July 2004 Exam 50-390/2004-301 Draft JPMs
ML042450272
Person / Time
Site: Watts Bar Tennessee Valley Authority icon.png
Issue date: 04/05/2004
From: Ernstes M
Operator Licensing and Human Performance Branch
To: Scalice J
Tennessee Valley Authority
References
-RFPFR, 50-390/04-301, ES-301, ES-301-1 50-390/04-301
Download: ML042450272 (192)


See also: IR 05000390/2004301

Text

--

Draft Submittal

WATTS BAR JULY 2004 EXAM

50-390/2004-301

JULY 23, & JULY 26-30,2004

ES-301

Administrative Topics Qdtline

Form ES-301-1

Describe activity to be performed:

Calculate target boron concentration for load escalation using Appendix

E Of Sol-62.02. (NEW) [G 2.1.25, 2.8/3.1]

Operating Test Number

Calculate QPPR using Surveillance instruction I-SI-0-21. (0) [G 2.2.12,

3.013.4J

Evaluate RADCON survey map to determine posting requirements. (D)

[G 2.3.1, 2.6/3.0]

Medical Emergency Response. (D) (6

2.4.39,

3.3)

NUREG-1021, Draft Revision 9

ES-301

Adminisbative Topics Outline

Form ES-301-1

Facility:

WATTS BAR

Date of Examination: 7/26 - 713012004

Operating Test Number

1 Conduct of Operations

1

Describe activity to be performed:

Calculate target boron concentration for load escalation using Appendir

E Of SOi-62.02. (NEW) [G 2.1.25, 2.8/3.1]

Obtain and verify controlled procedure copy using Curator1BSL.

(8)

[G 2.2.21, 3113.21

Calculate QPTR using Surveillance instruction 1-SI-0-21. (5) [G 2.2.12,

3,013.41

Radiation Control

Evaluate RADCON survey map to determine posting requirements. (B)

G2.3.1, 2.6/3.01

2iassify the event in accordance with the Radiological Emergency Plan

REP). -(NEW) [G 2.4.38, 4.01

NUREG-1021, Draft Revision 9

A. 1 .a ROISRO

Page 1 of 12

REGION II

INITIAL LICENSE EXAMINATION

ADMINISTRATIVE JOB PERFORMANCE MEASURE

A.1 .a RO/SRO JPMRADMIN

Calculate Target Boron Cb for Load Escalation

Using Appendix E of Sol-62.02

APPLICANT

EXAMlNER

A.1.a RBlSRO

Page 2 of 12

REGION lI

INITIAL LKENSE EXAMINATION

ADMINISTRATIVE JOB PERFORMANCE MEASURE

Task: Calculate Target Boron Cb for Load Escalation Using Appendix E of Sol-62.82

Alternate Path:

NIB

Facilitv JPM #:

New

KIA Ratinds):

G2.1.25

[2.8/3.1]

Task Standard:

Performer completes a calculation for Target Boron Concentration per Sol-62.02,

Appendix E Reactivity balance calculation. Target RCS Boron Concentration is

determined. Performer notifies SM/Unit Supervisor of the results.

Preferred Evaluation Location:

Preferred Evaluation Method:

Simulator

In-Plant -

Perform

X

Simulate ~

References: Sol-62.02, Boron Concentration Control, Rev. 39; NUPOQ, WCAP-16134,

Nuclear Parameters and Operating Package for Watts Bar Unit 1. Cycle 6,

Rev 0.

Task Number:

RO-062-SOI-62-016

APPLICABLE FOR: RO/SRO

Examiner:

I

NAME

SIGNATURE

DATE

COMMENTS

A. 1 .a ROlSRO

Page 3 of 12

ToolsiEsuipmenffPrece~ure~

Needed:

Latest revision of Sol-62.02

~

~

NUPOP for WBN Unit 1 Cycle 5

NOB for WBN Unit I

Ruler or straight edge.

Calculator

NOTE: START THIS JPM AT A LOCATiON WHERE PERFORMER HAS ACCESS

TO PROCEDURES (Simulator, Main Control Room, TIC or provide

performer with procedure).

READ TO OPERATOR

DIRECTION TO TRAINEE:

I will explain the initial conditions, and state the administrative task to be

performed. I will provide initiating cues and reports on other actions when

directed by you. Ensure you indicate to me when you understand your assigned

task. To indicate that you have completed your assigned task return the handout

sheet I provided you.

(NITIAL CONDITIONS:

The Unit is operating at 79% rated thermal Power.

Core average bumup is 13000 MWDiMTU

Control Bank "D" rods are at 190 steps.

RCS Boron Concentration is 615

Target Rod Position at 100% RTP will be 220 Steps on Control Bank "B"

Power will be raised 3% Der hour.

Xenon printout from REACTINW has been performed by an STA.

You are an extra Unit Operator.

INITIATING CUES:

Using the information provided, the SMlUnit SRO has directed you to calcuate

Target Boron Centration for raising power to 100% per Sol-62.01 Appendix E

"Reactivity balance Calculation"

rn

Determine the RCS Target Boron concentration.

a

Notify SMIUnit SRO of the RCS Target Boron Concentration.

A. 1 .a ROiSRO

Page 4 of 12

START TIME:

STEP 1:

STANDARD:

Obtain a copy of the instruction.

A copy of Sol-62.02 Appendix E "Reactivity Balance Calculation"

has been obtained.

EXAMINER'S CUE: Provide the applicant a copy of the instruction.

COMMENTS:

NOTE 1

One calculation is required for each major change. Calculation is

an approximation of Final Target Boron CB. Rough interpolation of

NuPop figures is acceptable and expected.

Dilution or Boration value for power change from P, YC to Pz YO

power in the time period T with rods moving from step position R1

to R2. (Subscript convention: 1 = current point, 2 = target point)

Evaluator Note. JPM Steps 2 through 6 evaluate applicants completion

of the first page of Appendix E.

NOTE 2

STEP 2: [I]

CALCULATE target boron concentration by performing the

following:

Obtains: Current RCS Boron CB:

PPM.

CUE: When CHEM LAB notified, acknowledge request, then report

current RCS Boron Concentrations is 615

STANDARD: Applicant contacts Chem Lab for current boron concentration

(Value provided on task assignment sheet.

COMMENTS:

SAT

_____ UNSAT

-

SAT

-

UNS T

    • Italicized Cues Are To Be Used Only If JPM Performance is Being Sirnuiated.

A.1.a RQiSRO

Page 5 of 12

STEP 3:

Obtains: Core Burnup:

MWDIMTU

STANDARD: Applicant determibes current core burnup from task

assignment sheet. 'i 3000 MWDIMTU. (ICS point display

U7981 or Other ICs dispays that indicate core burnup Le.,

Xenon (Core burnup is provided on task assignment sheet).

COMMENTS:

STEP 4:

Obtains:

Current Reactor power = PI:

Target Reactor power = P2:

YO

%

Calculates: Total Reactor power change:

A%

STANDARD: Applicant determines current reactor power and target power

from information provided on assignment sheet. P I = 79%.

P2 =

assignment. Applicant determines total power change to be

-

21%.

Target reactor power was given on task

COMMENTS:

-

SAT

-

UNSAT

-

§AT

__ UNSAT

    • Italicized Cues Are To Be Used Only If JPM Performance is Being Simulat@d.

A.7.a R01SRO

Page 6 of 12

STEP 5:

0 btains:

Rate of Reactor Power change:

%Ihr

Number of hours to change power:

w-4

STANDARD: Applicant determines rate of reactor power change from task

assignment to be 3 YO per hour. Applicant calculates number

of hours projected to reach target power as 7 hrs.

COMMENTS:

STEP 6:

Qbtains:

Current Rod Position:

steps

Final Bod Position:

steps

STANDARD: Applicant determines final rod position from task assignment

as 220 Steps.. Applicant determines current rod position from

ICs or Control Board Step Counters (Value provided on task

assignment sheet). Value for current position is 190 steps.

COMMENTS:

-

SAT

-

UNSAT

-

SAT

-

U N SAT

    • italicized Cues Are TO Be Used On/y If JPM Performance Is Being Simulated.

A.1.a ROISRB

Page 7 of 12

CAUTION

Follow sign conventions explicity.

Evaluator Note. JPM Steps 7 through 11 evaiuate applicants completion

-

of the second page of Appendix E steps for Reactivity Balance.

STEP 7: Determines Ap Power Defect:

Power Defect 1 , ~ : From NUPOP, Figure 6-18, 19, or 20.

pcm PI3 -

pcm PD2 =

Pcm

Ap Power Defect

STANDARD: Applicant determines the PD1 for current power level is -2225

pcm (accept 2280 to 2250 pcm) from figure 6-20, and

determines PD2 for target power level as -2750 pcm (accept

2725 to 2775) from figure 6-20, and enters the values in

appropriate table locations. Applicant then calculates Ap

Power Defect by subtracting algebraically PD:! from PDI. The

value determined is S p c m (accept 500 to 550).

COMMENTS:

CRlTlCAb

STEP

-

SAT

-

UNSAT

    • italicized Cues Are To Be Used Oniy If JPM Performance Is Being .Simu/ated.

A.1.a ROISRO

Page 8 of 12

STEP 8: Determines Ap Xenon:

Xenonr: From WEACTW (either current conditions or projection to

initial condition).

pcm XEI.

Xenon2: From REACTW (projected over time period T).

pcm XE2.

NOTE: Xenon Values must be negative.

Applicant than calculates Ap Xenon by subtracting algebraically XE2

from XEl.

-2704.5 pcm XEr - -2568.5 pcm XE2 =

gcm

(current)

(Target)

Ap Xenon

STANDARD: Applicant determines the XE1 for current power level is -2704.5

pcm from Xenon REACTW printout, and determines XE2 fer

target power level as -2568.5 pcm from the same printout, and

enters the values in appropriate table locations. Applicant then

calculates Ap Xenon by subtracting algebraically XE2 from XE,.

The value determined is a

pcrn.

COMMENTS:

STEP 9 Determines Ap rods:

Rods 1, 2 : From NUPOP, Figure 6-24, or 25.

pcm Kods, -

pcm Rods2 =

pcm

(current)

(Target)

Ap Rods

STANDARD: Applicant determines the Rods1 for current rod position as 220

pcm (accept 205 - 235) from NUPOP Figure 6-25, and

determines Rods2 for target as a

(accept 0 - 35) pcm from

the same figure, and enters the values in appropriate table

locations. Applicant then calculates Ap Rods by subtracting

algebraicaily Rods2 from Rods,. The value determined is 215

pcm. (accept 280 - 230)

COMMENTS:

CRITICAL

STEP

_I SAT

UNSAT

CRITICAL

STEP

-

SAT

-

UNSAT

    • italicized Cues Are To Be Used Oniy If JPM Petformanee Ls B@hg Simulated.

STEP 10: Determines p boronl:

Current RCS Boron X 1000 + Inverse Boron Worth NUPOP, Figure

6-21).

Boron X (m

+

pcm/%Ap) =

Pcm

(current)

p BQRON,

STANDARD: Applicant enters m g p m for current boron concentration.

Applicant determines the inverse boron worth is

_1pcml%Ap

(accept 157 -159) from NUQOP Figure 6-21 for

the current boron concentration, and enters the values in

appropriate table location. Applicant then calculates p

BORON, by multiplying RCS boron concentration by the

product of 1000 pcm divided by current inverse boron worth

boron worth determined from figure 6-21 for the current RCS

boron concentration. p boron 1 value is calculated is minus

3897.338 pcm. (Accept -3872 to -4922)

p BORON,

COMMENTS:

A.1.a ROlSRO

Page 9 of 22

CRITICAL

STEP

-

SAT

-

UNSAT

    • italicized Cues Are To Be Used only If JPM Performance Is Being Simulated.

A.1.a ROiSRO

Page 10 of 12

STEP 11: Determines p boron2:

Calculates p boron;? by

Ap Power Defect + __ pcrn Ap Xenon - __ pcrn +

pcm (p BORON$, =

Pcm

p BORON2

STANDARD: Applicant calculates p boron;! by by algebraically

addinglsubtracting the change in power defect, change in

Xenon reactivity, change in reactivity due to rods and current

worth of RCS boron. The result of the calculation in reactivity

required by boron at the target power level. The values

previously calculated are entered into the table observing

proper signs.

+ s p c m (Ap Xenon)

- -

210 pcm (Ap Rods)

+ -3897.338 gcrn (p BORON1, = -3718.338 pcm

(Accept -3693 to -3743)

+ m p c m (Ap Power Defect )

p BORON2

COMMENTS:

Evaluator Note. JPM Steps 22 evaluate applicants completion of the

second page of Appendix E steps for Target PPM.

STEP 12: (

pcmpBORON2 X (

pprnl%Ap Inverse Boron

Worth +

pcrn/%Ap) =

P W

STANDARD: Applicant determinesTarget Boron Concentration by taking p

B0K0N2 times born worth and conversion factor. The target

boron concentration is calculated to be 586 pprn. (Accept 566

to 606)

COMMENTS:

CRITICAL

STEP

-

SAT

-

UNSAT

CRITICAL

STEP

-

SAT

-

UNSAT

    • /talicized Cues Are To Be Used Only I f JPM Performance Is Being Simuiated.

STEP 13:

NOTIFY SMlUnit SRO of RGS Parget Boron Centration

calculated.

EVALUATOR CUE: Role play as SMlUnit supervisor and acknowledge

report. Acknowledge request for independent

verification, State that this Admin JPM has been

completed. W e will stop here.

STANDARD: Applicant informs the SMlUnit Supervisor of the Target RCS

boron concentration that was calculated. Should also inform

him that acceptance criteria for this SI were not met.

COMMENTS:

__ SAT

-

UNSAT

END OF TASK

TIME STOP:

    • Italicized Cues Are TO Be Used Only If JPM Performance Is Being Sirnulafed.

APPLICANT CUE SHEET

(TO BE RETURNED YO EXAMINER UPON COMPLETION OF TASK)

DIRECTION TO TRAINEE:.

I will explain the initial conditions, and state the administrative task to be

performed. I will provide initiating cues and reports on other actions when

directed by you. Ensure you indicate to me when you understand your assigned

task. To indicate that you have completed your assigned task return the handout

sheet I provided you.

INlTlAL CONDITIONS:

The Unit is operating at 79% rated thermal Power

Core average burnup is 13000 MWDIMTU.

Control Bank D rods are at 190 steps.

RCS Boron Concentration is 615

Target Rod Position at 100% RTP will be 220 Steps on Control Bank D

Power will be raised 3% per hour.

Xenon printout from REACTINW has been performed by an STA

You are an extra Unit Operator.

INITlATlNG CUES:

Using the information provided, the SMlUnit SRO has directed you to calcuate

Target Boron Centration for raising power to 100% per SO!-62.01 Appendix E

Reactivity balance Calculation

Determine the RCS Target Boron concentration.

Notify SMlUnit SRO of the RCS Target Boron Concentration.

[REACTW -

TIME

(HRSO

.o

1 .o

2.0

3.0

4.0

5.0

6.0

7.0

'VERS WB2.11

POWR

79.0

82.0

85.0

88.0

91 .o

94.0

97.0

100.0

(c/o)

XENON CALCULATION

WATTS EAR UNIT 1 CYCLE 6

BOL NIX XENON DATA

XE

I

(% EQ)

(% EQ)

93.0

79.0

92.6

79.3

92.0

79.9

91.2

80.9

90.4

81.7

89.6

82.9

88.9

84.3

88.3

85.9

XE

WORTH

(PCM)

-2704.5

-2693.2

-2674.9

-2652.9

-2629.7

-2607.1

-2586.4

-2568.5

DEL XE

WORTH

.o

11.3

18.3

22.0

23.2

22.6

20.7

17.9

( P W

JPMRADMIN A.1.b

Page 1 of 8

REGION II

INITIAL LICENSE EXAMINATION

ADMlNlSTRATlVE JOB PERFORMANCE MEASURE

A.l .b JPMRADMIN

OBTAIN AND VERIFY CONTROLLED PROCEDURE

COPY USING CURATOR

APPLICANT

EXAMINER

JPMRADMIN A.l.b

Page 2 of 8

REGION ll

INITIAL LICENSE EXAMINATION

ADMINISTRATIVE JOB PERFORMANCE MEASURE

Task: OBTAIN AND VERIFY CONTROLLED PROCEDURE COPY USING CURATOR

Alternate Path: NIA

Facilitv JBM #:

New

KIA Ratinds):

2.1.21

[3.2/3.2]

Task Standard:

References: SPP-2.3 "Document Control" Rev. 5 Section 3.1 1 and 3.12.

Task Number:: AUO-119-SSP-2.55-004

APPLICABLE FOR: AUOIROISRO

10CFR55.45:

Validation Time:

min. Time Critical: No

Verify for use a controlled procedure copy using CURATOR.

s-_s--_ss---------------------------------_------------------------------

.........................................................................

Applicant:

Time Start:

NAME

SSN

Time Finish:

Performance Ratinn: SAT __ UNSAT

~

Performance Time -

COMMENTS

JPMRADMIN A.1.b

Page 3 of 8

ToolslEquipnaenffPrscedures Needed:

Access to computer that has Curator (FYI) that can produce hard copies of documents.

NQTE: START THIS JPM AT A LOCATION WHERE PERFORMER HAS ACCESS

TO COMPUTER THAT HAS CURATOR ACCESS TO WBN. (Main Control

Room, TIC or Shift Clerk's Office, Tagging Office, Classroom).

NOTE TO EVALUATOR: If curator (FYI) program is presently open or minimized, have

the performer exit the program before assigning the task. At the completion of the task,

have the performer exit curator (FYI) program.

READ TO OPERATOR

DIRECTION TO TRAINEE:

I will explain the initial conditions, and state the admini:

stive task to be

performed. I will provide initiating cues and reports on other actions when

directed by you. Ensure you indicate to me when you understand your assigned

task. To indicate that YOU have completed your assigned task return the handout

sheet I provided you.

INITIAL CONDITIONS:

The Unit is at 100% rated thermal power.

SOl-65.02 "Emergency Gas Treatment System" is scheduled lo be performed later in

the current shift.

You are the CRO.

INITIATING CUES:

The Unit Supervisor has directed you to obtain a copy of Sol-65.02 from

CURATOR.

Inform the Unit Supervisor when you have obtained this copy.

JPMRADMIN A.1.b

Page 4 of 8

START TIME:

STEP 1:

STANDARD:

Locate a computer that has access to CURATOR.

Performer locates computer that has access to CURATOR

COMMENTS:

STEP 2:

Open CURATOR software program and access W E " Curator

files.

STANDARD: Performer selects the "FYS" icon and opens program, selects

WBNFYI Prod and enters OK. Performer enters Login ID end

password.

NOTE TO EVALUATOR: Login ID can also be LOOKUP or GUEST,

Password can also be LOOKUP or GUEST.

COMMENTS:

__ SAT

UNSAT

I

SAT

-

UNSAT

    • Italicized Cues Are To Be Used only If JPhi Performance Is Being Simulated.

JPMRADMIN A.1.b

Page 5 of 8

STEP 3:

Select procedure general from Search Class List to obtain

Search Screen.

STANDARD: Performer Selects PROCEDURE GENERAL from the search

class list by selecting it (Le., highlighting it) with mouse, then

either double click mouse or use forward arrow at top of file.

COMMENTS:

STEP 4:

Enter procedure number into search screen in the Procedure

Number field.

STANDARD: Performer enters Sol-65.02 into procedure number field of the

search screen and then depresses enter key or clicks on

forward arrow. Performer may enter SO1 into the procedure

type field and select advance! then scroll until procedure found.

Performer may enter a combination of letters into the

procedure title field (Le., CONTAIN EMERGENCY or GAS

etc.).

COMMENTS:

SAT

-

UNSAT

-

SAT

__ UNSAT

    • /falicked Cues Are To Be Used Only If JPM Performance Is Being Simukted.

STEP 5:

Selects procedure 501-65.02 from the document list and opens

document.

STANDARD: Performer advances to next step Folder Screen and selects

SOl-65.02 and advances to document screen and then

advances to open document.

NOTE TO EVALUATOR: Document will open in the appropriate format

COMMENTS:

for viewing. (WORD or IMAGENATION).

STEP 6:

Print a copy of Sol-65.02, retrieve copy from printer.

STANDARD: Performer simulates printing a copy of Sol-65.02.

EVALUATOR CUE: Simulate what you would do to print the document.

NOTE TO EVALUATOR: Do not allow print of document.

COMMENTS:

JPMRADMIN A.1.b

Page 6 of 8

-

SAT

-

UNS T

-

SAT

-

UNSAT

    • italicized Cues Are To Be Used Only if JPM Performance Is Being Simulated.

JPMRADMIN A.1.b

Page 7 of 8

STEP 7:

Inform Unit Supervisor that a copy of Sol-65.02 has been

obtained from CURATOR.

STANDARD: Performer Informs Unit Supervisor that a copy of Sol-65.02

has been obtained from CURATOR.

    • CUE:

Acknowledge report as Unit Supervisor using repeat

back.

    • CUE:

Have applicant close all windows opened and exit from

curator.

COMMENTS:

END OF TASK

TIME STOP:

-

SAT

-

UMSAT

    • Italicized Cues Are To Be Used Only If JPM Performance Is Being Simulated.

APPLICANT CUE S#ET

(PO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK)

DIRECTION TO TRAINEE:

I will explain the initial conditions, and state the administrative task to be

performed. I will provide initiating cues and reports on other actions when

directed by you. Ensure you indicate to me when you understand your assigned

task. To indicate that you have completed your assigned task return the handout

sheet I provided you.

INITIAL CONDITIONS:

The Unit is at 100% rated thermal power.

Sol-65.02 "Emergency Gas Treatment System" is scheduled to be performed later in

the current shift.

You are the CRO.

INITIATING CUES:

e

The Unit Supervisor has directed you to obtain a copy of Sol-65.02 from

CURATOR.

e

Inform the Unit Supervisor when you have obtained this copy.

JPMRADMIN A.2

Page 1 of 13

REGION II

INITIAL LICENSE EXAMINATION

ADMINISTRATIVE JOB PERFORMANCE MEASURE

A.2 JPMRADMIN

CALCULATE QPTR USING I-SI-0-21

APPLICANT

EXAMINER

JPMRADMIN A.2

Page2of13

REGION I1

INITIAL LICENSE EXAMINATION

ADMINISTRATWE JOB PERFORMANCE MEASURE

Task: CALCULATE QPTR USING 1-SI-0-21

Alternate Path:

NIA

Facility JPM #

3-QT-JPMADA.2-1

KIA RatincW:

2.1.12

[2.9/4.0]

Task Standard:

Quadrant Power Tilt Ratio has been determined per I-SI-0-21 Section 6.7 and

Attachment I. Acceptance criteria are determined to be NOT met due for N-42

Upper Detector and N-44 Upper Detector.

