specified

means.

Contrary to the above requirements, the AC power cables to Unit 1 vital inverter 1-II and

Unit 2 vital inverter 2-II in the north end of the Unit 1 480V Board Room 1B (Fire Area

FAA-095) were not separated from circuits of redundant trains or protected from fire

damage by one of the three specified means and thus could adversely affect safe

shutdown. These cables had been unprotected for several years. Because this failure

to protect cables is of very low safety significance and has been entered into the

licensees corrective action program as PER 91841, this violation is being treated as an

NCV, consistent with Section VI.A of the NRC Enforcement Policy. It is identified as

NCV 05000327,328/2006005-04, Unprotected Power Cables to Vital Inverters in the

Unit 1 480V Board Room 1B. URI 05000327,328/2005011-02 is closed.

.7

(Closed) Unresolved Item (URI) 05000327,328/2005011-04, Appendix R Operator

Action to Throttle AFW in Main Steam Valve Vault Room

a.

Inspection Scope

This in-office review followed up on URI 05000327,328/2005011-04, which had been

opened for NRC review of the licensing basis for the post-fire operator action to throttle

AFW flow in the Unit 1 and 2 main steam valve vault rooms.

b.

Findings

Introduction. A Green NCV of Unit 2 License Condition 13, Fire Protection, was

identified for failure to maintain lighting in the Unit 2 main steam valve vault room. The

lighting was needed to support the post-fire time-critical operator action to throttle AFW

flow in the room.

Description. As described in IR 05000327,328/2005011, the NRC had identified that the

Unit 2 main steam valve vault room was completely dark. All of the normal lights were

out because the light bulbs were burned out and the installed Appendix R emergency

lights were off because normal power was available. When informed of this condition,

35

Enclosure

the licensee had promptly entered the issue into their corrective action program in PER

91899 and replaced the light bulbs to restore the normal lighting. The inspectors had

determined that the operator actions in the Unit 2 main steam valve vault room were

feasible with lighting, but were not feasible for one operator to reliably accomplish in

complete darkness. Additionally, the inspectors had questioned the acceptability of the

licensees reliance on the local manual operator actions without obtaining NRC approval

for a Deviation from the requirements of 10 CFR 50, Appendix R, Section III.G.2.

After further review of the licensing basis, the inspectors determined that strict

compliance with Appendix R to 10 CFR 50 was not a current requirement for Sequoyah

Units 1 and 2. Appendix R states that it applies to licensed nuclear power electric

generating stations that were operating prior to January 1, 1979. However, Sequoyah

Units 1 and 2 received their operating licenses after January 1, 1979. Prior to 1997, the

Sequoyah Unit 1 and Unit 2 License Conditions for Fire Protection had required that

TVA shall comply with Sections III.G, III.J, III.l, and III.O of Appendix R of 10 CFR 50,

except where the NRC has approved deviations. However, the Unit 1 and Unit 2

License Conditions for Fire Protection were changed in 1997 to no longer specifically

require compliance with Appendix R. The current License Conditions for Fire Protection

allow the licensee to make changes to the fire protection program if the changes do not

adversely affect post-fire safe shutdown. Consequently, if the local manual operator

actions in the main steam valve vault room were feasible and reliable, then they would

not adversely affect safe shutdown and the licensee could rely on them without needing

NRC review and approval.

The time-critical local manual actions to throttle AFW in the main steam valve vault room

were required in AOP-N.08, Appendix R Fire Safe Shutdown, Rev. 7, and in AOP-C.04,

Shutdown From Auxiliary Control Room, Rev. 8. The inspectors had determined that

the manual operator actions could be considered feasible if the installed lighting was

working. However, with no installed lights working, the manual operator actions were

not determined to be feasible. Consequently, the licensees failure to maintain the

lighting to support the operator actions created a condition that could adversely affect

safe shutdown during certain fires.

After the licensee replaced the light bulbs in the Unit 2 main steam valve vault room,

then both the Unit 2 and Unit 1 main steam valve vault rooms were lighted. With the

rooms lighted, the inspectors considered that the manual operator actions in the rooms

were feasible and would not adversely affect safe shutdown.

