ML051300259
| ML051300259 | |
| Person / Time | |
|---|---|
| Site: | Peach Bottom |
| Issue date: | 04/27/2005 |
| From: | Exelon Generation Co, Exelon Nuclear |
| To: | NRC/FSME |
| Diec D, NRR/DRIP/RPRP, 415-2834 | |
| Shared Package | |
| ML051300222 | List: |
| References | |
| Download: ML051300259 (29) | |
Text
Proposed Manual Action Rule Impact on Peach Bottom Preliminary Comments Presentation to NRC Staff April 27, 2005
Purpose
- The purpose of this presentation is to provide insights on the impact of the proposed Appendix R Manual Action Rulemaking on a specific plant.
- This plant is an older BWR-4/Mark-1 that uses a post-fire shutdown methodology similar to most BWR plants, but is bounding for decay heat and containment response.
Agenda
- Provide overview of existing PBAPS manual actions
- Provide details on the impact the proposed rule would have on PBAPS
Overview - Licensing Always Been Included in the PBAPS FSSD Analysis
- July 1983 Meeting and September 1983 Submittal
- Associated circuits that have a separation from the fire area less than that required by Section III.G.2 of Appendix R and have a connection to circuits of equipment whose spurious operation could adversely affect the shutdown capability have been adequately resolved by appropriate action pre-or post-fire.
- This analysis assumes that any manual capability credited as part of the safe shutdown system for the purposes of this review, will be based on verification that, at a minimum, sufficient numbers of operating shift personnel will be available to fight the fire and perform the necessary operator actions.
- The only requirements is that sufficient time must be available to restore the affected safe shutdown system function prior to the occurrence of an unrecoverable plant condition. For this analysis, a time-line/manpower concept is utilized to establish that sufficient time is available for restoration of the safe shutdown system function. The resulting time-line diagram shows the number of personnel involved in performing each safe shutdown function and the time required to perform those functions. The time-line diagram demonstrates that sufficient time and personnel are available to perform the safe shutdown functions.
Overview - Licensing
- Fire Protection Program Document (UFSAR) - 1986
- Per GL 86-10 guidance, gathers all related FP information into a single volume of the UFSAR. Describes FSSD methods including manual actions. Provides listing of manual actions
- 1989 Submittal on MHIF and manual actions
- Response to URI on MHIF and Manual Actions
- Safety Evaluation Report 1993
- Approves FPP
- August 1995 Submittal (G.L. 92-08 Response)
- FSSD re-analysis relies on operator manual actions
- T-Lag Meeting 1997
- Explained manual actions are used
- T-Lag Order
- Required completion of actions docketed in 1997 T-Lag meeting.
=
Background===
- Previously Approved
- Industry Definition of Current Licensing Basis based on NRC Definition (LIC-100, 10CFR54.3, GL 91-18)
- Docketed Correspondence
- Information contained in letters that are referenced in SERs
- Orders, License Conditions, Bulletin & Generic Letter responses.
- Appendix R implementation encompassed all of these
- Resolution of enforcement actions (URIs, Violations, LERs)
- Typically documented via inspection reports.
- Not limited to information explicitly stated in a Safety Evaluation Report
Overview - Risk
- Risk Impact of Manual Actions
- Required to be addressed in IPEEE (GL 88-20 Supplement 4, NUREG-1407)
- Addressed in Peach Bottom IPEEE Submittal
- Evaluated by NRC (NUREG/CR-4550, NUREG-1742, section 3.4.8.1)
- Re-evaluated in current PBAPS Fire PRA
- 1 dominant scenario per unit
- Remaining MA scenarios < 2.8E-7
Feasibility
- Timelines and staffing requirements
- Part of original FSSD design basis calculations
- Certain actions field tested during PBAPS extended shutdown
- 2002 Manual Action Feasibility Study
- Comprehensive Review of FSSD Manual Actions
- NRC inspection team reviewed during 2003 Fire Protection Triennial
- Found manual actions feasible with no safety concerns
Types of Actions
- Trip/Open Breakers
- Close Breakers
- Operate Handswitches
- Restore power to battery chargers
- Establish Lighting for Alt. SSD Panel
- Operate Valves
- Manually operate
- Operate at MCC
- Pull Control Power Fuses
- Insert Plug into Receptacle Skill of the craft
Feasibility
- PBAPS Manual Actions
- Most manual actions are similar to tasks operators perform on a frequent basis.