Preferred Evaluation Location:

Preferred Evaluation Method:

Simulator

In-Plant

~

Perform

X

Simulate -

References: 1-SI-0-21 "Excore QPTR & Axial Flux Difference" Rev. 13; Nuclear Operating

Book (NOB) A-2 Sheet 1 Rev 60, A-2 Sheet 2-4 Rev 59.

Task Number:: RO-092-SI-2-001

APLICABLE FOR: ROISRQ

10CFR55.45:

Validation Time:

13 min. Time Critical: No

-__---------_-------___s_________s_____s-----------------------------------

s--s---------s-----____-------------------------------------------------------

Applicant:

Time Start

NAME

SSN

Time Finish:

Performance Ratinn: SAT -

UNSAT __

Performance Time -

COMMENTS

Tools/EauicmenUProcedure% Needed:

Applicant Data Sheet

Latest revision of 1-SI-0-21

Latest revision of NOB Sheets A-2 (all four PR detector channels)

Calculator

JPMRADMIN A.2

Page 3 of 13

NOTE:

START THIS JPM AT A LOCATION WHERE PERFORMER HAS ACCESS

TO PROCEDURES (Simulator, Main Control Room, TIC, etc.).

NOTE TO EVALUATOR: Hand cut the Applicant Data Sheet along with the Applicants

Cue Sheet.

READ TO OPERATOR

DRECTIQN TO TRAINEE:

I wili explain the initial conditions, and state the administrative task to be

performed. I will provide initiating cues and reports on other actions when

directed by you. Ensure you indicate to me when you understand your assigned

task. To indicate that you have completed your assigned task return the handout

sheet I provided you.

lNlTlAL CONDITIONS:

The unit is operating at 1Q0% rated thermal power

AFD Monitor Alarm and QPTR alarms are out of service due to card problem in the

annunciator system.

1-SI-0-21 Excore QPTR &Axial Flux Difference SI is required to be performed every

12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> since both QPTR alarms are inoperabte.

Plant computer is not available for performing this SI.

You are a support CRO.

INlPlATlNG CUES:

Given the data that was just obtained from each power range channel upper and

lower detector currents, the Unit Supervisor directs you to perform Section 6.1

Excore QPTR Determination of 1-Si-(8-21. M&BE wiil NOT be utilized for data

measurements.

rn

Report the results to the Unit Supervisor when Attachment 1 and Section 6.1 have

been completed.

START TIME:

STEP 1:

Obtain a copy of the instruction.

STANDARD: A copy of I-SI-0-21 has been obtained.

EXAMINERS CUE: After the performer identified correct instruction,

the evaluator can provide a copy of the

instruction.

COMMENTS:

NOTE TO EVALUATOR: The following steps are from Section 6.1 of

1-SI-0-21

NOTE 1 Obtaining QPTR calculated values from the Process

Computer is the preferred method to check that the QBTR is

within Technical Specification limits. QPTR values are

obtained from Process Computer calculated computer

points for upper and lower radial flux tilt. These points are

available on the Tilting Factors disptay. The report may

be printed with turn on code TFREP.

NOTE 2 Up to one inoperable excore channel can be marked NIA if

THERMAL BOWER is c 75% RTP.

STEP 2: [Step I]

IF the process Computer is available, THEN PRINT the

Tilting Factors Report AND/OR PERFORM the QPTR

calculations using Attachment 1.

STANDARD: Performer goes to attachment I and commences

performance of attachment 1.

COMMENTS:

JPMRADMIN A.2

Page 4 of 13

~

SAT

-

UNSAT

-

SAT

__ UNSAT

    • Wicked Cues Are Tu Be Used only If JPM Performance Is Being Simu!aated.

JPMRADMIN A.2

Page 5 of 13

lOTE TO EVALUATOR: The following steps are from Attachment 1 of

1 -SI-Q-21

IOTE 1 Determining detector currents by measuring the voltage

across the detectors meter test points, using DVM, is the

IQTE 2

IQTE 3

most accurate method for measiring QPTR and for

determining the validity of a QPTR alarm.

Using detector current meter readings is another method to

quickly check that QPTR Is within limits. These meters are

not as accurate as the DVM readings and may produce

unacceptable results because: $)the meters on the 6

drawer may be scaled too high or (2) the meter may be

unstable due to drift or noise. When unacceptable results

are obtained OVM readings should be obtained, otherwise,

Step [I]

and [2] may be marked NIA if DVM not used.

Up to one inoperable excore channel can be marked NIA if

THERMAL P ~ W E R

is e 75% RTP.

TEP 3
[Step I] RECORD BVM information:

A.

TVA M&TE ID:

B.

Cal Due Date:

iBANDARB: Performer determine step in N/A based on initial conditions

for task performance and proceeds to the next step.

OMMENTS:

iTEP 4: [Step 21 ENSURE require M&PE is within its current calibration.

$ANDARB
Performer determines step is N/A based on initial conditions

for task performance and proceeds to the next step.

QMMENTS:

~

SAT

-

UNSAT

-

SAT

-

UNSAT

    • Italicized Cues Are To Be Used Only I f JBM Performance Is Being Simu%ated

JPMRADMIN A 2

Page 6 of 13

NOTE 1 The following determination may be made by measuring the

voltage across the 1000 ohm precision resistor in N E power

range drawer B. When using this method the Ohms Law

conversion from a millivolt measurement to a microamp

measurement only requires changing the unit designator (eg.,

280 millivolts converts to 280 microamps.

NOTE 2 Detector A is the TOP or UPPER Detector and Detector 13 is the

BOTTOM or LOWER detector on the NIS drawer El.

CAUTION

An inadvetent reactor trip may be prevented by ensuring

that no power range neutron high flux rate or power

range high flux channek are in the tripped condition

prior to taking EACH measurement in the NIS Power

Range Drawer 8.

STEP 4: [Step 31 DETERMINE the microamps for each upper and lower

excore detector on each NIS power range drawer B,

AND RECORD below:

STANDARD: Performer obtains the detector current microamp readings

from the handout given during task assignment and enters

the appropriate data into Attachment 1 step 3.

NOTE TO EVALUATOR: Values above in ( ) are detector currents from

handout.

COMMENTS:

-

SAT

UNSAT

    • italicized Cues Are To Be Used Only I f JPM Performance Is Being Simulated.

JPMRADMIN A 2

Page 7 of 13

NOTE: Rt and R b (detector calibration data) changes periodically

throughout the cycle. Current valu& arein NOB SheetA-2,

NIS Calibration Data.

STEP 5: [Step 41 OBTAIN and RECORD current values of Rt and Rb

(voltsimicroamps).

STANDARD: Performer obtains the detector current values from NOB

Sheets A-2 for the respective NIS Power Range Detectors

and records them in appropriate blocks on Attachment I

Step 4.

NOTE TO EVALUATOR: Values above in ( ) are detector currents from

respective NQB Sheets A-2.

COMMENTS:

-

SAT

-

UNSAT

    • !talicized Cues Are To Be Used Oniy if SPM Performance Is Being Simukated.

JPMRADMIN A.2

Page 8 of I 3

NOTE Reactor Engineering has developed a spreadsheet to ease the

calculations in this attachment. It is located on

\\\\KnxwbngfpG\\Voll \\RXEapps\\RXE files\\SI-0-21 .xIx. The test

director is responsible to verify that the formulas used in the

spreadsheet are correct.

STEP 6: [Step 51 CALCULATE calibrated output voltages by multiplying

the uncalibrated detector output currents by Rt or Rb

(as applicable).

A. Vt=ltxRt

6. Vb=ibXRb

...... -.

. __. ..

......

.

...i

LOWER DETKC'IOH

..... -.

........

T

'

T

P

E

R

DElECTOR

STANDARD: Performer calculates the calibrated output voltages [Step 31

by multiplying the respective detector's current reading

times resistance values [step 41 and records the results in

appropriate blocks on Attachment 1 Step 5.

COMMENTS:

-

SAT

I

UNSAP

    • Italicized Cues Are To Be Used Only If JBM Performance Is Being Simulated.

JPMRADMIN A.2

Page 9 of 13

STEP 7: [Step S] CALCULATE average calibrated output voltage for the

upper and lower detectors.

UPPER vt

LOWER vb

AVERAGE

(14.317+16.045+14.28+16

(15.053+19.293+14.669+1

.287)/4 = 15.232

5.479)/4 = 15.623

STANDARD: Performer calculates the average output voltages for the

upper detector by adding the respective upper detector's

calibrated output voltage readings [from Step 51 and

dividing the result by the number of channels in service.

This process is repeated for the lower detector using the

lower detector calibrated voltages. The results recorded in

appropriate blocks on Attachment 1 Step 6.

COMMENTS:

    • Etalicized Cues Are To Be Used Only If JBM Performance Is Being SirnuIated.

JPMRABMIN A.2

Page 10 of 13

STEP 8: [Step 71 CALCULATE QPTR values by dividing each detectors

(upper or lower) Calibration Output Voltage by the

average (upper or lower) Calibrated Output Voltage.

A. QPTRt = Vt + Avg Vt

B. QP-i-Rb = v b X Avg vb

STANBARB: Performer calculates QPTR values by dividing the

respective Calibrated Output Voltage [from step 51 by the

Average Calibrated Output Voltage for each NIS channel

detector [from step 61. The results recorded in

appropriate blocks on Attachment 1. Performer returns to

Section 6.1 Step 7.

COMMENTS:

NOTE TO EVALUATOR The following steps are from Section 6.1 of

I-si-0-21.

STEP 9: [Step 21 REVIEW the Upper (A) and Lower (B) QPTR values.

STANDARD: Performer reviews QPTR values from Attachment 1 Step 7.

COMMENTS:

-

SAT

_. UNSAP

§AT

-

UNSAP

    • /talicized Cues Are To Be Used Only If JPM Performance Is Being Simulated.

STEP 20: [Step 31

CHECK (4)

Acceptance Criteria.

ACCEPTANCE CRITERIA: All operable exeore

channels (upper (A) and lower(E3)) indicate a QPTR 2

1.02.

n YES NO

STANDARD: Performer determines that N-42 Upper Detector and N-44A

Upper Detector exceed 1 .Q2

QPTR. Performer then checks

NO statement.

COMMENTS:

STEP I 1  :

Inform the Unit Supervisor that Attachment 'i and Section

6.1 of 1-SI-0-21 has been completed and the resutts of the

QPTR.

STANDARD: Performer inform the Unit Supervisor of the completion of

Attachment 1 and Section 6.1 of I-SI-0-21 and reports that

acceptance criteria have not been satisfied. QPTR for N-42

Lower Detector is 1.047 and for N-44 Upper detector is

1.079 which exceed QPTR limit of 1.02.

EXAMINER'S CUE: Acknowledge report as Unit Supervisor, then

state We wi!l stop here.

COMMENTS:

END OF TASK

TlME STOP:

JPMRADMIN A.2

Page 11 of 13

SAT

-

UNSAT

-

SAT

-

UNSAT

    • /tallcized Cues Are To Be Used OR@ If JPM Performance Is Being Simulated.

APPLICANT CUE SHET

(TO BE RETURNED TO EXAMlNER UPON COMPLESlON OF TASK)

DIRECTION TO TRAINEE:

I will explain the initial conditions, and state the administrative task to be

performed. I will provide initiating cues and reports on other actions when

directed by you. Ensure you indicate to me when you understand your assigned

task. To indicate that you have completed your assigned task return the handout

sheet I provided you.

INlTlAL CONDITIONS:

The unit is operating at 100% rated thermal power

AFD Monitor Alarm and QPTR alarms are out of sewice due to card problem in the

annunciator system.

1-SI-0-21 Excore QPTR & Axial Flux Difference SI is required to be performed every

12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> since both QPTR alarms are inoperable.

Plant computer is not available for performing this SI

You are a support CRO.

INlTlATlNG CUES:

e

Given the data that was just obtained from each power range channel upper and

lower detector currents, the Unit Supervisor directs you to perform Section 6.2

Excore QPTR Determination of 141-0-21. M&TE will NOT be utilized for data

measurements.

e Report the results to the Unit Supervisor when Attachment 1 and Section 6.1 have

been completed.

APPLICANT DATA SHEET

(TO BE RETURNED TQ EXAMINER UPON COMPLETION OF TASK)

The foliowing microampere readings were taken from the Power Range

NCS detectors:

I b Detector Current

N-42A

I

368

386

I

N-438

I

369

385

I

I

N-448

I

371

386

I

JPMRADMIN A.3

Page 1 of 6

REGION

I NlTlAL LICENSE EXAM1 NATION

ADMINISTRATIVE JOB PERFORMANCE MEASURE

A.3 JPMRADMIN

Evaluate RADCON Suwey Map to determine posting

requirements

APPLICANT

EXAMINER

JPMRADMIN A.3

Page 2 of 6

REGION II

INITIAL LICENSE EXAMINATION

ADMINISTRATIVE JOB PERFORMANCE MEASURE

Task: Evaluate RADCON Survey Map to determine posting requirements

Alternate Path: N/A

Facilitv JPM #:

WA Ratinals):

2.3.1

[2.6/3.0]

Task Standard:

RO ADMIN JPM -Category 8.3

Candidate determines appropriate radiological posting requirements associated

with the attached RABCON survey map.

Preferred Evaluation Location:

Simulator 2

In-Plant __

Preferred Evaluation Method:

Perform

X

Simulate __

COMMENTS

ToolslEcruiDmenffProcedures Needed:

JPMRADMIN A.3

Page 3 of 6

BADCON survey map

Latest revision of SPP-5.1, 'Radiological Controls"

NOTE: START THIS JPM AT A LOCATION WHERE PERFORMER HAS ACCESS

TO PROCEDURES (Simulator, Main Control Room, TIC, etc.).

NOTE TO EVALUATOR: Hand out the Survey Map along with the Applicant's Cue Sheet.

READ TO OPERATOR

DIRECTION TO TRAINEE:

I will explain the initial conditions, and state the administrative task to be

performed. I will provide initiating cues and reports on other actions when

directed by you. Ensure you indicate to me when you understand your assigned

task. To indicate that you have completed your assigned task return the handout

sheet I provided you.

INITIAL CONDITIONS:

Plant is operating normally at power.

You are an NAUQ on shift.

INITIATING CUES:

Evaluate the provided RADCON suwey map and determine the appropriate

radiological posting requirements for this room.

Report the results to the Unit Supervisor.

JPMRADMIN A 3

Page 4 of 6

START TIME:

STEP I:

Candidate reviews materials given and may determines

references needed.

STANDARD: Candidate becomes familiar with materials. May refer to

SPP-5. T Radiological Controls.

COMMENTS:

STEP 2: Evaluation as Radiation Areas.

STANDARD: Candidate should determine the general area readings near

the bottom of the map (I00 mrem) the candidate should

identify the room as a High Radiation Area. (Candidate

may specify that the entire room is a Radiation Area and

the area where general area readings were 2 100 mrem

would be specifically posted as a High Radiation Area).

COMMENTS:

___ SAT

-

UMSAT

I

SAT

__ UNSAT

Vfalicized Cues Are To Be Used On/y I f JPM Performance Is Being Sirnuhied

STEP 3: Evaluation as Contaminated Area.

STANDARD: Candidate should also determine that the area where

smears 5, 6, 7, 8, 9, I O , 1 I,

12, and 13 were taken would

be posted as a Contaminated Area. These smears

indicated removable contamination > 1000 clprnllO0 cm2.

COMMENTS:

STEP 4: Results of the evaluation are reported to the Unit Supervisor.

STANDARD: Candidate reports results of the previous two steps.

EXAMINER'S CUE: Acknowledge report. as Unit Supervisor, then

state We will stop here.

CQMMENTS:

END OF TASK

TIME STOP:

JPMRADMIN A.3

Page 5 of 6

__ SAT

-

SAT

-

UNSAT

    • Italicized Cues Are To Be Used only If JPM Performance Is Being Simulated.

APPLICANT CUE SHEET

(TO BE RETURNED SO EXAMINER UPON COMPLETION OF TASK)

DlRECTlON TO TRAINEE.:

I will explain the initial conditions, and state the administrative task to be

performed. I will provide initiating cues and reports on other actions when

directed by you. Ensure you indicate to me when you understand your assigned

task. To indicate that you have completed your assigned task return the handout

sheet I provided you.

INITIAL CONDITIONS:

Plant is operating normally at power.

You are an NAUQ on shift.

iNlTlATlNG CUES:

Evaluate the provided RADCON survey map and determine the appropriate

radiological posting requirements for this room.

Report the results to the Unit Supervisor.

--_

/Survey # 042804-1

[Datflirne: 4/28/2004 14%

~-

WBTC Mock-up

-

JPMRADMIN A.4 80

Page 1 of 10

REGION II

INITIAL LICENSE EXAMINATION

ADMINISTRATIVE JOB PERFORMANCE MEASURE

A.4.RO JPMRADMIN

RESPOND TO A MEDICAL EMERGENCY IN

ACCORDANCE WITH EPIP-10

APPLICANT

EXAMINER

JPMRADMIN 8.4 RQ

Page 2 of 'IO

REGION II

INITIAL LICENSE EXAMINATION

ADMINISTRATIVE JOB PERFORMANCE MEASURE

Task: Respond To A Medical Emergency

Alternate Path:

N/A

Facility JPM #

3-QT-JPMADA.4-1

KIA Ratlnnls):

2.4.39

[3.3/3.1]

Task Standard:

Performer performs actions of Appendix A of PIP-IO, "Medical Emergency

Response".

Preferred Evaluation Location:

Preferred Evaluation Method:

Simulator

In-Plant ___

Perform

X

Simulate

~

References: EPIP-IO, "Medical Emergency Response", Rev. 18.

Task Number:

RO-100-501-100-011

APPLICABLE FOR: RO/SRQ

Examiner:

NAME

I

§IGNATURE

DATE

COMMENTS

JPMRADMIN A.4 RO

Page 3 Qf 10

SIMULATOR OPERATOR INSTRUCTIONS:

This JPM may be performed either on the simulator or in another location. If performed

on the simulator refer to the fullowing.

1. Initialize to any IC.

2. Acknowiedge all alams.

3.

Freeze sirnulator for duration of task performance.

4. NOTE: This JPM may be performed using a console booth instructor who acts

as personnel outside the main control room. Cues may be made by him as

indicated by the JPM.

SlMULATQR OPERATOR INSTRUCTIONS:

When directed by the evaluator, place phone call to the Horseshoe to initiate the

medical emergency:

Call the Horseshoe and state the following:

I want to report a medical emergency.

ToolslE~ui~menffPfocedures

Needed:

Latest revision of EPIP-10

JPMRABIISIN A.4 RO

Page 4 of 10

NOTE START THIS JPM AT A LOCATION WHERE PERFORMER HAS ACCESS

TO PROCEDURES (Simulator, Main Control Room, TIC or provide

performer wlth procedure).

READ TO OPERATOR

DIRECTION TO TRAINEE:

I will explain the initial conditions, and state the administrative task to be

performed. I will provide initiating cues and reports on other actions when

directed by you. Ensure you indicate to me when you understand your assigned

task. To indicate that you have completed your assigned task return the handout

sheet I provided you.

INITIAL CONDITIONS:

You are the Control Room Operator (CRO)

on shift.

You have received a telephone call reporting an onsite medical emergency.

INITIATING CUES:

Respond to the medical emergency in accordance with PIP-IO.

JPMRADMIN A.4 RO

Page 5 of 10

START TIME:

STEP 1:

Obtain a copy of the instruction.

STANDARD: A copy of EPIP-IO has been obtained.

EXAMINERS CUE: After the performer locates and obtains correct

instruction, the evaluator can provide a copy of the

instruction.

COMMENTS:

NOTE TO EVALUATOR: The following steps are from EPIP-10, Appendix

A.

Control room personnel will USE the following checklist in their RESPONSE to

an onsite medical emergency.

STEP 2: [Step A]

Obtain NAME of caller.

STANDARD: CRO requests name of caller and records on Appendix A.

CUE: State to the performer that your name is John Doe.

COMMENTS:

-

SAT

-

UNSAT

-

SAT

-

UNSAT

JPMRADMIN A.4 RO

Page 6 of 10

STEP 3: [Step B] LOCATION (Bldg., Elev., Column).

STANDARD: Performer requests the location of the caller and records on

Appendix A.

CUE: State to the performer that you are just south of the

station air compressors on elevation 708 in the

Turbine Building.

COMMENTS:

STEP 4: [Step C] Type of Medical Emergency.

STANDARD: Performer requests the type of Medical Emergency and

records on Appendix A.

CUE: State to the performer that you found a male victim lying

on the floor unconscious but has heartbeat and is

breathing.

COMMENTS:

STEP 5: [Step D] Number of Personnel Involved

STANDARD: Performer requests how many people involved and records on

Appendix A.

CUE: State to the performer: no other individuals are involved.

COMMENTS:

CRITICAL

STEP

-

SAT

-

UNSAT

CRITICAL

STEP

-

§AT

I_

UNSAT

-

SAT

UNSAT

JPMRADMIN A.4 RO

Page 7 of 10

STEP 6:. [Step E] Immediate Area Hazards (Radiological, Safety).

STANDARD: Requests if immediate hazards exist and records on

Appendix A.

CUE: State to the performer: no hazards exist in the area.

COMMENTS:

STEP 7: [Step F] Telephone number of Caller.

STANDARD: Request the telephone number of the caller and records on

Appendix A.

CUE: State to the performer that the phone number of the phone

you are calling from is 5555.

COMMENTS:

STEP 8: [Step G] ALERT and DISPATCH MERT PERSONNEL

STANDARD: Performer alerts and dispatches MER1 personnel.

CUE: As MERT personnel, acknowledge performers

communication.

COMMENTS:

CRITICAL

STEP

-

SAT

-

UNSAT

-

SAT

-

UMSAT

CRITICAL

STEP

-

SAT

-

UNSAT

JPMRABMIN A.4 RO

Page 8 of 10

STEP 9: [Step HI Make the foliowing plant announcement with public

address:

ATTENTION ALL SITE PERSONNL.

ATTENTION ALL SITE PERSONNEL.

A MEDICAL emergency has been reported. The MRT is

to ACTIVATE and RESPOND to the following LOCATION:

,I

STANDARD: Performer makes public address announcement and has

MERT respond to Turbine Building elevation 708, just south of

the station air compressors.

EXAMINIZRS CUE: If NOT being performed on the simulator, do NOT

allow performer to actually perform this

announcement. Ensure it is simulated.

COMMENTS:

STEP I O : [Step I]

CONFIRM that the Shift Manager (SM) has been notified.

STANDARD: Performer ensures the SM has been notified. (may make

phone call or announce to the control crew that a medical

emergency is in progress.)

    • CUE:

Acknowledge report as Shift Manager.

COMMENTS:

-

SAT

-

UNSAT

CRITICAL

STEP

-

SAT

-

UNSAT

JPMRADMIN A.4 80

Page 9 of 10

STEP 1 'i : [Step S] CONFIRM that the Fire Protection Section Duty Shift

Supervisor (Fire Brigade Leader) was notified by:

Radio or

Telephone (extension #331 I

or #3355) or

Pocket Pager #40566

STANDARD: Performer ensures the Fire Protection Section Duty ShiR

Supervisor was notified by Radio, Telephone, or Pocket Pager.

