ML041770158

From kanterella
Jump to navigation Jump to search

Tech Spec Pages for Amendment 340 Regarding TS 3.6.5, Reactor Building Spray and Cooling Systems.
ML041770158
Person / Time
Site: Oconee Duke Energy icon.png
Issue date: 06/04/2004
From:
NRC/NRR/DLPM
To:
References
TAC MC3370
Download: ML041770158 (8)


Text

Reactor Building Spray and Cooling Systems 3.6.5 3.6 CONTAINMENT SYSTEMS 3.6.5 Reactor Building Spray and Cooling Systems LCO 3.6.5 Two reactor building spray trains and three reactor building cooling trains shall be OPERABLE.


--------------------- J r-- - --- - ---- di__.__

Only one train of reactor building spray and two trains of reactor building cooling are required to be OPERABLE during MODES 3 and 4.

APPLICABILITY: MODES 1, 2,3, and 4.

ACTIONS k rI%-

A---- --------------- 1 I A ______

LCO 3.0.4 Is not applicable for Unit 2.

_~~ -- - -- - - - - _---___------_- __

CONDITION REQUIRED ACTION COMPLETION TIME A. One reactor building A.1 Restore reactor 7 days spray train inoperable in building spray train to MODE 1 or 2. OPERABLE status. AND 14 days from discovery of failure to meet the LCO B. One reactor building B.1 Restore reactor 7 days cooling train inoperable building cooling train to In MODE 1 or 2. OPERABLE status. AND 14 days from discovery of failure to meet the LCO (continued) ml OCONEE UNITS 11,2, & 3 3.6.5-1 Amendment No. 3 40 I

Reactor Building Spray and Cooling Systems B 3.6.5 BASES LCO Each reactor building spray train shall include a spray pump, spray (continued) headers, nozzles, valves, piping, Instruments, and controls to ensure an OPERABLE flow path capable of taking suction from the BWST (via the LPI System) upon an Engineered Safeguards Protective System signal and manually transferring suction to the reactor building sump. The OPERABILITY of RBS train flow instrumentation is not required for OPERABILITY of the corresponding RBS train because system resistance hydraulically maintains adequate NPSH to the RBS pumps and manual throttling of RBS flow Is not required. However, TS 3.3.8, Required Action F.1 requires the affected RBS train to be declared inoperable when the RBS flow instrument is Inoperable. A license amendment is being processed to eliminate this requirement. During an event, LPI train flow must be monitored and controlled to support the RBS train pumps to ensure that the NPSH requirements for the RBS pumps are not exceeded.

If the flow instrumentation or the capability to control the flow in a LPI train is unavailable then the associated RBS train's OPERABILITY is affected until such time as the LPI train Is restored or the associated LPI pump is placed in a secured state to prevent actuation during an event.

Each reactor building cooling train shall include cooling coils, fusible dropout plates, an axial vane flow fan, Instruments, valves, and controls to ensure an OPERABLE flow path. Valve LPSW-1 08 shall be locked open to support system OPERABILITY.

APPLICABILITY In MODES 1,2, 3, and 4, an accident could cause a release of radioactive material to containment and an increase in containment pressure and temperature, requiring the operation of the reactor building spray trains and reactor building cooling trains.

In MODES 5 and 6, the probability and consequences of these events are reduced due to the pressure and temperature limitations of these MODES.

Thus, the Reactor Building Spray System and the Reactor Building Cooling System are not required to be OPERABLE in MODES 5 and 6.

ACTIONS The Actions are modified by a Note indicating that the provisions of LCO 3.0.4 do not apply for Unit 2 only. As a result, this allows entry into a MODE or other specified condition in the Applicability with the LCO not met after performance of a risk assessment addressing inoperable systems and components, consideration of the results, determination of the acceptability of entering the MODE or other specified condition in the Applicability, and establishment of risk management actions, if appropriate.

OCONEE UNITS 1, 2, & 3 B 3.6.5-4 Amendment No. 340 1

Reactor Building Spray and Cooling Systems B 3.6.5 BASES ACTIONS The risk assessment may use quantitative, qualitative, or blended (continued) approaches, and the risk assessment will be conducted using the plant program, procedures, and criteria in place to implement 10 CFR 50.65(a)(4), which requires that risk impacts of maintenance activities to be assessed and managed. The risk assessment must take Into account all inoperable Technical Specifications equipment regardless of whether the equipment is included in the normal 10 CFR 50.65(a)(4) risk assessment scope. The risk assessments will be conducted using the procedures and guidance endorsed by Regulatory Guide 1.182, "Assessing and Managing Risk Before Maintenance Activities at Nuclear Power Plants." Regulatory Guide 1.1 82 endorses the guidance In Section 11 of NUMARC 93-01, "Industry Guideline for Monitoring the Effectiveness of Maintenance at Nuclear Power Plants." These documents address general guidance for conduct of the risk assessment, quantitative and qualitative guidelines for establishing risk management actions, and example risk management actions. These include actions to plan and conduct other activities in a manner that controls overall risk, Increased risk awareness by shift and management personnel, actions to reduce the duration of the condition, actions to minimize the magnitude of risk increases (establishment of backup success paths or compensatory measures), and determination that the proposed MODE change Is acceptable. Consideration should also be given to the probability of completing restoration such that the requirements of the LCO would be met prior to the expiration of ACTIONS Completion Times that would require exiting the Applicability. -t The provisions of this Note should not be Interpreted as endorsing the failure to exercise the good practice of restoring systems or components to OPERABLE status before entering an associated MODE or other specified Condition Inthe Applicability.

