ML042170356
ML042170356 | |
Person / Time | |
---|---|
Site: | Oconee ![]() |
Issue date: | 07/20/2004 |
From: | Casto C Division of Reactor Safety II |
To: | Rosalyn Jones Duke Energy Corp |
References | |
EA-04-115 IR-04-012 | |
Download: ML042170356 (6) | |
See also: IR 05000269/2004012
Text
ATTACHMENT 2 CONTAINS PROPRIETARY INFORMATION
July 20, 2004
Duke Energy Corporation
ATTN: Mr. Ronald A. Jones
Vice President
Oconee Nuclear Station PROPRIETARY INFORMATION REMOVED
7800 Rochester Highway
Seneca, SC 29672
SUBJECT: OCONEE NUCLEAR STATION - NRC TRIENNIAL FIRE PROTECTION
INSPECTION (FOLLOW UP) REPORT 05000269/2004012, 05000270/2004012
AND 05000287/2004012 PRELIMINARY GREATER THAN GREEN FINDING
Dear Mr. Jones:
On February 18, 2004, the U.S. Nuclear Regulatory Commission (NRC) completed the on-site
portion of an open item inspection for your Oconee Nuclear Station Units 1, 2, and 3. Following
additional in-office review, the inspection was completed on July 13, 2004. The enclosed
inspection report documents the inspection findings, which were discussed on July 13, 2004,
with Mr. Noel Clarkson and other members of your staff.
This inspection was an on-site and in-office examination of an Unresolved Item (URI)
05000269, 270, 287/2002003-001, Failure to Meet License Basis Commitment For Staffing the
Standby Shutdown Facility (SSF) for a Confirmed Fire. This issue was unresolved pending a
review by the NRC to determine if a loss of function occurs and a safety significance
determination.
PROPRIETARY INFORMATION
Exempt from public release under the Freedom of
Information Act (5 U.S.C. 552). Ref: 2.390(d)(1)
Nuclear Regulatory Commission review required
before public release.
Determination made by:
Charles R. Ogle, Chief, EB1, DRS, RII
Signature /RA/ Date 7/20/4
DOCUMENT TRANSMITTED HEREWITH CONTAINS SENSITIVE UNCLASSIFIED INFORMATION
WHEN SEPARATED FROM ATTACHMENT 2, THIS DOCUMENT IS DECONTROLLED
2
ATTACHMENT 2 CONTAINS PROPRIETARY INFORMATION
Based on the results of this inspection, the NRC determined that the Oconee fire response
procedures were not consistent with the licensing basis in regards to the criteria for manning of
the Standby Shutdown Facility (SSF). In some scenarios this could result in a delay of transfer
of control to the SSF which could challenge the capability of the installed SSF makeup pump.
As a result, in some scenarios, this could result in pressurizer level failing to be maintained
within the indicating range as required by Appendix R. This apparent violation is identified as
AV 05000269, 270, 287/2002004-12, Failure to Meet Licensing Basis for Staffing the SSF in the
Event of a Confirmed Plant Fire.
This finding was assessed based on the best available information, including influential
assumptions, using the applicable Significance Determination Process (SDP) and was
preliminarily determined to be a Greater than Green finding. The NRCs calculated change in
core damage frequency for this finding is provided in Attachment 2. However, due to
uncertainties in developing the plant response to fires that leave the SSF as the exclusive core
damage mitigation strategy, this finding has been preliminarily characterized as Greater than
Green. Additional information in this regard from Duke Energy Corporation would allow a more
refined risk analysis.
The finding has a greater than very low safety significance because it could affect fire protection
defense in depth. The finding does not represent a current safety concern because you have
modified your procedures to ensure that the SSF is manned upon confirmation of a fire.
Before we make a final decision on this matter, we are providing you an opportunity (1) to
present to the NRC your perspectives on the facts and assumptions, used by the NRC to arrive
at the finding and its significance, at a Regulatory Conference or (2) submit your position on the
finding to the NRC in writing. If you request a Regulatory Conference, it should be held within
30 days of the receipt of this letter and we encourage you to submit supporting documentation
at least one week prior to the conference in an effort to make the conference more efficient and
effective. If a Regulatory Conference is held, it will be open for public observation. If you decide
to submit only a written response, such submittal should be sent to the NRC within 30 days of
the receipt of this letter.