EXAMINER'S CUE: Do NOT allow performer to actually perform this

notification. Ensure it is simulated.

CUE: Acknowledge report as Fire Protection Section Duty Shift

Supervisor.

COMMENTS:

STEP 12: [Step MI CONFIRM1600RDINATE MERT response (via radio or

phone) until Incident Commander assumes control.

STANDARD: Performer confirmsicoordinate the MERT response until the

Incident Commander assumes control.

CUE: As Incident Commander, notify the performer that you

have assumed control of the emergency. We will stop

here.

COMMENTS:

END OF TASK

TIME STOP:

-

SAT

-

UNSAT

CRiTiCAL

STEP

-

SAT

-

UNSAT

APPLICANT CUE SHEET

(TO BE RETURNED TO XAMINER UPON COMPLETION OF TASK)

DIRECTION TO TRAINEE:

I will explain the initial conditions, and state the administrative task to be

performed. I will provide initiating cues and reports on other actions when

directed by you. Ensure you indicate to me when you understand your assigned

task. To indicate that you have completed your assigned task return the handout

sheet I provided you.

INITIAL CONDITIONS:

You are the Control Room Operator (CKO) on shift

You have received a teiephone call reporting an onsite medical emergency.

INITIATING CUES:

Respond to the medical emergency in accordance with PIP-10.

f

k

APPENDIX A

CONTROL ROOM OPERATOR MEDICAL RESPONSE CHECKLIST

onsite medicai emergency.

A. Obtain NAME of caller

0

B. LOCATION (Bldg., Elev., Coiumn)

0

C. Type of Medical Emergency

0

D. Number of Personnel Involved

0

E. Immediate Area Hazards (Radiological, Safety)

Bs

0

0

F. Telephone Number of Caller

H. Make the following plant announcement with public address:

G. ALERT and DISPATCH MERT PERSONNEL

"ATTENTION ALL SITE PERSONNEL."

"ATTENTION ALL SITE PERSONNEL."

"A MEDICAL emergency has been reported. The MERT is to

ACTIVATE and RESPOND to the following LOCATION: ..

1. CONFIRM that the Shift Manager (SM)

has been notified.

J. CONFlRM that the Fire Protection,Section Duty Shift

I7

Supewisw (Fire Brigade Leader) was notified by:

Telephone (extension #33t 1 or #3355) and Pocket Pager #40%6

K. CONFlRMlCOORDlNATE MERT response (via radio or phone)

0

until Incident Commander assumes control.

PAGE 8 of 24

REVISION I 8

REGION II

JPMRADMIN A.4 SRO Scenario 1

Page 1 of 20

INITIAL LICENSE EXAMINATION

JOB PERFORMANCE MEASURE

Admin A.4 /Scenario 1

Classify the Event per the REP (SGTR with Ruptured SG

Faulted Inside Containment)

APPLICANT

EXAMINER

JPMRADMIN 8.4 SRO Scenario 1

Page 2 of 20

EVALUATION SHEET

~ Task: Classify the Event Per The RP (SGTR With Ruptured SG Faulted Inside Containment)

Alternate Path: NIA

Facilitv SPM #:

New

KIA Ratinak):

009 '32.04 [3.8/4.0]

009 EK3.06 [3.9/4.01 009 EA2LM [3.8/4.3]

2.4.38 [2.2/4.0]

009 EA2.33 [3.3/3.%]

009 EK3.10 13.413.61

2.4.30 [2.2/3.6]

2.1.14 [2.4/3.3]

Task Standard:

The event is classified as an ALERT based on EAL 1.2.3- "RCS Barrier. SGTR that results in a

safety injection actuation OR entry into E-3." Notifications are made per EPIP-3.

Preferred Evaluation Location:

Simulator

X

In-Plant -

Perform

X

Simulate

~

References: PIP-1 "Emergency Pian Classification Flowpath", Rev. 21; EPIP-3 ALERT", Rev. 26;

Preferred Evaluation Method:

EPIP-8 "Personnel Accountability and Evacuation". Rev 20.

Task Number: SRO-113-EPIP-001

10CFR55.45: 11, 12, 13

APPLlCA5LE FOR: SRO

Applicant:

Time Start:

NAME

SSN

Time Finish:

Performance Ratinq: SAT __ UNSAT __

Performance Time __

Examiner:

/

NAME

SIGNATURE

BATE

COMMENTS

JPMRADMIN A.4 SRO Scenario 1

Page 3 of 20

SIMULATOR OPERATOR INSTRUCTIONS:

1. Phis JPM will commence from the point where simulator is frozen at the end of simulator

exam scenario 1

SIMULATOR OPERATOR INSTRUCTIONS:

1. Obtain copy of EPP-3 to facilitate role plays for contacts made by the performer.

2. Performer must use NRC ring down phone.

REQUIRED MATERIALS: EQIP-2 and EPIP-3

SAFETY CONSIDERATIONS: None

JPMRADMIN A.4 SRO Scenario 1

Page 4 of 20

ToolslEquiprnenffProcedures Needed:

Ensure clean copy of EPIP-3 and PIP-8 in all copies of Emergency instructions on the

Simulator Floor and in the file drawer of Unit Supervisors desk.

READ TO OPEFWTOR

DIRECTION TO TRAINEE:

I will expiain the initial conditions, and state the task to be performed. All control

room steps shall be performed for this JPM, including any required

communications. I will provide initiating cues and reports on other actions when

directed by you. Ensure you indicate to me when you understand your assigned

task. To indicate that you have completed your assigned task return the handout

sheet I provided you.

INITIAL CONDITIONS:

Simulator represents the current plant conditions.

Sirnulator operation is frozen

INITIATING CUES:

Using the current conditions, make the initial classification of the event per the

REP and make the required notifications.

Portions of this JPM are time critical.

JPMRADMIN 8.4 SRO Scenario 1

Page 5 of 20

START TIME:

STEP 1:

Refers to EPIP-I to determine level of event

STANDARD: Performer refers to PIP-I and declares an ALERT based

on EAL 1.2.3 RCS Barrier, SGTR that results in a safety

injection initiation OR entry into E-3. This must be

completed within 16 minutes of task assignment.

This step is critical to ensure proper activation of TVA

resources for event In progress.

COMMENTS: RECORD time that declaration was made:

STEP 2:

Implements EPIP-3, ALERT

STANDARD: EPIP-3, ALERT, is implemented.

COMMENTS:

CRITICAL

STEP

-

SAT

-

UNSAT

I

SAT

-

UNSAT

JPMRADMIN A.4 SRO Scenario 1

Page 6 of 20

NOTE 1

IF ongoing onsite Security events may present risk to the

emergency responders, THEN ... CONSULT with Security to

determine if site access is dangerous to the life and health of

emergency responders.

IF ongoing events makes site access dangerous to the life and

health of emergency responders WHEN activating EPS ...

SELECT STAGING AREA button on the terminal INSTEAD of

the EMERGENCY button. Offsite personnel will be directed to

the Training Center CR 19 (INC). Responders presently within

the Protected Area will monitor Plant Announcements and

report to the TCS or OSC as conditions permit.

NOTE 2

STEP 3:

[STEP I]

DIRECT Shift Personnel to activate the

Emergency Paging System (EPS) to staff the TSC and

Operations Support Center (OSC). Shift Personnel should

confirm activation and provide the 20 minute printed report

to the SM for review.

A

IF the EPS system fails, call the QDS, ringdown or (5-

751-1700) and have him activate the EPS.

5

IF the above methods of activating the EPS fail, Shift

Personnel must use the Radiological Emergency

Response Call Lists to staff the TSC and OSC. This

list is located in the EPS Manuai near the terminal.

STANDARD: Shift personnel are notified to activate the emergency

paging system (EPS)

to staff the TSC and Operations

Support Center (OSC) or EPS is activated in the control

room.

This step is criticai to ensure proper actiwation of TVA

resources for event in progress.

    • CUE: After the shift personnel are notified, acknowledge the

request to activate the Emergency Paging System.

COMMENTS:

CRITICAL.

STEP

-

SAT

UNSAT

JPMRADMIN A.4 SRO Scenario 1

Page 7 of 20

STEP 4:

[STEP 21 lNlPiATE Appendix A, Initial Notification

Information.

STANDARD: Appendix A is accurately completed.

COMMENTS:

NOTE: ODs should be notified witkin 5 minutes after declaration of the

~

event.

STEP 5:

[STEP 31 NOTiFY the ODs direct by OD% Ringdown or No.

5-751-1900 or 5-751-2495 and PROVIDE the information

from Appendix A.

IF the ODs cannot be contacted within I 0 minutes, the

Tennessee Emergency Management Agency is to notified of

the Radiological Emergency Plan activation by calling 9-1-

800-262-3300 or 9-1-675-741 -0001 or 9-1-800-262-3400.

STANDARD: The ODS is notified and provided the information on

Appendix A. This notification must be made within 5

minutes of event declaration.

Step is critical to ensure timely staffing of CECC and

notification of the appropriate state agencies.

EVALUATOR NOTE: DO NOT allow actual call to ODs. Ensure call is

to simulator instructor

    • CUE: (Booth Operator) Role play as the ODS and repeat

back the report.

COMMENTS: RECORD time that ODS was notified:

CRITICAL

STEP

-

§AT

__ UNSAT

JPMRADMIN A.4 SRO Scenario I

STEP 6:

[STEP 41 ANNOUNCE to the crew: AN ALERT is being

declared based on EAL 1.2.3,

RCS Barrier, SGTR.

I will

be the Site Emergency Director.

describing the event may vary.

Step is critical to alert crew to the declaration ofthe

ALERT and provide for tracking personnel.

STANDARD: The above announcement is made to the crew. Wording

CUE

COMMENTS:

After the crew is notified, acknowledge the report.

STEP 7:

[STEP 51 FAX Appendix A to the ODS. (# pre-

programmed or 5-751-8620), or TEMA at 9-1-615-242-

9635.

STANDARD: Appendix A is placed in the fax machine and transmission

simulated.

    • CUE: Do NOT allow fax to be transmitted.

COMMENTS.

Page 8 of 20

CRITICAL

STEP

-

SAT

-

UNSAT

-

SAT

-

UNSAT

JPMRADMIN A.4 SRO Scenario 1

Page 9 of 20

STEP 8:

[STEP 61 ANNOUNCE to the plant: "ATTENTION ALL

SITE PERSONNEL. ATTENTION ALL SITE PERSONNEL.

AN ALERT emergency is being declared based on EAL

1.2.3 "RCS Barrier, SGPR." Staff the TSC and QSG.

(Repeat)

STANDARD: A public address announcement for Plant Emergency

Response Personnel to staff the TSC and OSC is made

over the plant paging system. Wording describing the event

may vary.

Step is critical to alert all plant personnel of the REP

declaration and instructions staffing TSC and OSC.

COMMENTS:

CAUTION If there is any possibility of a radiological release, A

severe weather condition (such as a Tornado) or

security adversary attack, HOLD assembly and

accountability actions until these conditions have been

resolved. Do not send personnel into areas of

unknown radiological conditions or security risk

without first contacting Radiological Control (RADCON)

or Security.

CRlTlCAL

STEP

__ SAT

-

UNSAT

JPMRADMIN A.4 SRO Scenario 1

Page 10 of 20

NOTE TO Evaluator: Performance Steps 9 through 17 will only be

critical if the decision was made to initiate assembly

and accountability.

If assembly & accountability is not being performed

than go to JPM STEP 18 after JPM Step 9 is completed.

STEP 9:

[STEP 71 EVALUATE piant conditions, and IF conditions

warrant, THEN INITIATE EPIP-8, Personnel Accountability

and Evacuation, Appendix D

STANDARD: Performer decides if conditions warrant initiating assembly

and accountability. If the decision is that conditions do

require assembly & accountability then the performer goes

to PIP-8 then return to EQIP-3 when directed for next step.

If the decision is that conditions do NOT require Assembly

& Accountability then performer proceeds to EQlP 3 step 8.

(Evaluation steps Page I 6 JPM Step 18)

COMMENTS:

EVALUATOR NOTE: The following steps are from EPIP-8 Appendix D.

STEP I O :

[STEP 11 The SMlSED has determined that conditions

require the activation of the assembly and accountability

siren system and process:

STANDARD: The performer determines that assembly and accountability

should be performed and continues to the next step.

COMMENTS:

-

SAT

-

UNSAT

SAT

UNSAT

JPMRADMIN 14.4 SRO Scenario 1

STEP 11 :

[STEP 21 NOTIFY Nuclearsecurity (NS)

at ext. 8464 or

8495 that:

A.

The assembly and accountability sirens will be

activated immediately. AND

B. NS should implement Appendix E.

STANDARD: The performer notifies Nuclear Security that assembly and

accountability sirens will be activated and Nuclear Security

should implement Appenix E.

This step is critical to ensure assembly card readers

are enabled.

    • CUE:

(Booth Operator) Role play as the Security and repeat

back the reportlrequest.

COMMENTS:

STEP -I2

[STEP 31 NOTIFY Radiological Control (RABCON) at ext

7865 That:

A.

The assembly and accountability sirens will be

activated immediately. AND

B. RADCON should implement Appendix F.

STANDARD: The performer notifies RABCQN that assembly and

accountability sirens will be activated and Nuclear Security

should implement Appenix F.

This step is critical to ensure assembly card readers

are enabled.

    • CUE:

(Booth Operator) Role play as the RADGON and repeat

back the reportlrequest.

COMMENTS:

Page 11 of 20

CRITKAL

STEP

-

SAT

-

UNSAT

CRlTICAL

STEP

-

SAT

-

UNSAT

JPMRADMiN A.4 SRO Scenario 1

STEP 13:

[STEP 41 MAKE a public address announcement similar

to: Attention all plant personnel, the site assembly and

accountability process has been initiated. All personnel

report immediately to your assigned assembly areas.

(Repeat)

STANDARD: A public address announcement for Plant Assembly &

Accountability is made over the plant paging system.

Wording of this announcement may vary.

StSP is critical to alert all plant that personnel assembly

& accountability is being conducted.

COMMENTS:

STEP 14:

[STEP 51 ACTIVATE the assembly and accountability

sirens.

STANDARD: The performer pushes assembly alarm EVAC AUTO or

EVAC MANUAL push button.

This step is critical to activate assembly &

accountability alarm.

COMMENTS:

Page 12 of 20

CRITICAL

STEP

-

SAT

-

UNSAP

CRITICAL.

STEP

-

SAT

-

UNSAB

JPMRABMIN A.4 SRO Scenario 1

Page 13 of 20

STEP 15:

STANDARD:

COMMENTS:

[STEP SI WHEN the Assembly and Accountability Sirens

have completed the 3-minute cycle and silenced, THEN

MAKE a PA announcement similar to:

"Attention all plant personnel, the site assembly and

accountability process has been initiated. All personnel

report immediately to your assigned assembly areas and be

accounted for".

(Repeat)

After the sirens have silenced, a public address

announcement for Plant Assembly & Accountability is made

over the plant paging system. Wording of this

announcement may vary.

-

SAT

-

UNSAT

JPMRADMIN A.4 §BO Scenario 1

Page 14 of 20

NOTE: IF at any time during the assembly and accountability

process RADCON determines that radiatfon guidelines

for an assembly area@) have been exceeded, THEN

REQUEST NS to re-locate affected personnel to another

assembly area OR evacuate affected personnel offsite.

STEP 16:

[STEP 71 NOTIFY Central Emergency Control Center

(CECC) Director either by the direct ring-down telephone in

the TSC or at ext. 751-1614. OR

If the CECC Director can not be reached, notidy the

Operations Duty Specialist (ODS) at ext. 751-1700 that:

A.

The assembly and accountability sirens have been

activated. AND

i3. WBN EPlP-8 is currently being implemented for

assembly and accountability.

STANDARD: The CECC director or the ODS has been notified that

assembly and accountability is being conducted at Watts

Bar and that the sirens have been activated.

    • CUE:

(Booth Operator) Role play as the CECC Director or

ODS and repeat back the reportlrequest.

COMMENTS:

STEP 17:

[STEP 81 REFER TO EPIP-2 through EPIP-5 for remaining

actions while Accountability is being performed.

STANDARD: The performer refers to EPIP-3, step 8 while Accountability

is being performed.

COMMENTS:

-

SAT

_- UNSAP

JPMRABMIN A.4 SRO Scenario 1

Page 15 of 20

Evaluator Note: The following steps are from EPIP-3

STEP 18:

[STEP 81 CALL FSADCON Lab (~7865)

and SAY: We are

in an ALERT, implement EPP-I4 Radiological Control

Response and CECC EPIP-9.

STANDARD: The WDCON Lab is notified to implement EPIP-14 and

CECC EPIP-9.

This step is critical to notify RADCON so proper

surveys, etc. are implemented.

(Booth Operator) Acknowledge the request to

implement EPIP-14 and CECC PIPS.

    • CUE:

COMMENTS:

STEP 19:

[STEP 91 IF there are personnel injuries, IMPLEMENT

WBN EPIP-IO, Medical Emergency Response.

STANDARD: Performer determines that it is NOT necessary to

implement EPIP-10.

    • CUE:

Inform the performer that there are NO personnel

injuries.

COMMENTS:

CRiTlCAL

STEP

-

SAT

-

UNSAT

-

SAT

-

UNSAK

JPMRADMIN A.4 SRO Scenario 1

Page 16 of 20

NOTE: Security and Access Control will be implemented

through PIP-31, Security and Access Control.

STEP 20:

[STEP 101 NOTIFY Duty Plant Management in

accordance with SPP-3.5, AND PROVIDE ALEKT

Notification information.

STANDARD: Duty Plant Manager is provided the Appendix A information.

This step is critical as it alerts plant management to

REP activation.

    • CUE:

(Booth Operator) Role play as the Duty Plant Manager

and acknowledge the report.

COMMENTS:

STEP 21:

[STEP 111 EVALUATE the need to implement PIP-13,

Initial Dose Assessment for Radiological Emergencies, for

a dose projection if radioactivity is being released through

normal plant release paths.

STANDARD: The performer determines whether or not EPIP-13 is to be

implemented. Either decision is acceptable.

    • CUE

(Booth Operator) If RADCON is notified to implement

EPlP-13, acknowledge the report.

COMMENTS:

CRlTlCAL

STEP

I

SAT

-

UNSAT

I

SAT

-

UNSAT

JPMRADMIN A.4 SRO Scenario 1

Page 17 of 20

STEP 22:

[STEP 121 RECEIVE Confirmation call from the OD§ (to

verify notification of the State of Tennessee) (MA this step,

if the state was contacted directly).

STANDARD: The performer determines whether or not ODS has notified

the State of Tennessee of REP Activation.

"*CUE:

(Booth Operator) Role play as the ODS and report that

the State of Tennessee has been Notified of REP

Activation at Watt Bar Nuclear Plant.

COMMENTS:

-

SAT

-

UNSAT

JPMRADMIN A.4 SRO Scenario 1

Page 18 of 20

NRC notifisation should be made as soon as practicable

but within one hour of ALERT declaration. Whenever

NRC requests, a qualified person must provide a

continuous update to NRC Operations Center.

EVALUATOR NOTE: DO NOT allow actual call to NRC. Ensure call is

STEP 23:

[STEP 131 NOTiFY the NRC, using designated NRC

phone (ENS), of plan activation. The following commercial

numbers are for the NRC Operations Center.

9-2-301-826-51 00 (MAIN)

9-1 -301 -951 -O550 (BACKUP)

9-1 -301 -81 6-51 51 (FAX)

STANDARD: The NRC is notified of plan activation using designated line.

This step is criticar as it alerts NRC to REP activation.

EVALUATOR NOTE: DO NOT allow actual sal! to NRC. Ensure call is

to simulator instructor.

    • CUE:

(Booth Operator) Role play the NRC and acknowledge

the report.

1 COMMENTS:

CRITICAL

STEP

I

SAP

-

UNSAT

JPMRADMIN A.4 SRQ Scenario 1

Page 19 of 20

STEP 24:

[STEP 141 NOTIFY the NRC Resident Inspector by calling

1776 and PROVIDING the information on Appendix A.

STANDARD: The NRC Resident Inspector is provided Appendix A

information.

This step is critical as it alerts NRC to RP activation.

EVALUATOK NOTE: DO NOT allow actual call to NRC Resident.

Ensure call is to simulator instructor.

(Booth Operator) Role play the NRC Resident and

acknowledge the report.

    • CUE:

EVALUATOR NOTE: Give the following cue to performer when the

performer completes the call to the NRC Resident

Inspector:

Role play and report that the TSC is staffed, and that

the SED will be coming to the control room $or a

turnover of SED duties. W e will stop here.

  • "CUE:

COMMENTS:

END OF TASK

TIME STOP:

CRITICAL

STEP

-

§AT

-

UNSAT

APPLICANT CUE SHEET

(TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK)

DIRECTION TO TRAINEE:

I will explain the initial conditions, and state the task to be performed. Ail control

room steps shall be performed for this JPM, including any required

communications. I will provide initiating cues and reports on other actions when

directed by you. Ensure you indicate to me when you understand your assigned

task. To indicate that you have completed your assigned task return the handout

sheet I provided you.

INITIAL CONDITIONS:

Simulator represents the current piant conditions.

Simuiator operation is frozen.

INITIATING CUES:

Using the current conditions, make the initial classification of the event per the

REP and make the required notifications.

Portions of this JPM are time critical.

ES-301

Control Roomh-Plant Systems Outline

Form 3-301-2

Facility. Watts Bar

Exam Level (circle one-/

SRO(I) / SRO(U)

Date of Examination: 7/26 - 713012004

Operating Test No.:

/I

System I JPWI Title

a. JPMF?018A, Perform a Boration of RCS During ATWS per I

8,

S, A I

1

//

11

FR-S.I.

7

b. JPMROZA, Place Excess Letdown In Service per SOI-

62.81,

1 c. JPMR071A, Align SI Pumps for Hot Leg Recirculation per

ES-I .4.

! 1 g. JPMO42ATransfer RCP Board from Normal to Alternate

I

N, S, L

1

6

I/

h. JPMR044, Align of the Upper Cntmt Monitor to the Lower

H

Cntmt From the MCR.

a. JPMA024, Isolate the RCP Seal Injection and Thermal

Barrier per ECA-0.0.

b. JPMA034, Reset the TBAFW Pump (after mechanical

overspeed) per Sol-3.02

dified from bank, (N)ew, (A)Mernatts path, (C)ontroi

NUREG-1021, Draft Revision 9

-

ES-301

Control Roomlln-Plant Systems Outline

Form ES-301-2

Facility: Watts Bar

Exam Level (circle one): RO I SRO(I)@

Control Room Systems (8 for RO; 7 for SRO-I; 2 or 3 for SRO-U)

Date of Examination: 7/26 - 7/30/2004

Operating Test No.:

System / JPM Title

FR-S.1.

c. JPMR0718, Align SI Pumps for Hot beg Recirculation per

ES-1.4.

