Letter Sequence Approval |
---|
|
|
MONTHYEARML0425302482004-09-23023 September 2004 Request for Additional Information, Revise the Minimum Critical Power Ratio Safety Limit. TAC No MC2599 Project stage: RAI ML0428002672004-09-29029 September 2004 Submittal of Part 21 Final Report: Non-conservative SLMCPR Project stage: Request ML0434906672005-01-0707 January 2005 Withholding from Public Disclosure, Response to Request for Additional Information (RAI) Associated with a License Amendment Request for Revision of the Minimal Critical Power Ratio Safety Limit, Dated 12/06/2004 Project stage: RAI ML0433501802005-01-0707 January 2005 Request for Withholding from Public Disclosure, Additional Information Regarding the Cycle Specific SLMCPR for Plant Unit 1 Cycle 10. Project stage: Other ML0503503642005-02-0303 February 2005 Technical Specification Pages Revision of the Minimum Critical Power Ratio Safety Limit Project stage: Other ML0500604382005-02-0303 February 2005 Issuance of Amendment Revision of the Minimum Critical Power Ratio Safety Limit Project stage: Approval 2004-09-29
[Table View] |
Similar Documents at Perry |
---|
Category:Letter
MONTHYEARIR 05000440/20230042024-01-30030 January 2024 Integrated Inspection Report 05000440/2023004 L-23-207, License Amendment Request (LAR) for Adoption of TSTF-264-A Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs2024-01-24024 January 2024 License Amendment Request (LAR) for Adoption of TSTF-264-A Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs L-24-017, 30-Day Voluntary Report in Accordance with Industry Groundwater Protection Initiative2024-01-24024 January 2024 30-Day Voluntary Report in Accordance with Industry Groundwater Protection Initiative IR 05000440/20234022024-01-10010 January 2024 Cyber Security Inspection Report 05000440/2023402 ML24003A8032024-01-0303 January 2024 Notification of NRC Fire Protection Team Inspection Request for Information ML23321A0472023-12-20020 December 2023 Letter to Rod L. Penfield - Perry Nuclear Power Plant, Unit 1 - License Renewal Regulatory Audit Regarding the Environmental Review of the License Renewal Application L-23-171, CFR 50.55a Request Number VR-9. Revision 0, Feedwater Check Valve Exercising Test Frequency2023-12-0808 December 2023 CFR 50.55a Request Number VR-9. Revision 0, Feedwater Check Valve Exercising Test Frequency L-23-244, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-0606 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000440/20230112023-11-28028 November 2023 Biennial Problem Identification and Resolution Inspection Report 05000440/2023011 IR 05000440/20234032023-11-27027 November 2023 Security Baseline Inspection Report 05000440/2023403 ML23292A2972023-11-17017 November 2023 Table of Contents LAR (L-2023-LLA-0111) L-23-238, Mid-Cycle Revision to the Core Operating Limits Report for Operating Cycle 202023-11-10010 November 2023 Mid-Cycle Revision to the Core Operating Limits Report for Operating Cycle 20 L-23-052, Submittal of the Updated Safety Analysis Report, Revision 232023-10-27027 October 2023 Submittal of the Updated Safety Analysis Report, Revision 23 ML23292A2482023-10-19019 October 2023 Fws to NRC, Federal Agency Coordination Under ESA Section 7 for Perry Nuclear Plant, Unit 1, License Renewal, and Concurrence with Not Likely to Adversely Affect Determination for Northern Long-eared Bat ML23292A2472023-10-19019 October 2023 Fws to NRC, Perry Nuclear Plant, Unit 1, License Renewal List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected IR 05000440/20230032023-10-11011 October 2023 Integrated Inspection Report 05000440/2023003 ML23249A1032023-10-0303 October 2023 Letter to Rod L. Penfield, Site Vice President-Perry Nuclear Power Plant, Unit 1-Notice of Intent to Conduct Scoping Process and Prepare an Environmental Impact Statement ML23237B4222023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Letter Regarding Order Approving Transfer of Licenses and Draft Conforming License Amendments ML23269A1242023-09-27027 September 2023 Request for Withholding Information from Public Disclosure ML23261C3642023-09-25025 September 2023 License Renewal Application Online Reference Portal ML23261B0192023-09-25025 September 2023 Aging Management Audit Plan Regarding the License Renewal Application Review ML23256A3592023-09-22022 September 2023 Determination of Acceptability and Sufficiency for Docketing, Proposed Review Schedule, and Opportunity for a Hearing Regarding the Energy Harbor Nuclear Corp. Application for License Renewal L-23-205, Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-09-12012 September 2023 Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments L-23-206, Ohio National Pollutant Discharge Elimination System (NPDES) Permit 3IB00016 MD2023-09-12012 September 2023 Ohio National Pollutant Discharge Elimination System (NPDES) Permit 3IB00016 MD L-23-172, Quality Assurance Program Manual2023-08-31031 August 2023 Quality Assurance Program Manual IR 05000440/20234012023-08-28028 August 2023 Public - Perry Nuclear Power Plant Security Baseline Inspection Report 05000440/2023401 ML23129A1722023-08-25025 August 2023 Request for Withholding Information from Public Disclosure for Beaver Valley Power Station, Units 1 and 2; Davis Besse Nuclear Power Station, Unit 1; and Perry Nuclear Power Plant, Unit 1 IR 05000440/20230052023-08-24024 August 2023 Updated Inspection Plan for Perry Nuclear Power Plant (Report 05000440/2023005) ML23172A2852023-08-23023 August 2023 Safety Evaluation Irradiated Fuel Management Plan and Preliminary Decommissioning Cost Estimate ML23227A2202023-08-15015 August 2023 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Perry Nuclear Power Plant L-23-188, Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-08-0707 August 2023 Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments L-23-001, License Amendment Request to Remove the Table of Contents from the Technical Specifications2023-08-0707 August 2023 License Amendment Request to Remove the Table of Contents from the Technical