ML050380440

From kanterella
Jump to navigation Jump to search
Undated Draft, Revision 3, NRC Fire Protection Inspection Report No. 05000400/2003007
ML050380440
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 02/03/2005
From: Ogle C
NRC/RGN-II/DRP/RPB1
To: Scarola J
Carolina Power & Light Co
References
EA-00-022, EA-01-310, FOIA/PA-2004-0277 IR-03-007
Download: ML050380440 (13)


See also: IR 05000400/2003007

Text

i

EA-00-022

EA-01 -310

Carolina Power & Light Company

ATTN: Mr. James Scarola

Vice President - Harris Plant

Shearon Harris Nuclear Power Plant

P. 0. Box 165, Mail Code: Zone 1

New Hill, North Carolina 27562-0165

SUBJECT:

SHEARON HARRIS NUCLEAR POWER PLANT - NRC FIRE PROTECTION

INSPECTION REPORT NO. 05000400/2003007

Dear Mr. Scarola:

On October _,

2003, the U.S. Nuclear Regulatory Commission (NRC) completed an in-office

review of the significance of the triennial fire protection inspection findings of inspection report

05000400/2002011 related to your Shearon Harris Nuclear Power Plant. The enclosed report

documents the results of our significance determination, which was discussed on October

2003, by telephone with Mr. _

_

and other members of your staff.

This report documents two NRC-identified findings of very low significance (Green). Both of

these findings were determined to involve violations of NRC requirements. However, because

of the very low safety significance and because they are entered into your corrective action

program, the NRC is treating these two findings as non-cited violations (NCVs) consistent with

Section VI.A. of the NRC enforcement Policy. If you contest any NCV in this report, you should

provide a response within 30 days of the date of this inspection report, with the basis for your

denial, to the Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington,

DC 20555-0001; with copies to the Regional Administrator, Region II; the Director, Office of

Enforcement, United States Nuclear Regulatory Commission, Washington, DC 20555-0001;

and the NRC Resident Inspector at the Shearon Harris Nuclear Power Plant.

In accordance with 10 CFR 2.790 of the NRC's uRules of Practice," a copy of this letter, its

enclosure, and your response (if any) will be available electronically for public inspection in the

NRC Public Document Room or from the Publicly Available Records (PARS) component of

NRC's document system (ADAMS). ADAMS is accessible from the NRC Website at

http://www.nrc.aov/readina-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

Charles R. Ogle, Chief ~

Engineering Branch 1

Division of Reactor Safety

Docket No.: 50-400

CP&L

2

License No.: NPF-63

Enclosure: Inspection Report 05000400/200307

w/Attachment: Supplemental Information

cc w/encl: (use normal distribution list plus EICS and OE)

Distribution w/encl:

L. Slack, EICS

B. Mozafari, NRR

OEMAIL

RIDSNRRDIPMLIPB

PUBLIC

OFFICE

RII:DRS

RII:DRS

RiI:DRS

RII:DRP

RII:EICS

SIGNATURE

NAME

ISchin

WRogers

DCPayne

PFrednckson

CEvans

DATE

E-MAIL COPY?

Y

NO

YES

NO

YES

NO

YES

NO

YES

NO

YES

NO

I PUBLIC DOCUMENT

YES

NO

_I_

I_

_I_

I_..-_

_I____..__ _____

I

OFFICIAL RECORD COPY

DOCUMENT NAME: P:\\HiarIs IR 03-07R3.wpd

U.S. NUCLEAR REGULATORY COMMISSION

REGION II

Docket No.:

License No.:

Report No.:

Licensee:

Facility:

Location:

Dates:

Inspectors:

Approved by:

50-400

NPF-63

05000400/2003007

Carolina Power & Light (CP&L)

Shearon Harris Nuclear Power Plant

5413 Shearon Harris Road

New Hill, NC 27562

February 1, 2003 - October _, 2003

W. Rogers, Senior Reactor Analyst, Region II

R. Schin, Senior Reactor Inspector, Region II

Charles R. Ogle, Chief

Engineering Branch 1

Division of Reactor Safety

Enclosure

SUMMARY OF FINDINGS

IR 05000400/2003-007; 02/01/2003 - 10/U2003; Shearon Harris Nuclear Power Plant;

Significance Determination of Fire Protection Findings.

