Letter Sequence Draft RAI |
---|
|
|
MONTHYEARML0407702472004-01-22022 January 2004 Draft Information Inputs Preliminary RAI DC Electrical Power Technical Specifications Changes Pursuant to TSTF 360 - Attachment 7 Project stage: Draft RAI ML0418303532004-07-0101 July 2004 License Amendments 113 & 113 Regarding Direct Current (DC) Electrical Power Systems Project stage: Acceptance Review 2004-01-22
[Table View] |
|
---|
Category:E-Mail
MONTHYEARML24292A0282024-10-18018 October 2024 NRR E-mail Capture - Acceptance Review Comanche Peak Adoption of TSTF-51, TSTF-471, and TSTF-571 ML24262A1302024-09-18018 September 2024 NRR E-mail Capture - Acceptance Review Comanche Peak Multiple Relief Requests for Unit 2 Third Inservice Inspection Interval Due to Impracticality (EPID L-2024-LLR-0053 Through -0058) ML24205A2162024-07-23023 July 2024 September 2024 Emergency Preparedness Program Inspection - Request for Information ML24204A0022024-07-18018 July 2024 NRR E-mail Capture - Request for Additional Information Comanche Peak Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule ML24095A1532024-04-0404 April 2024 NRR E-mail Capture - Acceptance Review Comanche Peak Request to Revise Technical Specifications to Adopt TSTF-591, Revise Risk Informed Completion Time (RICT) Program (EPID 2024-LLA-0023) ML24095A2382024-04-0404 April 2024 NRR E-mail Capture - Acceptance Review Comanche Peak Request to Revise Technical Specifications to Adopt TSTF-589, Eliminate Automatic Diesel Generator Start During Shutdown ML24052A0122024-02-16016 February 2024 NRR E-mail Capture - Comanche Peak - Draft Request for Additional Information - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications ML24033A2642024-02-0202 February 2024 NRR E-mail Capture - Comanche Peak - Revised Draft Request for Additional Information - License Amendment Request to Extend the Allowed Outage Time for an Inoperable Emergency Diesel Generator ML24036A0122024-02-0202 February 2024 NRR E-mail Capture - Comanche Peak - Request for Additional Information - License Amendment Request to Extend the Allowed Outage Time for an Inoperable Emergency Diesel Generator ML24025A0172024-01-22022 January 2024 NRC Request for Concurrence with Endangered Species Act Determinations for Comanche Peak License Renewal, Issuance of Draft Supplemental Environmental Impact Statement, and Opportunity for Public Comment ML24019A0742024-01-19019 January 2024 NRR E-mail Capture - Comanche Peak - Draft Request for Additional Information - License Amendment Request to Extend the Allowed Outage Time for an Inoperable Emergency Diesel Generator ML24008A2492023-12-18018 December 2023 Texas SHPO Response for Comanche Peak Deis Review and Comment ML23311A2202023-11-20020 November 2023 NRC to Fws, NRC Request for Concurrence with Endangered Species Act Determinations for Comanche Peak License Renewal, Issuance of Draft Supplemental Environmental Impact Statement, and Opportunity for Public Comment (Consultation Code: 2023 ML23255A2882023-09-12012 September 2023 NRR E-mail Capture - Comanche Peak - Acceptance of Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule ML23256A1492023-09-11011 September 2023 Email from Mark Yoo (NRC) to Ken Peters (Vistra) - Comanche Peak LRA - Request for Additional Information - Set 4 ML23226A0072023-08-11011 August 2023 NRR E-mail Capture - Comanche Peak 1 and 2 – Audit Plan - License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors ML23188A0442023-07-0707 July 2023 Email from Mark Yoo (NRC) to Ken Peters (Vistra) - Comanche Peak LRA - Request for Additional Information - Set 3 ML23181A0722023-06-29029 June 2023 NRR E-mail Capture - Comanche Peak - Acceptance