Category:Letter type:GO
MONTHYEARGO2-24-109, Summary of Changes and Analysis for Revision 42 of Plant Procedures Manual 13.8.1, Emergency Dose Projection System Operations2024-11-0404 November 2024 Summary of Changes and Analysis for Revision 42 of Plant Procedures Manual 13.8.1, Emergency Dose Projection System Operations GO2-24-110, Summary of Changes and Analysis for Revision 45 of Plant Procedures Manual 13.4.1, Emergency Notification2024-11-0404 November 2024 Summary of Changes and Analysis for Revision 45 of Plant Procedures Manual 13.4.1, Emergency Notification GO2-24-088, Supplement to Response to Request for Additional Information Regarding License Amendment Request to Revise Columbia Emergency Plan2024-09-24024 September 2024 Supplement to Response to Request for Additional Information Regarding License Amendment Request to Revise Columbia Emergency Plan GO2-24-051, Application to Revise Technical Specifications to Adopt TSTF-592, Revise Automatic Depressurization System (ADS) Instrumentation Requirements2024-09-23023 September 2024 Application to Revise Technical Specifications to Adopt TSTF-592, Revise Automatic Depressurization System (ADS) Instrumentation Requirements GO2-24-082, Response to Request for Additional Information Regarding License Amendment Request to Revise Columbia Emergency Plan2024-09-10010 September 2024 Response to Request for Additional Information Regarding License Amendment Request to Revise Columbia Emergency Plan GO2-24-060, Reply to a Notice of Violation, EA-21-170 and EA-23-0542024-07-30030 July 2024 Reply to a Notice of Violation, EA-21-170 and EA-23-054 GO2-24-070, Response to Request for Additional Information Regarding Fifth Interval Inservice Testing Program2024-07-29029 July 2024 Response to Request for Additional Information Regarding Fifth Interval Inservice Testing Program GO2-24-063, Notification of Extension to Columbias Fourth 10-Year Interval Inservice Testing Program Plan2024-07-15015 July 2024 Notification of Extension to Columbias Fourth 10-Year Interval Inservice Testing Program Plan GO2-24-057, Notice of Readiness for Supplemental Inspection2024-06-19019 June 2024 Notice of Readiness for Supplemental Inspection GO2-24-056, Relief Request for the Columbia Generating Station Fourth Ten-Year Interval Inservice Testing2024-06-11011 June 2024 Relief Request for the Columbia Generating Station Fourth Ten-Year Interval Inservice Testing GO2-24-049, 2023 Annual Radiological Environmental Operating Report2024-05-13013 May 2024 2023 Annual Radiological Environmental Operating Report GO2-24-050, Annual Environmental Operating Report2024-04-30030 April 2024 Annual Environmental Operating Report GO2-24-042, 2023 Annual Radioactive Effluent Release Report2024-04-22022 April 2024 2023 Annual Radioactive Effluent Release Report GO2-24-044, Voluntary Response to Regulatory Issue Summary 2024-012024-04-11011 April 2024 Voluntary Response to Regulatory Issue Summary 2024-01 GO2-24-034, Supplement to License Amendment Request to Revise Columbia Generating Station Emergency Plan2024-03-20020 March 2024 Supplement to License Amendment Request to Revise Columbia Generating Station Emergency Plan GO2-24-041, Level of Financial Protection - Annual Reporting Requirement2024-03-12012 March 2024 Level of Financial Protection - Annual Reporting Requirement GO2-24-039, Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.462024-03-11011 March 2024 Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.46 GO2-24-036, Presentation Information for Pre-Application Meeting Regarding Columbia’S Replacement Steam Dryer Evaluation Approach for Extended Power Uprate2024-03-11011 March 2024 Presentation Information for Pre-Application Meeting Regarding Columbia’S Replacement Steam Dryer Evaluation Approach for Extended Power Uprate GO2-24-004, License Amendment Request to Revise Emergency Plan2024-01-30030 January 2024 License Amendment Request to Revise Emergency Plan GO2-24-003, Relief Requests for the Columbia Generating Station Fifth Ten-Year Interval Inservice Testing2024-01-29029 January 2024 Relief Requests for the Columbia Generating Station Fifth Ten-Year Interval Inservice Testing GO2-24-014, Independent Spent Fuel Storage Installation, Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2024-01-15015 January 2024 Independent Spent Fuel Storage Installation, Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation GO2-24-005, Docket No. 50-397 Supplement to Reply to a Notice of Violation; EA-21-1702024-01-0808 January 2024 Docket No. 50-397 Supplement to Reply to a Notice of