The in-office review was conducted by a regional inspector, a regional senior reactor analyst,

and NRC Headquarters risk analysts. Two Green findings, each a non-cited violation (NCV),

were identified. The significance of issues is indicated by their color (Green, White, Yellow,

Red) using IMC 0609 "Significance Determination Process" (SDP). Findings for which the SDP

does not apply may be "Green" or be assigned a severity level after NRC management review.

The NRC's program for overseeing the safe operation of commercial nuclear power reactors is

described in NUREG-1 649, "Reactor Oversight Process," Revision 3, dated July 2000.

A.

Inspector Identified Findings

Cornerstones: Mitigating Systems and Initiating Events

Green. The inspectors identified a non-cited violation of Operating License Condition

2.F, the Fire Protection Program, and Technical Specification (TS) 6.8.1, Procedures

and Programs, was identified for inadequate implementation of the fire protection

program. Physical and procedural protection for equipment that was relied on for safe

shutdown (SSD) during a fire in fire safe shutdown analysis (SSA) areas 1-A-BAL-B-B1,

1 -A-BAL-B-B2, 1 -A-BAL-B-B3, 1 -A-BAL-B-B4, 1-A-EPA, and 1 -A-BAL-C of the reactor

auxiliary building was inadequate. Consequently, a fire in one of these SSA areas

could result in a reactor coolant pump seal loss of coolant accident (LOCA) event, a

main steam line break (MSLB) event, a loss of high pressure safety injection, and/or a

loss of component cooling water to the reactor coolant pump seals. The licensee has

initiated corrective actions including assigning an additional operator to be available to

perform post-fire safe shutdown actions and performing a complete review of the safe

shutdown analysis and related operating procedures.

This finding was greater than minor because it involved a lack of required fire barriers

for equipment that was relied upon for safe hot shutdown following a fire. The finding

also had more than minor safety significance because it affected the objectives of the

Mitigating Systems and Initiating Events Cornerstones of Reactor Safety. The finding

affected the availability and reliability of systems that mitigate initiating events to prevent

undesirable consequences. It also affected the likelihood of occurrence of initiating

events that challenge critical safety functions. The finding was of very low significance

(Green) because of the low fire ignition frequencies, lack of combustible materials in

critical locations, and the effectiveness of the fire protection features and the unaffected

SSD equipment to mitigate a fire in each of the affected fire zones/areas. (Section

1 R05.03.b.1)

Green. The inspectors identified a non-cited violation of Operating License Condition

2.F, the Fire Protection Program, and Technical Specification (TS) 6.8.1, Procedures

and Programs, was identified for inadequate corrective action for previous Violation 50-

400/02-08-01. Physical and procedural protection for equipment that was relied on for

safe shutdown (SSD) during a fire in the new auxiliary control panel fire area 1-A-ACP

Enclosure

2

was inadequate. Consequently, a fire in area 1 -A-ACP could result in a loss of auxiliary

feedwater and a main steam line break (MSLB) event. The licensee has initiated

corrective actions including assigning an additional operator to be available to perform

post-fire safe shutdown actions and performing a complete review of the safe shutdown

analysis and related operating procedures.

This finding was greater than minor because it involved inadequate fire barriers for

equipment that was relied upon for safe hot shutdown following a fire. The finding also

had more than minor safety significance because it affected the objectives of the

Mitigating Systems Cornerstone of Reactor Safety. The finding affected the availability

and reliability of systems that mitigate initiating events to prevent undesirable

consequences. The finding was of very low significance (Green) because of the very

low ignition sources in the fire area, manual suppression capability, and the power

conversion system not being affected by a fire in this fire area. (Section 1 R05.03.b.2)

B.

Licensee-Identified Violations

None

Enclosure

REPORT DETAILS

1.

REACTOR SAFETY

Cornerstones: Initiating Events and Mitigating Systems

1R05 FIRE PROTECTION

.01

Significance Determination for Triennial Fire Protection Inspection Findings

a.

