April 2, 2003 LICENSEE:
Entergy Nuclear Operations, Inc.
FACILITY:
Indian Point Nuclear Generating Unit No. 2
SUBJECT:
SUMMARY
OF FEBRUARY 13, 2003, MEETING REGARDING BEST ESTIMATE SMALL-BREAK LOSS-OF-COOLANT ACCIDENT METHODOLOGY (TAC NO. MB7274)
On February 13, 2003, the U.S. Nuclear Regulatory Commission (NRC) staff held a meeting at its offices in Rockville, Maryland, with representatives from Entergy Nuclear Operations, Inc.,
the licensee for the Indian Point Nuclear Generating Unit No. 2 (IP2). The list of meeting attendees is included as Enclosure 1. Enclosures 2 is a copy of the slides presented at the meeting by the licensee. The presentations closely followed information presented in the slides.
The licensee, with support from its contractor, Westinghouse Electric Company, presented information discussing the background and overview of its proposed methodology that will be used to perform small-break loss-of-coolant accident (LOCA) analysis. This analysis is part of the evaluation of the calculated emergency core cooling systems (ECCS) performance following postulated accidents. The licensee stated that it has requested NRC review and approval of the proposed methodology in order to apply the methodology to support a possible power increase to about 3216 megawatts thermal (MWt) from the current licensed power level of 3071.4 MWt. The licensee also discussed its schedule leading to the implementation of a power uprate after refueling outage 16.
The NRC staff stated that a review of this type of methodology generally takes about 11/2 to 2 years if the computer code is provided with the application. If not provided, the review time could increase to 3 years. Since the proposed methodology will use a number of the existing code models, the NRC staff will also need to verify that the models are appropriate for this application. The staff stated that it will be conducting the review without contractor support. In addition, a meeting to discuss the approach and the results of the staffs review would probably be scheduled with the Advisory Committee on Reactor Safety.
Upon completion of the overview and scheduler discussions, the meeting was closed to the public in order to discuss aspects of a proprietary nature to the proposed methodology. In this regard, Westinghouse presented information related to its analytical codes, plant-specific application to IP2, uncertainty approach, and the phenomena identification and ranking table (PIRT) process. Westinghouse stated that the PIRT was independently reviewed by an external review team.
The NRC staff noted that the licensee needs to be clear about the application of this methodology beyond IP2 and that questions may arise during the review dealing with generic applicability.
/RA/
Patrick D. Milano, Senior Project Manager, Section 1 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-247
Enclosures:
As stated cc w/encls: See next page The NRC staff noted that the licensee needs to be clear about the application of this methodology beyond IP2 and that questions may arise during the review dealing with generic applicability.
/RA/
Patrick D. Milano, Senior Project Manager, Section 1 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-247
Enclosures:
As stated cc w/encls: See next page DISTRIBUTION:
PUBLIC PDI-1 Reading File S. Richards J. Wermeil R. Laufer F. Akstulewicz R. Caruso P. Milano R. Landry S. Little F. Orr L. Ward S. Bajorek N. Lauben T. McGinty, OEDO P. Eselgroth, RGN-I B. Platchek, RGN-I OGC ACRS DOCUMENT NAME: C:\\ORPCheckout\\FileNET\\ML030920642.wpd ADAMS Accession No.: ML030920642
- See previous concurrence OFFICE PDI-1:PM:
PDI-1:LA SRXB:SC*
PDI-1:SC NAME PMilano SLittle RCaruso RLaufer DATE 04/02/03 04/2/03 03/26/03 04/2/03 Official Record Copy
Indian Point Nuclear Generating Station Unit 2 Mr. Jerry Yelverton Chief Executive Officer Entergy Operations 1340 Echelon Parkway Jackson, MS 39213 Mr. Michael R. Kansler Senior Vice President and Chief Operating Officer Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Mr. Fred Dacimo Vice President - Operations Entergy Nuclear Operations, Inc.