Specifications IR 05000440/20230022023-08-0202 August 2023 Integrated Inspection Report 05000440/2023002 L-23-174, 30-Day Voluntary Report in Accordance with Industry Groundwater Protection Initiative2023-07-19019 July 2023 30-Day Voluntary Report in Accordance with Industry Groundwater Protection Initiative ML23198A2842023-07-17017 July 2023 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection L-23-146, License Renewal Application for the Perry Nuclear Power Plant2023-07-0303 July 2023 License Renewal Application for the Perry Nuclear Power Plant IR 05000440/20230102023-06-29029 June 2023 Comprehensive Engineering Team Inspection Report 05000440/2023010 ML23178A2422023-06-28028 June 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch III L-23-050, 2022 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models2023-06-22022 June 2023 2022 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models L-23-051, Plan, Nineteenth Inservice Inspection Summary Report2023-06-22022 June 2023 Plan, Nineteenth Inservice Inspection Summary Report L-22-249, License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-276-A Revision 2, Change TS 3.8.1. AC Sources-Operating. to Clarify the Power Factor Requirements When Performing Diesel Gener2023-06-0505 June 2023 License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-276-A Revision 2, Change TS 3.8.1. AC Sources-Operating. to Clarify the Power Factor Requirements When Performing Diesel Gener ML23144A3562023-05-25025 May 2023 Information Meeting with a Question and Answer Session to Discuss NRC 2022 End of Cycle Plant Performance Assessment of Perry Nuclear Power Plant, Unit 1 L-23-134, Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations2023-05-23023 May 2023 Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations L-23-065, Annual Financial Report2023-05-22022 May 2023 Annual Financial Report ML23124A1742023-05-17017 May 2023 Energy Harbor Fleet Vistra License Transfer - Request for Withholding Information from Public Disclosure for Commance Peak Plant, Units 1 & 2, Beaver Valley Station, Units 1 & 2, Davis Besse Station, Unit 1 and Perry Plant, Unit 1 ML23129A0112023-05-16016 May 2023 Notice of Consideration of Approval of Indirect and Direct License Transfer for Comanche Peak Plant, Units 1 & 2, Beaver Valley Station, Units 1 & 2, Davis Besse Station, Unit 1 and Perry Plant, Unit 1 (EPID L-2023-LLM-0000) (Letter) IR 05000440/20230012023-05-0404 May 2023 Integrated Inspection Report (05000440/2023001) L-23-122, Annual Radiological Environmental Operating Report2023-04-26026 April 2023 Annual Radiological Environmental Operating Report L-23-121, Annual Radiological Effluent Release Report2023-04-26026 April 2023 Annual Radiological Effluent Release Report 2024-01-30
[Table view] Category:License-Operating (New/Renewal/Amendments) DKT 50
MONTHYEARML23292A2972023-11-17017 November 2023 Table of Contents LAR (L-2023-LLA-0111) ML23237B4412023-09-29029 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Federal Register Notice, Direct and Indirect License Transfer Issuance Order ML23237B4282023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Enclosure 2, Draft Conforming License Amendments ML23237B4302023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Enclosure 4, Safety Evaluation for Transfer of Licenses and Draft Conforming License Amendments (EPID L-2023-LLM-0000) (Public) ML22284A1442023-02-0303 February 2023 Issuance of Amendment No. 200 Regarding the Revision of Methodology Used for Flood Hazard Analysis ML22348A1372023-01-0505 January 2023 Issuance of Amendment No. 199 to Adopt TSTF-541, Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position ML22210A0102022-09-16016 September 2022 Energy Harbor Fleet- Issuance of Amendments Regarding Adoption of TSTF 554, Revise Reactor Coolant Leakage Requirements ML21322A2602022-01-10010 January 2022 Issuance of Amendment No. 197 Regarding the Adoption of TSTF-566, Revision 0, Revise Actions for Inoperable RHR Shutdown Cooling Subsystem, and TSTF-580, Revision 1, Provide Exception from Entering Mode 4 with No Oper ML21270A1122021-11-16016 November 2021 Issuance of Amendment No. 196 Regarding Changes to the Emergency Plan ML21271A0782021-11-0505 November 2021 Issuance of Amendment No. 195 Regarding the Adoption of TSTF-230, Add New Condition B to LCO 3.6.2.3, 'Rhr Suppression Pool Cooling' ML21158A2122021-07-12012 July 2021 Issuance of Amendment No. 194 Regarding the Adoption of TSTF-002, Relocate the 10 Year Sediment Cleaning of the Fuel Oil Storage Tank to Licensee Control ML21081A0702021-04-27027 April 2021 Issuance of Amendment No. 193 Regarding the Adoption of TSTF-500, DC Electrical Rewrite - Update to TSTF-360 ML21035A1702021-03-0101 March 2021 Issuance of Amendment No. 192, Regarding Application to Revise Technical Specifications to Adopt TSTF-582, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements ML20154K7002020-07-0909 July 2020 Issuance of Amendment No. 190 Regarding Fire Protection Program Licensing Basis ML20118C1672020-05-22022 May 2020 Issuance of Amendment No. 189, Regarding Special Heavy Lifting Device Nondestructive Examination Frequency ML20099A1022020-05-22022 May 2020 Issuance of Amendment No. 188, Regarding Revision to Technical Specifications to Adopt TSTF-564, Safety Limit (Minimum Critical Power Ratio) MCPR ML20030A4402020-02-27027 February 2020 Issuance of Amendment Nos. 304, 194, 299, and 187; Order Approving Transfers of Facility Operating Licenses and Independent Spent Fuel Storage Installation General Licenses and Conforming Amendments ML19326A7592019-12-0202 December 2019 Firstenergy Nuclear Operating Company - Non-Proprietary, Letter & Encl 2-5, Order Approving Direct and Indirect Transfer of Licenses and Draft Conforming Amendments for Beaver Valley Units 1 and 2, Davis-Besse Unit 1, and Perry Unit 1 ML19163A0232019-08-14014 August 2019 Issuance of Amendment No. 186 Concerning Changes to Emergency Response Organization ML19022A3242019-02-25025 February 2019 Issuance of Amendment No. 185 Concerning Extension