Inspection Scope

In inspection report (IR) 50-400/02-11, nine findings had been identified as unresolved

items (URls) pending completion of the NRC significance determination process (SDP).

The nine URIs were as follows:

URI 50-400102-11 -01, Failure to Protect Charging System MOV 1 CS-1 65, VCT

Outlet to CSIPs, From Maloperation Due To a Fire

URI 50-400/02-11-02, Failure to Protect Charging System MOVs 1 CS-1 69, 1 CS-

214, 1 CS-21 8, and 1 CS-21 9 From Maloperation Due To a Fire

URI 50-400/02-11-03, Failure to Protect Charging System MOVs 1 CS-1 66, 1 CS-

168, and 1 CS-217 From Maloperation Due To a Fire

URI 50-400/02-11-04, Failure to Protect Component Cooling MOVs 1 CC-251

and 1 CC-208, CC for RCP Seals, From Maloperation Due To a Fire

URI 50-400/02-11-05, Reliance on Manual Actions in Place of Required Physical

Separation or Protection From a Fire

URI 50-400/02-11-06, Fire SSD Operator Actions With Excessive Challenges

URI 50-400/02-11-07, Too Many Fire SSD Actions for Operators to Perform

URI 50-400/02-11-08, Using the Boric Acid Tank Without Level Indication

URI 50-400/02-11-09, Failure to Provide Required Emergency Lighting for SSD

Operator Actions

This inspection report documents the results of the in-office completion of the NRC SDP

with respect to those nine URIs. The significance determination was accomplished as

described in NRC Inspection Manual Chapter (IMC) 0609, Signification Determination

Process; IMC 0609A, Significanhe Deterrnination of Reactor Inspection Findings' for At---

Power Situations; and IMC 0609F, Determining Potential Risk Significance of Fire

Protection and Post-Fire Safe Shutdown Inspection Findings. This involved evaluating

the significance of a potential fire in each of the seven affected fire safe shutdown

Enclosure

2

analysis (SSA) areas using the Phase 2 SDP, considering all examples of the findings

that could be involved in each fire. To better assess the overall significance of all of the

performance deficiencies, they were recharacterized as two overall findings: 1)

Inadequate Implementation of the Fire Protection Program for Safe Shutdown; and 2)

Inadequate Corrective Action for a Previous White Fire Protection Finding.

In addition, the performance deficiencies which could result in the loss of a safety

function were evaluated by Office of Nuclear Reactor Regulation (NRR) analysts using

the Phase 3 portion of the SDP. Inclusive in this evaluation were extensive walkdowns

of the applicable fire SSA areas by two fire protection contractors to observe ignition

sources and possible fire propagation from these ignition sources that could affect the

unprotected cables of concern. Also, electrical circuit drawings and the latest

information on cable hot short failure mechanisms and probabilities were used to

develop cable failure probabilities that could cause a loss of function for the unprotected

cables of concern.

b.

Findings

(1)

Inadequate Implementation of the Fire Protection Program for Safe Shutdown

Introduction: An overall finding was identified in that the implementation of the fire

protection program was inadequate. Eight of the nine URls described in IR 50-400/02-

11 were considered to include performance deficiencies related to this overall finding.

Based on evaluating those performance deficiencies for their effects during fires that

could occur in each of six affected fire SSA areas, this overall finding was determined to

have a very low significance (Green).

Description: The licensee's implementation of the fire protection program for ensuring

the ability to safely shut down the plant during a fire was inadequate, in that:

The fire SSA failed to identify several cables that were relied upon for safe

shutdown (SSD) during a fire. Consequently, those cables were not provided

with the required protection from fire damage. A fire could cause hot shorts in

the cables which would result in maloperation of equipment that was relied upon

for SSD during that fire.

The SSA identified many cables that were relied upon for SSD during a fire, for

which the licensee generally failed to provide the required physical protection

from fire damage. Instead, the SSA designated that operator actions would be

taken to prevent or mitigate the effects of the fire damage. However, the

licensee did not obtain NRC approval for these deviations from the approved fire

protection program.