Analysis. This finding is of greater than minor safety significance because it affected the

objectives of the Mitigating Systems Cornerstone of Reactor Safety. The finding

affected the availability and reliability of systems that mitigate initiating events to prevent

undesirable consequences and also involved a lack of required fire protection for

equipment relied upon for safe shutdown following a fire. The finding is of very low

safety significance because of the low frequency of fires that could lead to core damage

if the operator actions in the Unit 2 main steam valve vault room were not performed in a

timely manner.

The finding affected fire protection, so the Fire Protection Significance Determination

Process (SDP) (NRC Manual Chapter 0609, Appendix F) analysis was used. Because

the finding affected post-fire safe shutdown, represented a high degradation, and had a

36

Enclosure

duration of more than 30 days, the Fire Protection SDP Phase 1 analysis screened to

Phase 2. In the Phase 2 analysis, because licensee mitigation of a fire in almost every

area of the plant involved reliance on a manual action to throttle AFW in the Unit 2 main

steam valve vault room, and no credit was given for the manual action, the finding did

not screen to Green and an SDP Phase 3 analysis was needed.

A regional Senior Reactor Analyst performed the Phase 3 analysis, including onsite

inspection and consideration of fires initiating in all areas of the plant. The Phase 3

analysis determined that the mitigation of fires in some areas of the plant relied on local

manual throttling of the motor driven auxiliary feedwater pump flow in the main steam

valve vault room; however, delay in performing that action would not lead to core

damage. Fires in other areas of the plant relied on local manual throttling of turbine

driven auxiliary feedwater pump flow in the main steam valve vault room; however, the

frequency of those fires was low. Also, the existence of Flamastic 77 (a flame spread

retardant) would slow the growth of fires in those areas. The SDP Phase 3 analysis

concluded the finding was of very low safety significance (Green) because of the low

frequency of fires that could lead to core damage if the operator actions in the Unit 2

main steam valve vault room were not performed in a timely manner.

Enforcement. The Unit 2 License Condition 13 for Fire Protection requires that TVA

implement and maintain in effect all provisions of the approved fire protection program

referenced in the Sequoyah Nuclear Plants Final Safety Analysis Report and as

approved in NRC SERs, including the SERs contained in NUREG-011, Supplement 1,

and NUREG-1232, Volume 2. The License Condition also states that TVA may make

changes to the approved fire protection program without prior approval by the

Commission only if those changes would not adversely affect the ability to achieve and

maintain safe shutdown in the event of a fire.

The fire protection program included the safe shutdown methodology that relied on the

time-critical local manual operator actions to throttle emergency feedwater in the main

steam valve vault room. Those local manual operator actions had been in place for

many years and had been documented in NRC Inspection Report 05000327,328/1988-

024, which was referenced in the SER in NUREG-1232, Volume 2.

Contrary to the above requirements, the licensee did not maintain the lighting in the Unit

2 main steam valve vault room to support the time-critical local manual operator actions

in that room. Because this failure to maintain room lighting is of very low safety

significance and has been entered into the licensees corrective action program as PER

91899, this violation is being treated as an NCV, consistent with Section VI.A of the

NRC Enforcement Policy. It is identified as NCV 05000328/2006005-05, Failure to

Maintain Lighting for Time-Critical Local Manual Actions for Post-Fire Safe Shutdown.

URI 05000327,328/2005011-04 is closed.

.8

(Closed) Unresolved Item (URI) 05000327,328/2005011-05, Reliance on Local Manual

Operator Actions for Appendix R Fires

a.

Inspection Scope

This in-office review followed up on URI 05000327,328/2005011-05, which had been

opened for NRC review of the licensing basis related to reliance on local manual

37

Enclosure

operator actions that had not been specifically approved by the NRC for mitigating 10 CFR 50, Appendix R, Section III.G.2 fires.

b.

Findings

Introduction. The inspectors determined that licensee reliance on local manual operator

actions, that had not been approved by the NRC for mitigating 10 CFR 50, Appendix R,

Section III.G.2 fires, was not prohibited by the licensing basis. Consequently, this URI

did not represent a finding.

Description. As described in IR 05000327,328/2005011, the NRC had identified that the

licensee relied on many local manual operator actions, that had not been approved by

the NRC as a Deviation, to mitigate 10 CFR 50, Appendix R, Section III.G.2 fires.