Indian Point Nuclear Generating Units 1 & 2 295 Broadway, Suite 1 P.O. Box 249 Buchanan, NY 10511-0249 Mr. Dan Pace Vice President Engineering Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Mr. James Knubel Vice President Operations Support Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Mr. Christopher J. Schwarz General Manager Operations Entergy Nuclear Operations, Inc.
Indian Point Nuclear Generating Unit 2 295 Broadway, Suite 1 P.O. Box 249 Buchanan, NY 10511-0249 Mr. John Kelly Director of Licensing Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Ms. Charlene Faison Manager, Licensing Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Mr. John McCann Manager, Nuclear Safety and Licensing Indian Point Nuclear Generating Unit 2 295 Broadway, Suite 1 P. O. Box 249 Buchanan, NY 10511-0249 Mr. Harry P. Salmon, Jr.
Director of Oversight Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Mr. John M. Fulton Assistant General Counsel Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Mr. Thomas Walsh Secretary - NFSC Entergy Nuclear Operations, Inc.
Indian Point Nuclear Generating Unit 2 295 Broadway, Suite 1 P. O. Box 249 Buchanan, NY 10511-0249 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Senior Resident Inspector, Indian Point 2 U. S. Nuclear Regulatory Commission 295 Broadway, Suite 1 P.O. Box 38 Buchanan, NY 10511-0038
Indian Point Nuclear Generating Station Unit 2 Mr. William M. Flynn, President New York State Energy, Research, and Development Authority 17 Columbia Circle Albany, NY 12203-6399 Mr. J. Spath, Program Director New York State Energy, Research, and Development Authority 17 Columbia Circle Albany, NY 12203-6399 Mr. Paul Eddy Electric Division New York State Department of Public Service 3 Empire State Plaza, 10th Floor Albany, NY 12223 Mr. Charles Donaldson, Esquire Assistant Attorney General New York Department of Law 120 Broadway New York, NY 10271 Mayor, Village of Buchanan 236 Tate Avenue Buchanan, NY 10511 Mr. Ray Albanese Executive Chair Four County Nuclear Safety Committee Westchester County Fire Training Center 4 Dana Road Valhalla, NY 10592 Ms. Stacey Lousteau Treasury Department Entergy Services, Inc.
639 Loyola Avenue Mail Stop: L-ENT-15E New Orleans, LA 70113 Alex Matthiessen Executive Director Riverkeeper, Inc.
25 Wing & Wing Garrison, NY 10524 Paul Leventhal The Nuclear Control Institute 1000 Connecticut Avenue NW Suite 410 Washington, DC, 20036 Karl Copeland Pace Environmental Litigation Clinic 78 No. Broadway White Plains, NY 10603 Jim Riccio Greenpeace 702 H Street, NW Suite 300 Washington, DC 20001
MEETING ATTENDEES CONSOLIDATED EDISON COMPANY OF NEW YORK, INC.
INDIAN POINT NUCLEAR GENERATING UNIT NO. 2 FEBRUARY 13, 2003 NRC Staff:
Name Ralph Caruso Frank Akstulewicz Ralph Landry Frank Orr Len Ward Patrick Milano Steve Bajorek Norm Lauben Title Section Chief Section Chief Sr. Reactor Engineer Reactor Engineer Sr. Reactor Engineer Sr. Project Manager Sr. Advisor Sr. Nuclear Engineer Organization NRR/Division of Systems Safety and Analysis (DSSA)/Reactor Systems Branch (SRXB)
NRR/DSSA/SRXB NRR/DSSA/SRXB NRR/DSSA/SRXB NRR/DSSA/SRXB NRR/Division of Licensing Project Management/Project Directorate I Office of Research (RES)
RES Entergy Nuclear Operations:
Name David Morris Ardesar Irani Kevin Kingsley Walter Wittich Title Manager, Power Uprates Supervisor, Nuclear Engineering NRR Project Manager Sr. Project Manager Westinghouse Electric Company:
Name Robert Laubham Charles Brinkman Robert Kemper James Sechrist Jill Monahan Title Certified Sr. Project Manager Director, Washington Operations Sr. Engineer Manager Project Manager Other
Participants:
None