of Containment Leakage Test Frequency ML18292A8162018-12-12012 December 2018 Issuance of Amendment No. 184 Concerning Adoption of Technical Specification Task Force Traveler 542, Rev. 2, Reactor Pressure Vessel Water Inventory Control ML18199A2802018-08-23023 August 2018 Issuance of Amendment No. 183, Adopt Technical Specification Task Force Traveler TSTF-546, Revise APRM Channel Adjustment Surveillance Requirement ML18214A6672018-08-22022 August 2018 FENOC Fleet - Perry Nuclear Power Plant, Unit No. 1 - Correction to the Issuance of Amendment Request to Adopt TSTF-529, Clarify Use and Application Rules (CAC No. MG0136; EPID L-2017-LLA-0259) ML18179A4672018-07-30030 July 2018 FENOC-Beaver Valley Power Station, Unit No. 1 and 2; Davis-Besse Nuclear Power Station, Unit 1, and Perry Nuclear Power Plant, Unit 1 - Issuance of Amendments Request to Adopt TSTF-529, Clarify Use and Application Rules ML18157A0842018-06-25025 June 2018 Issuance of Amendment No. 181 Concerning Adoption of TS Task Force Traveler TSTF-306-A, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration (CAC No. MG0150; EPID L-2017-LLA-0286) ML18110A1332018-05-16016 May 2018 Unit No. 1 - Issuance of Amendment No. 180 Concerning Changes to Technical Specifications Regarding Implementation of the Alternative Source Term (CAC No. MF9818; EPID L-2017-LLA-0241) ML17325B6902018-01-18018 January 2018 Issuance of Amendment Concerning Adoption of Technical Specification Task Force (TSTF) Traveler 400-A, Revision 1, Clarify SR on Bypass of DG Automatic Trips (CAC No. MF9855, EPID L-2017-LLA-0246) (L-17-089) ML17257A0982017-10-19019 October 2017 Issuance of Amendment Concerning Revisions to the Environmental Protection Plan (CAC No. MF9652; EPID L-7017-LLA-0226) (L-17-043) ML17163A3542017-06-29029 June 2017 Issuance of Amendment Concerning Adoption of Tstf-501, Revision 1, Relocation of Diesel Fuel and Lube Oil Volume Values to Licensee Control (CAC No. MF8693) (L-16-236) ML17139C3722017-06-19019 June 2017 Issuance of Amendment Concerning Reduction of Steam Dome Pressure Value Specified in Technical Specification 2.1.1 (CAC No. MF8760) (L-16-179) ML17081A5092017-05-11011 May 2017 ISFSI, Davis-Besse ISFSI, Perry Nuclear Power Plant, Perry Nuclear Power Plant ISFSI - Issuance of Amendments Re. Application to Revise Technical Specifications to Adopt TSTF-545 Revision 3 ML17033A0142017-02-16016 February 2017 Issuance of Amendment Concerning Revision to Technical Specifications to Permit Installation of Upper Containment Pool Gate During Modes 1, 2, and 3 (CAC No. MF7476) (L-16-083) ML16158A3312016-09-14014 September 2016 Issuance of Amendment Concerning Revision to the Perry Nuclear Power Plant Emergency Plan ML16130A5362016-05-31031 May 2016 Issuance of Conforming Amendment Related to the Direct License Transfer of the Facility Operating License NPF-58 ML15307A3492016-02-23023 February 2016 Issuance of Amendment Concerning Adoption of TSTF-425, Relocate Surveillance Frequencies to Licensee Control (CAC No. MF3720) (L-14-106) ML15201A5292015-08-17017 August 2015 Issuance of Amendment Concerning Technical Specification 3.8.4 DC Sources - Operating (TAC No. MF5298) (L-14-271) ML15160A0282015-06-23023 June 2015 Issuance of Amendment Concerning Adoption of TSTF-535, Revise Shutdown Margin Definition to Address Advanced Fuel Designs (TAC No. MF4791)(L-14-137) ML15141A4822015-06-12012 June 2015 Issuance of Amendment Concerning Changes to Pressure Temperature Curves (TAC No. MF4351)(L-14-150) ML15133A5022015-06-10010 June 2015 Issuance of Amendment Concerning Extension of Cyber Security Milestone 8 (TAC No. MF5557)(L-14-421) ML15075A1392015-03-30030 March 2015 Issuance of Amendment Concerning Full Implementation of Alternative Source Term (TAC No. MF3197) (L-13-306) L-14-325, Issuance of Amendment Concerning Safety Limit Critical Power Ratio Values (TAC No. MF5007)(L-14-325)2015-03-27027 March 2015 Issuance of Amendment Concerning Safety Limit Critical Power Ratio Values (TAC No. MF5007)(L-14-325) ML15075A0912015-03-27027 March 2015 Issuance of Amendment Concerning Safety Limit Critical Power Ratio Values (TAC No. MF5007)(L-14-325) ML14205A6192014-08-29029 August 2014 Amendments to Indemnity Agreements (TAC MF0701, MF0702, MF0703, and MF0704) ML13136A1432013-05-16016 May 2013 Nucelar Power Plant, Unit 1 - Re-Issuance of Amendment Regarding Adoption of TSTF-275 and TSTF-300 ML13051B1442013-05-0606 May 2013 Issuance of Amendment Regarding Adoption of TSTF-275, Clarify Requirement for EDG Start Signal on RPV Level - Low, Low, Low During RPV Cavity Flood-Up, and TSTF-300 ML13017A4312013-04-18018 April 2013 Issuance of Amendment Revise Technical Specification 3.10.1, Inservice Leak, and Hydrostatic Testing Operation ML12221A4132012-10-0202 October 2012 Issuance of Amendments Change of the Name of a Owner Licensee to Firstenergy Nuclear Generation, LLC ML1128602452011-10-17017 October 2011 Issuance of Amendment No. 160, Revise Technical Specification 3.8.1, AC Sources - Operating, Regarding Use of a Delayed Circuit as a Required Offsite Circuit (Emergency Circumstances) ML1125211222011-10-0404 October 2011 Issuance of Amendment Adoption of TSTF - 514, Revision 3, Revise BWR Operability Requirements and Actions for RCS Leakage Instrumentation ML1119203822011-08-29029 August 2011 Issuance of Amendment Cyber Security Plan 2023-09-29
[Table view] Category:Safety Evaluation
