Supplemental Response to the April 29, 2003, Orders Modifying Licenses for Revised Design Basis Threat
ML041410261
Person / Time
Site: Robinson 
Issue date: 05/24/2004
From: John Nakoski
NRC/NRR/DLPM/LPD2
To: Moyer J
Progress Energy Carolinas
Chernoff, M H, NRR/DLPM, 301-415-4041
References
TAC MC2964
Download: ML041410261 (5)


Text

May 24, 2004 Mr. J. W. Moyer Vice President H. B. Robinson Steam Electric Plant, Unit 2 Carolina Power & Light Company 3581 West Entrance Road Hartsville, SC 29550

SUBJECT:

H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT 2 - SUPPLEMENTAL RESPONSE TO THE APRIL 29, 2003, ORDERS MODIFYING LICENSES FOR REVISED DESIGN BASIS THREAT (TAC NO. MC2964)

Dear Mr. Moyer:

On April 29, 2003, the U.S. Nuclear Regulatory Commission (NRC) issued an Order modifying the operating license for the H. B. Robinson Steam Electric Plant, Unit 2 to: (1) require compliance with a revised design basis threat (DBT); (2) implement new security force personnel training and physical fitness requirements; and (3) prescribe compensatory measures related to fitness-for-duty enhancements applicable to security force personnel.

Section III.A.1 of EA-03-086 (DBT Order) required that all licensees submit revised physical security plans, safeguards contingency plans, and guard training and qualification plans, including an implementation schedule, based on the revised DBT, to the Commission for review and approval no later than April 29, 2004. The Order further requires licensees to implement the revised physical security plans, revised safeguards contingency plans, and revised security force personnel training and qualification plans no later than October 29, 2004.

By letter dated April 29, 2004, you submitted a supplemental response to the Order for the H. B. Robinson Steam Electric Plant, Unit 2. During the acceptance review of your submittal by NRC staff, the need for additional information in Attachment E was identified. The need for additional information was discussed with Mr. William Guthrie of your staff on May 10, 2004. By letter dated May 18, 2004, you submitted a revised Attachment E.

The NRC staff will be reviewing your physical security plan in the months of May and June, your training and qualification plan during July, and your contingency plan during August. Should further information regarding your submittal be necessary to support our review, you will be notified promptly.

J. W. Moyer The NRC staff is currently reviewing your supplemental responses and intends to complete the review of your revised plan by October 29, 2004.

Sincerely,

/RA/

John A. Nakoski, Chief Security Plan Review Team Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-261 cc: See next page J. W. Moyer The NRC staff is currently reviewing your supplemental responses and intends to complete the review of your revised plans by October 29, 2004.

Sincerely,

/RA/

John A. Nakoski, Chief Security Plan Review Team Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-261 cc: See next page DISTRIBUTION:

PUBLIC SPRT R/F J. Nakoski J. Peralta C. Hawes M. Chernoff P. Peduzzi OGC ACRS NRR/DLPM - PMs NRR/DLPM - SCs C. Bixler, RII ADAMS Accession Number: ML041410261 OFFICE SPRT/NRR/PM SPRT/NRR/LA SPRT/NSIR/SSC SPRT/NSIR/SC SPRT/NRR/SC NAME MChernoff CHawes PPeduzzi JPeralta JNakoski DATE 5/21/04 5/21/04 5/21/04 5/21/04 5/24/04 OFFICIAL RECORD COPY

H. B. Robinson Steam Electric Plant, Unit No. 2 Carolina Power & Light Company cc:

Steven R. Carr Associate General Counsel - Legal Department Progress Energy Service Company, LLC Post Office Box 1551 Raleigh, North Carolina 27602-1551 Ms. Margaret A. Force Assistant Attorney General State of North Carolina Post Office Box 629 Raleigh, North Carolina 27602 U. S. Nuclear Regulatory Commission Resident Inspectors Office H. B. Robinson Steam Electric Plant 2112 Old Camden Road Hartsville, South Carolina 29550 Mr. T. P. Cleary Plant General Manager H. B. Robinson Steam Electric Plant, Unit No. 2 Carolina Power & Light Company 3581 West Entrance Road Hartsville, South Carolina 29550 Mr. Chris L. Burton Director of Site Operations H. B. Robinson Steam Electric Plant, Unit No. 2 Carolina Power & Light Company 3581 West Entrance Road Hartsville, South Carolina 29550 Public Service Commission State of South Carolina Post Office Drawer 11649 Columbia, South Carolina 29211 J. F. Lucas Manager - Support Services - Nuclear H. B. Robinson Steam Electric Plant, Unit No. 2 Carolina Power & Light Company 3581 West Entrance Road Hartsville, South Carolina 29550 Mr. C. T. Baucom Supervisor, Licensing/Regulatory Programs H. B. Robinson Steam Electric Plant, Unit No. 2 Carolina Power & Light Company 3581 West Entrance Road Hartsville, South Carolina 29550 Ms. Beverly Hall, Section Chief N.C. Department of Environment and Natural Resources Division of Radiation Protection 3825 Barrett Dr.

Raleigh, North Carolina 27609-7721 Mr. Robert P. Gruber Executive Director Public Staff - NCUC 4326 Mail Service Center Raleigh, North Carolina 27699-4326 Mr. Henry H. Porter, Assistant Director South Carolina Department of Health Bureau of Land & Waste Management 2600 Bull Street Columbia, South Carolina 29201 Mr. James W. Holt Manager Performance Evaluation and Regulatory Affairs PEB 7 Progress Energy Post Office Box 1551 Raleigh, North Carolina 27602-1551

H. B. Robinson Steam Electric Plant, Unit No. 2 Carolina Power & Light Company cc:

Mr. John H. ONeill, Jr.

Shaw, Pittman, Potts, & Trowbridge 2300 N Street NW.

Washington, DC 20037-1128 Mr. J. W. Moyer, Vice President H. B. Robinson Steam Electric Plant Unit No. 2 Carolina Power & Light Company 3581 West Entrance Road Hartsville, South Carolina 29550-0790