Tech Spec Pages for Amendment 207 Regarding Steam Generator Tube Inspections and Repair Criteria within the Hot-Leg Tubesheet Region
ML062420156
Person / Time
Site: Waterford Entergy icon.png
Issue date: 08/29/2006
From:
NRC/NRR/ADRO/DORL/LPLIV
To:
Fields M, NRR/DORL, 415-3062
Shared Package
ML062420419 List:
References
TAC MC6421
Download: ML062420156 (4)


Text

or indirectly any.control over (i) the facility, (ii)power or energy produced by the facility, or (iii) the licensees of the facility. Further, any rights acquired under this authorization may be exercised only in compliance with and subject to the requirements and restrictions of this operating license, the Atomic Energy Act of 1954, as amended, and the NRC's regulations. For purposes of this condition, the limitations of 10 CFR 50.81, as now in effect and as they may be subsequently amended, are fully applicable to the equity investors and any successors in interest to the equity investors, as long as the license for the facility remains in effect.

(b) Entergy Louisiana, LLC (or its designee) to notify the NRC in writing prior to any change in (i) the terms or conditions of any lease agreements executed as part of the above authorized financial transactions, (ii)any facility operating agreement involving a licensee that is in effect now or will be in effect in the future, or (iii) the existing property insurance coverages for the facility, that would materially alter the representations and conditions, set forth in the staffs Safety Evaluation enclosed to the NRC letter dated September 18, 1989. In addition, Entergy Louisiana, LLC or its designee is required to notify the NRC of any action by equity investors or successors in interest to Entergy Louisiana, LLC that may have an effect on the operation of the facility.

C. This license shall be deemed to contain and is subject to the conditions specified in the Commission's regulations set forth in 10 CFR Chapter 1 and is subject to all applicable provisions of the Act and to the rules, regulations and orders of the Commission now or hereafter in effect; and is subject to the additional conditions specified or incorporated below:

1. Maximum Power Level EOI is authorized to operate the facility at reactor core power levels not in excess of 3716 megawatts thermal (100% power) in accordance with the conditions specified herein.
2. Technical Specifications and Environmental Protection Plan The Technical Specifications contained in Appendix A, as revised through Amendment No. 207 and the Environmental Protection Plan contained in Appendix B, are hereby incorporated in the license. EOI shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.

AMENDMENT NO. 207

ADMINISTRATIVE CONTROLS STEAM GENERATOR (SG) PROGRAM (Continued)

b. Performance criteria for SG tube integrity. SG tube integrity shall be maintained by meeting the performance criteria for tube structural integrity, accident induced leakage, and operational leakage.
1. Structural integrity performance criterion: All in-service steam generator tubes shall retain structural integrity over the full range of normal operating conditions (including startup, operation in the power range, hot standby, and cool down and all anticipated transients included in the design specification) and design basis accidents. This includes retaining a safety factor of 3.0 against burst under normal steady state full power operation primary to secondary pressure differential and a safety factor of 1.4 against burst applied to the design basis accident primary to secondary pressure differentials. Apart from the above requirements, additional loading conditions associated with the design basis accidents, or combination of accidents in accordance with the design and licensing basis, shall also be evaluated to determine if the associated loads contribute significantly to burst or collapse. In the assessment of tube integrity, those loads that do significantly affect burst or collapse shall be determined and assessed in combination with the loads due to pressure with a safety factor of 1.2 on the combined primary loads and 1.0 on axial secondary loads.
2. Accident induced leakage performance criterion: The primary to secondary accident induced leakage rate for any design basis accident, other than a SG tube rupture, shall not exceed the leakage rate assumed in the accident analysis in terms of total leakage rate for all SGs and leakage rate for an individual SG.

Primary to secondary leakage is not to exceed 540 gpd through any one SG.

3. The operational leakage performance criterion is specified in LCO 3.4.5.2, "Reactor Coolant System Operational Leakage."
c. Provisions for SG tube repair criteria. Tubes found by inservice inspection to contain flaws with a depth equal to or exceeding 40% of the nominal tube wall thickness shall be plugged.