- Pre-engineered to be as simple as possible
- Most tasks can be accomplished without entering the affected fire area.
- Operators know plant layout and can often take alternate routes to reach the same location.
- Many post-fire safe shutdown tasks are similar to tasks performed for both normal and shutdowns addressed by other EOPs and AOPs.
Specific Concerns
- Time Margin for Manual Actions
- Current Design basis actions are based on assumed all-encompassing fire at T=0
- Creates perception issue
- Sequencing & timing taken on inflated importance
- For realistic fire scenarios
- Most manual actions are not required
- Sequence & timing less important
- Operators will have advance warning of fire conditions since T never really equals 0
Specific Concerns
- Dose
- NUREG-0737 - GDC-19 dose limits are applicable to emergency actions, not 10CFR20.
- 10CFR20 sets occupational limits, annual accounting & bookkeeping.
- Accounting and bookkeeping cant be managed in emergency situation, creates a distraction
- Not reasonable to maintain dose balance in reserve for post-fire actions, nor is it currently required for other non-fire post-accident conditions.
Typical Generic Actions
- Appendix R assumptions (ex., GL 86-10 guidance) non-mechanistically force us to assume many initiators.
- These same initiators already have generic manual actions as part of their response, regardless of the cause.
- Due to the design of Rx protection systems, no amount of fire barriers/encapsulation can completely prevent these initiators from occurring in a fire.
Typical Generic Actions
- Chapter 15 Accidents & Transients typically allow manual actions, 10 minutes after event initiation.
- Only exception is that actions to protect Tech Spec Safety Limits for Chapter 15 Accidents & Transients must be automatic (GL 91-18)
- Common (BWR/PWR)
- LOOP - Verify DG operation, including local observation and adjustment
- LOOP or 4kv transfer - Verify transfer, re-set power supplies & chargers, verify system alignments
- LO Inst Air - Reposition critical valves by hand or manually align backup supply to critical valves
- Any Event - Manage unit dependencies to support the accident unit (plant specific)
Typical Generic Actions
- SORV - Remove fuses
- LOFW - Maximize CRD flow (manual valve)
- Cont Isolation - Re-open instrument valves. Restore instrument nitrogen to valves in containment.
- LO RCP Seal Cooling - manually restore cooling and/or trip RCPs
- LOFW - manually initiate turbine-driven EFW
- ES Actuation - Reset actuation, return systems to standby
- Depressurization/Cooldown - Periodically Block ESAS
Impact of Proposed Rule
- Detection and Automatic Suppression In Fire Area Requiring the Manual Action
- Existing Detection and Suppression provided to meet specific hazards (BTP 9.5-1) and regulatory requirements (App. R).
- Existing exemptions in some areas for lack of detection (III.F) or lack of suppression (III.G.2.b, III.G.2.c) based on hazards analysis.
- Will these exemptions still be valid? Revision reqd?
Impact of Proposed Rule
- Most fire areas are large with multiple zones and rooms.
- Suppression often limited to an zone/room with a specific hazard and is not area wide.
- Further subdivision of fire areas into smaller areas would require additional FSSD analysis and upgrade of barriers.
Impact of Proposed Rule
- Primary impact was lack of full area automatic suppression systems.
- Exemption Requests to address these areas could be submitted.
- 13 out of 47 fire areas affected
- 168 rooms/zones affected within these 13 fire areas.