This apparent violation is being considered for escalated enforcement action in accordance with
the "General Statement of Policy and Procedure for NRC Enforcement Actions" (Enforcement
Policy), NUREG-1600. The current Enforcement Policy is included on the NRCs Web site at
http://www.nrc.gov/reading-rm/adams.html
Please contact Mr. Charles R. Ogle at (404) 562-4605 within seven days of the date of this
letter to notify the NRC of your intentions regarding the regulatory conference for the
preliminary Greater than Green finding. If we have not heard from you within 10 days, we will
continue with our significance determination and associated enforcement processes on this
finding, and you will be advised by separate correspondence of the results of our deliberations
on this matter.
DOCUMENT TRANSMITTED HEREWITH CONTAINS SENSITIVE UNCLASSIFIED INFORMATION
WHEN SEPARATED FROM ATTACHMENT 2, THIS DOCUMENT IS DECONTROLLED
3
ATTACHMENT 2 CONTAINS PROPRIETARY INFORMATION
Since the NRC has not made a final determination in this matter, no Notice of Violation is being
issued for the inspection finding at this time. In addition, please be advised that the
characterization of the apparent violation described in the referenced inspection report may
change as a result of further NRC review.
In accordance with 10 CFR 2.390 of the NRCs "Rules of Practice," a copy of this letter,
portions of its enclosure and your response (if any) will be available electronically for public
inspection in the NRC Public Document Room or from the Publicly Available Records (PARS)
component of NRCs document system (ADAMS). However, the NRC is continuing to review
the appropriate classification of the SDP Phase 3 Evaluation (Attachment 2) within our records
management program, considering changes in our practices following the events of September
11, 2001. Using our interim guidance, the attached analyses have been marked as Proprietary
Information or Sensitive Information in accordance with Section 2.390(d) of Title 10 of the Code
of Federal Regulations. Please control the document accordingly (i.e., treat the document as if
you had determined that it contained trade secrets and commercial or financial information that
you considered privileged or confidential). We will inform you if the classification of these
documents change as a result of our ongoing assessments. ADAMS is accessible from the
NRC web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading
Room).
If you have any questions regarding this letter, please contact me at 404-562-4600.
Sincerely,
/RA/
Charles A. Casto, Director
Division of Reactor Safety
Docket Nos.: 50-269, 50-270, 50-287
License Nos.: DPR-38, DPR-47, DPR-55
Enclosure: Inspection Report 05000280,281/2004012
w/Attachments: 1. Supplemental Information
2. Phase 3 SDP Evaluation (Proprietary Information)
cc w/encl: (See page 4)
DOCUMENT TRANSMITTED HEREWITH CONTAINS SENSITIVE UNCLASSIFIED INFORMATION
WHEN SEPARATED FROM ATTACHMENT 2, THIS DOCUMENT IS DECONTROLLED
4
ATTACHMENT 2 CONTAINS PROPRIETARY INFORMATION
cc w/encl:
B. G. Davenport
Compliance Manager (ONS)
Duke Energy Corporation
ON03RC
7800 Rochester Highway
Seneca, SC 29672
Lisa Vaughn
Legal Department (PB05E)
Duke Energy Corporation
422 South Church Street
P. O. Box 1244
Charlotte, NC 28201-1244
R. L. Gill, Jr., Manager
Nuclear Regulatory Issues
and Industry Affairs
Duke Energy Corporation
526 S. Church Street
Charlotte, NC 28201-0006
Distribution:
L. Olshan, NRR
L. Slack, RII, EICS
C. Ogle, RII, DRS
B. Westreich, NSIR (hard copy w/encl)
E. McNiel, NSIR (hard copy w/encl)
RIDSNRRDIPMLIPB
OEMAIL
OFFICE RII:DRS RII:DRS RII:DRS RII:DRP RII:EICS RII:DRS
NAME ODONOHUE ROGERS OGLE RHAAG EVANS CASTO
DATE 7/19/2004 7/15/2004 7/15/2004 7/16/2004 7/16/2004 7/20/2004