Some of the operator actions that were designated by the SSA were not

incorporated into operating procedures for SSD. Also, the operator actions in

procedures differed in many respects from the operator actions that were

Enclosure

3

analyzed in the SSA. For example, the operating procedures directed operators

to use some different flowpaths than those analyzed in the SSA.

Some operator actions in the SSD procedures would not work. They were too

challenging, involved entering the area of the fire, were not adequately analyzed,

or were too numerous for the available SSD non-licensed operator to perform.

Detailed examples related to this overall finding were included in the following eight

URls: 50-400/02-11-01, -02, -03, -04, -05, -07, -08, and -09.

Analysis: The inspectors and analysts evaluated the effects of the multiple examples of

this overall finding during a fire that could occur in each of the six affected fire SSA

areas of the reactor auxiliary building (RAB) using Phase 2 and Phase 3 of the SDP.

Based on that analysis, the inspectors and analysts concluded that this finding had more

than minor safety significance because it involved a lack of required fire barriers for

equipment that was relied upon for safe hot shutdown following a fire. The finding also

had more than minor safety significance because it affected the availability and reliability

objectives and the equipment performance attribute of the Mitigating Systems

Cornerstone of Reactor Safety. In addition, it affected the Initiating Events Cornerstone

of Reactor Safety in that it affected the objective of limiting the likelihood of occurrence

of initiating events that challenge critical safety functions and also affected the design

control attribute. The overall finding did not have more than very low safety significance

(Green) because of the low fire ignition frequencies that could impact the cables of

interest, the lack of combustible materials in critical locations, and the effectiveness of

the fire protection features and the unaffected SSD equipment to mitigate a fire in each

of the affected fire zones/areas.

Enforcement: As described in IR 50-400/02-11, Operating License Condition (OLC) 2.F

required that the licensee implement and maintain in effect all provisions of the

approved Fire Protection Program (FPP) as described in the Final Safety Analysis

Report (FSAR). The Updated FSAR (UFSAR), Section 9.5.1, FPP, stated that outside

containment, where cables or equipment (including associated non-essential circuits

that could prevent operation or cause maloperation due to hot.shorts, open circuits, or

shorts to ground) of redundant safe shutdown divisions of systems necessary to achieve

and maintain cold shutdown conditions are located within the same fire area outside of

primary containment, one of the redundant divisions must be ensured to be free of fire

damage. Section 9.5.1 further stated that if both divisions are located in the same fire

area, then one division is to be physically protected from fire damage by one of three

methods: 1) a three-hour fire barrier, 2) a one-hour fire barrier plus automatic detection

and suppression, or 3) a 20-foot separation with no intervening combustibles and with

automatic detection and suppression. The licensee had received no NRC approvals for

deviating from these requirements.

Also, OLC 2. F. and UFSAR Section 9.5.1 stated that Branch Technical Position (BTP)

9.5-1 was used in the design of the fire protection program for safety-related systems

and equipment and for other plant areas containing fire hazards that could adversely

Enclosure

4

affect safety-related systems. BTP 9.5-1, Section C.5.g, "Lighting and Communication,"

paragraph (1), required that fixed self-contained lighting consisting of fluorescent or

sealed-beam units with individual eight-hour-minimum battery power supplies should be

provided in areas that must be manned for safe shutdown and for access and egress

routes to and from all fire areas.

In addition, TS 6.8.1, Procedures and Programs, required procedures as recommended

by Regulatory Guide (RG) 1.33 and procedures for fire protection program

implementation. RG 1.33 recommended procedures for combating emergencies,

including fires. The licensee's interpretation of their fire protection program was that

they could and would rely on proceduralized operator actions in place of physically

protecting SSD equipment from fire damage (see Section 1 R05.04.b.1).

