On April 21, 2006, during a drawing review, Engineering discovered that the diesel generator ( DG) control circuitry caused a diesel generator connected (aligned) to the offsite power grid to be inoperable. A records review determined that on one occasion, March 23, 2004, DG #1 had been inoperable for maintenance. During this same time period, a surveillance test was performed that resulted in DG #2 being aligned to the grid and thus being inoperable. Both DG's inoperable constitutes a loss of safety function and is reportable under 10 CFR 50.73(a)(2)(v)(B) as an inability to remove residual heat.
This was caused by a procedure change in late 1998 that, based on inaccurate information, allowed a DG to be considered operable while aligned to the grid. In subsequent years the procedure change process has been revised to require more detailed and extensive reviews of procedure changes.
Immediate actions were to identify procedures that include aligning a DG to the offsite power grid during surveillance testing. These procedures have either been revised to require declaring the DG inoperable or already contained a requirement to declare the DG inoperable when aligned to the grid.
Further corrective actions include additional changes to the procedure revision process, reviewing a sample of other procedure changes that used that same process for accuracy, and modifying the DG control circuitry to no longer require declaring a DG inoperable when aligned to the grid. |
LER-2006-003, Both Diesel Generators Inoperable Due to Voltage Regulator Design Results in Loss of Safety FunctionDocket Number |
Event date: |
|
---|
Report date: |
|
---|
Reporting criterion: |
10 CFR 50.73(a)(2)(v)(B), Loss of Safety Function - Remove Residual Heat |
---|
Initial Reporting |
---|
2982006003R00 - NRC Website |
|
PLANT STATUS
At the time of the event, Cooper Nuclear Station (CNS) was in Mode 1 at approximately 100% power.
BACKGROUND
During surveillance testing, when the diesel generator (DG) is aligned parallel to the grid, the DG voltage regulator droop setting is not bypassed upon receipt of an emergency signal from, for example, a loss of voltage or a loss of coolant accident (LOCA). Because the voltage regulator remains in droop mode, and because existing analysis of the condition described above does not bound the condition, the DG is inoperable by definition.
Due to voltage regulator droop mode operation, prior to 1998, the DG's were declared inoperable whenever they were aligned parallel to the offsite power grid (grid) during surveillance tests. To reduce the accumulation of out-of-service time related to the inoperability requirement, a modification to enhance the DG circuitry was undertaken in early 1998. Because the initial work scope was insufficient to accomplish the original goal, a second work scope was proposed and approved. The modification was completed according to the second work scope but the need to declare the DG inoperable when aligned to the grid remained.
The key difference between the various DG operating mode responses is the logic of the unit, which for a LOCA (regardless if a concurrent loss of offsite power exists or not), causes most of the logic to appropriately change to an Emergency Start mode. Specifically, the following actions occur upon receipt of an Emergency Start Signal:
- The Non-Essential DG trips are bypassed.
- The Digital Reference Unit (speed input device) reverts to 60.0 Hz (removes the Engine Speed Droop function).
- The Engine Speed Governor reverts to a "high responsiveness" mode (the governor has the capability to operate in two modes. The two modes can be used to provide greater stability when operating in parallel to the grid (i.e., it is less responsive to step changes).
In contrast to these three logic changes, one other required change does not occur. This latter change relates to the voltage droop function. This function is enabled anytime the DROOP/PARALLEL switch is placed in the PARALLEL position, which is required for operating in parallel with the grid. The voltage droop function allows for stability while operating in parallel with the grid. This function is not disabled in response to an Emergency Start Signal.
While some circuitry changes were accomplished in 1998, the original need to declare the DG's inoperable remained. Consequently, all procedure changes resulting from the completion of control circuitry enhancement modification still contained this requirement. Six weeks after the modification was closed out and new procedures had been implemented, new procedure change requests (PCR's) were submitted that removed the inoperability requirement in DG surveillance tests. Because the new PCR's were processed as instant changes, there was no review by anyone directly involved in the modification.