E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO
OFFICIAL RECORD COPY DOCUMENT NAME: C:\ORPCheckout\FileNET\ML042170356.WPD
DOCUMENT TRANSMITTED HEREWITH CONTAINS SENSITIVE UNCLASSIFIED INFORMATION
WHEN SEPARATED FROM ATTACHMENT 2, THIS DOCUMENT IS DECONTROLLED
ATTACHMENT 2 CONTAINS PROPRIETARY INFORMATION
U. S. NUCLEAR REGULATORY COMMISSION
REGION II
Docket Nos.: 50-269, 50-270, 50-287
License Nos.: DPR-38, DPR-47, DPR-55
Report Nos.: 05000269/2004012, 05000270/2004012, 05000287/2004012
Licensee: Duke Energy Corporation
Facility: Oconee Nuclear Station
Location: 7800 Rochester Highway
Seneca, SC 29672
Dates: February 17 - July 13, 2004
Inspectors: K. ODonohue, Fire Protection Team Leader (Lead Inspector)
W. Rogers, Senior Reactor Analyst
Approved by: C. Casto, Director
Division of Reactor Safety
DOCUMENT TRANSMITTED HEREWITH CONTAINS SENSITIVE UNCLASSIFIED INFORMATION
WHEN SEPARATED FROM ATTACHMENT 2, THIS DOCUMENT IS DECONTROLLED
Enclosure
ATTACHMENT 2 CONTAINS PROPRIETARY INFORMATION
SUMMARY OF FINDINGS
IR 05000269/2004012, 05000270/2004012, 05000287/2004012; 02/17 - 07/13, 2004; Oconee
Nuclear Station, Units 1, 2, and 3; Significance Determination of Unresolved Item from Triennial
Fire Protection Inspection.
This in-office and on-site review were conducted by a regional inspector and a senior reactor
analyst. One preliminary Greater than Green finding with an apparent violation was identified.
The significance of most findings is indicated by their color (Green, White, Yellow, Red) using
IMC 0609 Significance Determination Process (SDP). Findings for which the SDP does not
apply may be Green or be assigned a severity level after NRC management review. The
NRC's program for overseeing the safe operation of commercial nuclear power reactors is
described in NUREG-1649, Reactor Oversight Process, Revision 3, dated July 2000.
A. NRC-Identified and Self-Revealing Findings
Cornerstone: Initiating Events and Mitigating Systems
- Preliminary Greater than Green. An apparent violation of 10 CFR 50, Appendix
R, Sections III.L.2.b and III.L.3 was identified, in that, for a severe fire in areas
requiring the manning of the Standby Shutdown Facility (SSF) and activation of
the SSF makeup pump, the licensees safe shutdown strategy and related
response procedures delayed the manning of the SSF until there was a loss of
function of high pressure injection and component cooling or feedwater. In some
scenarios, this would delay transfer of control to the SSF, thereby challenging
the operability of the installed SSF makeup pump. This could result in
pressurizer level failing to be maintained within the indicating range. The
licensee has revised the affected procedures and is evaluating the need for
additional corrective action.
This finding is greater than minor because it was associated with protection
against external factors and procedure quality cornerstone attributes. It
affected the objective of the Mitigating Systems cornerstone to ensure the
availability, reliability and capability of systems that respond to initiating events.
This degraded condition increased plant risk because, if a severe fire occurred in
areas requiring the manning of the SSF and activation of the SSF makeup pump,
the licensee's procedures may not preclude loss of reactor coolant beyond the
capability of the SSF makeup pump. (Section 4OA5.01)
B. Licensee-identified Violations:
None
DOCUMENT TRANSMITTED HEREWITH CONTAINS SENSITIVE UNCLASSIFIED INFORMATION
WHEN SEPARATED FROM ATTACHMENT 2, THIS DOCUMENT IS DECONTROLLED
Enclosure
ATTACHMENT 2 CONTAINS PROPRIETARY INFORMATION
Report Details
4. OTHER ACTIVITIES
4OA5 OTHER
.1 (Closed) URI 05000269, 270, 287/2002003-001: Failure to Meet License Basis
Commitment for Staffing the Standby Shutdown Facility in the Event of a Confirmed
Plant Fire.