MONTHYEARML23292A2972023-11-17017 November 2023 Table of Contents LAR (L-2023-LLA-0111) ML23237B4282023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Enclosure 2, Draft Conforming License Amendments ML23237B4302023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Enclosure 4, Safety Evaluation for Transfer of Licenses and Draft Conforming License Amendments (EPID L-2023-LLM-0000) (Public) ML23172A2852023-08-23023 August 2023 Safety Evaluation Irradiated Fuel Management Plan and Preliminary Decommissioning Cost Estimate ML22284A1442023-02-0303 February 2023 Issuance of Amendment No. 200 Regarding the Revision of Methodology Used for Flood Hazard Analysis ML22348A1372023-01-0505 January 2023 Issuance of Amendment No. 199 to Adopt TSTF-541, Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position ML22252A2212022-09-30030 September 2022 Authorization and Safety Evaluation for Alternative Request IR-063 ML22210A0102022-09-16016 September 2022 Energy Harbor Fleet- Issuance of Amendments Regarding Adoption of TSTF 554, Revise Reactor Coolant Leakage Requirements ML22187A2592022-07-12012 July 2022 Issuance of Relief Proposed Alternative Request Vr 12, Revision 0, Associated with the Fourth 10-Year Inservice Testing Interval ML22136A1132022-06-21021 June 2022 Issuance of Relief Proposed Alternative Requests VR-10, Revision 0, and VR-11, Revision 0, Associated with the Fourth 10-Year Inservice Testing Interval (EPIDs L-2021-LLR-0096; L-2021-LLR-0097) ML21322A2602022-01-10010 January 2022 Issuance of Amendment No. 197 Regarding the Adoption of TSTF-566, Revision 0, Revise Actions for Inoperable RHR Shutdown Cooling Subsystem, and TSTF-580, Revision 1, Provide Exception from Entering Mode 4 with No Oper ML21270A1122021-11-16016 November 2021 Issuance of Amendment No. 196 Regarding Changes to the Emergency Plan ML21271A0782021-11-0505 November 2021 Issuance of Amendment No. 195 Regarding the Adoption of TSTF-230, Add New Condition B to LCO 3.6.2.3, 'Rhr Suppression Pool Cooling' ML21158A2122021-07-12012 July 2021 Issuance of Amendment No. 194 Regarding the Adoption of TSTF-002, Relocate the 10 Year Sediment Cleaning of the Fuel Oil Storage Tank to Licensee Control ML21123A2172021-05-0505 May 2021 Issuance of Relief Requests Vr 4, Revision 0, Vr 6, Revision 0, and Vr 8, Revision 0, Associated with the Fourth 10-Year Inservice Testing Interval (EPIDs L 2021 Llr 0010, L 2021 Llr 0011, L 2021 Llr 0012 COVID-19 ML21123A2892021-05-0404 May 2021 Issuance of Relief Request Vr 7, Revision 0, Associated with the Fourth 10-Year Inservice Testing Interval ML21081A0702021-04-27027 April 2021 Issuance of Amendment No. 193 Regarding the Adoption of TSTF-500, DC Electrical Rewrite - Update to TSTF-360 ML21063A2532021-03-0505 March 2021 Issuance of Relief Request SR-2, Revision 0, from Certain Requirements of the ASME OM Code (EPID L-2021-LLR-0005 (COVID-19)) ML21063A1572021-03-0404 March 2021 Safety Evaluation for Alternative Request SR-2, Revision 0 Related to one-time Extension Snubbers Testing to ASME OM Code for the Fourth 10-year Inservice Interval at Perry Nuclear Power Plant Unit 1, Docket Nos. 50-440 ML21035A1702021-03-0101 March 2021 Issuance of Amendment No. 192, Regarding Application to Revise Technical Specifications to Adopt TSTF-582, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements ML20363A0062021-01-29029 January 2021 Issuance of Relief Proposed Alternative Request Associated with Fourth 10-Year Inservice Inspection Interval ML20311A6582020-11-10010 November 2020 Issuance of Relief Proposed Alternative Request Associated with Fourth Ten Year Interval Inservice Inspection Interval ML20279A4402020-10-0808 October 2020 Energy Harbor Fleet-Beaver Valley Power Station; Davis-Besse Nuclear Power Station, and Perry Nuclear Power Plant - Request to Use a Provision of a Later Edition of the ASME Engineers Boiler and Pressure Vessel Code, Section XI ML20266G2652020-09-24024 September 2020 Correction Letter for Relief Request IR-062 Regarding Weld Examination Coverage for the Third Inservice Inspection Interval ML20252A0262020-09-18018 September 2020 Relief Request IR-062 Regarding Weld Examination Coverage for the Third Inservice Inspection Interval ML20189A0032020-07-10010 July 2020 Relief Request PR-3 for Fourth 10-Year Pump and Valve Inservice Testing Program ML20154K7002020-07-0909 July 2020 Issuance of Amendment No. 190 Regarding Fire Protection Program Licensing Basis ML20118C1672020-05-22022 May 2020 Issuance of Amendment No. 189, Regarding Special Heavy Lifting Device Nondestructive Examination Frequency ML20099A1022020-05-22022 May 2020 Issuance of Amendment No. 188, Regarding Revision to Technical Specifications to Adopt TSTF-564, Safety Limit (Minimum Critical Power Ratio) MCPR ML19305B1312019-12-0202 December 2019 Firstenergy Nuclear Operating Company - Enclosure 6, Non-Proprietary Safety Evaluation, Direct and Indirect Transfer of Licenses and Draft Conforming Amendments for Beaver Valley Units 1 and 2, Davis-Besse Unit 1, and Perry Unit 1 ML19163A0232019-08-14014 August 2019 Issuance of Amendment No. 186 Concerning Changes to Emergency Response Organization ML19028A0302019-04-11011 April 2019 FENOC - Beaver Valley Power Station, Unit 1 & 2; Davis-Besse Nuclear Power Station Unit 1; and Perry Nuclear Power Plant Unit 1 - Approval of Certified Fuel Handler Training and Retraining Program ML19072A0122019-03-15015 March 2019 Correction to License Amendment No. 184 Related to Adoption of Technical Specification Task Force Traveler TSTF-542, Revision 2, Reactor Pressure Vessel Water Inventory Control ML19072A0852019-03-15015 March 2019 Correction to Request for Alternatives Related to Inservice Testing Program for the Fourth 10 Year Inservice Testing Interval ML19029A0902019-02-25025 February 2019 Request for Alternatives Related to Inservice Testing Program for the Fourth 10-Year Inservice Testing Interval (EPID Nos. L-2018-LLR-0092, 0093, 0094, 0095, and 0096) ML19022A3242019-02-25025 February 2019 Issuance of Amendment No. 185 Concerning Extension of Containment Leakage Test Frequency ML19037A0412019-02-25025 February 2019 Request for Alternative to Use ASME Code Case N-831 ML18292A8162018-12-12012 December 2018 Issuance of Amendment No. 184 Concerning Adoption of Technical Specification Task Force Traveler 542, Rev. 2, Reactor Pressure Vessel Water Inventory Control ML18199A2802018-08-23023 August 2018 Issuance of Amendment No. 183, Adopt Technical Specification Task Force Traveler TSTF-546, Revise APRM Channel Adjustment Surveillance Requirement ML18179A4672018-07-30030 July 2018 FENOC-Beaver Valley Power Station, Unit No. 1 and 2; Davis-Besse Nuclear Power Station, Unit 1, and Perry