Under the procedure change process in use at that time an instant change was required to be a "non intent" change, meaning that the procedure change would not change the intent of the procedure. This included what the procedure could be used to accomplish, the level of nuclear safety, or the design or licensing basis.
The justification for the new PCR's incorrectly presumed that the modification had been completed as described in the original work scope. Consequently, from December 12, 1998 to April 21, 2006, diesel generators were not declared inoperable as they should have been during surveillance testing when they were aligned parallel to the grid.
Since the DG does not automatically disable the voltage droop function, which is not accounted for in the applicable analyses, the DG must be declared inoperable whenever this function is utilized. This function is only utilized in support of DG parallel operation with the grid.
EVENT DESCRIPTION
Records review identified one occasion during the past three years, March 23, 2004, when both DG's were inoperable at the same time. DG #1 was inoperable due to maintenance being done at the same time that a surveillance procedure was being performed on DG #2. Because DG #2 was aligned parallel to the grid, it was inoperable.
During surveillance testing, when the DG is aligned parallel to the grid, the DG voltage regulator droop setting is not bypassed as it should be upon receipt of an emergency signal from, for example, a loss of voltage or a LOCA. Because the voltage regulator remains in droop mode, and existing analysis does not bound the condition, the DG is inoperable.
BASIS FOR REPORT
Both DG's simultaneously inoperable is a condition that could prevent fulfillment of a safety function that mitigates the consequences of an accident and is reportable under 10 CFR 50.73 (a)(2)(v).
SAFETY SIGNIFICANCE
This condition is not risk significant, because both offsite power sources remained available to support safety functions for the duration of this condition. In addition, the combination of equipment out of service at the time of the parallel operation did not create a configuration with unacceptable consequences.
This condition is limited in time frame in that the surveillance test duration for the configuration is approximately 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> in length. It is judged that the short time frame in which the condition existed has negligible impact on core damage frequency. The incremental core damage probability for the short time period in which the diesel generator function was found to be degraded is well below the 1.0E-06 threshold established as significant by the industry.
This condition did not challenge a fuel, reactor coolant pressure, primary containment, or secondary containment boundary. The condition did not impact the plant's ability to safely shut down or maintain the reactor in a safe shutdown condition.
Therefore, the impact of this configuration is considered negligible. As a result, the event is bounded by the baseline Plant Specific Analysis model and has negligible risk significance.
This is a Safety System Functional Failure.
CAUSE
The cause of this event was the use of inaccurate information to justify a procedure change. Inappropriate application of the procedure change process resulted in inadequate reviews such that the inaccurate information in the justification section of the procedure change request was not challenged and compared to the base documents. Reviewing work completion records would have identified the use of original scope information instead of work completion records to justify the procedure change.
CORRECTIVE ACTION
The following corrective action has been completed.
1. CNS procedures related to DG that include aligning the DG to the grid during surveillance testing were identified. These procedures have either been revised to require declaring the DG inoperable when aligned in parallel with the grid, or already contained the requirement to declare the DG inoperable.
The following corrective actions have been entered into the CNS corrective action program.
1. The procedure change process will be revised to provide a list of conditions that meet the requirements of "non-intent.
2. A sample of non-administrative instant procedure changes implemented using the instant change process that was in use between 1998 and 2000 will be reviewed to ensure that the information upon which the change was based is accurate and the instant change met the requirements to qualify as an instant change.
3. Determine the availability of the DG's between December 12, 1998 and April 21, 2006. Determine the impact on performance indicators reported to the Nuclear Regulatory Commission during the same period.
4. The DG control circuitry will be modified so that it is not necessary to declare a DG inoperable when it is aligned parallel to the grid during DG surveillance testing.