3

I

I

c.

JPMl29A, Return the PRT to Normal per 501-68.01.

D, S, A

5

d

e.

h.

I

I

In-Plant Systems (3 for RO, 3 for SRO-I, 3 or 2 for SRO-U)

a

JPMA024, Isolate the RCP Seal Injection and Th

Barrier per ECA-0 0

JPMAOOIB.. Perform Local Restart of Control and Service

Air Compressors per AOI-10

b

C

  • Type Codes: (D)irect from bank, (M)sdified from bank, (N)ew, (A)lternate path, (C)ontrol

room, (S)imulator, (L)ow-Power, (R)CA

_II

NLIREG-1021, Drat? Revision 9

_____

ES-301

Control Roomlln-Plant Systems Outline

Form ES-381-2

Facility: Watts Bar

Date of Examination: 7/26 - 7/3012004

Exam bevel (circle one): RO

SRO(U)

Operating Test No.:

A

System / JPM Title

b. JPMR022A, Place Excess Letdown In Service per SOI-

62.01.

I

c. JPMR071A, Align SI Pumps for Hot Leg Recirculation per

ES-1.4.

11 d. JPMR075, Remove 1 RCP from Service (<P-8) per AOI-5.

~

~~

e. JPM129A, Return the PRT to Normal per SOI-68.01.

(1 g. JPM042A, Transfer RCP Board from Normal to Alternate

a. JPMA024, Isolate the RCP Seal Injection and Thermal

b. JPMA034, Reset the TDAFW Pump (after mechanical

overspeed) per Sol-3.02

6. JPMAOOIB, Perform Local Restart of Control and Service

I

Air Compressors per AOI-10.

  • Type Codes: (D)irect from bank. (M)odified from bank, (N)ew, (A)iternate path, (C)ontrol

I room, (S)irnulator, &)ow-Power, (R)CA

NUREG-1021. Draft Revision 9

B.1.a ROlSRO

Page 1 of 10

REGION II

INITIAL LlCENSE EXAMINATION

JOB PERFORMANCE MEASURE

B-1 .a RQlSRQ JPMROl8A

Perform Boration Of The RCS During An ATWS

Per FR-S.1

APPLICANT

EXAMINER

B.1.a RO/SRO

Page 2 of 40

REGION II

INITIAL LICENSE EXAMINATION

JOB PERFORMANCE MEASURE

Task: Perform Boration Of The RCS During An ATWS Per FR-S. 1

Alternate Path:

Emergency Borate Valve 1-FCV-62-138 cannot be open from MCR requiring

use of RNO to open varve lecaily. Local Operation also fails requiring use of

alternate boration valve 1-ISV-62-929.

3-OT-JPMR01BA Rev 6

Facilitv JPM #:

K/A Ratinafs):

029-EK3.Il [4.2/4.3] 023-EAT .02 [3.6*/3.3]

2.1.20 [4.3/4.2]

2.1.32 [4.2/3.4]

029EA1.03 [3.5*/3.2]

029-EA1.05 [3.7*/3.6*]

Task Standard:

Preferred Evaluation Location:

Preferred Evaluation Method:

Simulator X In-Plant __

Perform

X

Simulate ~

References: FR-S. 1, Nuclear Power Generation/ATWS, (Rev 16)

Task Number:: RO-113-FR-S.1-001

APPLICABLE FOR: ROl§RO

1QCFR55.45: 4, 5, 6, 7, 8, 12

Validation Time:

8 min.

Time Critical: No

The RCS has been borated per FR-S. 1 Step 4.

-_---_s-------------___s__s__________s__-----------------------------------

_____-_-____-_-____-__s_______s_______s_---------------------_-------------

Applicant:

Time Start:

NAME

SSN

Time Finish:

Performance Rating: §AT __ UNSAT _s

Performance Time __

COMMENTS

B.1.a ROlSRO

Page 3 of 10

SIMULATOR OPERATOR INSTRUCTIONS:

1. Initialize to IC 153.

2.

3.

Piace Hold Order on CCP IB-B.

Insert the foilowing over ride: ior rdihs82138a close to fail 1-FCVS2-I38 to the

closed position.

3. After performer indicates understanding of the task, place simulator to RUN

4. Place simulator to RUN after performer has been briefed.

5. This JPM has been pre-shot in IC#l53. Shouid IC#153 be erased or fail to perform

as expected then use the following set-up instructions:

Initialize in IC #5Q.

Insert remote function cvrQ3 off to remove power from CCP-1 B-B.

Insert override to fail 1-FI-62-139 as is: ier zaofi62439 as is.

Insert the following over ride: ior zdihs62138a close to fail 1-FCV-62-138 io the

Insert imf rpOlc ATWS Condition.

Insert ior zdific335 close

When RX Trip Signal is activated, trip the Turbine, start XJ AFW pump, wait for

After the Reactor Coolant Pump transfer occurs, FREEZE the simulator.

Place H.0. on CCP B.

After performer indicates understanding of the task. place simulator to RUN.

SIMULATOR OPERATOR INSTRUCTIONS:

Step 10 of the JPM requires the following remote function to OPEN 1-lSV-62-929:

Pull to lock CCP ZB-B.

closed position.

PC5 to trip and dear horns and annunciators.

mrf cvrlO open for 1-ISV-62-929

B.l .a R01SR0

Page4of40

TQsls/EttUiplrrsent/Proceelures Needed:

Ensure clean copy of FR-§.I in ail copies of Functional Restoration Guidelines on the

Simulator Floor.

READ TO OPERATdR

DIRECTION TO TRAINEE:

I will explain the initial conditions, and state the task to be performed. All control

room steps shall be performed for this JPM, including any required

communications. I will provide initiating cues and reports on other actions when

directed by you. Ensure YOU indicate to me when you understand your assigned

task. To indicate that you have completed your assigned task return the handout

skeet I provided you.

INlTlAL CONDITkONS:

Unit in Mode 1 at 100% RTP

1-FI-62-139 BA TO BLENDER FLOW is OQS, being calibrated by 1Ms.

CCP I

B-B is out of sewice (hold order)

A valid Rx Trip First-Out Alarm (§/e /ow ievel) was received

No Rx Trip occurred.

E-0 was entered and transition made to FR-S.1.

The first three steps of FR-S.1 have been completed.

The OAC will monitor the Rods inserting.

You are the CRO.

iNlTlATlNG CUES:

You are to perform boration of the RCS per FR-S.1 Step 4.

You are to notify the Unit Supervisor when the borabion has been established.

E.1.a RO/SRO

Page 5 of 10

START TIME:

STEP 1:

Obtain a copy of the procedure.

STANDARD: A copy of FR-S.1 has been obtained.

COMMENTS:

-

SAT

I_ UNSAT

STEP 2:

[Step 41 INITIATE RCS boration:

a. ENSURE at least one centrifugal charging pump

RUNNING.

__ SAT

STANDARD: Charging Pump A is verified to be running by either Red light

on 1-HS-62-108A or Amps on I-El-62-108A.

_I UNSAT

COMMENTS:

STEP 3:

[STEP 4b] OPEN RWST outlet valves 1-LCV-62-135 and 'I-

LCV-62-136.

STANDARD: 1-HS-62-135A and I-HS-62-136A have been placed in the

OPEN position. Step is critical to provide RWST flow path

for boration of RCS.

EVALUATOR NOTE: Either one oftha 2 valves being opened will satisfy

this step.

COMMENTS:

CRITICAL

STEP

__ SAT

-

UNSAT

i

STEP 4:

[STEP 4cl

CLOSE VCT outlet valves 1 -bCV-62-132 and 1

LCV-62-133.

STANDARD:

1-HS-62-132A and 1-HS-62-133A have been placed in the

CLOSE position.

Step is critical isolate VCT from

operating CCP and ensure RWST boration source.

EVALUATOR NOTE: Either one sf the 2 valves being closed will satisfy

this step.

COMMENTS:

STEP 5:

[STEP 4d] OPEN BIT outtet values, 1-FCV-63-25 and 1-

FCV-63-26.

STANDARD: 1-MS-622% and 1-HS-62-26A have been placed in the

OPEN position. Step is critical increased boration flow

path to RCS.

EVALUATOR NOTE: Either one of the 2 valves being opened will

satisfy this step.

COMMENTS:

STEP 6:

[STEP 4el

CHECK BIT flow.

STANDARD: Flow is determined by use of 1-Fl-63-170

COMMENTS:

f3.Z.a ROlSRO

Page 6 of 10

CRITICAL

STEP

-

SAT

I

UNSAT

CRITICAL

STEP

-

SAT

-

UNSAT

-

SAT

-

UNSAT

B.1.a ROlSRO

Page 7 of 10

STEP 7:

[STEP 4fl

PLACE BA pumps in FAST speed.

STANDARD: Hand switches for boric acid pumps are been placed in the

fast speed position (1-HS-62-230D & -232D).

COMMENTS:

STEP 8:

[STEP 4g] Throttle OPEN emergency borate valve I-FCV-62-

138 to maintain boric acid flow greater than 35 gpm.

STANDARD: I-HS-62-138A (Emergency Borate Valve), has been placed in

the OPEN position AND Fl-62-137A has been checked for

flow > 35 gpm. FCV-62-138 will not OPEN and the RNO

column must be entered.

COMMENTS:

NOTE:

Steps 9 through 12 of this JPM are the RNO steps for FR-SI,

Step 4g

STEP 9:

[STEP 4g RNO] IF BA flow less than or equal to 35 gpm:

THEM:

e

Locally QPEN emergency borate valve Z-FCV-62-138

[blender station elev 71 31 OR

STANDARD: An AUO has been directed lo open 1-FCV-62-138.

    • CUE:

When notified as AUQ, acknowledge the report using

repeat back. Then report that 4-FCV-62-138 cannot be

opened locally from the push button or hand wheel.

COMMENTS:

SAT

-

UNSAT

-

UNSAT

I

SAT

-

UNSAT

5.l.a RO/SRO

Page 8 of 10

STEP 18:

[STEP 4g RNOJ a ALIGN manual boration:

1) Locally OPEN alternate boration valve 1 -ISV-62-929

[blender station eiev 7131.

STANDARD: An AUO has been directed to open 1-ISV-62-929. Step is

critical in that provides boration path from BAT to CCP.

When notified as AUO, acknowledge the report using

repeat back.

    • CUE:

Then report that you have opened I-ISV- 62-929

COMMENTS:

CONSOL OPERATOR NOTE: Use Remote Function Page CV to Open

1-62-929 or insert mrf cvrl0 open.

STEP 11:

[STEP 4g RNO] 2) OPEN blender BA supply I-FCV-62-140

STANDARD: 1-HS-62-140D has been placedkhecked in the OPEN

position.

COMMENTS:

STEP 12:

[STEP 4g RNQ] 3) MONITOR BA flow.

STANDARD: BA Flow is checked on 2-FI-62-139 at > 35 gpm or the AUO at

local station has been notified to check BA flow.

If AUO contacted, report the flow is 38 gpm.

    • CUE:

COMMENTS:

CRITICAL

STEP

-

SAY

-

UNSAT

-

SAT

-

UNSAT

-

SAT

-

UNSAT

STEP 13:

Notify the Unit Supervisor that the step 4 is complete.

STANDARD: The Unit Supervisor has been notified that Step 4 of FR-S.l

has been completed.

    • CUE:

When notified, acknowledge the report using repeat

back.

COMMENTS:

END OF TASK

TIME STOP:

B.1 a ROlSRO

Page 9 of 10

-

SAT

-

UNSAT

CANDEDATE CUE SHEET

(TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK)

DlRECTlQN PO TRAINEE:

I will explain the initial conditions, and state the task to be performed. All control

room steps shall be performed for this JPM, including any required

communications. I will provide initiating cues and reports on other actions when

directed by you. Ensure you indicate to me when you understand your assigned

task.

INITIAL CONDITIONS:

Unit in Mode 'I at 100% RTP

1-FI-62-139

%A TO BLENDER FLOW is OOS, being calibrated by IMs.

CCP 1 B-5 is out of service (hold order).

A valid Rx Trip First-Out Alarm (SIG low level) was received.

No Rx Trip occurred.

E-0 was entered and transition made to FR-§.I

The first three steps of FR-§.I have been completed.

The OAC will monitor the Rods inserting.

You are the CRO.

INITIATING CUES:

You are to perform boration of the RCS per FR-S.1 Step 4.

You are to notify the Unit Supemisor when the boration has been established.

B.7.b ROlSRO

Page 1 of 9

REGION ll

IN lTlAL LICENSE EXAM1 NATlO N

JOB PERFORMANCE MEASURE

B.l .b RQiSRO JPMR022A

Place Excess Letdown In Service Per SO!-62.01

APPLICANT

EXAMINER

B.1.b ROlSRO

Page 2 of 9

REGION II

INITIAL LICENSE EXAMINATION

JOB PERFORMANCE MEASURE

-

Task: Place Excess Letdown In Service Per $01-62.01

Alternate Path: N/A

Facility JPM #:

3-OT-JPMR022A Rev 2

WA RatinqW:

004 A 4.06 [3.6/3.1]

004 A 1 .I 1 [3.0/3.0]

004 A 2.22 [3.2/3.1]

2.2.30 [3.9/3.4]

2.1.23 [3.9/4.0]

004 A 2.22 [3.2/3.1]

Task Standard:

Excess Letdown has been placed in service per $01-62.01, Section 8.3

Preferred Evaluation Location:

Preferred Evaluation Method:

Simulator

In-Plant -

Perform

X

Simulate -

References: $01-62.01~ CVCS-Charging and Letdown, (Rev 46)

Task Number:: RO-062-$01-62-007

APPLICABLE FOR: RO/SRO

lOCFR55.45: 6, 12

Validation Time:

11 min. Time Critical: No

-_s-_____s-__--____----------------------------------------------~~--------

___________________--------------------------------------------------------

Applicant:

Time Start:

NAME

SSN

Time Finish:

Performance Ratina: SAT -

UNSAT __

Performance Time -

Examiner:

I

NAME

SIGNATURE

DATE

COMMENTS

B.1.b ROlSRO

Page 3 cf 9

SIMULATOR OPERATOR INSTRUCTIONS:

1, Initialize to IC 158.

2.

PLACE 1-FCV-62-59, EXCESS LETDOWN DIVERT in the DIVERT position.

3. Acknowledge all alans.

4.

Place simulator in FREEZE until the performer indicates an understanding of the

task.

5. NOTE: This JPM has been pre-shot in IC #158. Should IC #I58 be erased or fail

to perform as expected then use the following set-up instructions:

a. Initialize simulator to any at power maintained IC.

b. Isolate the following letdown and charging valves:

I-FCV-62-72

1-FCV-62-69

1 -FCV-62-70

1-FCV-62-73

1 -FCV-62-90

1-FCV-62-74

1 -FCV-62-9 1

1-FCV-62-76

c. Place 1-FCV-62-93 in manual and stabilize seal flow at 8 to 9 gpm per RCP

seal.

d. PLACE 1-FCV-62-59, EXCESS LETDOWN DIVERT in the DIVRT position.

e. Acknowledge all alarms.

f. Place the simulator in FREEZE until the performer indicates an understanding

of the task.

g. After performer indicates understanding of the task, place simulator to RUN.

SIMULATOR OPERATOR INSTRUCTIONS:

None

B.1.b RB/SRO

Page 4 of 9

ToollslEauipmentlProcedures Needed:

Ensure clean copy of Sol-62.01 in all copies of System Operating lnstructions on the

Simulator Floor.

READ TO OPERATOR

DIRECTION TO TRAINEE:

I will explain the initial conditions, and state the task to be performed. All control

room steps shall be performed for this JPM, including any required

communications. I will provide initiating cues and reports on other actions when

directed by you. Ensure you indicate to me when you understand your assigned

task. To indicate that you have completed your assigned task return the handout

sheet I provided you.

INITIAL CONDITIONS:

The Unit is operating at power.

A small leak has been found on the normal letdown path

Letdown and Charging have been isolated.

You are the Operator at the Controls.

The RABCON Supervisor has been informed of the intent to establish Excess Letdown.

INITIATING CUES:

The Unit Supervisor has directed you to establish Excess letdown to the VCP per

procedure.

YOU are to notify the Unit Supervisor when the procedure has been compketed.

B.1.b RO/SRB

Page 5 of 9

START TIME:

STEP 1:

Obtain a copy of the procedure.

XANBARD: A copy of SOI-62.01, Section 8.3 has been obtained.

XIMMENTS:

--

CAUTION 1 RCP Seal leakoff flow must be within lit~& specified

in Appendix B of SOl-68.02, according to the #I

seal

differential pressure. As excess letdown is placed into

service, the #I seal leafoff flow could potentially fall

below the limits.

CAUTION 2 With normal Letdown isolated, C,

may only be raised

small amounts, to avoid excessive letdown to the

RCDT.

NOTE 1 RADCON Shift Supervisor should be notified of intent to place

NOT 2 Charging and RCP seal flow must be manually controlled.

excess Letdown in service.

STEP 2: [STEP I] OPEN Excess LDHX CCS valves:

NO MEN C U T

EXC LTDN HX OUT CI

STANDARD: 1-HS-70-143A and 1-HS-78-85A placed in the OPEN

position. Step is critical to establish cooling water flow to

the letdown heat exchanger.

COMMENTS:

__ SAT

__ UNSAT

CRlTlCAL

STEP

-

SAT

__ UNSAT

%.

STEP 3:

[STEP 21 CHECK I-HS-62-59A, CVCS EXCESS

LETDOWN DIVERT FLOW CNTL, aligned to one of the

following (N/A choice NOT aligned):

[a] NORM

[b] DIV

STANDARD: 1-HS-62-59A has been placed to the NORM position.

Step is critical to allow excess letdown to be aligned to

VCT per task assignment.

COMMENTS:

NOTE As VCT level rises, 1-LCV-62-118, .LETDOWN DIVERT TO

HUT, Auto Diverts to HUTS.

STEP 4:

[STEP 31 PERFORM the following:

STANDARD: I-HS-62-54A and I-HS-62-55A have been placed in the

OPEN positions. Step is critical to establish excess

letdown Row path from RCS to VCT.

COMMENTS:

E.1.b ROlSRO

Page 6 of 9

CRITICAL

STEP

-

SAT

-

UNSAT

CRITICAL

STEP

~

SAT

__ UNSAT

B.1.b ROlSRO

Page 7 of 9

CAUTION

xcess letdown design flow is 20 gpm. Preop W-2.2

determined that 1-FCV-62-56, CVCS EXCESS

LETDOWN FLOW CONTROL, can pass up to 50 gprn

(depending on RCS pressure and I-HIC-62-56A

output), which could cause higher than designed

excess letdown and CCS temperature.

NOTE

If excess letdown is being placed in service in preparation

for 1-TRl-62-901, flow may be maintained at a small value

to allow piping and the heat exchanger to remain at an

elevated temperature and pressure

step

EVALUATOR MOTE: Steps 5 and 6 are both part of the same instruction

STEP 5:

[STEP 41

SLOWLY OPEN I-HIC-62-56A, EXCESS

LTDN FLOW CONTROL,

STANDARD: 1-FCV-62-56 has been throttled open using 1 -HIC-62-568

Step is critical to establish excess letdown flow path

flow path to RCS.

COMMENTS:

STEP 6:

[STEP 41 to maintain Excess LD Hx Outlet temperature

below 206°F and Excess LD Hx CCS Qutiet temperature

below 135 "F

STANDARD: I-TI-62-58 on 1-M-5 has been checked below 206°F and

1-TI-70-86 on 0-M-27 has been checked below 135°F.

COMMENTS:

CRITICAL

STEP

SAT

-

UNSAT

-

SAT

-

UNSAT

B.1.b ROSRO

Page 8 of 9

STEP 7:

STANDARD:

    • CUE:

Notify the Unit Supervisor that the step 4 is complete.

The Unit Supervisor has been notified that Step 4 of FR-S.l

has been completed.

When notified, acknowledge the report using repeat

back.

COMMENTS:

END OF TASK

TIME STOP:

_I SAT

I

UNSAT

APPLICANT CUE SHEET

(TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK)

DIRECTION TO TRAINEE:

I will explain the initial conditions, and state the task to be performed. All control

room steps shall be performed for this JPM, including any required

communications. B will provide initiating cues and reports on other actions when

directed by you. Ensure you indicate to me when you understand your assigned

task.

INITIAL CONDITIONS:

The Unit is operating at power.

A srnali leak has been found on the normal letdown path.

Letdown and Charging have been isolated.

You are the Operator at the Controls

The RADCON Supervisor has been informed of the intent to establish Excess Letdown.

INITIATING CUES:

The Unit Supervisor has directed you to estabtisk Excess letdown to the VCT per

procedure.

You are to notify the Unit Supervisor when the procedure has been cornpkted.

B.l .c ao/sao

Page 2 of 1 1

REGION I1

INITIAL LICENSE EXAMINATION

JOB PERFORMANCE MEASURE

Task: Align SI pumps for Hot Leg Recirculation per ES-I .4

Alternate Path: N/A

Facility JPM #:

New

KIA Ratinn(s):

006 A 3.03 [4.1/4.1j

006 A 4.01 [4.1/3.9j 006 A 4.02 [4.0*/3.8]

006 A 4.04 [3.7*/3.6] 006 A 4.08 f4.214.31 2.1.20 [4.3/4.2]

2.1.23 [3.9/4.0]

2.1.31 [4.2/3.9]

The SI pumps have been aligned for hot leg recirculation per ES-1.4 Step 3

Task Standard:

Preferred Evaluation Location:

Preferred Evaluation Method:

Simulator

In-Plant __

References: E§-I .4

Transfer To Hot Leg Recirculation Rev. 9

Task Number:: 88-1 13-ES-1.4-001

APPLICABLE FOR: ROlSRQ

1OCFR55.45: 3, 6. 7, 8

Validation Time: 6 min.

Time Critical: No

Perform

X

Simulate -


_-_-__-----__-________sssss_______---------------_-_-------------_---

sss________-____________________________------------------------_----------

Candidate:

Time Start:

NAME

SSN

Time Finish:

Performance Ratincl: SAT -

UNSAT __

Performance Time -

Examiner:

/

NAME

SIGNATURE

DATE

E.1 .c ROlSRO

Page 3 of 11

SIMULATOR OPERATOR INSTRUCTIONS:

1.

initialize to IC # 159.

2.

Acknowledge all alarms and clear motor trip-out white lights.

3.

After performer indicates understanding of task, place simulator in RUN

4. This JPM has been pre-shot in IC # f59. Should IC # 159 be erased or fail to

perform as expected then use tRe foilowing set-up instructions:

Initialize to IC-50.

Insert imf thofa 100 @ 100% Severity ( Hot beg Break Loop 2).

stop RCPs.