Violation; EA-21-170 GO2-23-136, Guarantee of Payment of Deferred Premium2023-12-20020 December 2023 Guarantee of Payment of Deferred Premium GO2-23-135, Notice of Readiness for Supplemental Inspection2023-12-14014 December 2023 Notice of Readiness for Supplemental Inspection GO2-23-130, Reply to a Notice of Violation; EA-23-0542023-12-14014 December 2023 Reply to a Notice of Violation; EA-23-054 GO2-23-105, Licensing Basis Document Update and Biennial Commitment Change Report2023-12-12012 December 2023 Licensing Basis Document Update and Biennial Commitment Change Report GO2-23-107, Application to Revise Technical Specifications to Adopt TSTS-584, Eliminate Automatic RWCU System Isolation on SLC Initiation2023-12-0505 December 2023 Application to Revise Technical Specifications to Adopt TSTS-584, Eliminate Automatic RWCU System Isolation on SLC Initiation GO2-23-126, Docket No. 50-397 Voluntary Response to Regulatory Issue Summary 2023-012023-11-28028 November 2023 Docket No. 50-397 Voluntary Response to Regulatory Issue Summary 2023-01 GO2-23-121, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-11-27027 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation GO2-23-097, In-Service Inspection Summary Report for the Twenty-Sixth Refueling Outage (R26)2023-09-0606 September 2023 In-Service Inspection Summary Report for the Twenty-Sixth Refueling Outage (R26) GO2-23-100, Technical Specification Section 5.6.4 Post Accident Monitoring Instrumentation 14-Day Report for Inoperable Suppression Pool Level Indication2023-08-31031 August 2023 Technical Specification Section 5.6.4 Post Accident Monitoring Instrumentation 14-Day Report for Inoperable Suppression Pool Level Indication GO2-23-056, Application to Revise Technical Specifications to Adopt TSTF-230, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling2023-08-29029 August 2023 Application to Revise Technical Specifications to Adopt TSTF-230, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling GO2-23-093, Supplement to Reply to a Notice of Violation: EA-21-1702023-07-27027 July 2023 Supplement to Reply to a Notice of Violation: EA-21-170 GO2-23-068, Notification of Completion of Commitments Required Prior to Entry Into the Period of Extended Operation2023-07-19019 July 2023 Notification of Completion of Commitments Required Prior to Entry Into the Period of Extended Operation GO2-23-090, Reply to a Notice of Violation2023-07-12012 July 2023 Reply to a Notice of Violation GO2-23-073, Notification of NPDES Permit Issuance2023-06-26026 June 2023 Notification of NPDES Permit Issuance GO2-23-072, Cycle 27 Core Operating Limits Report2023-06-0505 June 2023 Cycle 27 Core Operating Limits Report GO2-23-055, Independent Spent Fuel Storage Installation, 2022 Annual Radiological Environmental Operating Report2023-05-15015 May 2023 Independent Spent Fuel Storage Installation, 2022 Annual Radiological Environmental Operating Report GO2-23-006, License Amendment Request to Clean-Up Operating License and Appendix a Technical Specifications2023-05-0101 May 2023 License Amendment Request to Clean-Up Operating License and Appendix a Technical Specifications GO2-23-053, 2022 Annual Environmental Operating Report2023-04-26026 April 2023 2022 Annual Environmental Operating Report GO2-23-057, 2022 Annual Radioactive Effluent Release Report2023-04-25025 April 2023 2022 Annual Radioactive Effluent Release Report GO2-23-012, Application to Revise Technical Specifications to Adopt Tstf-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position2023-03-27027 March 2023 Application to Revise Technical Specifications to Adopt Tstf-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position GO2-23-038, Plant Decommissioning Fund Status Report2023-03-15015 March 2023 Plant Decommissioning Fund Status Report GO2-23-041, Generation Station - Level of Financial Protection - Annual Reporting Requirement2023-03-15015 March 2023 Generation Station - Level of Financial Protection - Annual Reporting Requirement GO2-23-034, Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.462023-03-13013 March 2023 Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.46 GO2-23-035, Supplement to License Amendment Request to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-03-0909 March 2023 Supplement to License Amendment Request to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling GO2-23-019, Emergency Plan - Summary of Changes and Analysis for Revision 68 of the EP-012023-02-0808 February 2023 Emergency Plan - Summary of Changes and Analysis for Revision 68 of the EP-01 GO2-22-131, Guarantee of Payment of Deferred Premium2022-12-19019 December 2022 Guarantee of Payment of Deferred Premium GO2-22-122, Response to Request for Additional Information Related to License Amendment Request to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2022-11-28028 November 2022 Response to Request for Additional Information Related to License Amendment Request to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b GO2-22-076, Status of License Renewal Commitments2022-10-31031 October 2022 Status of License Renewal Commitments 2024-09-24