Introduction: An apparent violation (AV) was identified for failure to comply with 10 CFR
50, Appendix R, Sections III.L.2.b and III.L.3, in that, for a severe fire in areas requiring
the manning of the SSF and activation of the SSF makeup pump, the licensees method
for implementing their alternative shutdown capability did not ensure that the reactor
coolant makeup function would be capable of maintaining the reactor coolant level within
the level indication of the pressurizer. This inspection finding was assessed using the
SDP and preliminarily determined to be Greater than Green (i.e., an issue with low to
moderate increased importance to safety, which may require additional NRC
inspections.)
Description: During the baseline triennial fire protection inspection, the inspectors
identified a finding involving the timeliness associated with manning the SSF, having
potential safety significance greater than very low significance. Specifically, per
procedure, the manning of the SSF was not to be initiated until the fire damage caused
a loss of both the high pressure injection (HPI) and component cooling (CC) systems or
a loss of all feedwater. The inspectors were concerned that waiting until loss of function
occurred to man the SSF could result in a loss of RCS inventory due to additional
challenges to and subsequent failures of a power operated relief valve (PORV) or
pressure safety valve (PSV). (Abnormal Procedure, AP/0/A/1700/025, Standby
Shutdown Facility Emergency Operating Procedure, Revision 20, implemented the
Auxiliary Shutdown design capability from the SSF in the event of a fire in areas
requiring the manning of the SSF and activation of the SSF makeup pump.)
By letter dated September 20, 1982, the licensee responded to a staff request for
additional information (letter dated July 17, 1982). In response to staff concerns
regarding the potential for spurious operation of reactor coolant system (RCS) isolation
valves (Question No. 4) the licensee stated:
"Upon confirmation of a fire in the plant, operating personnel will be dispatched to the
SSF where they will establish communication with the control room...If vital control and
monitoring functions (eg., reactor coolant pressure boundary, reactor coolant makeup
capability) become unacceptably degraded or unavailable from the control room, a
prompt transfer can be made and control established from the SSF....As stated above,
DOCUMENT TRANSMITTED HEREWITH CONTAINS SENSITIVE UNCLASSIFIED INFORMATION
WHEN SEPARATED FROM ATTACHMENT 2, THIS DOCUMENT IS DECONTROLLED
Enclosure
2
ATTACHMENT 2 CONTAINS PROPRIETARY INFORMATION
spurious operation is extremely unlikely within the first 10 minutes. To preclude
unacceptable consequences of spurious operation in the longer term, circuits are
designed to either preclude spurious operation or retain operability of the systems
necessary to mitigate such operation."
By letter dated April 28, 1983, the staff issued its SER of the Oconee Nuclear Station
SSF. This SER was based, in part, on the above referenced Duke response. Based on
review of these documents, the inspectors determined that upon a confirmed fire in the
Cable Spread Room or other areas where shutdown from the SSF may be required, the
SSF should be manned immediately upon the confirmation of a fire and communication
established with the MCR. However, as described above, the licensees procedures did
not require the SSF to be manned (or activated) until significant fire damage occurred.
This delay in manning the SSF could result in additional challenges to the PORVs and
PSVs and result in loss of RCS inventory beyond the SSF makeup capability. In some
scenarios this could result in a failure to maintain the RCS PZR level within the
indicating range.
The licensee captured this issue in its corrective action program in Problem
Investigation Process (PIP) O-02-00609.
Analysis: This finding affects the protection against external factors and procedure
quality cornerstone attributes. It affected the objective of the Mitigating Systems
cornerstone to ensure the availability, reliability and capability of systems that respond to
initiating events because existing procedural guidance may result in a fire damage
scenario that could impact the ability of the unit (s) to achieve and maintain safe
shutdown conditions. Because the finding affects fire protection, it was assessed in
accordance with the NRC Reactor Oversight Processs SDP as described in NRC
Inspection Manual Chapter 0609, Appendix F (MC 0609, App. F). The Phase 1
screening conclusion was that a Phase 2 screening should be performed. However,
due to the unique failure mechanism associated with the performance deficiency, the
senior risk analyst determined that a Phase 2 SDP would not be performed and the
finding was screened to a Phase 3 analysis.
Summary of Phase 3 SDP Analysis
This evaluation was performed by Region II SRAs. The Oconee Phase 3 SDP Analysis
is included in this inspection report as Attachment 2.