Insert rfi sir14 to on (Restore power to FCV-63-1).

Insert rfi sir06 to on (Restore power to FCV-63-22).

Insert rfi sir0l to on (Restore power to C I A FCVs 63-67, 80, 98, 11 8)

Ensure I-FCV-1-153 (CCS to RHR Hx) is OPEN.

C6ose 1-HS-70-207 (CDWE Supply from Hdr 1B).

Ensure CCS flows and pressures stabilize.

Alarm Silence Generator Gore Monitor Alarm

Perform transfer tu Containment Sump, steps 1 through 28 of ES-I .3

Place simulator to FREEZE after transfer complete.

SIMULATOR OPERATOR INSTRUCTIONS:

None

[NOTE: Operator actions for this task are considered important by the WBN PRA with

respect to Core Damage Frequency.]

B.1.c RB/SRO

Page 4 of 11

Tool~lEquipmenffProcedures Needed:

Ensure clean copy of E§-1.4 in the simulator copies on the Simulator Floor.

READ TO OPERATOR

DIRECTION TO TRAINEE:

I will explain the initial conditions, and state the task to be performed. All control

room steps shali be performed for this JPM, including any required

communications. I will provide initiating cues and reports on other actions when

directed by you. Ensure you indicate tu me when you understand your assigned

task. To indicate that you have completed your assigned task return the handout

sheet I provided you.

INITlAL CONDITIONS:

A Large Break LOCA has occurred

Three (3) hours has elapsed since the Large Break LOCA occurred

E-? had been entered and all steps through 31b have been completed.

RHR has been aligned for hot leg recirculation per ES-1.4 Step 1.

You are the Operator at the Cuntrols.

INlTlATlNG CUES:

The Unit Supervisor directs you to align SI pumps for hot leg recirculation

per ES-1.4 Step 3.

You are to notify the Unit Supervisor when Step 3 is complete.

B.l.c ROlSRO

Page5of 11

START TIME:

STEP 1:

EXAMINER'S CUE: After the performer has identified the correct

instruction, the evaluator can provide a copy of

the instruction.

Obtain a copy of the appropriate procedure.

STANDARD: A copy of ES-1.4 has been obtained.

COMMENTS:

STEP 2:

[9 ALIGN SI pumps for hot leg recirc:

a. STOP SI pump A-A.

STANDARD: SI pump IA-A is stopped with 1-HS-63-IOA. Step is

critical since following step isolates the SI pump's

discharge. Recirc path to RWST was isolated in ES-

1.3.

COMMENTS:

SAT

I

UNSAT

CRITICAL

STEP

-

SAT

__ UNSAT

    • Italicized Cues Are To Be Used Only If JPM Performance Is Being Simulated.

B.2.c ROlSRO

Page 6 of 41

STEP 3:

[3.b] CLOSE Train A crosstie valve 1-FCV-63-152

STANDARD:

I-HS-63-152A is placed to the close position and green

valve position indicating light is verified ON, red valve

position light OFF on respective valve hand switch. Step

is critical to isolate SI pump A-A discharge from SI

pump 1B-B discharge.

COMMENTS:

STEP 4:

[3c] OPEN Train A hot leg injection valve 1-FCV-63-156.

STANDARD: 1-HS-63-1568 is placed to the open position and red valve

position indicating light is verified ON, green valve position

light OFF on respective valve hand switch. Step is critical

to align SI pump A-A discharge to RCS hot legs 1 & 3.

COMMENTS:

CRITICAL

STEP

__ SAT

-

UNSAT

CRITICAL

STEP

I

SAT

_I UNSAT

    • italicized Cues Are To Be Used Only MJPM Petformame Is Being Simulated.

6.l.c RO/SRO

Page 7 of 11

STEP 5: 3 4 START SI pump A-A.

STANDARD: SI pump 1A-A is started with 1-HS-63-1OA. Step is

critical to establish SI pump A-A flow to RCS hot legs 1

& 3.

COMMENTS:

STEP 6:

[3e]

ENSURE Train A hot leg flow on 1-FI-63-152.

STANDARD: Performer ensures Train A hot leg flow is indicated on 1-

FI-63-151 (SI PMP A FLOW).

COMMENTS:

STEP 7:

[3fl

STOP SI pump 3-B.

STANDARD: SI pump 15-5 is stopped with 1-HS-63-15A. Step is

critical since following step isolates the SI pumps

discharge. Recirc path to RWST was isolated in ES-

z .3.

COMMENTS:

CRITICAL

STEP

SAT

__ UNSAT

-

SAT

UNSAT

CRITICAL

STEP

-

SAT

-

UNSAP

    • Italicized Cues Are To Be Used Only If JPM Performance Is Being Simulafed.

B.1.c ROlSRO

Page 8 of 11

STEP 8:

[3gl CLOSE Train S crosstie valve 1-FCV-63-153.

STANDARD: 1-HS-63-153A is placed to the close position and green

valve position indicating light is verified ON, red valve

position light OFF on respective valve hand switch. Step is

critical to isolate SI pump 1B-B discharge from SI pump

1A-A discharge.

NOTE TO EVALUATOR: Step is critical if Operator has not closed the

COMMENTS:

Train A crosstie valve I-FCV-63-152. (JPM Step 3).

STEP 9:

[3h] OPEN Train 5 hot leg injection valve 1-FCV-63-259

STANDARD: 1-HS-63-153A is placed to the open position and red valve

position indicating light is verified ON, green valve position

light OFF on respective valve hand switch. Step is critical

to align SI pump A A discharge to RCS hot legs 2 i3 4.

COMMENTS:

1 COMMENTS:

CRITICAL

STEP

-.

SAT

-

UNSAT

CRETICAL

STEP

-

SAT

I

UNSAT

    • l&alicized Cues Are To Be Used Oniy If SPM Performance Is Being Simulated.

B.1.c ROlSRO

Page 9 of 11

[3i] START SI pump B-B.

STANBARD: SI pump 1B-B is started with 1-HS-63-158. Step is

critical to establish Si pump 1B-E3 flow to RCS hot legs

2 & 4.

COMMENTS:

STEP .% 1:

[3j] ENSURE Train E? hot leg flow on 4-Fi-63-20

STANBARD:

Performer ensures Train 5 hot leg flow is indicated on

f-FI-63-20 (SI PMP B FLOW).

COMMENTS:

STEP 12:

[3k] ENSURE power restored to 1-FCV-63-22 using

Appendix A (ES-1 A), 1-FCV-63-22 Breaker

Operation.

STANRARR: Performer AUO to restore power to 1 -FCV-63-22 in

accordance with Appendix A of ES-I .4.

    • CUE:

If asked, State to power was restored to 1-FCV-62-22

per Appendix D of E-I.

COMMENTS:

CRITICAL

STEP

-

SAT

-

UNSAT

-

SAT

I

UNSAT

-

SAT

-

UNSAT

    • Italicized Cues Are To Be Used Only If JPM Performance Is Being Simulated.

B.1.c RO/SRO

Page 10 of 11

STEP 13:

[31]

CLOW SI pump cold leg injection valve l-FCV-63-

22.

STANDARD: 1-HS-63-228 is placed to the close position and green

valve position indicating light is verified ON, red valve

position light OFF on respective valve hand switch.

    • CUE:

After valve has been closed, state to performer that

another operator will complete procedure, this JPM

is complete. We will stop here.

COMMENTS:

END OF TASK

TIME STOP:

    • Italicized Cues Are To Be Used On/y If JPM Performance Es Being Simdated.

APPLICANT CUE SHEET

(TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK)

DlRECTlON TO TRAINEE:

I will explain the initial conditions, and state the task to be performed. All control

room steps shall be performed for this JPM, including any required

communications. I will provide initiating cues and reports on other actions when

directed by you. Ensure you indicate to me when you understand your assigned

task. To indicate that you have completed your assigned task return the handout

sheet I provided you.

INITIAL CONDITIONS:

A Large Break LOCA has occurred.

Three (3) hours has elapsed since the Large Break LOCA occurred.

E-I had been entered and all steps through 31b have been completed

RHR has been aligned for hot leg recirculation per §-I

.4 Step 1.

You are the Operator at the Controls.

INlTlATlNG CUES:

The Unit Supervisor directs you to align SI pumps for hot leg recirculation

per 25-1.4 Step 3.

YOU are to notify the Unit Supervisor when Step 3 is complete.

B.1.c ROlSRO

Page I of 11

REGION ll

I M IT1 AL L I C E N S E EXAM I N AT f 0 N

JOB PERFORMANCE MEASURE

B-1 .c RO/SRO JPMR071 B

Align SI Pumps for Hot Leg Recirculation per ES-1.4

APPLICANT

--

-

EXAMlNER

B.1.d BOER0

Page I

of 13

REGION II

INITIAL LICENSE EXAMINATION

JOB PERFORMANCE MEASURE

B.1 .d ROISRO JPMR075

Remove One RCP From Service (P

P8) Per AOi-5

APPLICANT

EXAMINER

B.1.d RB/SRO

Page 2 of 13

REGION II

INITIAL LICENSE EXAMINATION

JOB PERFORMANCE MEASURE

Task: Remove One RCP From Service (<P-8) Per AOB-5

Alternate Path: No

Facility JPM #:

3-OT-JPMR075 Rev 2

WA Ratlngls):

017 AA 1.85 [3.813.8]

017 AA 1.13 [3.4/3.4] 017 AA 1.08 [3.0*/2.9]

019 AB 1.20 [2.7/2.7]

017 AA 1.22 [4.0/4.2]

2.4.4 [4.0/4.3]

Task Standard: Reactor Coolant Pump #3 has been shutdown without a Hi-Hi Steam

Generator Level occurring in #3 SIG per AOI-5.

Preferred Evaluation Location:

Simulator

In-Plant __

Preferred Evaluation Method:

Perform

X

Simulate __

Candidate:

Time Start:

NAME

SSN

Time Finish:

Performance Ratina: SAT ___ UNSAT

~

Performance Time -

COMMENTS

SIMULATOR OPERATOR INSTRUCTIONS:

1.

Initialize to IC # 162.

B.1.d ROlSRO

Page 3 of I 3

2. Acknowledge all alarms.

3. After performer indicates understanding of task, place simulator in run.

4. NOTE: This JPM has been pre-shot in IC #I62 Should IC #I62 be erased OF fail

to perform as expected then use the following set-up instructions:

a.

Initialize to I C 4

b.

Reduce load to = I 5  % and then place rod control into manual and transfer

steam dumps to pressure mode.

Reduce reactor and turbine load to approximately 9%

c.

d. Insert the following overrides:

ior zaoti6229 220

ior zaoti6230 220

e

ior an:ov:14c090 on

e. Place simulator to FREEZE.

f.

Place simulator in run when directed by the examiner.

SIMULATOR OPERATOR INSTRUCTIONS:

NONE

B.1.d ROlSRO

Page 4 of 13

ToolslEquipmentlProcedures Needed:

Ensure clean copy of AQt-5 in all copies of Abnormal Operating Instructions on the

Simulator Floor.

READ TO OPERATOR

DIRECTION TO TRAINEE:

I will explain the initial conditions, and state the task to be performed. All control

room steps shall be performed for this JPM, including any required

communications. I will provide initiating cues and reports on other actions when

directed by you. Ensure you indicate to me when you understand your assigned

task. To indicate that you have completed your assigned task return the handout

sheet I provided you.

INITIAL CONDITIONS:

Unit is at approximately 9% RTP

RCP #3 Pump Bearing Temperature is high

RCP lf3 Restart is planned after brief entry into containment.

You are the Operator at the Controls.

INITIATING CUE3

The Unit Supervisor has directed you to remove RCP #3 from service according

to A014 Section 3.2.

You are to notify the Unit Supervisor when ready to transition to Section 3.4, RCP

RESTART.

B.1 .d ROlSRO

Page 5 of 13

START TIME:

STEP 1:

Obtain a copy of the procedure.

STANDARD: A copy of AO8-5 Section 3.2 has been obtained.

EXAMINERS CUE: Afier fhe performer has identified the correct

instruction, the evaluator can provide a copy of the

instruction.

COMMENTS:

CAUTION

Following the shutdown of the RCP, the affected

loop Tavg may drop below Tcold in the active

loops. Tavg will recover to a value equal to

Tcold in the active loops fslbwing isolation of

feedwater to the affected SIG.

As affected SG RCS loop flow reverses, steam

flow will drop to zero. SG level will initially drop

due to shrink from loss of RCS heat input and

then rise if feed flow continues.

N O E S

Malfunctions addressed by this procedure require RCP

shutdown as soon as possible following a rapid load

reduction.

Exceeding any of the limits listed on Attachment 1 of this

procedure will require immediate shutdown of the affected

RCP.

a

Malfunctions resulting in high #I

seal leakoff will require

closing #I

seal return FCV following RCP coastdown.

-

-

SAT

UNSAT

    • ltaRicized Cues Are To Be Used Only If JPM Performance Rs Being Simulated.

B.1.d ROISRB

Page 6 of 43

NOTE TO EVALUATQR: :Evaluator wiEl need to give the following cue

iflwhen the candidate refers to the ICs screen for RCP #3:

    • CUE: State that the plant computer indications for seal

leakoff and pump bearing temperature are reading EJ

220 "F.

STEP 2:

[Step I] CHECK RCP immediate shutdown required.

  • REFER TO ATTACHMENT 1, RCP Immediate Shutdown

Criteria.

STANDARD: Performer refers to Attachment 1 and determines that

immediate shutdown is not required, but RCP bearing

temperature is = 220 T and seal outlet temperature is = 220

OF. by checking 1-TI-62-29 and 1-TI-62-30.

    • CUE:

When contacted role play as appropriate andstate that

shaff vibration is 8 mils and stable, and frame vibration

js 0.8 mils and stable.

COMMENTS:

STEP 3:

[Step 1 RNQ] MONITOR RCP immediate shutdown

Criteria:

  • IF RCP shutdown required, THEN PERFORM Step 2.

GOT0 Step3.

STANBARB: Performer determines that immediate shutdown is not

required, and proceeds to Step 3.

COMMENTS:

-

SAT

-

UNSAT

    • italicized Cues Are To Be Used Only If JPM Performance is Being Simulated.

B. 1 .d ROlSRO

Page 7 of 13

STEP 4:

[Step 31 REDUCE reactor power to less than 10% to ailow

removal of one RCP.

REFER TO AOI-39, Rapid Load Reduction.

REFER TO GO-5, Unit Shutdown from 30 % Reactor

Power to Hot Standby.

OR

STANDARD: Performer checks the following parameters and determines

that reactor power is less than $0% (also given in initial

conditions) and continues to next step:

Power Range channels 1-NI-41B, -428, -438,

-44B

LOOP AT I-T1-68-2D, -25D, 44D, -67D.

COMMENTS:

i

I

STEP 5:

[Step 41

DO NOT CONTINUE this instruction UNTIL

reactor power is iess than 10%.

~

STANDARD: The performer has determines that power is less than 15%

(from previous step) and continues to next step.

COMMENTS:

I

-

SAT

_I UNSAT

-

SAT

-

UNSAT

    • lfalicized Cues Are To Be Used Only If JPM Performance ls Being Simulated,

B.1.d ROlSRO

Page 8 of 13

STEP 6:

[Step 51

CHECK if RCP restart is possible:

0

Limiting condition for pump operation can be

immediately resolved.

STANDARD: The performer determines from initial conditions that

immediate restart is planned or performer checks with Unit

Supervisor to determine if RCP restart is possible.

If asked respond as Unit Supervisor that RCP

immediate resfart is planned foSrlowing containment

entry.

    • CUE:

COMMENTS:

STEP 7:

[Step 61

WHEN reactor power less than to IO%, THEN:

a. DEFEAT IOOP

signals to Tavg and AT auctioneer

units for affected loop.

STANDARD: 1-XS-68-2D and 1-XS-68-2M have been placed in the

LOOP 3 position and then pulled out. This step is critical

to remove loop three signals from Tavg and delta T

auctioneer units.

COMMENTS:

STEP 8:

[Step 6 continued]

b. ENSURE control rods in

MANUAL.

STANDARD: Rod Bank Select switch 92-RESS) on 1-M-4 has been

checked in MANUAL.

COMMENTS:

SAT

-

UNSAT *

CRITICAL

STEP

-

SAT

-

UNSAT

-

SAT

-

UNSAT

    • Italicized Cues Are To Be Used O ~ l y

If JPM Performance Is Being Simulated.

B.1.d ROlSRO

Page 9 of 13

STEP 9:

[Step 6 continued]

valve in MANUAL and raise level in affected SIG to 60% narrow

range.

C. PLACE affected loop bypass reg

STANDARD:

The #3 SIG level is raised to 80% narrow range by manually

opening the MFW bypass reg. Valve 1-LIC-3-90A.

COMMENTS:

STEP I O :

[Step 6 continued]

d. STOP affected RCP.

STANDARD: 1-HS-68-50BA has been placed in MANUAL position

(pushed in). 1-HS-68-50AA, #3 RCP Normal Bkr

Handswitch has been placed in STOP position. This step

is critical In stopping affected RCP.

COMMENTS:

-

SAT

_. UNSAT

CRITICAL

STEP

__ SAT

__ UNSAT

    • Italicized Goes Are To Be Used Onry If JPM Performance Is Being Simulated.

t3.l.d ROISRB

Page 10 of 13

NOTE TO EVALUATOR: Applies to following steps; Steam flow

indications are initially off-scale !OW, and will come on-

scale after the #3 RCP is stopped. Flow indications may

fluctuate on and off scale.

STEP 11:

[Step 71

MAINTAIN affected SG level on PROGRAM:

LOWER MFW flow as steam flow drops.

STANDARD: The feedwater flow to #3 S/G is reduced to prevent #3 SIG

level from rising by manualiy closing the MFW bypass reg.

Valve with 1-LIC-3-90A. This step is critical to prevent

SIG overfill as steam flow lowers from SIG #.

COMMENTS:

STEP 12:

[Step 81

ISOLATE blowdown from affected SG

STANDARD: #3 SIG blowdown is isolated by piacing I-HS-1-25/183 in

close. This step is critical to prevent SIG low level.

COMMENTS:

CRITICAL

STEP

-

UNSAT

CRITICAL

STEP

    • ltaiicized Cues Are TQ Be Used Qnly If JBM Performance Is Being Simulated.

B.1 d ROISRO

~

P x l 1 of 13

STEP 13:

[Step 91

a.

b.

CLOSE affected spray valve.

IF RCP 1 OR 2 was stopped, THEN:

PLACE affected pzr spray controller in MANUAL

STANDARD: Performer determines that #3 RCP was stopped; therefore

NO action is required by this step.

COMMENTS:

STEP 14:

[Step I O ] REFER TO Tech Specs:

LCO 3.4.1, RCS Press, Temp and Flow DNB Limits.

0

LCO 3.4.2,

RCS Minimum Temp For Critically.

LCO 3.4.4, RCS Loops Modes 1 and 2.

STANDARD: Performer refers to Tech Specs OR notifies US to refer to

Tech Specs.

    • CUE:

When performer refers to Tech Spec or Unit

Supervisor is directed to refer to Tech Spec, state that

the Unit Supervisor will research Tech Specs.

COMMENTS:

-

SAT

-

UNSAT

SAT

-

UNSAT

    • Italicized Cues Are To Be Used Only If JPM Petformame Is Being Simulated.

B.1.d ROlSRO

Page 12 of 13

STEP 15:

[Stepll]

CHECK RCP restart criteria:

Plant conditions stable.

0

RCP ready for restart.

  • OPS Supt approval for RCP restart.

STANDARD: Performer determines Plant conditions are stable and RCP

ready for restart.

    • CUE: When performer asks Unit Supervisor when the RCP

will be ready for RESTART, or QPS Supt approval is

sought for RESTART, then state this JBM has been

completed. We will stop here.

COMMENTS:

END OF TASK

TIME STOP:

SAT

-

-

UNSAT

    • Italicized Cues Are To Be Used Only \\f JPM Performance is Being Sirnulafed.

APPLICANT CUE SHEET

(TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK)

DIRECTION TO TRAINEE:

I will explain the initial conditions, and state the task to be performed. A11 control

room steps shall be performed for this JPM, inchding any required

communications. B will provide initiating cues and reports on other actions when

directed by you. Ensure you indicate to me when you understand your assigned

task. To indicate that you have completed your assigned task return the handout

sheet I provided you.

INITIAL CONDITIONS:

Unit is at approximately 9% RBP

RCP #3 Pump Bearing Temperature is high

RCP #3 Restart is planned after brief entry into containment.

You are the Operator at the Controls.

INITIATING CUES:

The Unit Supervisor has directed you to remove RCP #3 from service according

to 4401-5 Section 3.2.

You are to notify the Unit Supervisor when ready to transition to Section 3.4, RCP

RESTART.

B. 1 .e ROlSRO

Page I

of 9

REGION II

INITIAL LICENSE EXAMINATION

JOB PERFORMANCE MEASURE

B.1 .e ROiSRO JPMRI29A

Return the PRT to Normal per Sol-68.01

APPLICANT

EXAM!"?

B.l.e ROWRO

Page 2 of 9

REGION II

INITIAL LICENSE EXAMINATION

JOB PERFORMANCE MEASURE

-

Task: RETURN THE PKT TQ NORMAL PER Sol-68.01

Alternate Path:

1-PCV-68-340 fails open after PRT is cooled requiring performer to respond

by attempting closure of its associated motor operated block valve. A

manual reactor trip and safety injection will be required (auto reactor trip and

auto SI have been defeated).

Facilitv JPM #:

3-0T-JPMR129A Rev 1

KIA Ratinds):

010 A 1.03

(2.913.2)

2.1.23

(3.914.0)

2.1.28

(3.213.3)

002 K 1.05

(3.Z3.4)

Task Standard:

PRT cooling is established and the level is being maintained per SQI-68.01.

Performer attempts closure of 1-FCV-68-333 then manually trips the reactor

and manually initiates SI.

Preferred Evaluation Location:

Preferred Evaluation Method:

Simulator

In-Plant __

Perform

X

Simulate

~

References: SQ1-68.01 "Reactor Coolant System Pressurizer Relief Tank" Rev. 40

Task Number:: RQ-068-Sol-68-006

APPLICABLE FOR: ROISUO

1OCFR55.45:

2, 3, 4, 6

Validation Time: 15 min. Time Critical: No

_______---______________________________----------------------------------

___-__________--_----------------------------------------------------------

Candidate:

Time Start:

NAME

SSN

Time Finish:

Performance Ratins: SAP -

UNSAT -

Performance Time -

Examiner:

NAME

I

SIGNATURE

BATE

COMMENTS

B.1.e ROISRQ

Page 3 of 9

SIMULATOR OPERATOR INSTRUCTIONS:

1.

Initialize to IC # 163

2.

Acknowledge all alarms.

3.

Freeze simulator until the performance indicates understanding of the task and time

is ailowed for control board familiarization.