PREVIOUS EVENTS
A review of CNS LERs since 2000 was conducted. There were no reportable events similar to this event.
|
---|
|
|
| | Reporting criterion |
---|
05000305/LER-2006-010 | | | 05000456/LER-2006-001 | Unit 1 Reactor Coolant System Pressure Boundary Leakage Due To Inter-Granular Stress Corrosion Cracking of a Pressurizer Heater Sleeve | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(ii)(A), Seriously Degraded | 05000454/LER-2006-001 | Technical Specification Required Action Completion Time Exceeded for Inoperable Containment Isolation Valves Due to Untimely Operability Determination | | 05000423/LER-2006-001 | Loss Of Safety Function Of The Control Room Emergency Ventilation System | 10 CFR 50.73(a)(2)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident | 05000369/LER-2006-001 | Ice Condenser and Floor Cooling System Containment Isolation Valve inoperable longer than allowed by Technical Specification 3.6.3. | | 05000353/LER-2006-001 | HPCI Ramp Generator Signal Converter Failure | 10 CFR 50.73(a)(2)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident 10 CFR 50.73(a)(2)(v), Loss of Safety Function | 05000352/LER-2006-001 | Loss Of One Offsite Circuit Due To Invalid Actuation Of Fire Suppression System | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000336/LER-2006-001 | | 10 CFR 50.73(a)(2)(v)(A), Loss of Safety Function - Shutdown the Reactor | 05000316/LER-2006-001 | Failure to Comply with Technical Specification 3.6.2, Containment Air Locks | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000315/LER-2006-001 | Plant Shutdown Required by Technical Specification Action 3.6.5.B.1 | | 05000293/LER-2006-001 | | 10 CFR 50.73(a)(2)(iv), System Actuation | 05000289/LER-2006-001 | | | 05000287/LER-2006-001 | Actuation of Emergency Generator due to Spurious Transformer Lockout | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000251/LER-2006-001 | Turkey Point Unit 4 05000251 1 OF 6 | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000247/LER-2006-001 | Manual Reactor Trip Due to Multiple Dropped Control Rods Caused by Loss of Control Rod Power Due to Personnel Error | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000440/LER-2006-001 | Incorrect Wiring in the Remote Shutdown Panel Results in a Fire Protection Program Violation | | 05000413/LER-2006-001 | | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000368/LER-2006-001 | Completion of a Plant Shutdown Required by Technical Specifications Due to Loss of Motive Power to Certain Containment Isolation Valves as a Result of a Phase to Ground Short Circuit in a Motor Control Cubicle | 10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown | 05000306/LER-2006-001 | | 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown | 05000298/LER-2006-001 | Cooper Nuclear Station 05000298 1 of 4 | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000286/LER-2006-001 | I | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000282/LER-2006-001 | | 10 CFR 50.73(a)(2)(iv)(A), System Actuation 10 CFR 50.73(a)(2)(v), Loss of Safety Function | 05000266/LER-2006-001 | | 10 CFR 50.73(a)(2)(v), Loss of Safety Function | 05000261/LER-2006-001 | Manual Reactor Trip Due to Failure of a Turbine Governor Valve Electro-Hydraulic Control Card | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000255/LER-2006-001 | | 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition | 05000461/LER-2006-002 | Turbine Bypass Function Lost Due to Circuit Card Maintenance Frequency | | 05000458/LER-2006-002 | Loss of Safety Function of High Pressure Core Spray Due to Manual Deactivation | | 05000456/LER-2006-002 | Units 1 and 2 Entry into Limiting Condition for Operation 3.0.3 due to Main Control Room Ventilation Envelope Low Pressure | | 05000443/LER-2006-002 | Noncompliance with the Requirements of Technical Specification 6.8.1.2.a | | 05000387/LER-2006-002 | DMissed Technical Specification surveillance requirement | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000362/LER-2006-002 | Unit 3 Shutdown to Inspect Safety Injection Tank Spiral Wound Gaskets | | 05000336/LER-2006-002 | Manual Reactor Trip Due To Trip Of Both Feed Pumps Following A Loss Of Instrument Air | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000316/LER-2006-002 | | 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000315/LER-2006-002 | Failure to Comply with Technical Specification Requirement 3.6.13, Divider Barrier Integrity | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000293/LER-2006-002 | | | 05000289/LER-2006-002 | | | 05000251/LER-2006-002 | Intermediate Range High Flux Trip Setpoint Exceeded Technical Specification Allowable Value | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000440/LER-2006-002 | Scaffold Built in the Containment Pool Swell Region | 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition | 05000413/LER-2006-002 | Safe Shutdown Potentially Challenged by an External Flooding Event and Inadequate Design and Configuration Control | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000388/LER-2006-002 | Missed Technical Specification LCO 3.8.1 Entry for Unit 2 During Unit 1 ESS Bus Testing | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000348/LER-2006-002 | Main Steam Isolation Valve Failure to Close | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000305/LER-2006-002 | | 10 CFR 50.73(a)(2)(v)(C), Loss of Safety Function - Release of Radioactive Material 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000301/LER-2006-002 | | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000286/LER-2006-002 | 450 Broadway, GSB P.O. Box 249 Buchanan, N.Y. 10511-0249Entergy Tel (914) 734-6700 Fred Dacimo Site Vice President Administration September 13, 2006 Indian Point Unit No. 3 Docket No. 50-286 N L-06-084 Document Control Desk U.S. Nuclear Regulatory Commission Mail Stop O-P1-17 Washington, DC 20555-0001 Subject:L Licensee Event Report # 2006-002-00, "Manual Reactor Trip as a Result of Arcing Under the Main Generator Between Scaffolding and Phase A&B of the Isophase Bus Housing" Dear Sir: The attached Licensee Event Report (LER) 2006-002-00 is the follow-up written report submitted in accordance with 10 CFR 50.73. This event is of the type defined in 10 CFR 50.73(a)(2)(iv)(A) for an event recorded in the Entergy corrective action process as Condition Report CR-IP3-2006-02255. There are no commitments contained in this letter. Should you or your staff have any questions regarding this matter, please contact Mr. Patric W. Conroy, Manager, Licensing, Indian Point Energy Center at (914) 734-6668. Fred R. Dacimo Site Vice President Indian Point Energy Center Docket No. 50-286 NL-06-084 Page 2 of 2 Attachment: LER-2006-002-00 CC: Mr. Samuel J. Collins Regional Administrator — Region I U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Resident Inspector's Office Resident Inspector Indian Point Unit 3 Mr. Paul Eddy State of New York Public Service Commission INPO Record Center NRC FORM 366 U.S. NUCLEAR REGULATORY COMMISSION APPROVED BY OMB NO. 3150-0104 EXPIRES: 06/30/2007
(6-2004)
. Estimated burden per response to comply with this mandatory collection request: 50 hours.DReported lessons learned are incorporated into the licensing process and fed back to industry. Send comments regarding burden estimate to the Records and FOIA/Privacy Service Branch (T-5 F52), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by internetLICENSEE EVENT REPORT (LER) e-mail to infocollects@nrc.gov, and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0104), Office of Management and Budget, Washington, DC 20503. If a means used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection. ■ 1. FACILITY NAME 2. DOCKET NUMBER I 3. PAGE
INDIAN POINT 3 05000-286 1 OF 6
4.TITLE: Manual Reactor Trip as a Result of Arcing Under the Main Generator Between
Scaffolding and Phase A&B of the Iso-phase Bus Housing | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000282/LER-2006-002 | | 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000269/LER-2006-002 | High Energy Line Breaks Outside Licensing Basis May Result in Loss of Safety Function | | 05000263/LER-2006-002 | | | 05000255/LER-2006-002 | | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000254/LER-2006-002 | Quad Cities Nuclear Power Station Unit 1 05000254 1 of 3 | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000483/LER-2006-003 | Unexpected Inoperability of the Emergency Exhaust System due to Inoperable Pressure Boundary | 10 CFR 50.73(a)(2)(v)(C), Loss of Safety Function - Release of Radioactive Material 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications |
|