May 20, 2004 Mr. George Vanderheyden Vice President Constellation Generation Group, LLC 1650 Calvert Cliffs Parkway Lusby, Maryland 20657
SUBJECT:
CALVERT CLIFFS NUCLEAR POWER PLANT, UNITS 1 AND 2 -
SUPPLEMENTAL RESPONSE TO THE APRIL 29, 2003, ORDERS MODIFYING LICENSES FOR REVISED DESIGN BASIS THREAT (TAC NOS. MC2900 AND MC2901)
Dear Mr. Vanderheyden:
On April 29, 2003, the Nuclear Regulatory Commission (NRC) issued an Order modifying the operating licenses for Calvert Cliffs Nuclear Power Plant, Units 1 and 2 to: (1) require compliance with a revised Design Basis Threat (DBT); (2) implement new security force personnel training and physical fitness requirements; and (3) prescribe compensatory measures related to fitness-for-duty enhancements applicable to security force personnel.
Section III.A.1 of EA-03-086 (DBT Order) required that all licensees submit revised physical security plans, safeguards contingency plans, and guard training and qualification plans, including an implementation schedule, based on the revised DBT, to the NRC for review and approval no later than April 29, 2004. The DBT Order further requires licensees to implement the revised physical security plans, revised safeguards contingency plans, and revised security force personnel training and qualification plans no later than October 29, 2004.
By letter dated April 29, 2004, you submitted a supplemental response to the DBT Order for Calvert Cliffs Nuclear Power Plant, Units 1 and 2.
You provided information on your security plan as it relates to your Independent Spent Fuel Storage Installation (ISFSI). You will be notified by separate correspondence of the NRC staffs plan for review of your ISFSI security plan.
G. Vanderheyden The NRC staff will review your physical security plan in the months of May and June, your training and qualification plan during July, and your contingency plan during August. Should further information regarding your submittal be necessary to support our review, you will be notified promptly.
The NRC staff plans to complete the review of your supplemental response by October 29, 2004.
Sincerely,
/RA/
John A. Nakoski, Chief Security Plan Review Team Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-317 and 50-318 cc: See next page
ML041390047 OFFICE SPRT/NRR/PM SPRT/NRR/LA SPRT/NSIR/SSC SPRT/NSIR SPRT/NRR/SC NAME MChernoff CHawes PPeduzzi JPeralta JNakoski DATE 5/20/04 5/20/04 5/20/04 5/20/04 5/20/04
Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2 cc:
President Calvert County Board of Commissioners 175 Main Street Prince Frederick, MD 20678 James M. Petro, Esquire Counsel Constellation Energy Group, Inc.
750 East Pratt Street, 5th floor Baltimore, MD 21202 Jay E. Silberg, Esquire Shaw, Pittman, Potts, and Trowbridge 2300 N Street, NW Washington, DC 20037 Mark Geckle Calvert Cliffs Nuclear Power Plant 1650 Calvert Cliffs Parkway Lusby, MD 20657-4702 Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 287 St. Leonard, MD 20685 Mr. Richard I. McLean, Manager Nuclear Programs Power Plant Research Program Maryland Dept. of Natural Resources Tawes State Office Building, B3 Annapolis, MD 21401 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Kristen A. Burger, Esquire Maryland Peoples Counsel 6 St. Paul Centre Suite 2102 Baltimore, MD 21202-1631 Patricia T. Birnie, Esquire Co-Director Maryland Safe Energy Coalition P.O. Box 33111 Baltimore, MD 21218 Mr. Loren F. Donatell NRC Technical Training Center 5700 Brainerd Road Chattanooga, TN 37411-4017