Nuclear Power Plant, Unit 1 - Issuance of Amendments Request to Adopt TSTF-529, Clarify Use and Application Rules ML18157A0842018-06-25025 June 2018 Issuance of Amendment No. 181 Concerning Adoption of TS Task Force Traveler TSTF-306-A, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration (CAC No. MG0150; EPID L-2017-LLA-0286) ML18110A1332018-05-16016 May 2018 Unit No. 1 - Issuance of Amendment No. 180 Concerning Changes to Technical Specifications Regarding Implementation of the Alternative Source Term (CAC No. MF9818; EPID L-2017-LLA-0241) ML18023A6252018-01-29029 January 2018 Approval of Alternative to Use BWRVIP Guidelines in Lieu of Certain ASME Code Requirements (CAC No. MG0149; EPID 2017-LLR-0112) (L-17-183) ML18004A1222018-01-22022 January 2018 FENOC-Beaver Valley, Davis-Besse, and Perry - Alternative for the Use of ASME Code Case N-513-4 (CAC Nos. MG0120, MG0121, MG0122, and MG0123; EPID L-2017-LLR-0088) ML17325B6902018-01-18018 January 2018 Issuance of Amendment Concerning Adoption of Technical Specification Task Force (TSTF) Traveler 400-A, Revision 1, Clarify SR on Bypass of DG Automatic Trips (CAC No. MF9855, EPID L-2017-LLA-0246) (L-17-089) ML17257A0982017-10-19019 October 2017 Issuance of Amendment Concerning Revisions to the Environmental Protection Plan (CAC No. MF9652; EPID L-7017-LLA-0226) (L-17-043) ML17270A0302017-10-16016 October 2017 Approval of Alternative to Use ASME Code Case N-513-4 for Repair of Emergency Service Water System Piping (CAC No. MG0130; EPID L-2017-LLR-0080)(L-17-278) ML17193A3822017-07-18018 July 2017 Correction to Safety Evaluation for License Amendment No. 177 ML17163A3542017-06-29029 June 2017 Issuance of Amendment Concerning Adoption of Tstf-501, Revision 1, Relocation of Diesel Fuel and Lube Oil Volume Values to Licensee Control (CAC No. MF8693) (L-16-236) ML17139C3722017-06-19019 June 2017 Issuance of Amendment Concerning Reduction of Steam Dome Pressure Value Specified in Technical Specification 2.1.1 (CAC No. MF8760) (L-16-179) 2023-09-28
[Table view] |
Text
February 3, 2005 Mr. Lew W. Myers Chief Operating Officer FirstEnergy Nuclear Operating Company Perry Nuclear Power Plant P.O. Box 97, A290 10 Center Road Perry, OH 44081
SUBJECT:
PERRY NUCLEAR POWER PLANT, UNIT 1 - ISSUANCE OF AMENDMENT RE: REVISION OF THE MINIMUM CRITICAL POWER RATIO SAFETY LIMIT (TAC NO. MC2599)
Dear Mr. Myers:
The Commission has issued the enclosed Amendment No. 132 to Facility Operating License No. NPF-58 for the Perry Nuclear Power Plant, Unit 1. This amendment revises the Technical Specifications in response to your application dated April 5, 2004, as supplemented by letters dated June 22 and December 6, 2004.
This amendment modifies the existing minimum critical power ratio (MCPR) safety limit contained in Technical Specification 2.1.1.2. Specifically, the change modifies the MCPR safety limit values by decreasing the limit for two recirculation loop operation from 1.10 to 1.08, and decreasing the limit for single recirculation loop operation from 1.11 to 1.10.
A copy of the Safety Evaluation is also enclosed. The Notice of Issuance will be included in the Commission's next biweekly Federal Register notice.
Sincerely,
/RA/
William A. Macon, Jr., Project Manager, Section 2 Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-440
Enclosures:
- 1. Amendment No. 132 to NPF-58
- 2. Safety Evaluation cc w/encls: See next page
February 3, 2005 Mr. Lew W. Myers Chief Operating Officer FirstEnergy Nuclear Operating Company Perry Nuclear Power Plant P.O. Box 97, A290 10 Center Road Perry, OH 44081
SUBJECT:
PERRY NUCLEAR POWER PLANT, UNIT 1 - ISSUANCE OF AMENDMENT RE: REVISION OF THE MINIMUM CRITICAL POWER RATIO SAFETY LIMIT (TAC NO. MC2599)
Dear Mr. Myers:
The Commission has issued the enclosed Amendment No. 132 to Facility Operating License No. NPF-58 for the Perry Nuclear Power Plant, Unit 1. This amendment revises the Technical Specifications in response to your application dated April 5, 2004, as supplemented by letters dated June 22 and December 6, 2004.
This amendment modifies the existing minimum critical power ratio (MCPR) safety limit contained in Technical Specification 2.1.1.2. Specifically, the change modifies the MCPR safety limit values by decreasing the limit for two recirculation loop operation from 1.10 to 1.08, and decreasing the limit for single recirculation loop operation from 1.11 to 1.10.
A copy of the Safety Evaluation is also enclosed. The Notice of Issuance will be included in the Commission's next biweekly Federal Register notice.
Sincerely,
/RA/
William A. Macon, Jr., Project Manager, Section 2 Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-440
Enclosures:
- 1. Amendment No. 132 to NPF-58
- 2. Safety Evaluation DISTRIBUTION:
PUBLIC PDIII-2 R/F WMacon TBoyce, O-12H2 ACRS OGC DClarke GGrant, RIII GSuh DLPMDPR WRuland GHill (2)
FAkstulewicz MRazzaque DOCUMENT NAME: E:\Filenet\ML050060438.wpd Package Accession Number: ML050380249 Amendment Accession Number: ML050060438 TS Accession Number: ML050350364 *No major changes to SE dated 12/20/04 OFFICE PM:PDIII-2 LA:PDIII-2 SC:SRXB-A* OGC SC:PDIII-2 NAME WMacon DClarke FAkstulewicz RHoefling GSuh DATE 1/21/05 1/24/05 12/20/04 2/1/05 2/2/05 OFFICIAL RECORD COPY
FIRSTENERGY NUCLEAR OPERATING COMPANY DOCKET NO. 50-440 PERRY NUCLEAR POWER PLANT, UNIT 1 AMENDMENT TO FACILITY OPERATING LICENSE Amendment No. 132 License No. NPF-58
- 1. The U.S. Nuclear Regulatory Commission (the Commission) has found that:
A. The application for amendment by the FirstEnergy Nuclear Operating Company (the licensee) dated April 5, 2004, as supplemented by letters dated June 22 and December 6, 2004, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commission's rules and regulations set forth in 10 CFR Chapter I; B. The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C. There is reasonable assurance (I) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; D. The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E. The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.