After further review of the licensing basis, the inspectors determined that strict

compliance with Appendix R to 10 CFR 50 was not a current requirement for Sequoyah

Units 1 and 2. Appendix R states that it applies to licensed nuclear power electric

generating stations that were operating prior to January 1, 1979. However, Sequoyah

Units 1 and 2 received their operating licenses after January 1, 1979. Prior to 1997, the

Sequoyah Unit 1 and Unit 2 License Conditions for Fire Protection had required that

TVA shall comply with Sections III.G, III.J, III.l, and III.O of Appendix R of 10 CFR 50,

except where the NRC has approved deviations. However, the Unit 1 and Unit 2

License Conditions for Fire Protection were changed in 1997 to no longer specifically

require compliance with Appendix R. The current License Conditions for Fire Protection

allow the licensee to make changes to the fire protection program if the changes do not

adversely affect post-fire safe shutdown. Consequently, if the local manual operator

actions were feasible and reliable, then they would not adversely affect safe shutdown

and the licensee could rely on them without needing NRC review and approval.

With the exception of the action to locally control AFW pump flow in the Unit 2 main

steam valve vault room (described above in Section 4OA5.7), the inspectors had found

that the local manual actions that were reviewed were all feasible. Therefore, the

licensee could rely on them without obtaining NRC review and approval. URI

05000327,328/2005011-05 is closed.

.9

Institute of Nuclear Power Operations (INPO) Plant Assessment Report Review

a.

Inspection Scope

The inspectors reviewed the interim report for the INPO plant assessment report of

Sequoyah conducted in July 2006. The inspectors reviewed the report to ensure that

issues identified were consistent with the NRC perspectives of licensee performance

and if any significant safety issues were identified that required further NRC follow-up.

b. Findings

No findings of significance were identified.

38

Enclosure

4OA6 Meetings, Including Exit

Exit Meeting Summary

On January 3, 2007, the resident inspectors presented the inspection results to

Mr. R. Douet and other members of his staff, who acknowledged the findings. The

inspectors asked the licensee whether any of the material examined during the

inspection should be considered proprietary. No proprietary information was identified.

4OA7 Licensee-Identified Violations

The following violation of very low safety significance (Green) was identified by the

licensee and is a violation of NRC requirements which meet the criteria of Section VI of

the NRC Enforcement Policy, NUREG-1600, for being dispositioned as an NCV.

TS 6.8.1 requires that written procedures shall be established, implemented, and

maintained covering the activities recommended in Appendix A of Regulatory

Guide 1.33, Revision 2, February 1978. Contrary to this, on November 28, 2006,

an AUO improperly implemented 0-GO-13,Reactor Coolant System Drain and

Fill Operations, Revision 54, Appendix AC by mispositioning an RCS loop 4 drain

valve. This revealed itself through the subsequent transfer of RCS inventory to

the Reactor Coolant Drain Tank and lowering of RCS pressurizer level. The

error was promptly corrected by operations staff and the event was identified in

the licensees corrective action program as PER 115534. This finding is of very

low safety significance because it did not challenge RCS inventory control by

exceeding available makeup capacity.

ATTACHMENT: SUPPLEMENTAL INFORMATION

Attachment

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee personnel

J. Adams, Boric Acid

D. Bodine, Chemistry/Environmental Manager

R. Bruno, Training Manager

R. Douet, Site Vice President

B. Dungan, Outage and Site Scheduling Manager

J. Epperson, Licensed Operator Requal Lead

J. Goulart, ISI

K. Jones, Site Engineering Manager

Z. Kitts, Licensing Engineer

D. Kulisek, Plant Manager

G. Morris, Licensing and Industry Affairs Manager

T. Niessen, Site Quality Manager

M. A. Palmer, Radiation Protection Manager

M. H. Palmer, Operations Manager

K. Parker, Maintenance and Modifications Manager

J. Proffitt, (Acting) Site Licensing Supervisor

J. Reisenbuechler, Operations Training Manager

R. Reynolds, Site Security Manager

N. Thomas, Licensing Engineer

S. Tuthill, Chemistry Operations Manager

J. Whitaker, ISI

K. Wilkes, Emergency Preparedness Manager

NRC personnel:

R. Bernhard, Region II, Senior Reactor Analyst

D. Pickett, Project Manager, Office of Nuclear Reactor Regulation

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

Opened

05000328/2006005-02

URI

Inability to Perform Required Actions of

AOP-N.08, Appendix R Fire Safe Shutdown

(Section 1R15)

Opened and Closed

05000327,328/2006005-01

NCV

Failure to Certify Qualifications and Status

of Licensed Operators Were Current and

Valid (Section 1R11.3)

A-2

Attachment

05000327,328/2006005-03

NCV

Inadequate 20-foot Separation Zones for

Fire Protection in Unit 1 480V Board Room

1B (Section 4OA5.5)

05000327,328/2006005-04

NCV

Unprotected Power Cables to Vital Inverters

in the Unit 1 480V Board Room 1B (Section

4OA5.6)05000328/2006005-05

NCV

Failure to Maintain Lighting for Time-Critical

Local Manual Actions for Post-Fire Safe

Shutdown (Section 4OA5.7)

Closed

05000327,328/2515/169

TI

Mitigating Systems Performance Index

Verification (Section 4OA5.4)

05000327,328/2005011-01

URI

Reliance on 20-foot Separation Zones for

Fire Protection in Unit 1 480V Board Room

1B (Section 4OA5.5)

05000327,328/2005011-02

URI

Unprotected Power Cables to Vital Inverters

in the Unit 1 480V Board Room 1B (Section

4OA5.6)

05000327,328/2005011-04

URI

Appendix R Operator Action to Throttle

AFW in Main Steam Valve Vault Room

(Section 4OA5.7)

05000327,328/2005011-05

URI

Reliance on Local Manual Operator Actions

for Appendix R Fires (Section 4OA5.8)

Discussed

05000327, 328/2515/150

TI

Reactor Pressure Vessel Head and Vessel

Head Penetration Nozzles (NRC Order EA-

03-009) - Unit 2 (Section 4OA5.2)

05000327, 328/2515/166

TI

Pressurized Water Reactor Containment

Sump Blockage (NRC Generic Letter 2004-

02) - Unit 2 Section 4OA5.3)

Attachment

LIST OF ACRONYMS

AC

alternating currrent

AFW

auxiliary feedwater

ANSI

American National Standards Institute

AOP

abnormal operating procedures

ARC

alternate repair criteria

ASME

American Society of Mechanical Engineers

ATWS

anticipated transient without scram

AUO

auxiliary unit operator

BACC

boric acid corrosion control

BMV

bare metal visual

CCP

cooling charging pump

CCPIT

cooling charging pump injection tank

CFR

Code of Federal Regulations

CR

condition report

CRDM

control rod drive mechanism

CVCS

chemical volume control system

DCN

design change notice

ECCS

emergency core cooling system

ECT

eddy current testing

EDY

effective degradation years

ERCW

essential raw cooling water

ETSS

examination technique specifications sheet

FCV

flow control valve

FE

functional evaluation

FME

foreign material exclusion

FOSAR

foreign object search and recovery

HR

high radiation

HUT

holdup tank

INPO

Institute of Nuclear power Operations

IR

inspection report

ISFSI

independent spent fuel storage installation

ISI

inservice inspection

LHRA

locked high radiation area

MCC

motor control center

MRP

materials reliability program

MSPI

mitigating systems performance index

NCV

non-cited violation

NDE

non-destructive examination

NRC

U.S. Nuclear Regulatory Commission

ODSCC

outer diameter stress corrosion cracking

OPDP

operations department procedure

PAR

publically available records

PER

problem evaluation report

PER

protective action recommendation

PORV

power-operated relief valve

PWSCC

primary water stress corrosion cracking

RCP

reactor coolant pump

A-15

Attachment

RCS

reactor coolant system

RHR

residual heat removal

RP

radiation protection

RPVH

reactor pressure vessel head

RTP

rated thermal power

RWP

radiation work permit

RWST

refueling water storage tank

SDP

significance determination process

SER

safety evaluation report

SG

steam generator

SI

safety injection

SI

surveillance instructions

SSC

structure, system, or component

TDAFP

turbine driven auxiliary feedwater pump

TI

temporary instruction

TS

technical specification

TVA

Tennessee Valley Authority

UFSAR

updated final safety analysis report

UHI

upper head injection

URI

unresolved item

UT

ultrasonic testing

WOs

work orders