of License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors ML23181A0202023-06-29029 June 2023 Email from Mark Yoo (NRC) to Ken Peters (Vistra) - Comanche Peak LRA - Request for Additional Information - Set 2 ML23172A0152023-06-20020 June 2023 NRR E-mail Capture - Re Comanche Peak - Acceptance of License Amendment Request Regarding General Design Criterion 5 of Appendix a to 10 CFR Part 50 and Regulatory Guide 1.81 ML23167A0222023-06-14014 June 2023 Email: Request for Additional Information (RAI) Letter for the Review of the Comanche Peak Initial License Renewal Application, Set 1 ML23145A2332023-05-25025 May 2023 Email from Mark Yoo (NRC) to Ken Peters (Vistra) - Comanche Peak LRA - Request for Confirmation of Information - Set 2 ML23143A1382023-05-23023 May 2023 Email from Mark Yoo (NRC) to Ken Peters (Vistra) - Comanche Peak LRA - Request for Confirmation of Information - Set 1 ML23139A0802023-05-18018 May 2023 NRR E-mail Capture - Comanche Peak – Draft Supplemental Information Request - License Amendment Request Regarding General Design Criterion 5 of Appendix a to 10 CFR Part 50 and Regulatory Guide 1.81 ML23138A1522023-05-18018 May 2023 Lr Docs - (External_Sender) Comanche Peak Nuclear Power Plants ML23135A9132023-05-15015 May 2023 NRR E-mail Capture - Comanche Peak - Draft Supplemental Information Request - License Amendment Request to 10 CFR 50.69 ML23131A2932023-05-11011 May 2023 Lr Docs - License Renewal for Comanche Peak Nuclear Power Plant, Units 1 and 2 ML23128A1612023-05-0808 May 2023 NRR E-mail Capture - Comanche Peak Nuclear Power Plant, Units 1 and 2, Beaver Valley Power Station, Unit Nos. 1 and 2, Davis-Besse Nuclear Power Station, Unit 1, and Perry Nuclear Power Plant, Unit No. 1 - Acceptance of Requested Licensing ML23110A7122023-04-20020 April 2023 NRR E-mail Capture - Comanche Peak - Verbal Authorization of Proposed Alternative RV-1 (L-2023-LLR-0019) ML23103A4682023-04-11011 April 2023 NRR E-mail Capture - Comanche Peak – Request for Additional Information - License Amendment Request to Apply the Westinghouse Full Spectrum Loss of Coolant Accident Evaluation Model ML23086B9852023-03-27027 March 2023 NRR E-mail Capture - Comanche Peak – Draft Request for Additional Information - Request to Apply the Westinghouse Full Spectrum Loss of Coolant Accident Evaluation Model ML23061A1612023-03-0202 March 2023 E-mail from David Griggs Regarding Submission to NRC Electronic Information Exchange on 03/01/2023 for Citizens for Fair Utility Regulation in Comanche Peak Proceeding ML23032A3842023-02-0101 February 2023 LRA On-Site Audit Needs List ML23214A0192023-01-30030 January 2023 (External_Sender) Request to Broaden Extended Deadline to the General Public (with Attachments) - C3 ML23214A0202023-01-29029 January 2023 (External_Sender) Requesting a Deadline Extension on NRC-2002-0183, Comanche Peak License Renewal - C2 ML23214A0182023-01-26026 January 2023 (External Sender) NRC-2022-0183-0003 (with Attachment) - C6 ML23214A0162023-01-24024 January 2023 (External Sender) EPA Scoping Comment Letter for the Comanche Peak Nuclear Power Plant License Renewal (with Attachment) - C8 ML23214A0142023-01-23023 January 2023 (External Sender) Docket NRC-2022-0183 Comanche Peak Nuclear Power Plant Renewal (with Attachment) - C1 ML23214A0172023-01-17017 January 2023 (External Sender) NRC License Extension? No! ML23214A0132023-01-17017 January 2023 (External Sender) Docket Id NRC-2022-0183, Request for Extension of License for Comanche Peak, Comment for Environmental Scoping - C9 ML23214A0122023-01-13013 January 2023 (External Sender) Correction to Comment Submitted 01-13-23 - C11 ML22362A0992022-12-28028 