- 2. Accordingly, the license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment, and paragraph 2.C.(2) of Facility Operating License No. NPF-58 is hereby amended to read as follows:
(2) Technical Specifications The Technical Specifications contained in Appendix A and the Environmental Protection Plan contained in Appendix B, as revised through Amendment No. 132, are hereby incorporated into this license. The FirstEnergy Nuclear Operating Company shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.
- 3. This license amendment is effective as of its date of its issuance and shall be implemented within 90 days of the date of issuance.
FOR THE NUCLEAR REGULATORY COMMISSION
/RA/
Gene Y. Suh, Chief, Section 2 Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation
Attachment:
Changes to the Technical Specifications Date of Issuance: February 3, 2005
ATTACHMENT TO LICENSE AMENDMENT NO. 132 FACILITY OPERATING LICENSE NO. NPF-58 DOCKET NO. 50-440 Replace the following page of the Appendix A Technical Specifications with the attached revised page. The revised page is identified by amendment number and contains marginal lines indicating the areas of change.
Remove Insert 2.0-1 2.0-1
SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO AMENDMENT NO. 132 TO FACILITY OPERATING LICENSE NO. NPF-58 FIRSTENERGY NUCLEAR OPERATING COMPANY PERRY NUCLEAR POWER PLANT, UNIT 1 DOCKET NO. 50-440
1.0 INTRODUCTION
By application to the U.S. Nuclear Regulatory Commission (NRC, Commission) dated April 5, 2004 (Reference 1), as supplemented by letters dated June 22 (Reference 2) and December 6, 2004 (Reference 3), FirstEnergy Nuclear Operating Company (the licensee) requested changes to the Technical Specifications (TSs) for the Perry Nuclear Power Plant, Unit 1 (PNPP). The supplements dated June 22 and December 6, 2004, provided additional information that clarified the application, did not expand the scope of the application as originally noticed, and did not change the NRC staffs original proposed no significant hazards consideration determination as published in the Federal Register on May 11, 2004 (69 FR 26189).
The proposed changes would modify the existing minimum critical power ratio (MCPR) safety limit contained in TS 2.1.1.2. Specifically, the changes would modify the MCPR safety limit values, as calculated by Global Nuclear Fuel (GNF), by decreasing the limit for two recirculation loop operation from 1.10 to 1.08, and decreasing the limit for single recirculation loop operation from 1.11 to 1.10. In addition, the term "Minimum Critical Power Ratio" will be inserted into the TS prior to the first use of the acronym, "MCPR."
The safety limit for MCPR (SLMCPR) is one of the limits used to protect the nuclear fuel. Since the parameters that result in fuel damage are not directly observable during reactor operation, the thermal and hydraulic conditions that result in the onset of transition boiling (i.e., MCPR = 1.00) have been used to mark the beginning of the region in which fuel damage could occur. Although it is recognized that the onset of transition boiling would not result in damage to boiling water reactor (BWR) fuel rods, the critical power at which boiling transition is calculated to occur has been adopted as a convenient limit. The safety limit is defined as the critical power ratio in the limiting fuel assembly for which more than 99.9 percent of the fuel rods in the core are expected to avoid boiling transition, considering the power distribution within the core and various uncertainties. The SLMCPR provides a 95 percent probability at the 95 percent confidence level that following any abnormal operating occurrence, greater than 99.9 percent of the fuel rods avoid the boiling transition.
2.0 REGULATORY EVALUATION
Title 10 of the Code of Federal Regulations, Part 50 (10 CFR 50), Appendix A, General Design Criterion (GDC) 10, "Reactor design," states, in part, that the reactor core and associated coolant, control, and protective system be designed to assure that the specified acceptable fuel
design limits are not exceeded during any condition of steady-state operation, normal operational transients, and anticipated operational occurrences.
Fuel design limits can likely be exceeded if the core exceeds critical power. Critical power is a term used for the power at which the fuel departs from nucleate boiling and enters a transition to film boiling. For BWRs, the critical power is predicted using a correlation known as the GE critical quality boiling length correlation, or better known as the GEXL correlation. Due to core wide and operational variations, the margin to boiling transition is most easily described in terms of a critical power ratio (CPR), which is defined as the rod critical power as calculated by GEXL divided by the actual rod power. The more a CPR value exceeds 1.0, the greater the margin to boiling transition is. The SLMCPR is calculated using a statistical process that takes into account all operating parameters and the uncertainties. The operating limit MCPR (OLMCPR) is equal to the SLMCPR plus a CPR margin for transients. At the OLMCPR, at least 99.9% of the rods avoid boiling transition during steady state operation and transients caused by single operator error or equipment malfunction.
Safety limits are required to be included in the TSs by 10 CFR 50.36, Technical Specifications. The SLMCPR is calculated on a cycle-specific basis because it is necessary to account for the core configuration-specific neutronic and thermal-hydraulic response.
In accordance with 10 CFR 50.90, Application for amendment of license or construction permit, and TS 2.1.1, the licensee was required to submit their evaluation for NRC staff review in support of the SLMCPR changes. TS 2.1.1, "Reactor Core Safety Limits," will be changed by revising Section 2.1.1.2 to read:
With the reactor steam dome pressure > 785 psig and core flow > 10% rated core flow:
The Minimum Critical Power Ratio (MCPR) shall be > 1.08 for two recirculation loop operation or > 1.10 for single recirculation loop operation.
3.0 TECHNICAL EVALUATION
The proposed PNPP cycle-specific SLMCPR values (1.08 for two recirculation loop operation, and 1.10 for single recirculation loop operation for Fuel Cycle 10) were determined using the NRC-approved methods detailed in Reference 4. The PNPP-specific evaluation for the Fuel Cycle 10 core reload resulted in different calculated SLMCPR values from the previous cycle because different inputs were used, and due to the differences in the core design and bundle design used between Fuel Cycles 9 and 10. Compliance with a SLMCPR greater than or equal to the calculated value will ensure that less than 0.1 percent of the fuel rods will experience boiling transition. This in turn ensures fuel damage does not occur following transients due to excessive thermal stresses on the fuel cladding. The MCPR operating limits are set higher (i.e., more conservative) than the safety limit such that potentially limiting plant transients prevent the MCPR from decreasing below the SLMCPR during the transient. As a result, there is no impact on any of the limiting Appendix 15B transients described in the PNPP Updated Safety Analysis Report (USAR).
