MONTHYEARML0425302482004-09-23023 September 2004 Request for Additional Information, Revise the Minimum Critical Power Ratio Safety Limit. TAC No MC2599 Project stage: RAI ML0428002672004-09-29029 September 2004 Submittal of Part 21 Final Report: Non-conservative SLMCPR Project stage: Request ML0434906672005-01-0707 January 2005 Withholding from Public Disclosure, Response to Request for Additional Information (RAI) Associated with a License Amendment Request for Revision of the Minimal Critical Power Ratio Safety Limit, Dated 12/06/2004 Project stage: RAI ML0433501802005-01-0707 January 2005 Request for Withholding from Public Disclosure, Additional Information Regarding the Cycle Specific SLMCPR for Plant Unit 1 Cycle 10. Project stage: Other ML0503503642005-02-0303 February 2005 Technical Specification Pages Revision of the Minimum Critical Power Ratio Safety Limit Project stage: Other ML0500604382005-02-0303 February 2005 Issuance of Amendment Revision of the Minimum Critical Power Ratio Safety Limit Project stage: Approval 2004-09-29
[Table View] |
Similar Documents at Perry |
---|
Category:Letter
MONTHYEARIR 05000440/20230042024-01-30030 January 2024 Integrated Inspection Report 05000440/2023004 L-23-207, License Amendment Request (LAR) for Adoption of TSTF-264-A Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs2024-01-24024 January 2024 License Amendment Request (LAR) for Adoption of TSTF-264-A Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs L-24-017, 30-Day Voluntary Report in Accordance with Industry Groundwater Protection Initiative2024-01-24024 January 2024 30-Day Voluntary Report in Accordance with Industry Groundwater Protection Initiative IR 05000440/20234022024-01-10010 January 2024 Cyber Security Inspection Report 05000440/2023402 ML24003A8032024-01-0303 January 2024 Notification of NRC Fire Protection Team Inspection Request for Information ML23321A0472023-12-20020 December 2023 Letter to Rod L. Penfield - Perry Nuclear Power Plant, Unit 1 - License Renewal Regulatory Audit Regarding the Environmental Review of the License Renewal Application L-23-171, CFR 50.55a Request Number VR-9. Revision 0, Feedwater Check Valve Exercising Test Frequency2023-12-0808 December 2023 CFR 50.55a Request Number VR-9. Revision 0, Feedwater Check Valve Exercising Test Frequency L-23-244, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-0606 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000440/20230112023-11-28028 November 2023 Biennial Problem Identification and Resolution Inspection Report 05000440/2023011 IR 05000440/20234032023-11-27027 November 2023 Security Baseline Inspection Report 05000440/2023403 ML23292A2972023-11-17017 November 2023 Table of Contents LAR (L-2023-LLA-0111) L-23-238, Mid-Cycle Revision to the Core Operating Limits Report for Operating Cycle 202023-11-10010 November 2023 Mid-Cycle Revision to the Core Operating Limits Report for Operating Cycle 20 L-23-052, Submittal of the Updated Safety Analysis Report, Revision 232023-10-27027 October 2023 Submittal of the Updated Safety Analysis Report, Revision 23 ML23292A2482023-10-19019 October 2023 Fws to NRC, Federal Agency Coordination Under ESA Section 7 for Perry Nuclear Plant, Unit 1, License Renewal, and Concurrence with Not Likely to Adversely Affect Determination for Northern Long-eared Bat ML23292A2472023-10-19019 October 2023 Fws to NRC, Perry Nuclear Plant, Unit 1, License Renewal List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected IR 05000440/20230032023-10-11011 October 2023 Integrated Inspection Report 05000440/2023003 ML23249A1032023-10-0303 October 2023 Letter to Rod L. Penfield, Site Vice President-Perry Nuclear Power Plant, Unit 1-Notice of Intent to Conduct Scoping Process and Prepare an Environmental Impact Statement ML23237B4222023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Letter Regarding Order Approving Transfer of Licenses and Draft Conforming License Amendments ML23269A1242023-09-27027 September 2023 Request for Withholding Information from Public Disclosure ML23261C3642023-09-25025 September 2023 License Renewal Application Online Reference Portal ML23261B0192023-09-25025 September 2023 Aging Management Audit Plan Regarding the License Renewal Application Review ML23256A3592023-09-22022 September 2023 Determination of Acceptability and Sufficiency for Docketing, Proposed Review Schedule, and Opportunity for a Hearing Regarding the Energy Harbor Nuclear Corp. Application for License Renewal L-23-205, Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-09-12012 September 2023 Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments L-23-206, Ohio National Pollutant Discharge Elimination System (NPDES) Permit 3IB00016 MD2023-09-12012 September 2023 Ohio National Pollutant Discharge Elimination System (NPDES) Permit 3IB00016 MD L-23-172, Quality Assurance Program Manual2023-08-31031 August 2023 Quality Assurance Program Manual IR 05000440/20234012023-08-28028 August 2023 Public - Perry Nuclear Power Plant Security Baseline Inspection Report 05000440/2023401 ML23129A1722023-08-25025 August 2023 Request for Withholding Information from Public Disclosure for Beaver Valley Power Station, Units 1 and 2; Davis Besse Nuclear Power Station, Unit 1; and Perry Nuclear Power Plant, Unit 1 IR 05000440/20230052023-08-24024 August 2023 Updated Inspection Plan for Perry Nuclear Power Plant (Report 05000440/2023005) ML23172A2852023-08-23023 August 2023 Safety Evaluation Irradiated Fuel Management Plan and Preliminary Decommissioning Cost Estimate ML23227A2202023-08-15015 August 2023 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Perry Nuclear Power Plant L-23-188, Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-08-0707 August 2023 Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments L-23-001, License Amendment Request to Remove the Table of Contents from the Technical Specifications2023-08-0707 August 2023 License Amendment Request to Remove the Table of Contents from the Technical Specifications IR 05000440/20230022023-08-0202 August 2023 Integrated Inspection Report 05000440/2023002 L-23-174, 30-Day Voluntary Report in Accordance with Industry Groundwater Protection Initiative2023-07-19019 July 2023 30-Day Voluntary Report in Accordance with Industry Groundwater Protection Initiative ML23198A2842023-07-17017 July 2023 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection L-23-146, License Renewal Application for the Perry Nuclear Power Plant2023-07-0303 July 2023 License Renewal Application for the Perry Nuclear Power Plant IR 05000440/20230102023-06-29029 June 2023 Comprehensive Engineering Team Inspection Report 05000440/2023010 ML23178A2422023-06-28028 June 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch III L-23-050, 2022 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models2023-06-22022 June 2023 2022 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models L-23-051, Plan, Nineteenth Inservice Inspection Summary Report2023-06-22022 June 2023 Plan, Nineteenth Inservice Inspection Summary Report L-22-249, License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-276-A Revision 2, Change TS 3.8.1. AC Sources-Operating. to Clarify the Power Factor Requirements When Performing Diesel Gener2023-06-0505 June 2023 License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-276-A Revision 2, Change TS 3.8.1. AC Sources-Operating. to Clarify the Power Factor Requirements When Performing Diesel Gener ML23144A3562023-05-25025 May 2023 Information Meeting with a Question and Answer Session to Discuss NRC 2022 End of Cycle Plant Performance Assessment of Perry Nuclear Power Plant, Unit 1 L-23-134, Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations2023-05-23023 May 2023 Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations L-23-065, Annual Financial Report2023-05-22022 May 2023 Annual Financial Report ML23124A1742023-05-17017 May 2023 Energy Harbor Fleet Vistra License Transfer - Request for Withholding Information from Public Disclosure for Commance Peak Plant, Units 1 & 2, Beaver Valley Station, Units 1 & 2, Davis Besse Station, Unit 1 and Perry Plant, Unit 1 ML23129A0112023-05-16016 May 2023 Notice of Consideration of Approval of Indirect and Direct License Transfer for Comanche Peak Plant, Units 1 & 2, Beaver Valley Station, Units 1 & 2, Davis Besse Station, Unit 1 and Perry Plant, Unit 1 (EPID L-2023-LLM-0000) (Letter) IR 05000440/20230012023-05-0404 May 2023 Integrated Inspection Report (05000440/2023001) L-23-122, Annual Radiological Environmental Operating Report2023-04-26026 April 2023 Annual Radiological Environmental Operating Report L-23-121, Annual Radiological Effluent Release Report2023-04-26026 April 2023 Annual Radiological Effluent Release Report 2024-01-30
[Table view] |
Text
January 7, 2005 Ms. Margaret E. Harding, Manager Fuel Engineering Services, Global Nuclear Fuel - Americas, LLC P.O. Box 780 Wilmington, NC 28402
SUBJECT:
FIRSTENERGY NUCLEAR OPERATING COMPANY - REQUEST FOR WITHHOLDING INFORMATION FROM PUBLIC DISCLOSURE FOR PERRY NUCLEAR POWER PLANT UNIT 1 (TAC NO. MC2599)
Dear Ms. Harding:
By letter to the U.S. Nuclear Regulatory Commission (NRC) dated April 5, 2004, FirstEnergy Nuclear Operating Company submitted an affidavit dated October 3, 2003, executed by Margaret E. Harding, in which you requested that the information contained in the following document be withheld from public disclosure pursuant to Title 10 of the Code of Federal Regulations (10 CFR), Part 2, Section 2.390: Additional Information Regarding the Cycle Specific SLMCPR For Perry Unit 1 Cycle 10.