December 2022 NRR E-mail Capture - Comanche Peak - Acceptance of License Amendment Request to Apply Westinghouse Fsloca Evaluation Model ML22362A0972022-12-28028 December 2022 NRR E-mail Capture - Comanche Peak - Acceptance of License Amendment Request to Adopt WCAP-17661-P-A, Revision 1, Improved RAOC and CAOC Fq Surveillance Technical Specifications, ML22325A2742022-11-21021 November 2022 NRR E-mail Capture - Comanche Peak - Request for Additional Information - Proposed Alternative P-1 Regarding IST of Safeguards Building Sump Pumps ML22318A3102022-11-10010 November 2022 NRR E-mail Capture - Comanche Peak - Draft Request for Additional Information - Proposed Alternative P-1 Regarding IST of Safeguards Building Sump Pumps ML22237A2842022-08-25025 August 2022 CPNPP 2022 EP Program Inspection RFI Hjs 08252022 ML22229A0792022-08-17017 August 2022 NRR E-mail Capture - Comanche Peak - Acceptance of Requested Licensing Action - Proposed Alternative P-1 Regarding IST of Safeguards Building Sump Pumps ML22230B1092022-08-17017 August 2022 NRR E-mail Capture - Comanche Peak Unit 2 - Request for Additional Information - 2RE19 Inspection Summary Report for Steam Generator Tubing ML22220A1942022-08-0808 August 2022 NRR E-mail Capture - Comanche Peak Unit 2 - Draft Request for Additional Information - 2RE19 Inspection Summary Report for Steam Generator Tubing ML22133A0472022-05-13013 May 2022 July 2022 Emergency Preparedness Exercise Inspection - Request for Information 2024-09-18
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24204A0022024-07-18018 July 2024 NRR E-mail Capture - Request for Additional Information Comanche Peak Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule ML24192A1862024-07-10010 July 2024 Notification of Inspection (NRC Inspection Report 05000445/2024003 and 05000446/2024003) and Request for Information ML24052A0122024-02-16016 February 2024 NRR E-mail Capture - Comanche Peak - Draft Request for Additional Information - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications ML24036A0122024-02-0202 February 2024 NRR E-mail Capture - Comanche Peak - Request for Additional Information - License Amendment Request to Extend the Allowed Outage Time for an Inoperable Emergency Diesel Generator ML24033A2642024-02-0202 February 2024 NRR E-mail Capture - Comanche Peak - Revised Draft Request for Additional Information - License Amendment Request to Extend the Allowed Outage Time for an Inoperable Emergency Diesel Generator ML24019A0742024-01-19019 January 2024 NRR E-mail Capture - Comanche Peak - Draft Request for Additional Information - License Amendment Request to Extend the Allowed Outage Time for an Inoperable Emergency Diesel Generator ML24018A1072024-01-18018 January 2024 – Notification of Commercial Grade Dedication Inspection (05000445/2024012 and 05000446/2024012) and Request for Information ML23256A1492023-09-11011 September 2023 Email from Mark Yoo (NRC) to Ken Peters (Vistra) - Comanche Peak LRA - Request for Additional Information - Set 4 ML23256A1502023-09-11011 September 2023 Request for Additional Information Requests - Comanche Peak - Set 4 ML23213A2162023-08-0202 August 2023 Vistra Operations Company, LLC Notification of License Renewal Inspection and Request for Information ML23188A0452023-07-0707 July 2023 Request for Additional Information Requests - Comanche Peak - Set 3 ML23188A0442023-07-0707 July 2023 Email from Mark Yoo (NRC) to Ken Peters (Vistra) - Comanche Peak LRA - Request for Additional Information - Set 3 ML23181A0212023-06-29029 June 2023 Request for Additional Information Requests - Comanche Peak - Set 2 ML23181A0202023-06-29029 June 2023 Email from Mark Yoo (NRC) to Ken Peters (Vistra) - Comanche Peak LRA - Request for Additional Information - Set 2 ML23167A0232023-06-14014 June 2023 Request for Additional Information (RAI) for the Review of the Comanche Peak Initial License Renewal Application (Lra), Set 1 ML23167A0222023-06-14014 June 2023 Email: Request for Additional Information (RAI) Letter for the Review of the Comanche Peak Initial License Renewal Application, Set 1 ML23145A2322023-05-25025 May 2023 LRA - Request for Confirmation of Information - Set 2 ML23132A2542023-05-23023 May 2023 Supplemental Information Needed for Acceptance of Requested Licensing Action LAR to Adopt 10 CFR 50.69,Risk-Informed Categorization & Treatment of Structures,Systems & Components for Nuclear Power Reactors EPID L-2023-LLA-0057 ML23143A1372023-05-23023 May 2023 LRA - Request for Confirmation of Information - Set 1 ML23068A0562023-05-0909 May 2023 Request for Additional Information - Comanche Peak License Renewal Application Environmental Review ML23068A0732023-04-13013 April 2023 Requests for Confirmation of Information for the Environmental Review of the Comanche Peak Nuclear Power Plant, Units 1 and 2, Licensed Renewal Application (EPID Number: L-2022-LNE-0004) (Docket Numbers 50-445 and 50-446) ML23103A4682023-04-11011 April 2023 NRR E-mail Capture - Comanche Peak – Request for Additional Information - License Amendment Request to Apply the Westinghouse Full Spectrum Loss of Coolant Accident Evaluation Model ML23086B9852023-03-27027 March 2023 NRR E-mail Capture - Comanche Peak – Draft Request for Additional Information - Request to Apply the Westinghouse Full Spectrum Loss of Coolant Accident Evaluation Model ML23010A1442023-01-0909 January 2023 Inservice Inspection Request for Information ML22325A2742022-11-21021 November 2022 NRR E-mail Capture - Comanche Peak - Request for Additional Information - Proposed Alternative P-1 Regarding IST of Safeguards Building Sump Pumps ML22318A3102022-11-10010 November 2022 NRR E-mail Capture - Comanche Peak - Draft Request for Additional Information - Proposed Alternative P-1 Regarding IST of Safeguards Building Sump Pumps ML22230B1092022-08-17017 August 2022 NRR E-mail Capture - Comanche Peak Unit 2 - Request for Additional Information - 2RE19 Inspection Summary Report for Steam Generator Tubing ML22220A1942022-08-0808 August 2022 NRR E-mail Capture - Comanche Peak Unit 2 - Draft Request for Additional Information - 2RE19 Inspection Summary Report for Steam Generator Tubing IR 05000445/20224012022-06-28028 June 2022 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000445/2022401; 05000446/2022401 ML22083A0262022-03-23023 March 2022 NRR E-mail Capture - Comanche Peak - Request for Additional Information - Request to Adopt TSTF 505 Revision 2 ML21286A7912021-10-13013 October 2021 NRR E-mail Capture - Comanche Peak - Request for Additional Information - Request to Adopt TSTF-577 Revision 1 ML21253A2242021-09-0909 September 2021 Request for Information Occupational Radiation Safety Inspection (71124.01, 71124.02, and 71151) from 10/18-22/2021 ML21253A2332021-09-0909 September 2021 Request for Information: Comanche Peak Nuclear Power Plant, Units 1 and 2 (05000445 and 05000446); Occupation Radiation Safety (71124.01, 71124.02, 7511) ML21245A3072021-09-0202 September 2021 Request for Information ML21245A307 ML21166A3382021-06-22022 June 2021 Supplemental Information Needed for Acceptance of Requested Licensing Action LAR to Adopt TSTF-505, Rev. 