Contrary to the above requirements, the licensee failed to adequately implement and

maintain in effect all of the provisions of the approved FPP. The licensee failed to

ensure that one of the redundant safe shutdown divisions of systems necessary to

achieve and maintain cold shutdown conditions was protected from fire damage; failed

to have adequate procedures for combating fire emergencies; and failed to provide the

required emergency lighting in areas that must be manned for safe shutdown; as

described above in the eight examples of this overall finding. Because the identified

examples of this failure to adequately implement and maintain in effect all of the

provisions of the approved FPP are of very low safety significance and have been

entered into the corrective action program [Action Reports (ARs) 76260, 80212, 80089,

69721, 80215, 75065, and 79047], this violation is being treated as a non-cited violation

(NCV), consistent with Section VL.A of the NRC Enforcement Policy: NCV 50-400/03-

07-01; Inadequate Implementation of the Fire Protection Program for Safe Shutdown.

(2)

Inadequate Corrective Action for a Previous White Fire Protection Finding

Introduction: In IR 50-400/02-08, the NRC had left VIO 50-400/02-08-01 open for

further NRC review of the new manual operator actions that had been added as part of

the licensee's corrective action for the violation. In IR 50-400/02-11, the NRC had

documented the review of those new manual operator actions and had identified that the

licensee's corrective actions had contributed to four new findings. For this significance

determination, those findings were grouped into one overall finding of inadequate

corrective action for a previous White fire protection finding. Based on evaluating the

multiple examples of this overall finding for their effects during a fire that could occur in

the one affected fire area, this overall finding was determined to have a very low

significance (Green).

Description: The licensee's corrective actions for a previous White fire protection finding

(VIO 50-400/02-08-01), associated with a Thermo-Lag fire barrier assembly between the

'B' train switchgear room / auxiliary control panel and the 'A' train cable spreading room,-

were inadequate. The corrective actions were inadequate because they failed to rectify

deficiencies in design, construction, and operation related to SSD from a fire in the area

Enclosure

5

of the ACP room. The licensee's corrective actions contributed to four new findings that

are now grouped into the overall finding of inadequate corrective action:

The corrective actions created a new fire area and many new manual operator

actions for a fire in the new fire area instead of providing the required physical

protection of cables. This finding was described in URI 50-400/02-11-05,

Reliance on Manual Actions in Place of Required Physical Separation or

Protection From a Fire.

The corrective actions also created a manual operator action with excessive

challenges such that there was not reasonable assurance that all non-licensed

operators (NLOs) would be able to perform the action during a fire event. This

finding was described in URI 50-400/02-11-06, Fire SSD Operator Actions With

Excessive Challenges.

In addition, the corrective actions created too many local manual operator

actions for the new fire area for the one SSD NLO to perform. This finding was

described in URI 50-400/02-11-07, Too Many Fire SSD Actions for Operators to

Perform

Further, the corrective actions failed to provide the required emergency lighting

for the new manual actions. This finding was described in URI 50-400/02-11-09,

Failure to Provide Required Emergency Lighting for SSD Operator Actions

Analysis: The inspectors and analysts evaluated the effects of the multiple examples of

the overall finding of inadequate corrective action during a fire that could occur in the 1-

A-ACP fire area of the RAB, using Phase 2 of the SDP. Based on that evaluation, the

inspectors and analysts concluded that the overall finding had more than minor safety

significance because it involved inadequate fire barriers for equipment that was relied

upon for safe hot shutdown following a fire. The finding also had more than minor

safety significance because it affected the availability and reliability objectives and the

equipment performance attribute of the Mitigating Systems Cornerstone of Reactor

Safety. The finding affected the availability and reliability of systems that mitigate

initiating events to prevent undesirable consequences. The finding did not have more

than very low safety significance (Green) because of the very low ignition sources in the

fire area, manual suppression capability, and the power conversion system not being

affected by a fire in this fire area. The Green significance determination was also

confirmed by a walkdown of the fire area by two contractors.

Enforcement: OLC 2.F and the UFSAR, Section 9.5.1, FPP, included quality assurance

(QA) requirements for fire protection. The FPP stated that a QA program was being

used to identify and rectify any possible deficiencies in design, construction, and

operation of the fire protection systems. Also, as described in Section-i R05.01 .b.1 - -

above, OLC 2.F required that one of the redundant divisions would be free of fire

damage. Further, if both divisions were located in the same area, then one of the

divisions was to be physically protected from fire damage by one of three specified

Enclosure

6

methods. Further, OLC.2.F required that battery-backed emergency lights be provided

in locations where operators were required to perform actions for SSD from a fire. In

addition, TS 6.8.1, Procedures and Programs, required procedures for implementing the

fire protection program and for combating fires.