As indicated earlier, the licensee stated in the submittal that their evaluations yielded different calculated SLMCPR values because different inputs were used for Fuel Cycles 9 and 10. In comparing the PNPP Fuel Cycle 9 and 10 SLMCPR values, it is important to note the impact of the differences in the core and bundle designs, as presented in the submittal. In general, the calculated safety limit is dominated by two key parameters: (1) flatness of the core bundle-by-bundle MCPR distributions, and (2) flatness of the bundle pin-by-pin power/R-factor distributions. It was further stated that greater flatness in either parameter yields more rods susceptible to boiling transition, and therefore, the necessity of a higher (more conservative) calculated SLMCPR. On the basis of the calculated values, as presented in the submittal, it can be concluded that the Fuel Cycle 10 core MCPR distribution is slightly flatter than the distribution evaluated for Fuel Cycle 9. Furthermore, the uncontrolled bundle pin-by-pin power distributions were compared between the PNPP Fuel Cycle 9 bundles and the Fuel Cycle 10 bundles. Pin-by-pin power distributions are characterized in terms of R-factors using the NRC-approved methodology (Reference 5). For the PNPP Fuel Cycle 10 limiting case analyzed at end of cycle, the calculated values suggest that the PNPP Fuel Cycle 10 bundles are more peaked than the bundles used for the Fuel Cycle 9 SLMCPR analysis.
The licensees calculations use the GEXL14 correlation for GE14 fuel. The potential impact of a bias on the calculated SLMCPR due to a GE14 top-peaked (or outlet-peaked) or a GE14 double-humped axial power shape was considered. The licensee states that for PNPP Fuel Cycle 10, no top-peaked or double-humped axial power shapes will be present.
After the initial review, the NRC staff requested the licensee to provide additional information.
By letter dated December 6, 2004, the licensee submitted responses to the NRC staffs request for additional information (RAI), as discussed below.
The calculated values presented in the licensee's submittal for Fuel Cycle 10 indicate that the core bundle-by-bundle MCPR distribution is slightly flatter than the distribution evaluated for Fuel Cycle 9; whereas, Fuel Cycle 10 has a more peaked in-bundle pin-by-pin power distribution than what was used for Fuel Cycle 9. Contrary to the licensees assertion that greater flatness in either core bundle-by-bundle MCPR distribution or bundle pin-by-pin power/R-factor distribution results in a higher calculated SLMCPR, the NRC staff noted that although the bundle-by-bundle MCPR distribution is flatter for Fuel Cycle 10, the proposed SLMCPR for Fuel Cycle 10 is lower (less conservative) than Fuel Cycle 9. In RAI question no. 1, the NRC staff requested the licensee to explain this apparent contradiction.
In their response, the licensee stated that the submittal statement, "Greater flatness in either parameter yields more rods susceptible to boiling transition," means that if all other parameters are held constant then if the core bundle-by-bundle MCPR distributions showed greater flatness this would yield more rods susceptible to boiling transition. On the other hand, if all other parameters were held constant and if the bundle pin-by-pin power/R-factor distributions showed greater flatness then this would yield more rods susceptible to boiling transition. However, when both parameters change, as was the case for the PNPP, the trend is determined by a combination of the two parameters based on a statistical analysis discussed in the RAI response. The NRC staff finds the response to be acceptable.
In RAI question no. 2, the NRC staff stated that the proposed cycle-specific determination of the SLMCPR values for PNPP Fuel Cycle 10 are only acceptable provided that all the restrictions stated in the NRC staff's safety evaluation (SE) dated March 11, 1999
(Reference 4), approving the General Electric (GE) licensing topical reports NEDC-32601P, NEDC-32694P, and Amendment 25 to NEDE-24011P-A, are met. The NRC staff, therefore, requested the licensee to affirm that all the restrictions discussed in the SE have been satisfied.
In order for the licensee to generate the proposed SLMCPR values, if it was necessary to deviate from any of the assumptions and the conditions outlined in the NRC staff SE for a cycle-specific determination of the SLMCPR, then the licensee should discuss those deviations and provide the technical justifications for their acceptability.
In their response, the licensee stated that the PNPP SLMCPR calculations comply with all the restrictions stated in the NRC staffs evaluation of the SLMCPR methodology. The restrictions cited on page 3 of the March 11, 1999, SE, were identified as restrictions (1) through (4).
Restrictions (1) and (2) are satisfied since the GE12 and GE14 fuel in the PNPP core were specifically covered in NEDC-32601P, and the change to R-factor methodology is covered in Reference 5. Restriction (3) discusses the bundle-by-bundle MCPR distribution criteria parameter value that needs to be attained during the evaluation to assure that the limiting core conditions used in the SLMCPR evaluation will result in conservative SLMCPR values (higher values) compared to values that would be obtained for expected operation of the plant. This criterion is still considered to be applicable to current fuel and core designs. Restriction (4) refers specifically to the use of the reduced power uncertainties as defined in NEDC-32694P.
The Fuel Cycle 10 SLMCPR evaluation was performed using the NRC staff-approved methodology covered in GETAB NEDO-10958-A (Reference 6), power uncertainties.
Therefore, Restriction (4) does not apply to the PNPP Fuel Cycle 10 SLMCPR evaluation. The NRC staff finds the response acceptable.
Finally, RAI question no. 3, the NRC staff requested the licensee to confirm whether the proposed SLMCPR values for PNPP Fuel Cycle 10 are applicable only for the currently approved (for Fuel Cycle 9) operating conditions, and that operation beyond the currently approved conditions and power level is not anticipated for Fuel Cycle 10.
In their response, the licensee stated that PNPP is licensed for a maximum of 3758 megawatts thermal, and is operated in accordance with the conditions described within the PNPP USAR
[e.g., maximum extended operating domain]. The licensee does not currently have a license amendment request to change the power level or operating conditions either in progress or before the NRC for review.
On August 24, 2004, GNF and General Electric Nuclear Energy (GENE) notified the NRC by issuing a 10 CFR Part 21, Reporting of Defects and Noncompliance, report (Reference 7) that the process for determining the MCPR safety limit could result in non-conservative MCPR safety limits. GNF and GENE determined that using limiting control rod blade patterns developed for less than rated flow at rated power conditions could sometimes yield more limiting bundle-by-bundle MCPR distributions and/or more limiting bundle axial power shapes than the limiting control rod patterns developed for a rated flow/rated power SLMCPR calculation. GNF and GENE took corrective actions that require the SLMCPR to be calculated at the rated power/rated flow and at the minimum core flow/rated power conditions, using appropriate limiting control rod patterns. By letter dated September 29, 2004 (Reference 8),
GNF and GENE notified the NRC that a number of BWRs are unaffected by this issue, and that PNPP was one of the facilities listed as being unaffected by this issue.
