ML042260376
| ML042260376 | |
| Person / Time | |
|---|---|
| Site: | Indian Point |
| Issue date: | 08/04/2004 |
| From: | Dacimo F Entergy Nuclear Northeast, Entergy Nuclear Operations |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| NL-04-096, TAC MB7274, TAC MC1385 | |
| Download: ML042260376 (2) | |
Text
' En tergy Entergy Nuclear Northeast Indian Point Energy Center 450 Broadway, GSB PO. Box 249 Buchanan, NY 10511-0249 Tel 914 734 6700 Fred Dacimo Site Vice President Administration August 4, 2004 Re:
Indian Point Unit No. 2 Docket No. 50-247 NL-04-096 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001
SUBJECT:
Withdrawal of Approval Requests for Relief Request 69 (TAC MC1385) and Best Estimate SBLOCA Methodoloov (TAC MB 7274)
References:
- 1. Entergy letter to NRC (NL-03-179), "ASME Section Xl Inservice Inspection Program Relief Request No. 69", dated November 18, 2003.
- 2. Entergy letter to NRC (NL-03-016); "Request for Review of WCAP-14936, Code Qualification Document for Best Estimate Small Break LOCA Analysis",
dated January 20, 2003.
Dear Sir; Entergy Nuclear Operations, Inc. (Entergy) is withdrawing the requests for approval previously submitted in References 1 and 2.
Reference 1 was an inservice inspection program relief request regarding the visual examination of bolted connections in systems containing borated water. Entergy now plans to perform inspections during the Fall 2004 refueling outage without the use of the subject relief request.
Reference 2 was a request for NRC review of WCAP-14936, which describes a best estimate analysis methodology applicable to small break loss of coolant accidents. Entergy was proposing to apply the new methodology in a license amendment request for a power uprate.
Entergy has determined that the best estimate methodology is no longer needed to support the power uprate project.
Gil-
?
NL-04-096 Docket No. 50-247 Page 2 of 2 There are no new commitments identified in this submittal. If you have any questions or require additional information, please contact Mr. Kevin Kingsley at 914,734-6695.
Fred R. Dacimo Site Vice President Indian Point Energy Center cc:
Mr. Patrick D. Milano, Senior Project Manager Project Directorate I, Division of Reactor Projects I/Il U.S. Nuclear Regulatory Commission Mail Stop 0 8 C2 Washington, DC 20555 Mr. Hubert J. Miller Regional Administrator Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Resident Inspector's Office Indian Point Unit 2 U.S. Nuclear Regulatory Commission P.O. Box 59 Buchanan, NY 10511