Impact of Proposed Rule
- Exemption Justification
- Low combustible loading in most zones
- Typical combustibles in the areas are not prone to fast spreading fires.
- Spatial and physical separation between rooms/zones within fire area
- Typically, damage to a specific part of the fire area results in the need for manual actions.
- Existing barriers while not credited for App. R will slow fire growth and limit exposure.
Impact of Proposed Rule
- Unintended Consequences
- New suppression systems will create hazards to some equipment.
- Flooding design basis impacted
- Gridlock future changes to FP program
- Significantly limit what changes could be made under Standard FP Licensing Condition w/o prior NRC approval (contrary to Commission policies on burden reduction for requirements marginal to safety, GL 86-10, GL 88-12).
Impact of Proposed Rule
- $67 Million - Cost Estimate for sprinklers
- Excludes Turbine deck, Refuel floor, Feedwater heater rooms, Stair towers
- Additional factors to consider (not in $ est.)
- Dose - Significant dose during installation and future testing.
- Drainage - Many areas do not have floor drains (or the drains covered for Rad/Environmental reasons).
- Plant Equipment - Impact of sprinkler flow and pipe breaks would have to be addressed.
- Impact on capacity of existing fire protection water supply system.
Impact of Proposed Rule
- Fire Area Example
- Turbine Building (Fire Area 50)
- Large fire area encompassing both U2 & U3 areas.
- 143,000 ft2 already provided with automatic sprinkler protection.
- Lube oil rooms, moisture separators, condenser pits, common areas, 13kV Switchgear areas, feed pump rooms, railroad bay and hatch area.
Impact of Proposed Rule
- Turbine Building (Fire Area 50)
- 87,000 ft2 not proposed to have automatic suppression (exemption required)
- Pipe tunnels, ventilation equipment area, feedwater heater rooms, turbine deck (turbine bearings and underskirt area have sprinklers)
- Cost for sprinklers if required would exceed $26 million
- 57,000 ft2 could need sprinkler protection under proposed rule (exemption would be submitted)
- Areas do not present FSSD hazards
- Areas not required to have suppression under prior NRC rules or guidelines.
- Cost for sprinkler installation would exceed $17 million
Impact of Proposed Rule
- RadWaste Building (Fire Area 2)
- Large multistory building between two reactor buildings, common fire area
- Suppression systems in HPCI pump rooms and in old baling and drumming room
- 45,000 ft2 would need sprinkler protection under the proposed rule
- Projected cost would exceed $13 million
- Secondary Containment breaches involved
Impact of Proposed Rule
- Radwaste Building (Fire Area 2)
- Exemption Request would be submitted
- Low combustible loading throughout building (except where suppression is provided)
- Building is well compartmentalized primarily for radiation considerations
- Many high dose rooms
Impact of Proposed Rule
- Training
- Increase in training requirements in FSSD procedures will impact the training organization.
- Training cycle already full.
- FSSD procedures are covered on two year cycle but not in detail required by the proposed rule.
- Training is already performed, however proposed rule will result in 94 unique training events per operator.
- Result will be less training time to spend on other more risk significant events.
- Train on the same action, for multiple fire areas?
Impact of Proposed Rule
- Procedures
- Written using a template
- Supplement the EOPs
- Format provides consistent and easy to understand guidance for the operator.
- Human factors reviews.
- Operator feedback
- 1 procedure per fire area per unit
- Each action is in a separate tear-out
Summary
- Improvement in Safety Does Not Support Proposed Rule Given the Cost of Compliance
- Cost of additional automatic suppression systems could exceed $70 million at PBAPS
- Training burden may impact plant safety since less time will be available for other even more risk relevant training.
- Ignores 25 years of precedent on manual actions at PBAPS
- Significant burden developing exemptions
- PBAPS Triennial inspection found all actions feasible
Conclusion
- The results from NRC fire protection inspections to date indicate that there is insufficient evidence that the generic use of these manual actions poses a safety concern. - Reg Analysis 12/2004