OCONEE UNITS 1, 2, & 3 B 3.6.5-5 Amendment No.. 340 I

Reactor Building Spray and Cooling Systems B 3.6.5 BASES ACTIONS A.1 (continued)

With one reactor building spray train inoperable in MODE 1 or 2, the Inoperable reactor building spray train must be restored to OPERABLE status within 7 days. Inthis Condition, the remaining OPERABLE spray and cooling trains are adequate to perform the iodine removal and containment cooling functions. The 7 day Completion Time takes Into account the redundant heat removal capability afforded by the OPERABLE reactor building spray train, reasonable time for repairs, and the low probability of an accident occurring during this period.

The 14 day portion of the Completion Time for Required Action A.1 is based upon engineering judgment. It takes Into account the low probability of coincident entry into two Conditions in this LCO coupled with the low probability of an accident occurring during this time. Refer to Section 1.3, Completion Times, for a more detailed discussion of the purpose of the "from discovery of failure to meet the LCO" portion of the Completion Time.

8.1 With one of the reactor building cooling trains inoperable in MODE 1 or 2, the inoperable reactor building cooling train must be restored to OPERABLE status within 7 days. The components Inthis degraded condition provide iodine removal capabilities and are capable of providing at least 100% of the heat removal needs after an accident. The 7 day Completion Time was developed taking into account the redundant heat removal capabilities afforded by combinations of the Reactor Building Spray System and Reactor Building Cooling System and the low probability of an accident occurring during this period.

The 14 day portion of the Completion Time for Required Action B.1 is based upon engineering judgment. It takes into account the low probability of coincident entry Into two Conditions in this LCO coupled with the low probability of an accident occurring during this time. Refer to Section 1.3 for a more detailed discussion of the purpose of the "from discovery of failure to meet the LCO" portion of the Completion lime.

C.1 With one reactor building spray train and one reactor building cooling train inoperable In MODE 1 or 2, at least one of the inoperable trains must be restored to OPERABLE status within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. In this Condition, the remaining OPERABLE spray and cooling trains are adequate to provide Iodine removal capabilities and are capable of providing at least 100% of the heat removal needs after an accident. The 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Completion Time OCONEE UNITS 1, 2, & 3 B 3.6.5-6 Amendment No. 340 l

Reactor Building Spray and Cooling Systems B 3.6.5 BASES ACTIONS C.1 (continued) takes into account the heat removal capability afforded by the remaining OPERABLE spray train and cooling trains, reasonable time for repairs, and the low probability of an accident occurring during this period.

D.1 If the Required Action and associated Completion Time of Condition A, B or C are not met, the unit must be brought to a MODE Inwhich the LCO, as modified by the Note, does not apply. To achieve this status, the unit must be brought to at least MODE 3 within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />. The allowed Completion Time is reasonable, based on operating experience, to reach the required unit conditions from full power conditions in an orderly manner and without challenging unit systems.

E.1 With one of the required reactor building cooling trains Inoperable in MODE 3 or 4, the required reactor building cooling train must be restored to OPERABLE status within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

The 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Completion Time Is reasonable based on engineering judgement taking into account the iodine and heat removal capabilities of the remaining required train of reactor building spray and cooling.

F.1 With one required reactor building spray train inoperable In MODE 3 or 4, the required reactor building spray train must be restored to OPERABLE status within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. The 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Completion Time is reasonable based on engineering judgement taking into account the heat removal capabilities of the remaining required trains of reactor building cooling.

G.1 If the Required Actions and associated Completion Times of Condition E or F of this LCO are not met, the unit must be brought to a MODE in which the LCO does not apply. To achieve this status, the unit must be brought to MODE 5 within 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />. The allowed Completion Times are reasonable, based on operating experience, to reach the required unit OCONEE UNITS 1, 2, & 3 B 3.6.5-7 Amendment No. 340 I

Reactor Building Spray and Cooling Systems B 3.6.5 BASES ACTIONS G.1 (continued) conditions from full power conditions in an orderly manner and without challenging unit systems.

H.1 With two reactor building spray trains, two reactor building cooling trains or any combination of three or more reactor building spray and reactor building cooling trains inoperable in MODE I or 2, the unit is in a condition outside the accident analysis. Therefore, LCO 3.0.3 must be entered immediately.

With any combination of two or more required reactor building spray and reactor building cooling trains inoperable in MODE 3 or 4, the unit is in a condition outside the accident analysis. Therefore, LCO 3.0.3 must be entered Immediately.