Contrary to the above requirements, the licensee's corrective actions for previous VIO

50-400/02-08-01 were inadequate because they failed to rectify deficiencies in design,

construction, and operation related to SSD from a fire in the area of the ACP room. The

licensee failed to protect various equipment either physically or procedurally from the

effects of a fire where that equipment was relied on for SSD. The licensee entered the

finding into the corrective action program as AR 80215. Because the identified

examples of this inadequate corrective action are of very low safety significance and

have been entered into the corrective action program, this violation is being treated as

an NCV, consistent with Section VLA of the NRC Enforcement Policy: NCV 50-400/03-

07-02; Inadequate Corrective Action for a Previous White Fire Protection Finding.

The previous open items related to these two overall findings are closed; including VIO

50-400/02-08-01 and URls 50-400/02-11-01, -02, -03, -04, -05, -06, -07, -08, and -09.

40A6 Meetinos. including Exit

The team presented the inspection results to Mr. _

_

and members of his staff

at the conclusion of the inspection on

, 2003. The licensee acknowledged the

findings presented. Proprietary information is not included in this inspection report.

Enclosure

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee personnel

D. Baksa, Supervisor, Equipment Performance

J. Caves, Licensing Supervisor

R. Duncan, Director of Site Operations

M. Fletcher, Manager, Fire Protection Program

A. Khanpour, Manager, Engineering

NRC personnel

J. Brady, Senior Resident Inspector, Shearon Harris

C. Ogle, Chief, Engineering Branch 1 (EB1), Division of Reactor Safety (DRS), Region II (R1l)

C. Payne, Fire Protection Team Leader, EB1, DRS, Ril

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

Opened and Closed

50-400/03-07-01

50-400/03-07-02

NCV

NCV

Inadequate Implementation of the Fire Protection Program

for Safe Shutdown (Section 1 R05.01.b.1)

Inadequate Corrective Action for a Previous White Fire

Protection Finding (Section 1 R05.01.b.2)

Closed

50-400/02-08-01

VIa

Failure to Implement and Maintain NRC Approved Fire

Protection Program Safe Shutdown System Separation

Requirements (Section 1 R05.01.b.2)

50-400/02-11-01

50-400/02-11-02

-- 50-400/02-11-03

URI

URI

URI

Failure to Protect Charging System MOV 1 CS-165, VCT

Outlet to CSIPs, From Maloperation Due To a Fire

(Section 1R05.01.b.1)

Failure to Protect Charging System MOVs 1 CS-1 69,1 CS-

214,1 CS-218, and 1 CS-219 From Maloperation Due To a

Fire (Section 1 R05.01.b.1)

Failure to Protect Charging System MOVs 1 CS-1 66, 1 CS-

168, and I CS-217 From Maloperation Due To a Fire

(Section 1R05.01.b.1)

Attachment

50-400/02-11-04

50-400/02-11-05

50-400/02-11-06

50-400/02-11-07

50-400/02-11-08

50-400/02-11-09

URI

URI

URI

URI

URI

URI

2

Failure to Protect Component Cooling MOVs 1 CC-251 and

1 CC-208, CC for RCP Seals, From Maloperation Due To a

Fire (Section 1 R05.01.b.1)

Reliance on Manual Actions in Place of Required Physical

Separation or Protection From a Fire (Section

1 R05.01.b.2)

Fire SSD Operator Actions With Excessive Challenges

(Section 1 R05.01.b.2)

Too Many Fire SSD Actions for Operators to Perform

(Section 1 R05.01.b.2)

Using the Boric Acid Tank Without Level Indication

(Section 1 R05.01.b.1)

Failure to Provide Required Emergency Lighting for SSD

Operator Actions (Section 1 R05.01.b.2)

Attachment