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML21165A1022021-06-13013 June 2021 Pi&R; Request for Information ML21103A3982021-04-13013 April 2021 CP Security Inspection Information Request 2021403 ML20225A0932020-08-12012 August 2020 Notification of Inspection 05000445/2020004 and 05000446/2020004 and Request for Information ML20105A1072020-04-13013 April 2020 NRR E-mail Capture - Comanche Peak - Request for Additional Information - Exigent Amendment Request for One Time Change to Unit 2 Steam Generator Inspection Frequency ML20104A0022020-04-11011 April 2020 NRR E-mail Capture - Comanche Peak Unit 2 - Request for Additional Information - Proposed Alternative to ASME OM Code for Deferral of Snubber Testing (SNB-1) and Visual Examinations (SNB-2) ML20045E3512020-02-13013 February 2020 Information Request February 13, 2020 Notification of Inspection and Request for Information Comanche Peak Unit 2 NRC Inspection Report 05000446/2020002 ML19346B3812019-12-11011 December 2019 NRR E-mail Capture - Comanche Peak RAIs - Quality Assurance Program Reduction in Commitment ML19319A5432019-11-14014 November 2019 NRR E-mail Capture - Draft Comanche Peak RAIs - Quality Assurance Program Reduction in Commitment ML19058A3592019-02-27027 February 2019 NRR E-mail Capture - Comanche Peak Nuclear Power Plant, Unit Nos. 1 and 2 - Final Request for Additional Information Concerning License Amendment Request to Revise the Emergency Plan IR 05000445/20170072018-02-0808 February 2018 Notification of Nrc Design Bases Assurance Inspection (Programs) (05000445/2017007 and 05000446/2017007) ML17276B8622017-10-0303 October 2017 Notification of NRC Design Bases Assurance Inspection (Programs)(05000445/2017007 and 05000446/2017007) and Initial Request for Information ML17087A2032017-03-28028 March 2017 NRR E-mail Capture - Comanche Peak, Unit 2 - Final Request for Additional Information Regarding Request No. 2B3-1 ML17066A2372017-03-0707 March 2017 Notification of NRC Triennial Fire Protection Baseline Inspection (05000445/2017008 and 05000446/2017008) and Request for Information ML17048A4172017-02-17017 February 2017 Notification of NRC Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/ Staffing/Multi-Unit Dose Assessment... ML16034A1962016-02-0808 February 2016 Independent Spent Fuel Storage Installation - Request for Additional Information, Application for Order Approving Transfer of Facility Operating Licenses and Conforming Amendment 2024-07-18
[Table view] |
Text
, C-.\TEMP\GW)00001.TMP oaigel i C:\TEMP\GW}OOOO1 .TMP Page 1 Mail Envelope Properties (401029CE.248:15:21310)
Subject:
Preliminary Request fir Additional Informiation Creation Date: 1/22/04 2:5 1PM From: Mohan Thadani Created By: MCT~nrc.gov Recipients Action Date & Time txu.corn Transferred 01/22/04 02:52PM ccorbin CC (Intemet:ccorbin @txu.com) rwalker5 (Internet:rvalker5 @txu.com) fred Transferred 0 1/22/04 02:52PM madden CC (Internetffred.madden @txu.com) nrc.gov owf2-po.OWFNDO Delivered 0 1/22/04 02:5 1PM RVJ CC (Ronaldo Jenkins) Opened 01/22/04 03:17PM SNS1I CC (Saba Saba) Opened 01/23/04 07:19AM nrc.gov owf4..po.OWFN_-DO Delivered 0 1/22/04 02:511PM MCT CC (Mohan Thadani) Opened 01/22/04 02:52PM NBL CC (Ngoc Le) nrc.gov owf5-po.OWFNDO Delivered 01/22/04 02:52PM THB CC (Thomas Boyce) Opened 01/22/04 02:57PM txu.com. Transferred 01/22/04 02:52PM dbuschbl. CC (Internet:dbuschbl @txu.com)
Post Office Delivered Route txu.com Internet fred Internet:txu.com owf2-po.OWVFNDO 01/22/04 02:5 1PM nrc.gov owf4-po.OWFN_-DO 01/22/04 02:51PM nrc.gov owf5..po.OWFNDO 01/22/04 02:52PM nrc.gov txu .com Files Size Date & Time MESSAGE 5622 01/22/04 02:5 1PM Options
CA\TEMP\GW}00001.TMP Page 2 Auto Delete: No Expiration Date: None Notify Recipients: Yes Priority: Standard Reply Requested: No Return Notification: None Concealed
Subject:
No Security: Standard To Be Delivered: Immediate Status Tracking: Delivered & Opened
- , .. .. .. ... ... F - . - - ^ . : .... .. > _ .... ... .. - - . - = .- . - I__ AT -; _ M ... . ^ _ _ . 5 i Mohan Thadani - Preliminary Request fir Additional Information l . . ... .. . . . - _ Page 1 From: Mohan Thadani To: Intemet:rwalker5@txu.com
- -bte: 1/22/04 2:5IPM
Subject:
Preliminary Request fir Additional Information Roger:
In reviewing the TXU's license amendment request, LAR 02-06 regarding DC electrical power tech. specs changes pursuant to TSTF 360, the NRC staff has identified the following preliminary request for additional information. After your staff reviews this preliminary request, I would like to set up a phone call for the NRC staff and theTXU staff to discuss the issues raised. During the call we will arrive at an agreement on the final form of the request, schedule for a response, and whether you would want a formal NRC letter of agreed upon request or telephone agreement is sufficient to respond to.
Thanks.
Mohan PRELIMINARY REQUEST FOR ADDITIONAL INFORMATION FOR COMANCHE PEAK STEAM ELECTRIC STATION UNITS 1 AND 2. TAC MB9532 AND MB9533:
1: It was stated in the submittal that there are two 100% capacity battery chargers per battery. For a plant in Modes 1, 2, 3, and 4, one charger for each battery is required to be operating and the other is kept as a spare.
(A) Please explain the administrative control, if any, under which the plant operator would know which one of the two battery chargers is the *required" charger to maintain the DC subsystem operable. Please provide information regarding AC power supply sources to the battery chargers during normal plant operation and during loss of offsite power sources.
(B) Please explain steps taken, if any, to meet either required action for CONDITION 3.8.4.A.1 and/or CONDITION 3.8.4.A.2 when either the "required" charger and/or the "spare" charger are not yet restored to operable status.
(C) When the so-called 'required" charger is declared inoperable" and the "spare" charger is switched in to substitute for the inoperable charger, what maintenance actions, if any, will be initiated for the inoperable charger, while the completion time for CONDITION 3.8.4.A.1 AND CONDITION 3.8.4.A.2 is in effect?
2: It was stated in the submittal that CPSES is presently committed to IEEE Standard 450-1995 (Ref. 4),
which states that battery degradation is indicated when the battery capacity drops more than 10% from its capacity of the previous performance test. However, CPSES states in the submittal that degradation is indicated when the battery capacity drops by more than 10% relative to its average capacity on the previous performance test.
Please explain and provide justification for the use of the average capacity and clarify the difference between the IEEE definition and CPSES definition as stated in the submittal.
3: It was stated in the submittal that there are two 100% capacity battery chargers per battery. For plant in Mode 1, 2, 3, and 4, one charger for each battery is required to be operating and the other is kept as a spare.
Please define "100% capacity battery charger" and state if each of the chargers was designed to be capable of handling transient loading demand requirements for all initiating events if the associated battery is out of service for any reason. This includes the adequacy of the battery
. I .1 - ...... . - , -1 . - - . . -
.. - . .1. __- ... - I I Page I~Mohan Th ad ani - Preliminiariy Re-q~u-est fir -Ad'di-tio"n'alIn'f-o--rmat-io-n' - 21
... - I-. .- - - . - I -- .- .
charger to handle transient loading requirements caused by the re-alignment of the AC sources
'following a reactor trip.