SURVEILLANCE SR 3.6.5.1 REQUIREMENTS Verifying the correct alignment for manual and non-automatic power operated valves In the reactor building spray flow path provides assurance that the proper flow paths will exist for Reactor Building Spray System operation. This SR does not apply to valves that are locked, sealed, or otherwise secured in position, since these were verified to be in the correct position prior to locking, sealing, or securing. Similarly, this SR does not apply to automatic valves since automatic valves actuate to their required position upon an accident signal. This SR also does not apply to valves that cannot be Inadvertently misaligned, such as check valves. This SR does not require any testing or valve manipulation. Rather, it involves verification, through a system walkdown, that those valves outside containment and capable of potentially being mispositioned are In the correct position.

SR 3.6.5.2 Operating each required reactor building cooling train fan unit for 2 15 minutes ensures that all trains are OPERABLE and that all associated controls are functioning properly. It also ensures that blockage, fan or motor failure, or excessive vibration can be detected for corrective action.

The 31 day Frequency was developed considering the known reliability of the fan units and controls, the three train redundancy available, and the low

, l,2, & e i ~.-5 Amendmn roNe. ___J_ 34 __1J.

U NL UN LAX)ML v@ 1, UNITS at @3 3 b 3.6.5-8 Amendment No. . 34 0 I

Reactor Building Spray and Cooling Systems B 3.6.5 BASES SURVEILLANCE SR 3.6.5.2 (continued)

REQUIREMENTS probability of a significant degradation of the reactor building cooling trains occurring between surveillances and has been shown to be acceptable through operating experience.

SR 3.6.5.3 Verifying that each required Reactor Building Spray pump's developed head at the flow test point is greater than or equal to the required developed head ensures that spray pump performance has not degraded during the cycle. Flow and differential pressure are normal tests of centrifugal pump performance required by Section Xl of the ASME Code (Ref. 4). Since the Reactor Building Spray System pumps cannot be tested with flow through the spray headers, they are tested on recirculation flow. This test confirms one point on the pump design curve and is indicative of overall performance. Such inservice tests confirm component OPERABILITY, trend performance, and may detect incipient failures by indicating abnormal performance. The Frequency of this SR is in accordance with the Inservice Testing Program.

SR 3.6.5.4 Verifying the containment heat removal capability provides assurance that the containment heat removal systems are capable of maintaining containment temperature below design limits following an accident. This test verifies the heat removal capability of the Low Pressure Injection (LPI)

Coolers and Reactor Building Cooling Units. The 18 month Frequency was developed considering the known reliability of the low pressure service water, reactor building spray and reactor building cooling systems and other testing performed at shorter intervals that is intended to Identify the possible loss of heat removal capability.

SR 3.6.5.5 and SR 3.6.5.6 These SRs require verification that each automatic reactor building spray valve actuates to its correct position and that each reactor building spray pump starts upon receipt of an actual or simulated actuation signal. The test will be considered satisfactory if visual observation and control board indication verifies that all components have responded to the actuation signal properly; the appropriate pump breakers have closed, and all valves have completed their travel. This SR Is not required for valves that are OCONEE UNITS 1, 2, & 3 B 3.6.5-9 AmendmentNo. 340 I

I Reactor Building Spray and Cooling Systems B 3.6.5 BASES SURVEILLANCE SR 3.6.5.5 and SR 3.6.5.6 (continued)

REQUIREMENTS locked, sealed, or otherwise secured in position under administrative controls. The 18 month Frequency Is based on the need to perform these Surveillances under the conditions that apply during a unit outage and the potential for an unplanned transient if the Surveillances were performed with the reactor at power. Operating experience has shown that these components usually pass the Surveillances when performed at the 18 month Frequency. Therefore, the Frequency was concluded to be acceptable from a reliability standpoint.

SR 3.6.5.7 This SR requires verification that each required reactor building cooling train actuates upon receipt of an actual or simulated actuation signal. The test will be considered satisfactory if control board indication verifies that all components have responded to the actuation signal properly, the appropriate valves have completed their travel, and fans are running at half speed. The 18 month Frequency Is based on engineering judgment and has been shown to be acceptable through operating experience. See SR 3.6.5.5 and SR 3.6.5.6, above, for further discussion of the basis for the 18 month Frequency.

SR 3.6.5.8 With the reactor building spray header isolated and drained of any solution, station compressed air Is Introduced Into the spray headers to verify the availability of the headers and spray nozzles. Performance of this Surveillance demonstrates that each spray nozzle is unobstructed and provides assurance that spray coverage of the containment during an accident Is not degraded. Due to the passive nature of the design of the nozzles, a test at 10 year intervals is considered adequate to detect obstruction of the spray nozzles.

REFERENCES 1. UFSAR, Section 3.1.

2. UFSAR, Section 6.2.
3. 10 CFR 50.36.
4. ASME, Boiler and Pressure Vessel Code, Section Xl.

OCONEE UNITS 1, 2, & 3 B 3.6.5-1 0 Amendment No. 340 l