[Table view] |
Text
ENERGY NORTH WEST PO. Box 968
- Richland, Washington 99352-0968 April 28, 2004 G02-04-083 SAFEGUARDS INFORMATION U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555
Subject:
COLUMBIA GENERATING STATION, DOCKET NO. 50-397; SUPPLEMENTAL RESPONSE TO THE APRIL 29, 2003, ORDERS TO COLUMBIA GENERATING STATION
Dear Sir or Madam:
The NRC issued an Order dated April 29, 2003, Requiring Compliance with Revised Design Basis Threat ("Order EA-03-086 or Order") and other security related Orders (collectively "Orders") for the Columbia Generating Station. This Supplemental Response of Energy Northwest to Order EA-03-086 supplements the previous response dated June 3, 2003, that Energy Northwest filed pursuant to 10 CFR § 50.4 and section III, Conditions A.1, B.1, and B.2.
Order EA-03-086 imposes license conditions on nuclear power plants licensed pursuant to the Atomic Energy Act of 1954 and Title 10 of the Code of Federal Regulations.Section III.A of the Order requires licensees to revise their physical security plans and safeguards contingency plans to provide protection against the revised design basis threat (DBT) set forth in to the Order.Section III.A also requires licensees to revise the security force training and qualification plan to implement the revised DBT. These revised plans, along with an implementation schedule, were required to be submitted to the' Commission for review and approval no later than April 29, 2004.
NOTE: ATTACHMENTS A & C TO THIS LETTER CONTAIN "SAFEGUARDS INFORMATION" AND MUST BE PROTECTED ACCORDINGLY. UPON SEPARATION OF ATTACHMENTS A & C , THIS LETTER AND ATTACHMENTS B & D ARE "DECONTROLLED" SAFEGUARDS INFORMATION
SUPPLEMENTAL RESPONSE TO THE APRIL 29, 2003, ORDERS TO COLUMBIA GENERATING STATION Page 2 of 5 In accordance with the Order and 10 CFR § 50.4, Energy Northwest is submitting this Supplemental Response for the above-mentioned licensed facility. This submittal includes, as Attachment A, revisions to the Columbia Generating Station Physical Security Plan, the Contingency Plan, and the Training and Qualification Plan as required by Order EA-03-086.
These plans contain the integrated commitments to comply with Order EA-03-086 and the other security related Orders issued on February 25, 2002, January 7, 2003, and April 29, 2003. As a result, these plans supercede previous submittals of Energy Northwest in these areas, including those related to the February 25, 2002, January 7, 2003, and April 29, 2003, Orders. Energy Northwest will continue to implement the provisions of those previous submittals except to the extent that they are superceded by these plans. All changes that have been or will be made have been evaluated to ensure that they do not compromise plant safety.
Energy Northwest has developed these plans to be consistent with NEI-03-01 (Revision 1),
Nuclear Power Plant Access Authorization Program (April 2004); NEI-03-09 (Revision 2 (draft)), Security Officer Training Program (April 2004); and NEI-03-12 (Revision 2 (draft)),
Template for the Security Plan, Training and Qualification Plan, Safeguards Contingency Plan, and Independent Spent Fuel Storage Installation Security Program (April 2004). The schedule for completing those actions, which includes the identification of major transitional activities, is provided in Attachment B to this submittal. To facilitate the NRC review, any provisions that are different from NEI-03-12 are identified and the justification provided in Attachment C, Deviations from NEI-03-12, to this submittal. Attachment D, Previous Exemptions to 10 CFR Part 73, is a listing of any exemptions to 10 CFR Part 73 previously granted to Energy Northwest and an explanation of their status under the plans hereby submitted. Energy Northwest is not considering adopting any of the alternatives provided in NEI-03-12 or in "NRC Guidance on Implementation of the April 2003 Revised Design Basis Threat." Energy Northwest has chosen to implement Option 2 of NEI-03-12, Section 9.4.1.2.