4. NOTE: This JPM has been preshot in IC #163. The following is the setup instructions

if needed:

Initialize to IC # 50.

Brain PRT to slightly <70% with 1-HS-68-318

Open and close PZF PQRV (without tripping reactor) until PWT temperature is

approximately 120°F.

Allow pressurizer pressure to return to normal.

Close both valves after pressure is lowered.

Insert the following override: ior zdihs68333a open to fail open 1-FCV-68-333

Block valve for 1-PCV-68-340.

Insert the following malfunctions:

irnf rp0lb Automatic Reactor Trip Signal Failure

irnf sp02b Auto SI initiation Signal Failure

irnf rc07b (ea) 1QQ to fail 1-PCV-68-340 to 100% assigned to event trigger 1,

Acknowledge all alarms

5. After performer indicates understanding of task, place simulator in run.

SIMULATOR OPERATOR INSTRUCTIONS:

After completion of JPM Step 5 or when cued by evaluator then enter the following

malfunction trigger: irnf itrigger to fail PQRV 68-340 to 100%.

B.1.e ROlSRO

Page 4 Qf 9

ToolslEsuignaenffProcedures Needed:

Ensure clean copy of SO%-68.01 in all copies of Operating Instructions on the Simulator

Floor.

READ TO OPERATOR

DlRECTlON TO TRAINEE:

I will explain the initial conditions, and state the task to be performed. All control

room steps shall be performed for this JPM, including any required

communications. I will provide initiating cues and reports an other actions when

directed by you. Ensure you indicate to me when you understand your assigned

task. To indicate that you have completed your assigned task return the handout

sheet E provided you.

INITIAL CQNDITIQNS:

The Unit is at 100% RTP

Leakage past a Pressurizer PQRV has caused the PRT temperature to go up to

120°F.

You are the Operator at the Controls (OAC).

INITIATING CUES:

The Unit Supervisor has directed you to cool the PRT to normal per the

appropriate SO!.

You are to notify the Unit Supervisor when the conditions in the PRT are normal.

B.1.e ROISRQ

Page 5 of 9

START TIME:

STEP 1:

Obtain a copy of the procedure.

STANDARD: A copy of Sol-68.01 section 8.3 has been obtained.

EXAMINERS CUE: After the performer has demonstrated the method of

obtaining the correct instruction, the evaluator can

provide a copy of the instruction.

COMMENTS:

STEP 2:

[Step I] PERFORM the following:

[a] NOTIFY UO of the anticipated primary water usage.

[b] ENSURE Primary Water is aligned per Sol-81.01.

[c] ENSURE a Primary Makeup Water Pump is running.

[d] ENSURE the non-running Primary Makeup Water Pump

handswitch is in P-Auto.

STANDARD: Performer determines that primary water makeup pump is

aligned normal with Primary Water Pump A in service by

checking red light LIT on 1-HS-82-3A and that Primary Water

Pump B is off by checking green light LIT on 1-HS-81-7A with

associated handswitch in P-AUTO (pulled cut or pulled up).

    • CUE:

State to performer that Primary Water is aligned per SO[-

81.01.

COMMENTS:

-

SAT

-

UNSAT

    • Italicized Cues Are To Be Used Onry If JPM Performance Is Being Simulated.

5.l.e RO/SRO

Page 6 of 9

NOTE 4:

Reduced Primary Water header pressure in the following step

may require the non-running Primary Water Pump to be

started.

STEP 3:

[Step 21 IF PRT temperature rises to 12OoF, THEN

PERFORM the following:

CRITICAL

STP

STANDPIPES

FBI WATER TO PRT

1-M-5

OPEN

STANDARD: 1-FCV-81-12 and I-FCV-68-303 are opened by placing I-HS- 81-12A and 1-HS-68-3038 to the open position and verified

open by red indicating lights LIT on associated valve hand

switches. Step is critical provide flow path for cooling

water to the PRT.

CQMMENTS:

-

SAT

_. UNSAT

    • italicized Cues Are Po Be Used only If JBM Performance Is Being Simulated.

B.l .e ROlSRO

Page 7 of 9

STEP 4:

[STEP 31 WHEN PRT level rises to 8Q% OR PRT temperature

12OoF, THEN PERFORM the following:

PRI WATER TO PRT

STANDARD: When PRT level increases to 80% or if PRT temperature falls

below 120°F, the performer will close 1-FCV-81-12 and I-FCV- 68-303 placing l-HS-81-12A and 1-HS-68-3038 to the close

position and verify valves are closed by green indicating lights

LIT on associated valve hand switches. Step is critical to

prevent PRT level increase above 80% or reduce primary

water usage when tank is less than 120°F.

COMMENTS:

STEP 5:

[Step 41 NOTIFY U.8. to ENSURE ONE Primary Water Pump

STOPPED and handswitch in Manual.

STANDARD: Performer stops, if necessaryy, one primary water makeup

pump if the P-AUTO pump started with I-HS-81-7A by pushing

in switch and going to stop, then returns switch to MANUAL

(pushed in or pushed down).

COMMENTS:

CRITICAL

STEP

-

SAT

-

UNSAT

-

SAT

-

UNSAT

    • Italicized Cues Are TO Be Used Only I f JPM Performance Is Being Simulated.

E.1.e ROlSRO

Page 8 of 9

STEP 6:

[Step 51 IF required, THEN PERFORM Section 8.1, Return

PRT Level to Normal from High Level.

STANDARD: Performer determines that Section 8.1 doesldces not need to

be performed to lower PRT level. Outcome depends on level

in tank.

COMMENTS:

NOTE TO EVALUATOR: CUE console operator for trigger 1. imf itrigger to

fail P O W 68-340 fully open.

STEP 6:

Initiate Reactor Trip and Safety Injection and GO TO E-0,

Reactor Trip and Safety Injection.

STANDARD: Performer determines that a PORV 68-340 has faiied open, and

attempts to close the valve and its associated block valve with

1 -HS-68-334AA and 1-HS-68-333A. Performer determines

that PORV and its associated block valve will not close.

Performer announces this to the Unit Supervisor. Performer

determines that RCS pressure is rapidly lowering based on

observation of PZR Pressure Indications and recorders.

Performer initiates a manual trip and safety injection with hand

switches 7-RP-l or 2 and 1-HS-63-133B or 133A. This step is

critical in response to pressurizer small break LOCA.

    • CUE: After performer has manually tripped the reactor and

initiated safety injection, then state to performer This

JPM has been completed. We will stop here.

COMMENTS:

END OF TASK

TIME STOP:

-

SAT

_I UNSAT

CRITICAL

STEP

I

SAT

-

UNSAT

    • Mahized Cues Are To Be Used Only If JPM Performance Is Being Simulated.

APPLICANT CUE SHEET

(TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK)

DIRECTION TO TRAINEE:

1 will explain the initial conditions, and state the task to be performed. AI% control

room steps shall be performed for this JPM, including any required

communications. I will provide initiating cues and reports on other actions when

directed by you. Ensure you indicate to me when you understand your assigned

task. To indicate that you have completed your assigned task return the handout

sheet I provided you.

INITIAL CONDITIONS:

The Unit is at 100% RTP

Leakage past a Pressurizer PORV has caused the PRT temperature to go up to

120°F.

You are the Operator at the Controls (OAC).

INITIATING CUES:

The Unit Supervisor has directed you to cool the PRT to normal per the

appropriate Sol.

You are to notify the Unit Supervisor when the conditions in the PRT are normal.

REGION II

B.1.f RQ/SRO

Page 1 of 9

INITIAL LICENSE EXAMINATION

JOB PERFORMANCE MEASURE

B.1.f ROISRO JPMRO16A

Place RHR Spray in Service per FR-Z.1

APPLICANT

EXAMINER

B. 1 .f ROlSRO

Page 2 of 9

REGlQN II

INITIAL LICENSE EXAMINATION

JOB PERFORMANCE MEASURE

Task: Place RHR Spray in Service Per FR-Z.1

Alternate Path: When 1-FCV-72-41 starts to open in the sequence to align the "B" Train RHR

for spray, the 18-5 RHR pumps trips, this required RNO response to get " A

train RHR spray in service.

3-OT-JFMROIGA Rev 4

Facility JPM #:

KIA Ratinq4s.):

005-A4.01 [3.6/3.4]

2.1.20 [4.3/4.2]

2.1.30 [3.9/3.4]

2.1.31 [4.2/3.9]

Task Standard:

Preferred Evaluation Location:

Preferred Evaluation Method:

Simulator

In-Plant ___

Perform

X

Simulate __

References: FR-Z.1, High Containment Pressure, (Rev 8)

Task Number:: RO-113-FR-Z.1-002

APPLICABLE FOR: ROlSRO

1OCFR55.45: 3, 4, 6, 7, 8

Validation Time: 10 min. Time Critical: No

Train "A" of RHR Spray has been placed in-service per FR-Z.I .

...........................................................................

-_______-____-_______ss_s_s_s___________-----------------------------------

Candidate:

Time Start:

NAME

SSN

Time Finish:

Performance Ratina: SAT -

UNSAT -

Performance Time -

COMMENTS

SIMULATOR OPERATOR INSTRUCTIONS:

I. Initialize to IC 466.

2.

Place Hold Order on A CS Pump

3.

Place simulator to RUN and acknowledge all alarms.

3.

Place simulator in FREEZE till performer has been briefed.

4. Place simulator to RUN after performer has been briefed

6.1 .f ROlSRO

Page 3 of 9

5. This JPM has been pre-shot in IC #166. Should IC #I66 be erased or fail to

perform as expected then use the following set-up instructions:

Initialize to IQO% BOL IC 50.

Insert irnf tho1 b 100 LOCA Hot Leg Loop 1 @ 100% .

insert irnf chOla 15 Cntmt Press Tx PDI 3-42 @ 15

Insert irnf ch01b 15 Cntntt Press Tx PDI 3-43 @ 15

Insert irnf chOlc 15 Cntmt Press Tx PBI 3-44 @ 15

Insert imf &Old 15 Cntmt Press Tx PDI 3-45 @ 25

STOP RCPS

Insert mrfsirl4 on (place power on 63-1).

Insert mrf csr04 off Select OFF (power to CS pump B).

Insert ior zaoei7212a 35 override value to 35 (CS pump B amps).

Insert ior zaofi7213 3000 override value to 3000 (CS pump B flow).

Insert ior zlohs7210a [3] override value to ON (CS pump 3 red light).

Insert isr zlohs7210a [1] override value to OFF (CS pump B light).

Insert ior zlohs7227a [=I]

override value to OFF (CS pump A light).

Insert ior zaotr726 106 override to 106 (CS Temp).

Insert ior zaopdi3042 12 override value to 12

Insert ior zaopdi3043 12 override value to 12

Insert ior zaopdi3044 12 override value to 12

Insert ior zaopdi3045 12 override value to 12

Insert ior zaopdi3045[1] 12 override value to 12

Insert lor zaopdi3045[2] 12 override value to 12

Insert ior zaopdr30133[1] 0.5 Cntmt Annulus AP

Insert ior zdihs72lOa ptlock (this helps simulate B CS pump on but is really off.

Perform appropriate procedures (E-0, ES-1.3) prior to placing RHR spray in service

Stop 1A-A CSP and Place in PTL and place hold order tag.

(through step 9 of Fa-Z.1).

SIMULATOR OPERATOR INSTRUCTIONS:

Step 6 of the JPM requires the following malfunction to be inserted when RHR Spray

valve 7-FCV-72-41 starts to OPEN:

irnf rho1 b to trip 1543 RHR pump

8.1 .f ROlSRO

Page 4 of 9

ToalslEquipmentlProcedures Needed:

Ensure clean copy of FR-Z.l in all copies of Functional Restoration Guidelines on the

Simulator FEOOF.

READ TO OPERATOR

DIRECTION TO TRAINEE:

I will explain the initial CoRditiORs, and state the task to be performed. All control

room steps shall be performed for this JPM, including any required

communications. I wili provide initiating cues and reports on other actions when

directed by you. Ensure you indicate to me when you understand your assigned

task. To indicate that you have compieted your assigned task return the handout

sheet I provided you.

INITIAL CONDITIONS:

The unit was at 100% when a Large Break LOCA occurred.

1A-A Containment Spray Pump has been tagged out of service.

15-5 Containment Spray Pump started and has been spraying Containment.

The break occurred an hour and 10 minutes ago.

All ECCS equipment is performing its design functions and is on Containment Sump

Recirc.

You are the Operator at the Controls (OAC).

INITIATING CUES:

The Unit Supervisor directs you to place RHR Spray in-service per FR-2.1 Step IO.

You are to notify the Unit Supervisor when RHR Spray is in service.

B.1 .f ROISRO

Page 5 of 9

START TIME:

STEP 1:

Obtain a copy of the procedure.

STANDARD: A copy of FIR-2.1 has been obtained.

COMMENTS:

STEP 2:

[Step I O ] DETERMINE if RHR Spray should be placed in

service:

a. CHECK the following conditions:

  • At least one hour elapsed since beginning of the

accident.

  • Cntmt Press greater than 9.5 psig.
  • RHR suction aligned to the cntmt sump.
  • At least one charging pump and one SI pump

running.

-

RD: 1. Performer has determined that an hour has lapsel- since

the beginning of the accident. [Given in initial

conditions1

2. Cntmt press has been checked > 9.5 psig.

3. I-FCV-63-72 and 1-FCV-63-73 verified to be open by

red indicating lights.

4. 1 CCP & 1 SIP verified to be running by indicating lights

or amps.

COMMENTS:

STEP 3:

[STEP lob] ALIGN Train B RHR spray:

1) ENSURE Train B RHR pump RUNNING.

S T A N D I : Train B RHR pump verified to be running by indicating light

or amps.

COMMENTS:

-

SAT

-

UNSAT

-

SAT

-

UNSAT

-

SAT

-

UNSAT

B.l .f ROISRO

Page 6 of 4

STEP 4:

[STEP 10b 211 Close KHR crosstie 1-FCV-74-35.

STANDARD: 1-HS-74-35-A has been placedlchecked in the CLOSED

position and the green light illuminated on HS.

COMMENTS:

STEP 5:

[STEP 10b 3)] CLOSE RHR injection 1-FCV-63-94.

STANDARD: 1-HS-63-94-A has been placed in the CLOSED position

and the green light illuminated on WS. Step is crltical to

establish B Train RHR Spray.

COMMENTS:

STEP 6:

[STEP 10b 4)] OPEN RWR spray 1-FCV-72-41,

STANDARD: 1-HS-72-41A has been placed/checked in the OPEN

position and the Red light illuminated on HS. Step is

critical to establish B Train RHR Spray Flow.

COMMENTS:

CONSOLE OPERATOR NOTE: When FCV-72-41 STARTS OPEN in

the this step imf rhOlb to trip the 1B RHR pump. If asked to check

pump -state that it tripped on instantaneous QVW current.

EVALUATOR NOTE: Performer will acknowledge trip of 1B-B RHR

pump and place hand switch in pull-to-lock. Performer will either

have US dispatch personnel or will dispatch personnel to

investigate the trip of 1B-B RHR pump.

-

SAT

UNSAT

CRITICAL

STEP

-

SAT

-- UNSAP

CRITICAL

STEP

SAT

-

UNSAT

5.1 .f ROlSRO

Page 7 of 9

STEP 7:

[STEP 10b RNO] ALIGN Train A RHR spray:

I)

ENSURE Train A RHR pump RUNNING.

I

STANDARD: Train A RHR pump verified to be running by indicating light

or amps.

COMMENTS:

STEP 8:

[STEP 10b RNO] 2) CLOSE RHR crosstie 1-FCV-74-33.

STANDARD: 1-HS-74-33-A has been placedkhecked in the CLOSED

position and the green light illuminated on HS.

COMMENTS:

[STEP 10b RMO] 3) CLOSE RHR injection I-FCV-63-93.

STANDARD: 1-HS-63-93-14 has been placed in the CLOSED position

and the green light illuminated

HS. Step is critical to

establish A Train RHR Spray.

COMMENTS:

I

-

SAT

_il UNSAT

-

SAT

-

UNSAT

CRITICAL

STEP

-

SAT

-

UNSAT

B.1.f ROlSRO

Page 8 of 9

STEP I O :

[STEP 1Qb RNO] 4) OPEN RHR spray 1-FCV-72-40,

STANDARD: 1-HS-72-408 has been placedlchecked in the OPEN

position and the Red light illuminated on hand switch.

Step is critical to establish A Train RHR Spray.

COMMENTS:

STEP 11:

Notify the Unit Supervisor thaf RHR spray is in service.

STANDARD: Notify the Unit Supervisor that RHW spray has been placed

En service.

    • CUE:

When notified, acknowledge the report using repeat

back.

COMMENTS:

END OF TASK

TIME STOP:

CRlTlCAL

STEP

I

SAT

-

SAT

-

UNSAT

APPLICANT CUE SHEET

(TO BE RETURNED PO EXAMINER UPON COMPLETlON OF TASK)

DIRECTION TO TRAINEE:

I will expiain the initial conditions, and state the task to be performed. All control

room steps shall be performed for this JPM, including any required

communications. I will provide initiating cues and reports on other actions when

directed by you. Ensure you indicate to me when you understand your assigned

task.

INITIAL CONDITIONS:

The unit was at 108% when a Large Break LOCA occurred.

1A-A Containment Spray Pump has been tagged out of service.

1 B-B Containment Spray Pump started and has been spraying Containment.

The break occurred an hour and 18 minutes ago

All ECCS equipment is performing its design functions and is on Containment Sump

Recirc.

You are the Operator at the Controls (OAC).

INITIATING CUES:

The Unit Supervisor directs you to place RHR Spray in-service per FR-Z.1 Step I O .

You are to notify the Unit Supervisor when RHR Spray is in service.

B.l .g ROiSRO

Page 1 of 18

REGION II

INITIAL LICENSE EXAMINATION

JOB PERFORMANCE MEASURE

B.l =g ROlSRO JPMRB42A

Transfer RCP Board from Normal to Alternate per

sol-202.01

APPLICANT

EXAMINER

B.1.g ROlSRO

Page 2 of 10

REGION LI

INITIAL LICENSE EXAMINATION

JOB PERFORMANCE MEASURE

T;rsk: Transfer RCP Board from Normal to Alternate per Sol-202.01

Alternate Path: NIA

Facility JPM #:

New

KIA Ratingls):

062A4.01 [3.3/3.1]

2.1.30 [3.9/3.4j

2 1.23 [4.8/3.4]

Task Standard:

The RCP 1A board is being fed from the Alternate Feeder (without an inadvertent

RCP trip) per Sol-282.01 Section 8.2.

Preferred Evaluation Location:

Simulator 2

In-Plant _s

Perform

X

Simulate -

References: Sol-202.04 "6.9 KV Reactor Coolant Board $A" Rev. 7

Task Number: RO-202-SOI-202-002

APPLICABLE FOR: KOISRO

Preferred Evaluation Method:

Examiner:

I

NAME

SIGNATURE

DATE

COMMENTS

SIMULATOR OPERATOR INSTRUCTIONS:

1

~

2. Place the Simulator in RUN

3. Acknowledge a16 alarms

Initialize to IC 175.

SIMULATOR OPERATOR INSTRUCTIONS:

NONE

B.1.g ROlSRO

Page 3 of 15

B.1.g RO/SRO

Page 4 of 10

ToolslEuuipmenffBrocedures Needed:

Ensure clean copy of SQI-202.01 in all copies of Operating Instructions on the

Simulator Floor.

READ TO OPERATOR

DIRECTION TO TRAINEE:

I will explain the initial conditions, and state the task to be performed. All control

room steps shall be performed for this JPM, including any required

communications. I will provide initiating cues and reports on other actions when

directed by you. Ensure you indicate to me when you understand your assigned

task. To indicate that YOU have completed your assigned task return the handout

sheet I provided you.

INITIAL CONDITIONS:

The Unit is in Mode 1 at 26% power.

RCP I

is being fed off its normal power source

You are the Operator At The Controls.

INITIATING CUES:

USER0 has directed you to transfer RCP 1 to its Alternate Supply per

Sol-202.01 and has granted approval to perform the task.

You are to notify the USlSRO when the transfer has been completed.

B.1.g ROlSRO

Page 5 of 10

START TIME:

STEP I:

EXAMINERS CUE: Affer the performer has demonstrated the mefhod of

obtaining the correct instruction, the evaluator can

provide a copy of the instruction.

Obtain a copy of the procedure.

STANDARD: A copy of Sol-202.01 has been obtained and performer has

turned to section 8.2.

I

COMMENTS:

STEP 2:

[Step $1 OBTAIN SRO approval

    • CUE:

If asked, role play as Unit Supervisor and approve transfer

of 1A Unit Board from its normal supply to it alternate

supply.

STANDARD: Performer obtains SRO approval to perform task. (May

assume approval granted since directed by Unit Supervisor to

perform task.)

COMMENTS:

-

SAP

-

UNSAT

-

SAP

-

UNSAT

    • Italicized Cues Are To Be Used Only !f JBM Performance Is Being Simulated-

STEP 3:

[STEP 21 CHECK voltage 6560 to 7260V lo Alternate ACB

on 1-1-57-112, START BUS AVOLTAGE iq-M-51.

STANDARD: I-El-57-1 12 has been checked and voltage verified to be within

the normal voltage range (6560 to 7260V).

COMMENTS:

STEP 4:

[STEP 31 ENSURE l-HS-68-8AA, RCP 1 NORMAL BKK &

LIFT PMP [1-M-5], PUSHED IN to place handswitch in control

ofACB 2112.

STANDARD: 1-HS-68-8AA has been placed in the IN position.

COMMENTS:

8.l.g ROlSRQ

Page 6 of 10

-

SAT

-

UNSAT

-

SAT

_I UNSAT

    • italicized Cues Are To Be Used Only If JPM Performance Is Being Simulated.

B.1.g ROlSRO

Page 7 of 10

STEP 5:

[STEP 41 ENSURE I-HS-68-8BA, RCP I

ALTERNATE BKR

& XFER SELECTOR [I-M-5], PUSHED IN to place ACE 2522

auto transfer circuit in MANUAL.

STANDARD: 1-HS-68-8BA has been verified in the PUSHED IN position.

COMMENTS:

STEP 6:

[STEP 51 MONITOR 1-EI-68-8A, RCP I

AMPS [1-M-5] during

transfer to ensure RCP Amp load transfers to Alt supply.

STANDARD: The performer verifies that the amps on ?-Ef-57-8A rise during

the transfer in the following steps.

COMMENTS:

CAUTION

Release handswitches SLOWLY after transfer is complete to

prevent inadvertent breaker actuation.

STEP 7:

[STEP 61 PLACE I-HS-68-$BA, RCP 1 ALTERNATE BMW &

XFER SELECTOR, in START and HOLQ UNTIL transfer is

complete.

STANDARD: l-HS-68-8BA Hand switch is placed in the Start Position and

held in the Start Position.

Step is critical to assure prevent loss of bus during

performance of the next step.