The Phase 3 analysis discusses the approach, site visit observations, assumptions,
screening analysis, fire ignition frequencies, fire scenario analysis, contributors to fire
risk, integrated assessment of fire-induced core damage frequency, and conclusions
developed from this analysis. The report also contains several appendices documenting
supplemental information used in the Phase 3 analysis.
DOCUMENT TRANSMITTED HEREWITH CONTAINS SENSITIVE UNCLASSIFIED INFORMATION
WHEN SEPARATED FROM ATTACHMENT 2, THIS DOCUMENT IS DECONTROLLED
Enclosure
3
ATTACHMENT 2 CONTAINS PROPRIETARY INFORMATION
The Phase 3 considers the conforming case where operation personnel are dispatched
to the SSF at the confirmation of a fire in the fire areas of concern. The Phase 3 then
considers the non-conforming case where operation personnel are dispatched only after
loss of critical plant functions. This time delay increases the challenges to the PORVs
or if they are not available, challenges to the PSVs. The additional risk is quantified by
the CDF. The core damage frequency (CDF) for fires which require the SSF to
prevent core damage was calculated in each case and summed for each unit.
The risk analysts concluded that the CDF [the difference between the conforming
case CDF and the non-conforming case CDF] was 3E-6 (low to moderate importance to
safety.)
SDP/Enforcement Review Panel (SERP) Evaluation
The total change in CDF due to the performance deficiency was found to be 3 E-6 / yr
for each unit. The dominant accident sequences that cause the largest CDF are fully
developed fires that require manning of the SSF. The color associated with this
magnitude of change in CDF is Greater than Green. Therefore, the SERP has
preliminarily determined this issue to be a Greater than Green finding.
Enforcement: Oconee Unit 1 Operating License DPR-38, Oconee Unit 2 Operating
License DPR-47, and Oconee Unit 3 Operating License DPR-55 Condition D provide, in
part, that the licensee implement and maintain in effect all provisions of the approved
fire protection program as described in the UFSAR and as approved in the SER dated
April 28, 1983 and subsequent supplements.
The licensees UFSAR commits to 10 CFR 50, Appendix R, Sections III.G and III.L.
Section III.G.3 states that alternative shutdown capability should be provided where the
protection of systems whose function is required for hot shutdown, does not satisfy the
requirements of III.G.2.Section III.L of Appendix R provides requirements to be met by
alternative shutdown methods.Section III.L.2.b states, in part, that The reactor coolant
makeup function shall be capable of maintaining the reactor coolant level. . . within the
level indication in the pressurizer in PWRs."Section III.L.3 specifies that procedures
shall be in effect to implement this capability.
Contrary to the above, on February 8, 2002, the inspectors determined that the
procedures specified for a fire requiring SSF manning and activation would not assure
that reactor cooling makeup function would be capable of maintaining reactor coolant
level within the indicated range of the pressurizer. Specifically, delaying the manning of
the SSF until after the occurrence of a loss of function of the high pressure injection and
component cooling or feedwater rather than manning the SSF immediately upon
confirmation of a fire in the areas of concern may not preclude an extended loss of
reactor coolant system inventory. This could result in pressurizer level failing to be
maintained within the indicating range. This apparent violation is identified as AV
DOCUMENT TRANSMITTED HEREWITH CONTAINS SENSITIVE UNCLASSIFIED INFORMATION
WHEN SEPARATED FROM ATTACHMENT 2, THIS DOCUMENT IS DECONTROLLED
Enclosure
4
ATTACHMENT 2 CONTAINS PROPRIETARY INFORMATION
05000269, 270, 287/2004012-01, Failure to Meet Licensing Basis for Staffing the SSF in
the Event of a Confirmed Plant Fire.
4OA6 Meetings, Including Exit
On July 13, 2004, the inspectors presented the inspection results by telephone to Mr.
Noel Clarkson and other members of your staff, who acknowledged the findings. The
inspectors confirmed that proprietary information was not provided or examined during
the inspection.