The following alternate tube repair criteria may be applied as an alternative to the 40%

depth based criteria:

1. Flaws located greater than 10.6 inches below the bottom of the hot leg expansion transition or top of the hot leg tubesheet, whichever is lower, may remain in service. Degradation detected between 10.6 inches below the bottom of the hot leg expansion transition or top of the hot leg tubesheet, whichever is lower, and the bottom of the hot leg expansion transition or top of the hot leg tubesheet, whichever is higher, shall be plugged on detection.

WATERFORD - UNIT 3 6-7b AMENDMENT NO. 207

ADMINISTRATIVE CONTROLS STEAM GENERATOR (SG) PROGRAM (Continued)

d. Provisions for SG tube inspections. Periodic SG tube inspections shall be performed.

The number and portions of the tubes inspected and methods of inspection shall be performed with the objective of detecting flaws of any type (e.g., volumetric flaws, axial and circumferential cracks) that may be present along the length of the tube, from 10.6 inches below the bottom of the hot leg expansion transition or top of the hot leg tubesheet, whichever is lower, completely around the U-bend to the tube-to-tubesheet weld at the tube outlet and that may satisfy the applicable tube repair criteria. The tube-to-tubesheet weld is not part of the tube. In addition to meeting the requirements of d.1, d.2, and d.3 below, the inspection scope, inspection methods, and inspection intervals shall be such as to ensure that SG tube integrity is maintained until the next SG inspection. An assessment of degradation shall be performed to determine the type and location of flaws to which the tubes may be susceptible and, based on this assessment, to determine which inspection methods need to be employed and at what locations.

1. Inspect 100% of the tubes in each SG during the first refueling outage following SG replacement.
2. Inspection 100% of the tubes at sequential periods of 60 effective full power months. The first sequential period shall be considered to begin after the first inservice inspection of the SGs. No SG shall operate for more than 24 effective full power months or one refueling outage (whichever is less) without being inspected.
3. If crack indications are found in any SG tube, then the next inspection for each SG for the degradation mechanism that caused the crack indication shall not exceed 24 effective full power months or one refueling outage (whichever is less). If definitive information, such as from examination of a pulled tube, diagnostic non-destructive testing, or engineering evaluation indicates that a crack-like indication is not associated with a crack(s), then the indication need not be treated as a crack.
e. Provisions for monitoring operational primary to secondary leakage.

WATERFORD - UNIT 3 6-7c AAMENDMENT NO. 207

ADMINISTRATIVE CONTROLS ANNUAL REPORTS (Continued)

(1) Reactor power history starting 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> prior to the first sample in which the limit was exceeded; (2) Results of the last isotopic analysis for radioiodine performed prior to exceeding the limit, results of analysis while limit was exceeded and results of one analysis after the radioiodine activity was reduced to less than limit. Each result should include date and time of sampling and the radioiodine concentrations; (3) Clean-up system flow history starting 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> prior to the first sample in which the limit was exceeded; (4) Graph of the 1-131 concentration and one other.radioiodine isotope concentration in microcuries per gram as a function of time for the duration of the specific activity above steady-state level; and (5) The time duration when the specific activity of the primary coolant exceeded the radiolodine limit.

6.9.1.5 STEAM GENERATOR TUBE INSPECTION REPORT A report shall be submitted within 180 days after the initial entry into HOT SHUTDOWN following completion of an inspection performed in accordance with the Specification 6.5.9, Steam Generator (SG) Program. The report shall include:

a. The scope of inspections performed on each SG,
b. Active degradation mechanisms found,
c. Nondestructive examination techniques utilized for each degradation mechanism,
d. Location, orientation (if linear), and measured sizes (if available) of service induced indications,
e. Number of tubes plugged during the inspection outage for each active degradation mechanism,
f. Total number and percentage of tubes plugged to date,
g. The results of condition monitoring, including the results of tube pulls, in-situ testing, and assessment of accident-induced leakage from all tubesheet indications, and
h. The effective plugging percentage for all plugging in each SG.

WATERFORD - UNIT 3 6-17a AMENDMENT NO. 207