Therefore, the changes in the MCPR safety limit values proposed by this license amendment request need not be revised.
On the basis of the information submitted by the licensee by letter dated April 5, 2004, and the information provided in response to the NRC staffs RAI, the NRC staff concludes that the calculated SLMCPR values of 1.08 for two-loop operation, and 1.10 for single-loop operation for PNPP are acceptable. The licensee affirmed that the Fuel Cycle 10 specific SLMCPR values were calculated based on the NRC-approved methodologies, as referenced in the submittal, and that all the assumptions and the restrictions outlined in the relevant NRC staff SEs have been met. The NRC staff, therefore, approves this license amendment as requested.
4.0 STATE CONSULTATION
In accordance with the Commission's regulations, the Ohio State official was notified of the proposed issuance of the amendment. The State official had no comments.
5.0 ENVIRONMENTAL CONSIDERATION
This amendment changes a requirement with respect to installation or use of a facility component located within the restricted area as defined in 10 CFR Part 20 or changes a surveillance requirement. The NRC staff has determined that the amendment involves no significant increase in the amounts, and no significant change in the types, of any effluent that may be released offsite and that there is no significant increase in individual or cumulative occupational radiation exposure. The Commission has previously issued a proposed finding that this amendment involves no significant hazards consideration and there has been no public comment on such finding (69 FR 26189). Accordingly, this amendment meets the eligibility criteria for categorical exclusion set forth in 10 CFR 51.22(c)(9). Pursuant to 10 CFR 51.22(b),
no environmental impact statement or environmental assessment need be prepared in connection with the issuance of this amendment.
6.0 CONCLUSION
The NRC staff has concluded, based on the considerations discussed above, that: (1) there is reasonable assurance that the health and safety of the public will not be endangered by operation in the proposed manner, (2) such activities will be conducted in compliance with the Commission's regulations, and (3) the issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public.
7.0 REFERENCES
- 1. Kanda, W.R., Perry Nuclear Power Plant, letter to U.S. NRC, License Amendment Request Pursuant to 10 CFR 50.90: Revision of the Minimum Critical Power Ratio Safety Limit, April 5, 2004 (ML043220206).
- 2. Kanda, W.R., Perry Nuclear Power Plant, letter to U.S. NRC, License Amendment Request Pursuant to 10 CFR 50.90: Revision of the Minimum Critical Power Ratio Safety Limits, June 22, 2004 (ML041890396).
- 3. Anderson, R.L., Perry Nuclear Power Plant, letter to U.S. NRC, Response to Request for Additional Information (RAI) Associated with a License Amendment Request for Revision of the Minimum Critical Power Ratio Safety Limit, December 6, 2004 (ML043500601).
- 4. Akstulewicz, F., NRC letter to Glen A. Watford, GE, "Acceptance for Referencing of Licensing Topical Reports NEDC-32601P, Methodology and Uncertainties for Safety Limit MCPR Evaluations; NEDC-32694P, Power Distribution Uncertainties for Safety Limit MCPR Evaluation; and Amendment 25 to NEDE-24011-P-A on Cycle Specific Safety Limit MCPR," March 11, 1999 (ML993140559).
- 5. Essig, T.H., NRC letter to Glen A. Watford, GE, "Acceptance for Referencing of Licensing Topical Report NEDC-32505P, Revision 1, R-Factor Calculation Method for GE11, GE12 and GE13 Fuel," January 11, 1999.
- 6. NEDO-10958-A, General Electric BWR Thermal Analysis Basis (GETAB): Data, Correlation and Design Application, January 1977.
- 7. Post, J.S., GE Nuclear Energy, letter to U.S. NRC, Part 21 Reportable Condition and 60-Day Interim Report Notification: Non-conservative SLMCPR, August 24, 2004 (ML042720293).
- 8. Post, J.S., GE Nuclear Energy, letter to U.S. NRC, Part 21 Final Report:
Non-conservative SLMCPR, September 29, 2004 (ML042800267).
Principal Contributor: M. Razzaque, NRR Date: February 3, 2005
Perry Nuclear Power Plant, Unit 1 cc:
David W. Jenkins Carol OClaire, Chief, Radiological Branch FirstEnergy Corporation Ohio Emergency Management Agency 76 South Main St. 2855 West Dublin Granville Road Akron, OH 44308 Columbus, OH 43235-7150 Resident Inspector's Office Mayor, Village of Perry U.S. Nuclear Regulatory Commission P.O. Box 100 P.O. Box 331 Perry, OH 44081-0100 Perry, OH 44081-0331 Dennis Clum Regional Administrator, Region III Radiological Assistance Section Supervisor U.S. Nuclear Regulatory Commission Bureau of Radiation Protection 801 Warrenville Road Ohio Department of Health Lisle, IL 60532-4531 P.O. Box 118 Columbus, OH 43266-0118 Sue Hiatt OCRE Interim Representative Zack A. Clayton 8275 Munson DERR Mentor, OH 44060 Ohio Environmental Protection Agency ATTN: Mr. Zack A. Clayton Manager - Regulatory Compliance P.O. Box 1049 FirstEnergy Nuclear Operating Company Columbus, OH 43266-0149 Perry Nuclear Power Plant P.O. Box 97, A210 Chairman 10 Center Road Perry Township Board of Trustees Perry, OH 44081 3750 Center Road, Box 65 Perry, OH 44081 Director, Site Operations FirstEnergy Nuclear Operating Company Daniel Z. Fisher Perry Nuclear Power Plant Transportation Department P.O. Box 97, SB306 Public Utilities Commission Perry, OH 44081 180 East Broad Street Columbus, OH 43215-3793 Mayor, Village of North Perry North Perry Village Hall Joseph J. Hagan 4778 Lockwood Road Senior Vice President, Engineering and North Perry Village, OH 44081 Services First Energy Nuclear Operating Company Donna Owens, Director 76 South Main Street Ohio Department of Commerce Akron, OH 44308 Division of Industrial Compliance Bureau of Operations & Maintenance Richard Anderson 6606 Tussing Road Vice President P. O. Box 4009 FirstEnergy Nuclear Operating Company Reynoldsburg, OH 43068-9009 Perry Nuclear Power Plant P.O. Box 97, A290 10 Center Road Perry, OH 44081