COMMENTS:

-

SAT

__ UNSAT

-

SAT

__ UNSAT

CRITICAL

STEP

-

SAT

___ UN§AT

    • italicized Cues Are To Be Used Only !f JPM Performance Is Being Simulated.

B.1 .g ROlSRO

Page 8 of 10

EVALUATOR NOTE: JPM Steps 8 and 9 evaluate procedure step

7.

STEP 8:

[STEP 71 PLACE I-HS-68-8AA, RCP 1 NORMAL 5KR &

LIFT PUMP, in STOP, and

STANDARD: 1-HS-68-8AA has been placed in the STOP position, then,

1-HS-68-8AA is released.

Step is critical to allow board transfer without

loss of bus or loads on the bus.

COMMENTS:

STEP 9:

[STEP 71 ENSURE Alt ACB 2522 CLOSED, and Normal

ACB 2? 12 OPEN.

STANDARD: 1.

Alternate Supply Bkr, 2522, red position indicating light

verified ON.

Normal Supply Bkr, 21 12, green position indicating light

verified ON.

2.

COMMENTS:

CRITICAL

STEP

-

SAT

-

UNSAT

    • ffaficized

Cues Are To Be Used Only I f JPM Betformanee Is Being Simufated.

B.1.g HBlSRO

Page 9 of 10

STEP I O :

Notify Unit Supervisor that 6.9kV RCP Board I A has been

transferred to its alternate supply.

-

SAT

    • CUE:

When notified, acknowledge the rsport using repeat

back.

STANDARD: The Unit Supervisor has been notified that 6.9kV RCP Board

la is on its alternate supply.

COMMENTS:

-

UNSAT

END OF TASK

/___

TIME STOP:

    • !falicized Cues Are To Be Used only if JPM Betformance Is Being SimuMxf.

APPLICANT CUE SHEET

(TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK)

DIRECTION TO TRAINEE:

I will explain the initial conditions, and state the task to be performed. All control

room steps shall be performed for this JPM, including any required

communications. I wilt provide initiating cues and reports on other actions when

directed by you. Ensure you indicate to me when you understand your assigned

task. Po indicate that you have completed your assigned task return the handout

sheet I provided you.

INITIAL CONDITIONS:

The Unit is in Mode 1 at 26% power.

RCP 1 is being fed off its normal power source.

You are the Operator At The Controls.

INITIATING CUES:

USlSRO has directed you to transfer RCP 4 to its Alternate Supply pes

SQI-202.04 and has granted approval to perform the task.

You are to notify the USlSRO when the transfer has been completed.

B.i.h RO

Page 1 of 14

REGION II

INITIAL. LICENSE EXAMINATION

JOB PERFORMANCE MEASURE

B.1.h RO JPMR044

Alignment of the Upper Containment Monitor to the

Lower Containment from the MCR

APPLICANT

EXAMINER

B3.h RO

Page 2 of 14

Task:

Alternate Path:

F

=

)</A Ratinqk):

Task Standard:

REGION II

(NITIAL LICENSE EXAMINATION

JOBPERFORNlANCENlEASURE

EVALUATION SHEET

ALIGNMENT OF THE UPPER CONTAINMENT MONITOR TO THE

CONTAINMENT FROM THE MCR

NIA

3-OT-JPMR044 Rev 6

073K1.02 [3.613.9]

OWER

Perform alignment of the upper containment rad monitor to the lower containment compartment.

Candidate:

Time Start :

NAME

SSN

Time Finish:

Performance Ratincl: SAT

UNSAT

Performance Time

Examiner:

I

NAME

SIGNATURE

DATE

B.1.h RO

Page 3 of 14

SIMULATOR OPERATOR INSTRUCTIONS:

1. Initialize to IC 181

2. Acknowledge all alarms

2. NOTE: This JPM has been pre-shot in IC #18?. Should IC #181 be erased or fail to

perform as expected then use the following set-up instructions:

a. Reset simulator to 100% IC #(40, 50, or 60); then perform the following

b. Go to run, acknowledge alarms.

c. Close the following valves and ensure green indicating light is lit on 0-M-12.

1-HS-90-109

1-HS-90-108

1-HS-90-109

1-HS-90-110

1-HS-90-1 I 1

The above will cause W173E to Alarm which is expected for the conditions.

d. Set up e l trigger for use in 4PM Step 6 by entering the following:

ior an:ov:06c087 (el) alarm

ior zlolrm90112c[3] (el) off

e. View simulator over ride summary to ensure that the above over rides have been

assigned to e l trigger.

f. Freeze simulator.

g. Place simulator in run when directed by the examiner

NOTE TO CONSOLE OPERATOR: This JPM requires the use of triggersloverrides which

must be inserted at the appropriate times (Performance Steps 5,8 and 9) to have

annunciator alarms or monitor lights that reflect operations that the candidate will request N O

to start/ stop radiation monitor sample pumpslreset iodine bow flow alarm locally.

B.4.h 80

Page 4 of 14

TooBs(EcluipmenffProc~du~es

Needed:

Ensure enough copies of Sol-90.02; GASEOUS PKOCESS RaDlATlON MONITORS

are available in the Simulator file cabinet, since Operators will obtain their own copy of the

procedure.

READ TO OPERATOR

DIRECTION TO TRAINEE:

B will explain the initial conditions, and state the task to be performed. All control

room steps shall be performed for this JPM, including any required

communications. I will provide initiating cues and reports on other actions when

directed by you. Ensure you indicate to me when you understand your assigned

task. To indicate that you have completed your assigned task return the handout

sheet I provided you.

INITIAL CONDITIONS:

You are the Unit 1 CRO.

Unit I

is at 100% power.

1 -RM-90-106 has been removed from service for maintenance per appropriate

procedure.

INITIATING CUES:

The Unit Supervisor has requested you to align the upper containment rad monitor

to lower containment per proper procedure. You are to notify the Unit Supervisor

when the alignment is complete.

B.7.h RO

Page 5 of 14

START TIME:

STEP 1:

Obtain a copy of the appropriate procedure.

STANDARD: Operator obtains a copy of S0%-30.02; GASEOUS

PROCESS RADIATION MONITORS Section 8.1.

COMMENTS:

NOTE Bf any Radiation Monitor experiences sufficient elevated reading

above normal request MIG to perform purge.

NOTE Chemistry shouid be notified to address compensatory measures

for any radiation monitor required operable per Tech Specs/BDCM,

which is being removed from service.

Role play as Chem Lab, acknowledge request to address cornp

measures since 1-RM-90-112 will not be aligned to upper

containment.

CUE:

STEP 2:

[I]

ENSURE Upper Containment Air Monitor Aligned per

Section 5.2.

STANDARD: Operator determines that the Upper Containment Air Monitor

is aligned per procedure.

Inform the operator that the upper containment air

monitor is aligned for normal operation per SO!-90.

02, Section 5.2.

CUE:

COMMENTS:

-

SAT

-

UNSAT

-

SAT

-

UNSAT

B.1.h RO

Page 6 of 14

STEP 3:

121 NQTlFY Chem lab of intent to realign monitors so that

proper sampling of Cntmt. and release permits are

addressed.

STANDARD: Operator notifies the Chem lab of intent to realign monitors

so that proper sampling of Cntmt. and release permits are

addressed.

Using repeat back, acknowledge the message.

CUE:

COMMENTS:

NQTE If 1-RM-90-112 is aligned in place of 1-RM-90-106, it is inoperable

during a lower containment purge until the alarm setpoints are

recalibrated.

STEP 4: [3] DEPRESS the TOGGLE MONITOR pushbutton on the ICS

PURGE computer screen AND ENSURE SPXLO96,

Radiation Monitor in Use, displays 1-RM-90-112.

STANDARD: Operator enters PURGE using any ICS key board, then

using mouse, selects push button TOGGLE MONITOR

106/112. Operator then verifies that computer point

SPXL096 RADIATION MONITOR IN USE is displaying 90-

112.

COMMENTS:

-

SAT

U N SAT

~

SAT

-

UNSAP

STEP 5: [4J CONTACT MIG to determine the appropriate value for ICs

point SPXR035, 1-RM-90-112B Bias, for setpoint

calculation and update SPXR095 in the ICs.

STANDARD: Operator contacts MIG and to determine Bias value to use

for IC§ point SPXR095.

CUE:

Role play as ME, acknowledge request, then state that bias

value must be calculated for 1-RM-90-112B. When the bias

value has been calculated, an Instrument Mechanic will adjust

value in ICs and notify the Unit Supervisor.

COMMENTS:

STEP 6: [5] SHUTDOWN Lower Containment Air Monitor per Section 7.2.

STANDARD: Operator determines that the Lower Containment Air Monitor

has already been removed from service per initial conditions.

CUE: If asked, inform the operator that the lower containment air

monitor has been removed from service.

COMMENTS:

B.1.h RO

Page 7 of 14

__ SAT

-

UNSAT

-

SAT

-

UNSAT

B.l.h RO

Page 8 of 14

STEP 7: [6]

ENSURE 1-RE-90-106 and 1-RE-90-112 pumps are OFF

before aligning monitor. The following handswitches control

power to the sample pumps [A3Uff37 on top of monitor

enclosure]:

I-HS-90-106A

1-HS-90-106B

  • 1-HS-90-112A

I-HS-90-1126

STANDARD: Operator contacts the Aux. Building AUO to ensure I-RE-90-

106 and 1-RE-90-112 pumps are OFF before aligning

monitor.

CONSOLE OPERATOR: Roll play as AUO, Acknowledge request, then

activate e l trigger by: imf itrigger, then contact

the candidate and give him/her the following cue:

CUE:

Inform the operator that both 1-RE-90-106 and 1-RE-90-

112 pumps are OFF and that 1-PMP90-112A was the

running pump.

COMMENTS:

STEP 8: [S]

RECORD the monitor sample pump STOPPED (N/A pump

NOT stopped):

[a] I

-HS-90-112A

[b] 1-HS-90-112B.

STANDARD: Operator records the monitor sample pump STOPPED and

N/As pump NOT stopped 1-HS-90-112B.

If asked, 1-PMP-90-112A was the running pump.

CUE:

COMMENTS:

-

SAT

-

UNSAT

I

SAT

-

UNSAT

E.1.h RO

Page 9 of 14

STEP 9:

[a] PERFORM the following:

NOMENCLATURE

-0WER CONTAINMENT

SUP TO 1-RE-SO-I12

)ROSS TIE

2NTMT TO RM-106 CIV-

)VI INSIDE CNTMT

ZNTMT TO RM-1QG CIV-

VI

OUTSIDE CNTMT

ZNTMT TO RM-112 CIV-

CVI OUTSIDE CNTMT

ZNTMT TO RM-112 CIV-

CVI INSIDE CNTMT

CNTMT TO RM-112 CIV-

CVI INSIDE CNTMT

CNTMT TO RM-112 CIV-

CVI INSIDE CNTMT

CNTMT TO RM-I 12 CIV.

STANDARD: Operator contacts the Aux. Building AUO and directs the

AUO to open I-ISIV-90-112A. The operator then places the

rad monitors containment isolation valves in the correct

configuration as per this check list and verifies position by

valve indicating lights.

NOTE: Rad monitoring will be inadequate if this valve

Lineup not done properly.

CUE:

When asked as AUQ, acknowledge request, then state that 1-

ISIV-90-112A is now OPEN.

COMMENTS:

CRITICAL

STEP

-

SAT

-

UNSAT

B.1.h RO

Page 10 of 14

STEP 10: [9]

START the monitor sample pump STOPPED in Step [7]

(N/A pump NOT started):

[a]

1-HS-90-I12A

[b]

1-HS-90-1128

STANDARD: Operator contacts the Aux Building AUO and directs the

AUO to start I-PMP-90-1128. Operator determines that step

[9] [b] is N/A. Rad monitoring will be inadequate if pump

is not started.

CONSOLE OPERATOR: Roll play as AUO, Acknowledge request. then

insert override: ior an:ov:05C087 off to set

W173E clear, then contact the candidate and

give himlher the following cue:

CUE: As AUO when contacted, inform the operator that 1-PMP-90-

112A has been started.

COMMENTS:

CRITICAL

STEP

-

SAT

-

UNSAT

B.1.h RO

Page II of 14

STEP 11: [IO] IF IODINE LOW FLOW ALARM on skid comes in, THEN

RESET with 1-HS-90-2 12JB.

STANDARD:

Operator informs the Aux Building N O to reset the lODiNE

LOW FLOW ALARM on the skid with I-HS-90-112JB, if in

alarm.

CONSOLE OPERATOR: Roll play as AUQ, Acknowledge request, then

modify override: zlo?rm90112~[3] on to turn

green operate light on for the iodine monitor and

give himlher the following cue:

CUE: When contacted as the AUO, acknowledge request using repeat

back, then inform the operator that the IODINE LOW FLOW is in

ALARM.

CUE: When asked to RESET alarm as AUO, then acknowledge

request (modify the over ride above), then state the alarm has

been reset.

COMMENTS:

-

SAT

-

U N SAT

B.1.h RQ

Page 12 of 14

STEP 12: 6111 PERFORM Monitor Source Check [O-M-l2], and

NSURE 1-RM-90-112 (A, B & C) green OPERATE

Lights LIT and red HIGH &yellow ALEKT Lights NOT

LIT.

ENSURE ANN 173-A UPR CNTMP AIR 1-RM-I 12 RAD

HI, NOT LIT.

ENSURE ANN 273-D UQR CNTMTAIR 1-RM-112

INSTR MALF, NOT LIT.

STANDARD: Operators performs a monitor source check and ensures that

1-RM-90-112

(A, B&C) green OPERATE bights are LIT and

red HIGH & yellow ALERT Lights NOT LIT.

ENSURES ANN 173-8 UPK CNTMTAIK 1-RM-112 RBB and til

and ANN 173-D UPR CNTMT AIR 1-RM-112 INSTR MALF

NOT LIT.

COMMENTS:

STEP 13:

[I21

ENSURE Local Panel Lights RESET

STANDARD: Directs the AUO, to ensure local panel lights are reset.

CUE: When contact as the AUO, inform the operator that t4e local

panel lights are reset.

COMMENTS:

-

SAT

I

UNSAT

SAT

-

UNSAT

B.1.h RO

Page 13 of 14

STEP 14:

IF the alarm setpoint values for 1-RM-90-112

were

changed in step [4] [due to purging lower

containment], return the alarm setpoint values to

normal WHEN the purge is secured.

STANDARD: Operator determines step is not applicable at this time.

COMMENTS:

STEP 15:

Notifies Unit Supervisor that Upper Cntmt monitor

has been aligned to lower Cntmt per SOI-90.02

Section 8.4. States that bias will be adjusted by

MIG when they have completed their calculation of

the bias value.

STANDARD: Unit Supervisor has been notified that Upper Cntmt monitor

has been aligned to lower Cntmt. And that the bias will be

adjusted later by MIG.

CUE:

COMMENTS:

When notified, acknowledge report using repeat back.

END OF TASK

TIME STOP:

-

SAT

-

UNSAT

__ SAT

-

UNSAT

APPLICANT CUE SHEET

(TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK)

DIRECTION TO TRAINEE:

I will explain the initial conditions, and state the task to be performed. All control

room steps shall be performed for this JPM, including any required

communications. I will provide initiating cues and reports on other actions when

directed by you. Ensure you indicate to me when you understand your assigned

task. Bo indicate that you Rave completed your assigned task return the handout

sheet I provided you.

INITIAL CONDITIONS:

You are the Unit 1 CRO.

Unit 1 is at 100% power.

1-RM-90-106 has been removed from sewice for maintenance per appropriate

procedure.

INITIATING CUES:

The Unit Supervisor has requested ysu to align the upper containment rad monitor

to lower containment per proper procedure. You are to notify the Unit Supervisor

when the alignment is complete.

B.2.a /Local

Page Z of 10

REGION II

INITIAL LICENSE EXAMINATION

JOB PERFORMANCE MEASURE

B.2.a JPMA024/Local

Isolate the RCP Seal Injection and Thermal Barrier

per ECA-0.0

APPLICANT

EXAMINER

B.2.a /Local

Page 2 of I O

REGION II

INITIAL LICENSE EXAMINATION

JOB PERFORMANCE MEASURE

Task: isolate The RCP Seal Injection And Thermal Barrier Per ECA-O.0

Alternate Path: N/A

Facilitv JPM #:

KIA Rating(sl:

855-EK3.02 [4.3/4.6]

004-Kl.04 [3.4/3.8]

2.1.30 [3.9/3.4]

Task Standard:

Preferred Evaluation Location:

Preferred Evaluation Method:

Simulator-

In-Plant X

Perform

Simulate

References: ECA-0.0 "boss of Shutdown Power" Rev.18

Task Number:: AUO-113-ECA-0.0-001

APPLICABLE FOR: AUOIROISRO

3-OT-JPMA024 Rev 6

The valves listed in Appendix " A of ECA-0.0 have been located and closed

RO-113-ECA-0.0-001

10CFR55.45: 6, 8, 9, 10

Validation Time: 22 rnin. Time Critical: No

...........................................................................

_______________________s_ss_ssss________-----------------------------------

Candidate:

Time Start:

NAME

SSN

Time Finish:

Perfsmance Rating: §AT -

UNSAT -

Performance Time -

Examiner:

NAME

!

SIGNATURE

BATE

COMMENTS

B.2.a /Local

Page 3 of 10

-

Toelsl~uuiprnentlPracedures Needed:

Hard Hat, Safety Glasses, Hearing Protection, and Plant Approved Shoes.

ECA-0.0 Appendix A

ALARA considerations, BIT room.

NOTE:

EVALUATOR NOTE:

Start this JPM in the MCR.

Provide copy of ECA-0.0 Attachment A to performer with

candidates cue sheet

READ TO OPERATOR

DIRECTION TO TRAINEE:

I will explain the initial conditions, and state the task to be performed. At1 control

room steps shall be performed for this JPM, including any required

communications. I will provide initiating cues and reports on other actions when

directed by you. Ensure you indicate to me when you understand your assigned

task. To indicate that you have completed your assigned task return the handout

sheet 1 provided you.

INITIAL. CONDITIONS:

The unit has just entered Mode 3 following a shutdown required by Tech. Specs due to

the Boss of 6.9kV Shutdown Board 1 B-B.

The B CVCS Seal Injection Water Filter is in service.

A tornado on site caused a complete loss of Off-Site power and the ?A-A Diesel

Generator failed to start.

The crew transitioned to ECA-0.0 due to the loss of shutdown power and is progressing

through the steps.

Attempts are being made to restore shutdown power.

You are an AUO on shift.

INITIATING CUES:

The CRO has directed you to perform Appendix A of ECA 0.0 to isolate the RCB

seals and thermal barrier.

You are to notify the CRO when you have finished Appendix A.

8.2.a Local

Page 4 of 10

START TIME:

STEP 7 :

Obtain a copy of Appendix A of ECA-0.0.

STANDARD: A copy of the Appendix A of ECA-0.0 has been obtained.

EXAMINERS CUE: Provide copy of Appendix A of ECA-Q.0 to

performer.

COMMENTS:

Note: These steps can be performed in amy order. (Steps 2- 9)

STEP 2:

[Step I] ISOLATE RCP seal return valves [reach rods

outside filter cubicle]:

CLOSE 1-ISV-62-642, CVCS SEAL WBR RETURN

FILTER INLET ISQL [A5T/713].

STANDARD: 1-ISV-62-642 has been located and turned clockwise to

close. Step is critical to isolate flow path from RCP

seals to VCT.

    • CUE:

After the performer demonstrates how to close valve,

state that the hand wheel turns several turns and

stops.

COMMENTS:

__ §AT

___ UNSAT

CRITICAL

STEP

-

SAT

-

UNSAT

    • Italicized Cues Are To Be Used Only If JPM Performance !s Being Simukted.

B.2.a /Local

Page 5 of 10

STEP 3:

[STEP 1 continued] 9

CLOSE 2-BW-62-643, CVCS

SEAL WTR RETURN FILTER BYPASS [A5Tnl3].

STANDARD: 1-BW-62-643 has been located and checked closed.

    • CUE:

After the performer demonstrates how to check valve

closed, state that the hand wheel does not turn when

clockwise motion is applied.

COMMENTS:

STEP 4:

[STEP 21 ISOLATE RCP seal injection [reach rods

outside seal water injection filter cubicles]:

CLOSE I-ISV-62-549, CVCS SEAL WTR INJ FLTW

E3 OUT !SOL [A5T/713].

STANDARD: 1-8SV-62-549 has been located and turned clockwise to

close. Step is critical because it isolates the flow path

from CVCS to RCP seals preventing thermal shock to

shaft and seal if CVCS charging is restored.

    • CUE: After the performer demonstrates how to close

valve, state that the hand wheel turns several turns

and stops.

COMMENTS:

-

SAT

-

UNSAT

CRITICAL

STEP

-

SAT

UNSAT

    • Italicized Cues Are To Be Used Only if JPM Petforaance is Being Simulated.

B.2.a /Local

Page 6 of 10

STANDARD:

    • CUE:

STEP 5:

[STEP 2 continued] * CLOSE 1-BW-62-546, CVCS

SEAL WTR BNJ FLTR BYP [MT/713].

-BW-62-546 has been located and checked closed.

After the performer demonstrates how to check

valve closed, state that the hand wheel does not turn

when clockwise motion is applied.

COMMENTS:

STEP 6:

[STEP 2 continued]

CLOSE 1-ISV-62-550, CVCS

SEAL WTR INJ FLTR A OUT ISOL [A5T/713].

STANBARD: 1 -ISV-62-550 has been located and checked closed.

After the performer demonstrates how to check

valve closed, state that the hand wheel does not turn

when clockwise motion is applied.

    • CUE:

COMMENTS:

I__ SAT

-

UNSAT

-

SAT

~

UNSAT

    • /falicked Cues Are To Be Ysed Only If JPM BerFormance Is Being Simulated.

B.2.a Local

Page 7 of 10

NOTE TO EVACUATQR: CUE: Stop performer before entering

BIT room (for ALARA concerns) and have candidate describe

valve location (valve 1-FCV-70-90). Use posted survey map.

After candidate describes the valves approximate location.

Simulate the performance of the next step without entering the

BIT Room.

STEP 7:

[STEP 31 ISOLATE RCP thermal barrier:

CLOSE I-FCV-70-90, THERMAL BARRIER CCS

RETURN [above south side of BIT].

STANDARD: 1 -FCV-70-90 has been located, actuator engaged and

turned clockwise to close. This step is critical to isolate

flow pat4 to protect CCS from steam formation in

CCS.

EXAMINER NOTE: This valve is in the BIT room, overhead just

below the ceiling in the southwest corner behind the

BIT. ALARA considerations. If candidate attempts to

climb up to valve without first checking with RADCON,

stop candidate and require contact with RADCON. See

note preceding this step.

    • CUE: After the performer demonstrates how to close

valve, state that the hand wheel turns many turns

and stops.