When the NRC approves the final revision of NEI-03-12, Energy Northwest will supplement this response, if necessary, to conform to NEI-03-12 as finally approved. However, with the filing of these plans, Energy Northwest will be implementing its revised protection strategy and completing plant modifications and security personnel training pursuant to these plans to ensure that implementation will be completed by October 29, 2004, as required by the Orders.
Upon completion of the implementation of these plans, Energy Northwest will be in compliance with all applicable security requirements. For the purpose of complying with the requirements of 10 CFR Part 73 to conduct an annual audit, the date of the letter that will be submitted to the NRC pursuant to Order EA-03-086 certifying that implementation of the plans is complete will be the effective date for determining commencement of the annual audit requirement period.
SUPPLEMENTAL RESPONSE TO THE APRIL 29, 2003, ORDERS TO COLUMBIA GENERATING STATION Page 3 of 5 Because of the requirement for these plans to be fully implemented by October 29, 2004; the need to integrate the requirement of the revised DBT Order with the Orders issued February 25, 2002, January 7, 2003, and April 29, 2003; and the Commission's determination that it would be appropriate to exercise enforcement discretion to accommodate any transitional issues which may arise as licensees, in good faith, take reasonable actions to implement the specific requirements of the Orders, Energy Northwest requests that enforcement discretion be exercised during the transition period until full implementation of the plans is accomplished and the physical plant modifications and security force training are complete. At that time, the revised plans will be fully implemented and the exercise of enforcement discretion will no longer be necessary.
In accordance with 10 CFR § 2.202(b), the following affirmation is provided:
I, JV Parrish, being duly sworn, subscribe to and say that I am the Chief Executive Officer for ENERGY NORTHWEST, the applicant herein; that I have the full authority to execute this oath; that I have reviewed the foregoing; and that to the best of my knowledge, information, and belief that the statements made in it are true.
Res ectf y submitted, J, arrish Chief Executive Officer Sworn to and subscribed before me thisof day of 7 2004.
A . A My Commission expires: 3 + DM
SUPPLEMENTAL RESPONSE TO THE APRIL 29, 2003, ORDERS TO COLUMBIA GENERATING STATION Page 4 of 5 The attachments to this letter are provided on CD-ROM. Information regarding the CD is provided on the following page in accordance with the NRC's Guidance for Electronic Submissions to the Commission (Federal Register Notice, 68 FR 58792, dated October 10, 2003).
If you have any questions or require additional information regarding this matter, please contact Ms. CL Perino, Licensing Manager at (509) 377-2075.
Respectfully, JV Parrish Chief Executive Officer Mail Drop 1023 Attachment A: Revisions to the Columbia Generating Station Physical Security Plan, the Safeguards Contingency Plan, and the Training and Qualification Plan as required by Order EA-03-086.
Attachment B: Schedule for Completing Plant Modifications, Security Personnel Training, and Major Transitional Activities as Required by the Orders.
Attachment C: Deviations from NEI-03-12.
Attachment D: Previous Exemptions to 10 CFR § 73 cc: BS Mallet - NRC - RIV w/o WA Macon - NRC - NRR w/o NRC Sr. Resident Inspector - 988C w/o RN Sherman - BPA/1399 w/o TC Poindexter - Winston & Strawn w/o
SUPPLEMENTAL RESPONSE TO THE APRIL 29, 2003, ORDERS TO COLUMBIA GENERATING STATION Page 5 of 5 CD-ROM TRANSMITTAL INFORMATION Contact Information:
Name: Ms. CL Perino Mailing Address: Energy Northwest MD PE20 P.O. Box 968 Richland, WA 99352 E-Mail Address: clperino~energy-northwest.com Phone Number: (509) 377-2075 A total of one (1) CD-ROM is included in the submission. The CD-ROM labeled "Supplemental Response to April 29, 2003, Orders to Columbia Generating Station-Safeguards Information" contains the following five (5) files:
001 Transmittal Letter.pdf, 129,724 bytes, publicly available 002 Attachment A Physical Security Plan.pdf, 1,051,332 bytes, safeguards information 003 Attachment B Schedule Completing Actions.pdf, 51,897 bytes 004 Attachment C NEI-03-12 Deviations.pdf, 85,175 bytes, safeguards information 005 Attachment D Previous Exemptions 10CFR73.pdf, 51,294 bytes