DOCUMENT TRANSMITTED HEREWITH CONTAINS SENSITIVE UNCLASSIFIED INFORMATION
WHEN SEPARATED FROM ATTACHMENT 2, THIS DOCUMENT IS DECONTROLLED
Enclosure
ATTACHMENT 2 CONTAINS PROPRIETARY INFORMATION
SUPPLEMENTAL INFORMATION
KEY POINTS OF CONTACT
Licensee personnel
G. Davenport, Compliance Manager (ONS)
D. Garland, Sr. Engineer
J. Smith, Regulatory Compliance
J. Weast, Regulatory Compliance
H. Barrett, Sr. Engineer (Design Basis Engineering)
N. Constance, Operations Training
D. Henneke, Sr. Engineer (PRA Engineering)
NRC personnel
M. Shannon
LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED
Opened
05000269,270,287/2004012-01 AV Failure to Meet Licensing Basis for Staffing the
SSF in the Event of a Confirmed Plant Fire
(Section 4OA5.1)
Closed
05000269,270,287/2002003-01 URI Failure to Meet License Basis Commitment for
Staffing the SSF in the Event of a Confirmed Plant
Fire (Section 4OA5.1)
LIST OF DOCUMENTS REVIEWED
Procedures:
AP/0/A/1700/025, Standby Shutdown Facility Emergency Operating Procedure, Revision 20
AP/0/A/1700/025, Standby Shutdown Facility Emergency Operating Procedure, Revision 25
AP/1/A/1200/008, Loss of Control Room, Revision 8
DOCUMENT TRANSMITTED HEREWITH CONTAINS SENSITIVE UNCLASSIFIED INFORMATION
WHEN SEPARATED FROM ATTACHMENT 2, THIS DOCUMENT IS DECONTROLLED
Attachment 1
2
ATTACHMENT 2 CONTAINS PROPRIETARY INFORMATION
Plant Issue Reports Reviewed:
PIP-O2-00609, Questions of Procedural Guidance for Spurious Actuation of EFW and
Acceptability of the Start of the 10 minute Time for Spurious Actuations
Other Documents:
Oconee UFSAR Chapter 9.5.1 Fire Protection System, 12/31/00
Special Study, Pwr Pressurizer Safety Valves and Main Steam Safety Valves and BWR
Safety/Relief Valves Performance, dated December 1998
NUREG-1715, Vol. W, Component Performance Study - Pressurizer Power-Operated Relief
Valves (PORVs), 1987 - 2000 (Draft)
Letter dated September 20, 1982 from H. Tucker (Duke) to H. Denton (NRC); Subject:
Response to July 17, 1982 staff request for additional information regarding Oconee Standby
Shutdown Facility
Safety Evaluation Report dated April 28, 1983
Response To Request For Technical Assistance Regarding Appendix R Compliance - Oconee
Nuclear Station (TAC NOS. 65629, 65630, 65631), Dated September 11, 1989
DOCUMENT TRANSMITTED HEREWITH CONTAINS SENSITIVE UNCLASSIFIED INFORMATION
WHEN SEPARATED FROM ATTACHMENT 2, THIS DOCUMENT IS DECONTROLLED
Attachment 1
3
ATTACHMENT 2 CONTAINS PROPRIETARY INFORMATION
LIST OF ACRONYMS
ASP Auxiliary Shutdown Panel
AV Apparent Violation
BTU British Thermal Units
CCDP Conditional Core Damage Probability
CDF Core Damage Frequency
CFR Code of Federal Regulations
CPV Cable Penetration Vault
CV&T Cable Vault and Tunnel
EIHP Early Inventory High Pressure Injection
ESGR Emergency Switchgear and Relay Room
FCA Fire Contingency Action
IEL Initiating Event Likelihood
IPEEE Individual Plant Examination of External Events
LOCA Loss of Coolant Accident
NCV Non-cited Violation
No. Number
NRC U.S. Nuclear Regulatory Commission
MCC Motor Control Center
MCR Main Control Room
PARS Publicly Available Records System
PI Plant Issue
PWR Pressurized Water Reactor
RCP Reactor Coolant Pump
SBCV Service Building Cable Vault
SCBA Self-contained Breathing Apparatus
SDP Significance Determination Process
SER Safety Evaluation Report
SERP SDP/Enforcement Review Panel
UFSAR Undated Final Safety Analysis Report
URI Unresolved Item
DOCUMENT TRANSMITTED HEREWITH CONTAINS SENSITIVE UNCLASSIFIED INFORMATION
WHEN SEPARATED FROM ATTACHMENT 2, THIS DOCUMENT IS DECONTROLLED
Attachment 1