COMMENTS:

CRiTlCAb

STEP

__ SAT

    • italicized Cues Are To Be Used Only I f JPM Performance Is Being Simwiated.

B.2.a /Local

Page 8 of 10

STEP 8:

[STEP 3 continued]

CLOSE l-ISV-70-677A, CCS

THRM BAR BSTR PUMP ?A-A DlSCH ISOCATION

[A5W/737].

STANDARD: 1-ISV-70-677A has been located and turned clockwise to

close. Step is critical to isolate flow path to prevent

thermal shock to RCP seals when CCS is restored.

    • CUE

After the performer demonstrates how to close

valve, state that the hand wheel turns many turns

and stops.

COMMENTS:

STEP 9:

[STEP 3 continued]

CLOSE l-!SV-70-6773, CCS

THRM BAR BSTR PUMP I

B-B DlSCH ISOLATION

[A5W/737].

STANDARD: l-ISV-70-677B has been located and turned clockwise to

close. Step is critical to isolate flow path to prevent

thermal shock to RCP seals when CCS is restored.

After the performer demonstrates how to close

valve, state that the hand wheel turns many turns

and stops.

  • CUE:

COMMENTS:

CRITICAL

STEP

-

SAT

-

UNSAT

CRITICAL

STEP

-

SAT

-

UNSAP

    • /falicized Cues Are To Be Used Ody If JPM Performance Is Being Simulated.

STEP I O :

Inform the Control Koorn Operator that Appendix A of

ECA-0.0 has been completed.

STANDAKD: The control room operator has been informed that the

Appendix A has been completed.

    • CUE:

When notified, acknowledge the report using repeat

back.

COMMENTS:

END OF TASK

TIM STOP:

B.2.a /Local

Page 9 Qf 10

-

SAT

-

UNSAT

    • Italicized Cues Are TO Be Used Only If JPM Performance Is Being Simulated.

CANDIDATE CUE SHEET

(TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK)

DIRECTION TO TRAINEE:

I will explain the initial conditions, and state the task to be performed. All control

room steps shall be performed for this JPM, including any required

communications. I will provide initiating cues and reports on other actions when

directed by you. Ensure you indicate to me when you understand your assigned

task. To indicate that you have completed your assigned task return the handout

sheet B provided you.

INITIAL CONDITIQNS:

The unit has just entered Mode 3 following a shutdown required by Tech. Specs due to

the loss of 6.9kV Shutdown Board IB-8.

The "B" CVCS Seal Injection Water Filter is in service.

A tornado on site caused a complete loss of Off-Site power and the 1A-A Diesel

Generator failed to start.

The crew transitioned to ECA-0.0 due to the loss of shutdown power and is progressing

through the steps.

Attempts are being made to restore shutdown power.

You are an AUO on shift.

INlTlATlNG CUES:

The CRO has directed you to perform Appendix "A" of ECA 0.0 to isolate the RCP

seals and thermal barrier.

You are to notify the CRO when you have finished Appendix A.

B.2.b /Local

Page 1 of 7

REGION II

INITIAL LICENSE EXAMINATION

JOB PERFORMANCE MEASURE

B.2.b JPMA034/Local

Reset the TDAFW Pump (after mechanical

overspeed) per SOI-3.02

APPLICANT

EXAMINER

B.2.b /Local

Page 2 of 7

REGION II

INITIAL LICENSE EXAMINATION

JOB PERFORMANCE MASURE

Bask: Reset The TSAFW Pump (After Mechanical Overspeed) Per 501-3.02

Alternate Path: NIB

Facility JPM #:

3-OT-JPMA034 Rev 6

K/A Ratinds):

061-K4.07 [3.1/3.3]

2.1.30 [3.9/3.4]

Task Standard:

The Turbine-Driven AFW pump Trip and Throttle (TT) valve has been reset as

indicated by the trip lever remaining in the engaged position.

Candidate:

Time Start:

SSN

Time Finish:

NAME

Performance Rating: SAT __ UNSAT

~

Performance Time -

COMMENTS

Ei.2.b /bacai

Page 3 of 7

PoolslEuuipmen~Broced~res

Needed:

Hard Hat, Safety Glasses, Hearing Protection, Gloves and Plant Approved Shoes.

Sol-3.02 (Latest Revision)

Safety Considerations: Keep away from rotating parts during JPM performance (Pump

has auto start)

NOTE:

JPM to be started at the Radwaste AUO Desk.

READ TO OPERATOR

DIRECTION TO TRAINEE:

I will explain the initial conditions, and state the task to be performed. All control

room steps shall be performed for this JPM, including any 'required

communications. I will provide initiating cues and reports on other actions when

directed by you. Ensure you indicate to me when you understand your assigned

task. To indicate that you have completed your assigned task return the handout

sheet I provided you.

INITIAL CONDITIONS:

A Reactor Trip has occurred from 100 % power.

The Turbine-Driven AFW pump has tripped on mechanical overspeed.

The MCW Operator informs you of the AFW pump turbine trip and that he ran the motor

in the closed direction for 30 seconds.

You are the Aux Building AUO.

INITIATING CUES:

The MCR operator directs you to locally check the Trip and Throttle (T and T)

valve in the proper position to be reset and then reset the Turbine-Driven AFW

pump Trip and Throttie valve.

You are to notify the MCR operator after the valve has been reset so that the MCR

alarm may be reset.

B.2.b /Local

Page 4 of 7

START TIME:

STEP I:

Obtain a copy of the procedure.

STANDARD: A copy of Sol-3.02 Section 8.3 has been obtained.

EXAMINERS CUE: After the performer has demonstrated the

method of obtaining the correct instruction, the

evaluator can provide a copy of the instruction.

COMMENTS:

NOTE: The following steps are the steps in Section 8.3.

NOTE 1

Following an Overspeed Trip, the I-HS-46-56!3, TB AFW PMP

TRIP/THV 1-FCV-1-51 PQS CNTL, local limit lights will show valve

CLOSED.

NOTE 2

FIGURE 1 provides additional information for local operation

STEP 2:

[STEP 4 1 IF a Mechanical Overspeed Trip occurred,

THEN RELATCH the Mechanical Overspeed Trip Device

locally.

STANDARD: The connecting rod has been placed in the reset position

(moved towards the T&T valve) by Pulling the reset

connecting rod towards the trip and throttle valve till

movement stops. Step is critical to reset mechanical

Overspeed trip mechanism.

    • CUE: If asked, before linkage is reset, state that the trip

lever is down, and the valve stem pieces are not

meshed.

    • CUE:

If asked, afler performer demonstrates proper

method to reset trip device, then state the trip lever

remains in the engaged position but the valve stem

pieces are meshed.

COMMENTS:

SAT

-

-

UNSAT

CRITICAL

STEP

-

SAT

sl_ UNSAT

    • Italicized Cues Are To Be Used Only I f JPlM Performance Is Being Simulated.

B.2.b /Local

Page 5 of 7

STEP 3:

[STEP 21 IF in the MCR, THEN PLACE 1-HS-46-56A-S,

T-D AFWP T&T VLV, in CLOSE, and HOLD for 30

seconds to latch 1-FCV-1-51 motor drive to the valve

stem.

STANDARD: Performer N/As step based upon task assignment initial

conditions and proceeds to next step.

COMMENTS:

~

UNSAT

STEP 4:

[STEP 3 1 IF local [A3T/692], THEN

[a] PLACE 1-XS-46-57, TB AFW PMP CONTROLS

TRANSFER SWITCH to AUX. [behind CCS Seal

leakage tank]

FCV-1-51 POS CNTL, TO CLOSE, and HOLD for 30

seconds to latch 1-FCV-1-51 motor drive to the valve

stem.

[b] DEPRESS 1-HS-46-56B, TD AFW PMP TRIP/THV 1-

STANDARD: Perkmer N/As step based upon task assignment initial

conditions.

I

COMMENTS:

-

SAT

-

UNSAP

    • italicized Cues Are To Be Used Only If JPM Performance Is Being Simulated.

STEP 5:

[STEP 41 IF Turbine will not be restarted immediately,

THEN ENSURE motor drive is latched to valve stem

(IQcaliy).

STANDARD: Performer verifies that motor drive is latched to valve

stem.

    • CUE: I f valve checked; the valve stem pieces are meshed

COMMENTS:

STEP 6:

NOTIFY Unit Operator that Turbine Driven AFW pump Trip

& Throttle Valve has been reset.

STANDARD: The MGR operator has been notified that Turbine Driven

AFW pump Trip & Throttle Valve has been reset.

    • CUE:

When notified, acknowledge the report using repeat

back

COMMENTS:

END OF TASK

TIME STOP:

B.2.b /Local

Page 0 of 7

-

SAT

-

UNSAT

-

SAT

-

UNSAT

    • italicized Cues Are To Be Used Only If JPM Performance Is Being Simulated.

CANDIDATE CUE SHEET

(TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK)

DIRECTION TO TRAINEE:

I will explain the initial conditions, and state the task to be performed. All control

room steps shall be performed for this JPM, including any required

communications. I will provide initiating cues and reports on other actions when

directed by you. Ensure you indicate to me when you understand your assigned

task. To indicate that you have completed your assigned task return the handout

sheet I provided you.

INITIAL CONDITIONS:

A Reactor Trip has occurred from 100 % power.

The Turbine-Briven AFW pump has tripped on mechanical overspeed.

The MCW Operator informs you of the AFW pump turbine trip and that he ran the motor

in the closed direction for 40 seconds.

You are the Aux Building AUO.

INITIATING CUES:

The NlCR operator directs you to locally check the Trip and Throttle (T and T)

valve in the proper position to be reset and then reset the Turbine-Driven AFW

pump Trip and Throttle valve.

You are to notify the MCR operator after the valve has been reset so that the MCR

alarm may be reset.

B.2.c Local

Page 1 of 22

REGION II

INITIAL LICENSE EXAMINATION

JOB PERFORMANCE MEASURE

B.2.c JPMAOOl B/Local

Perform local restart of Control and Service Air

Compressors per AOI-10

APPLICANT

EXAMINER

B.2.c /Local

Page 2 of 12

REGION II

INITIAL LICENSE EXAMINATION

JOB PERFORMANCE MEASURE

Perform local restart of Control and Service Air Compressors per AOI-10.

Alternate Path: Compressor "A has high discharge air temperature and high oil

indication lights. Compressor "a" fails to auto load.

3-OT-JPMA001B Rev 3

FaciliW JPM #:

  • atur

K/A Ratinds):

878-A3.01 [3.1/3.2]

065-AK3.08 [3.7/3.9] 065-AA2.08 [2.9/3.3]

2.1.20 [4.2/4.2]

2.1.30[3.1/3.2]

Task Standard: "A" and "B" Air Compressors have been aligned and started per AOI-10. Control Air

(Non-Essential) pressure has been re-established.

Preferred Evaluation Location:

Simulator -

References: 801-10 "Loss of Control Air" Rev. 27

Task Number:: AUO-032-AOI-010-002

APPLICABLE FOR: AUO/RB/SRB

Preferred Evaluation Method:

In-Plant

X

Perform

Simulate

X

RO-032-801-10-002

10CFR55.45: 3, 4, 6, 8

Validation Time:

10

min.

Time Critical: No


s--____s_______________------_----------------------------

_____________-------_________sss_ssss___-----------------------------------

Candidate:

Time Start:

NAME

SSN

Time Finish:

Performance Rating: SAT -

UNSAT _s

Performance Time -

COMMENTS

8.2.c /Local

Page 3 of 12

ToolslEcluipmentl8rocedures Needed:

Hard Hat, Safety Glasses, Hearing Protection, Gloves and Plant Approved Shoes.

AOI-10 Attachment 1

High Noise Area. Energized rotating equipment that can auto start.

NOTE:

EVALUATOR NOTE: Provide a copy of AOI-IO Attachment 1 to perfolrmer with

candidate's cue sheet.

Start this JPM in the MCR.

READ TO QPERATQR

DIRECTION TO TRAINEE:

I will explain the initial conditions, and state the task to be performed All control

room steps shall be performed for this JPM, including any required

communications. I will provide initiating cues and reports on other actions when

directed by you. Ensure you indicate to me when you understand your assigned

task. To indicate that you have completed your assigned task return the handout

sheet I provided you.

INITIAL CONDITIONS:

A Station Blackout has occurred resulting in a reactor trip.

The DGs have started and are feeding the SD Bds.

The Control and Service Air compressors were aligned normal with "C" air compressor

in the lead prior to the BlackouVtrip.

A loss of Non-essential and Service air has occurred (Air pressure is at 75 psig

drop p ing ) .

Essential Air is being supplied by the Aux. Air cornpressors

The 480V Aux Bldg Common Bd does not have voltage available on its normal or alt

Local control power is available to the air compressors (no alarm in MCR).

You are a support AUQ on shift

supply.

INITIATING CUES:

The MCR operator has dispatched you with a copy of Attachment 1 of AOl-10 with

instructions to perform steps 2 through 'IO.

Notify the MCR operator when the task is complete.

B.2.c /Local

Page 4 of 12

START TIME:

STEP 1:

Obtain a copy of the procedure.

STANDARD: A copy of AOI-IO, Attachment 1 ha5 been obtained.

EXAMINERS CUE Provide copy of AOI-10 Attachment 1 to

performer.

COMMENTS:

STEP 2:

[Step 21 Localiy CHECK 0-PCV-33-4, SERVICE AIR

SUPPLY [SOLATION, CLOSED [T7M/708].

STANDARD: 0-PCV-33-4 has been checked in the closed position by

either the green local indicating light or the stem down on

the valve.

    • CUE:

When the valve is checked, state fiat green light

QN, Red right OFF, Stem down, indication at C

COMMENTS:

-

SAT

-

UNSAT

-

SAT

__ UNSAT

    • Italicized Cues Are To Be Used Only !f JPM Performance Is Being Simulated.

B.2.c Local

Page 5 of 12

STEP 3:

[STEP 31 CHECK local station alarm DARK [ Panel O-L-

240, T7M/708]

STANDARD: Local Station (Panel 0-b-24Q) Alarms have been checked

and Operator proceeds to RNO column due to high

discharge air temp and high oil temp on A compressor.

Step is critical because A cornpressor would have

trip logic still set with switch not reset locally.

    • CUE:

When checked, state that Compressor A has a

high discharge air temp and high oil temp light

illuminated.

COMMENTS:

STEP 4:

[STEP 3 RNO a] IF local control station alarm LIT, THEN

PERFORM the following for each air cornpressor in alarm:

a.

RESET high air temp at each compressor (0-TS-32-

4T, -36, -31).

STANDARD: The High Air Temp reset push button, 0-TS-32-41, (on

west side of A air compressor) has been depressed.

Step is critical because A compressor cannot be

started with the alarm switch NOT reset.

    • CUE:

When checked, and after candidate indicates how to

depress pushbutton for 0-TS-32-41

state it is as you

see it (reseq.

COMMENTS:

CRITICAL

STEP

-

SAT

-

L A T

CRITLCAL

STEP

I__ SAT

-

UNSAT

    • ltaiicized Cues Are To Be Used Only E f JPM Performance Is Being Simulated.

B.2.c Local

Page 6 of 12

STEP 5:

[STEP 3 RNO b] RESET high oil temp at each air

compressor (0-TS-32-40, -35, -30).

STANDARD: The High oil Temp reset push button, 0-TS-32-40, (on

east side of A air cumpressor) has been depressed.

Step is critical because A compressor cannot be

started with the alarm switch NOT reset.

    • CUE:

COMMENTS:

When checked, and affer candidate indicates how to

depress pushbuffon for 0-TS-32-40 state it is as you

see it reset.

STEP 6:

[STEP 3 RNO c] RESET cummon alarm using C-HS-32-

233: COMPRESSOR A, B, C RESET [0-L-24< yellow

PB].

STANDARD: 0-HS-32-233 has been pushed. Step is critical because

A compressor cannot be started without using

pushbutton to reset trip logic.

COMMENTS:

CRlTlCAL

STEP

SAT

-

CRITICAL

STEP

-

SAT

    • ltaficired Cues Are To Be Used Only If JBM Performance Is Being Simulated.

B.2.c /Local

Page 7 of 12

STEP 7:

[STEP 3 RNO d] CHECK common and all local alarms,

DARK.

STANDARD: All alarms on panel have been checked dark.

    • CUE:

After high air temp and high oil temp. reset push

buttons at compressor

and 0-HS-32-256 has

been pushed, inform performer that all alarms

lights on panel are dark.

COMMENTS:

STEP 8:

[STEP 41 PLACE the following C&SS Compressors to

WAND [Q-L-240]:

A, 0-HS-32-25D.

B, Q-HS-32-26A.

STANDARD: 0-HS-32-25B for A Compressor and 0-HS-32-26A for

B Compressor have been placed to the HAND position.

Step is critical because the hand switches enable the

respective local start pushbuttons.

    • CUE:

COMMENTS:

Both handswitches point to HAND.

-

SAT

-

UNSAT

CRITICAL

STEP

-

SAT

-

UNSAT

    • /talicized Cues Are TO Be Used Only If JPM Performance Is Being Simulated.

B.2.c /Local

Page 8 of 12

STEP 9:

[STEP 51 PLACE 0-HS-32-25A1 STATION AIR

COMPRESSOR SEQUENCE CONTROL, to Position I.

STANDARD: 0-HS-32-25A, Station Air Compressor Sequence Selector

Control, has been placed in Position 1.

    • CUE:

State that Sequence Selector indicates position 3

before operation and fhen state position 1 affer

operation.

COMMENTS:

STEP I O :

[STEP 61 START Air Compressor A by pushing 0-HS- 32-25E.

'STANDARD: 0-HS-32-25E manual start push button is depressed

Step is critical to start air compressor.

    • CUE:

I f JPM Steps 4,5, 6, and 8 were SAT, then when PB

is depressed, if asked, state that a air cornpressor

sfart was heard. If JPM Steps 4, 5, 6, or 8 were

UNSAT, if asked, state that compressor staart was

not heard.

COMMENT'S:

___ SAT

-

UNSAT

CRITICAL

STEP

-

SAT

-

UNSAT

    • italicized Cues Are To Be Used Onry If JPM Performance Is Being Simulated.

B.2.c /Local

Page 9 of 12

STEP 11:

[STEP 73 CHECK Compressor A loads automatically.

STANDARD: It has been determined that air compressor "A" is NOT

loaded. Operator proceeds to RNO coiumn due to failure

of "A" compressor to load.

When checked, state that the air compressor sound

indicates that it has NOT loaded, state that air

pressure is NOT rising (several /oca/ gauges), or, if

both solenoids are checked to be magnetized, state

that they are de-energized.

    • CUE

COMMENTS:

STEP 12:

[STEP 7 RNO] IF Compressor A does not Auto load,

THEN PLACE 0-HS-32-43A and -435 to ON (Local O-JB-

291-226).

STANDARD: 0-HS-32-438 and 0-HS-42-43B have been placed to the

ON positions and it has been deteimined that air

compressor "Ai has loaded. Step is critical to ensure

solenoids energized to allow "A" air compressor to

load.

    • CUE: Affer hand switches have been placed to the ON

position and when checked, state that the air

compressor sound indicates that it has loaded, the

air pressure is rising, or, if both so/ensids are

checked to be magnefized, state that they are

energized.

COMMENTS:

-

SAT

___ UNSAT

CRlTICAL

STEP

-

SAT

UNSAT

    • Italicized Cues Are To Be Used Only I f JPM Performance is Being Simulated.

B.2.c /Locai

Page 10 of 12

STEP 13:

[STEP 7 RNO] IF Compressor A does not load from

local panel THEN:

a. CLOSE 0-ISV-32-578, STATION AIR COMPR A

UNLQADING HEIR ISOL.

UNLOADING HBR TEST.

b. VENT 0-TV-32-579, STATION AIR COMPR A

STANDARD: Performer determines that cornpressor has loaded

(previous step) and moves to the next step.

COMMENTS:

STEP 14:

[STEP 81 START Compressor B by pushing 0-HS-32-

268.

STANDARD: 0-HS-32-26B manual start push button is depressed

Step Is critical to start air compressor.

    • CUE:

If JPM Step 8 was SAP, then when PB is depressed,

if asked state that a air compressor sfasp was

heard. If JPM Steps 8 were UNSAT, if asked, state

that compressor starf was not heard.

COMMENTS:

STEP 15:

[STEP 91 CHECK Compressor B loads automatically.

STANDARD: It has been determined that air compressor "B" is fully

loaded.

    • CUE:

When checked, state that the air compressor sound

indicates that it has loaded or, if both solenoids are

checked to be magnetized, state that they are

energized.

COMMENTS:

-

SAT

__ UNSAT

CRITICAL

STEP

-

SAT

-

UNSAT

-

SAT

-

UNSAT

    • italicized Cues Are To Be Used Only 15 JPM Performance Is Being Simuiated.

5.2.c /Local

Page 11 of 12

STEP 16:

STANDARD:

[STEP 101 MONITOR Air Compressor operation.

Compressors auto loading.

Qil Pressure 25-30 psig on A, B, and C.

Cooling water flow.

Oil pressure is checked on both compressors to be 25-30

psig. (A. 0-PI-32-40 & B. 0-PI-32-35)

Cooling water is verified by observing discharge drains.

Compressors are checked for full load operation.

Operator determines that Compressor A will have to be

manuaily loaded and unloaded to maintain greater

then 80 psig.

NOTE: C Air Compressor is shutdown due to loss of

power

    • CUE:

Affer each parameter is checked, inform the

Performer that each compressor has 28 psi$ oil

pressure, the coolhng water fiow is normal and the

compressors are ful!y loaded.

EXAMINERS CUE: When operator determines that Compressor

A will have to be manually kwdedlunioaded

then terminate JBM by stating Well stop

here.

COMMENTS:

END OF TASK

TIME STOP:

    • Italicized Cues Are To Be Used Ody FJPM Performance Is Being Simulated.

CANDIDATE CUE SHEET

(TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK)

DIRECTION TO TRAINEE:

I vdl explain the initial conditions, and state the task to be performed. All control

room steps shall be performed for this JPM: including any required

communications. I will provide initiating cues and reports on other actions when

directed by you. Ensure you indicate to me when you understand your assigned

task. To indicate that you have completed your assigned task return the handout

sheet I provided you.

lNlTlAL CONDITIONS:

A Station Blackout has occurred resulting in a reactor trip.

The DGs have started and are feeding the SB Bds.

The Control and Service Air compressors were aligned normal with "C" air compressor

in the lead prior to the Blackoutltrip.

A loss of Non-essential and Service air has occurred (Air pressure is at 75 psig

dropping).

Essential Air is being supplied by the Aux. Air compressors.

The 48QV Aux Bldg Common Bd does not have voltage available on its normal or alt

supply.

Local control power is available to the air compressors (no alarm in MCR).

You are a support AUO on shift

INITfATING CUES:

The MCR operator has dispatched you with a COPY of Attachment 1 of AOI-10 with

instructions to perform steps 2 through I O .

Notify the MCR operator when the task is complete.