A nonproprietary copy of this document has been placed in the NRC's Public Document Room and added to the Agencywide Documents Access and Management System Public Electronic Reading Room.
The affidavit stated that the submitted information should be considered exempt from mandatory public disclosure for the following reasons:
- a. Information that discloses a process, method, or apparatus, including supporting data and analyses, where prevention of its use by GNF-As competitors without license from GNF-A constitutes a competitive economic advantage over other companies;
- b. Information which, if used by a competitor, would reduce his expenditure of resources or improve his competitive position in the design, manufacture, shipment, installation, assurance of quality, or licensing of a similar product.
We have reviewed your application and the material in accordance with the requirements of 10 CFR 2.390 and, on the basis of your statements, have determined that the submitted information sought to be withheld contains proprietary commercial information and should be withheld from public disclosure.
Therefore, the version(s) of the submitted information marked as proprietary will be withheld from public disclosure pursuant to 10 CFR 2.390(b)(5) and Section 103(b) of the Atomic Energy Act of 1954, as amended.
M. Harding Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the documents. If the need arises, we may send copies of this information to our consultants working in this area. We will, of course, ensure that the consultants have signed the appropriate agreements for handling proprietary information.
If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the NRC. You also should understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information. In all review situations, if the NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure.
If you have any questions regarding this matter, I may be reached at 301-415-3965.
Sincerely,
/RA/
William A. Macon, Project Manager, Section 2 Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-440 cc: See next page
M. Harding Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the documents. If the need arises, we may send copies of this information to our consultants working in this area. We will, of course, ensure that the consultants have signed the appropriate agreements for handling proprietary information.
If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the NRC. You also should understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information. In all review situations, if the NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure.
If you have any questions regarding this matter, I may be reached at 301-415-3965.
Sincerely,
/RA/
William A. Macon, Project Manager, Section 2 Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-440 cc: See next page DISTRIBUTION:
PUBLIC PDIII-2 R/F WRuland GGrant, RGNIII GSuh FAkstuleqicz WMacon DClarke ADAMS ACCESSION NO.: ML043350180 OFFICE LA:PDIII-1 PM:PDIII-2 SC:SRXB-A SC:PDIII-2 NAME DClarke WMacon FAkstulewicz GSuh DATE 12/13/04 12/16/04 1/6/05 1/7/05 OFFICE RECORD COPY
Perry Nuclear Power Plant, Unit 1 Mary E. O'Reilly Carol OClaire, Chief, Radiological Branch FirstEnergy Corporation Ohio Emergency Management Agency 76 South Main St. 2855 West Dublin Granville Road Akron, OH 44308 Columbus, OH 43235-7150 Resident Inspector's Office Mayor, Village of Perry U.S. Nuclear Regulatory Commission P.O. Box 100 P.O. Box 331 Perry, OH 44081-0100 Perry, OH 44081-0331 Dennis Clum Regional Administrator, Region III Radiological Assistance Section Supervisor U.S. Nuclear Regulatory Commission Bureau of Radiation Protection 801 Warrenville Road Ohio Department of Health Lisle, IL 60532-4531 P.O. Box 118 Columbus, OH 43266-0118 Sue Hiatt OCRE Interim Representative Zack A. Clayton 8275 Munson DERR Mentor, OH 44060 Ohio Environmental Protection Agency ATTN: Mr. Zack A. Clayton Mr. Vernon K. Higaki P.O. Box 1049 Manager - Regulatory Affairs Columbus, OH 43266-0149 FirstEnergy Nuclear Operating Company Perry Nuclear Power Plant Chairman P.O. Box 97, A210 Perry Township Board of Trustees 10 Center Road 3750 Center Road, Box 65 Perry, OH 44081 Perry, OH 44081 Frederick van Ahn, Plant Manager Daniel Z. Fisher FirstEnergy Nuclear Operating Company Transportation Department Perry Nuclear Power Plant Public Utilities Commission P.O. Box 97, SB306 180 East Broad Street Perry, OH 44081 Columbus, OH 43215-3793 Mayor, Village of North Perry Joseph J. Hagan North Perry Village Hall Senior Vice President, Engineering and 4778 Lockwood Road Services North Perry Village, OH 44081 FirstEnergy Nuclear Operating Company 76 South Main Street Donna Owens, Director Akron, Ohio 44308 Ohio Department of Commerce Division of Industrial Compliance Mr. Lew W. Myers Bureau of Operations & Maintenance Chief Operating Officer 6606 Tussing Road FirstEnergy Nuclear Operating Company P. O. Box 4009 Perry Nuclear Power Plant Reynoldsburg, OH 43068-9009 P.O. Box 97, A290 10 Center Road Perry, Ohio 44081