Other: ML052370264, ML052380011, ML052380020, ML052380030, ML052380034, ML052380037, ML052380039, ML052380040, ML052380042, ML052380045, ML052380062, ML052380075, ML052380129, ML052380136, ML052380137, ML052380139, ML052380140, ML052380142, ML052380145, ML052380148, ML052380152, ML052380155, ML052380159, ML052510118, ML060330481, ML062980229
|
MONTHYEARL-03-003, ISFSI - Submittal of Geotechnical and Probability Risk Assessment Calculation Packages2003-12-15015 December 2003 ISFSI - Submittal of Geotechnical and Probability Risk Assessment Calculation Packages Project stage: Request ML0402909182004-01-29029 January 2004 Meeting Notice with Pacific Gas and Electric (Pg&E) to Discuss 10 CFR Part 72 License Application for an Independent Spent Fuel Storage Installation at the Humboldt Bay Power Plant (72-27) (50-133) (L2383) - Agenda Attached Project stage: Meeting ML0420503102004-07-22022 July 2004 Request for Additional Information on License Application and Safety Analyses Report Project stage: RAI ML0420501822004-07-22022 July 2004 Ltr to L. Womack (Homboldt Bay Power Plant) from J. Hall - Request for Additional Information for the Humboldt Bay Independent Spent Fuel Storage Installation Application Project stage: RAI ML0435800642004-12-21021 December 2004 Notice of Meeting with Pacific Gas & Electric Company to Discuss Status of NRC Staff Reviews of Pg&Es 10 CFR Part 72 License Application for Independent Spent Fuel Storage Installation & Related Amendment Request for 10 CFR Part 50 License Project stage: Approval ML0500701232004-12-21021 December 2004 Revised Notice of Meeting with Pacific Gas & Electric Company to Discuss Status of NRC Staff Reviews of Pg&Es 10 CFR Part 72 License Application for ISFSI & Related Amendment Request for 10 CFR Part 50 License Project stage: Approval ML0503303912005-02-0202 February 2005 Summary of Meeting with Pacific Gas and Electric Company to Discuss the Application for the Humboldt Bay ISFSI (Tac No. L23683) Project stage: Meeting ML0523800342005-08-24024 August 2005 Enclosure 1 - Appendix - Technical Specification Bases for the Humboldt Bay ISFSI Project stage: Other ML0523800112005-08-24024 August 2005 Ltr to D. Jacobs from R. Hall, Preliminary License and SER for the Humboldt Bay ISFSI Project stage: Other ML0523800202005-08-24024 August 2005 Enclosure 1 - Preliminary License for the Humboldt Bay ISFSI Project stage: Other ML0523800302005-08-24024 August 2005 Enclosure 1 - Appendix - Technical Specifications for the Humboldt Bay ISFSI Project stage: Other ML0523702642005-08-25025 August 2005 Ltr J Hall to D Jacobs (Diablo Canyon Power Plant) Public Disclosure Determination for Information Related to the Humboldt Bay ISFSI (Tac. No. L23683) Project stage: Other ML0523801392005-08-31031 August 2005 Preliminary SER Chapter 10 - Conduct of Operations Evaluation Project stage: Other ML0523801362005-08-31031 August 2005 Preliminary SER Chapter 8 - Criticality Evaluation Project stage: Other ML0523801292005-08-31031 August 2005 Preliminary SER Chapter 7 - Shielding Evaluation Project stage: Other ML0523801402005-08-31031 August 2005 Preliminary SER Chapter 11 - Radiation Protection Evaluation Project stage: Other ML0523801592005-08-31031 August 2005 Preliminary SER Appendix - Title 10 Code of Federal Regulations Applicable to the Hb ISFSI Project stage: Other ML0523801422005-08-31031 August 2005 Preliminary SER Chapter 12 - Quality Assurance Evaluation Project stage: Other ML0523800752005-08-31031 August 2005 Preliminary SER Chapter 6 - Thermal Evaluation Project stage: Other ML0523800392005-08-31031 August 2005 Preliminary SER Chapter 1 - General Description Project stage: Other ML0523800452005-08-31031 August 2005 Preliminary SER Chapter 4 - Systems, Structures, and Components (Sscs) and Design Criteria Evaluation Project stage: Other ML0523801522005-08-31031 August 2005 Preliminary SER Chapter 15 - Accident Analysis Project stage: Other ML0523801452005-08-31031 August 2005 Preliminary SER Chapter 13 - Financial Qualifications and Decommissioning Evaluation Project stage: Other ML0523801552005-08-31031 August 2005 Preliminary SER Chapter 16 - Technical Specifications Project stage: Other ML0523800402005-08-31031 August 2005 Preliminary SER Chapter 2 - Site Characteristics Project stage: Other ML0523800372005-08-31031 August 2005 Preliminary SER Table of Contents - Executive Summary Project stage: Other ML0523801482005-08-31031 August 2005 Preliminary SER Chapter 14 - Waste Confinement and Management Evaluation Project stage: Other ML0523800622005-08-31031 August 2005 Preliminary SER Chapter 5 - Installation and Structural Evaluation Project stage: Other ML0523801372005-08-31031 August 2005 Preliminary SER Chapter 9 - Confinement Evaluation Project stage: Other ML0523800422005-08-31031 August 2005 Preliminary SER Chapter 3 - Operation Systems Project stage: Other ML0525101182005-09-0202 September 2005 Ltr J Hall to D Jacobs (Diablo Canyon Power Plant) Humboldt Bay ISFSI Application - Physical Security Plan (Tac. No. L23683) Project stage: Other ML0527600552005-09-30030 September 2005 Ltr to D. Jacobs, Diablo Canyon Power Plant, Federal Register Notice Publishing an Environmental Assessment and Finding of No Significant Impact for an Exemption from 10 CFR 72.72(d) (TAC No. L23683) Project stage: Approval ML0532203102005-11-17017 November 2005 Issuance of Materials License No. SNM-2514 for the Humboldt Bay Independent Spent Fuel Storage Installation-Cover Letter Project stage: Approval ML0603304812006-01-26026 January 2006 Independent Spent Fuel Storage Installation Final Safety Analysis Report Update, Revision 0 Project stage: Other ML0629802292006-09-14014 September 2006 Modification No. 241 to Contract No. NRC-02-02-012 Project stage: Other 2005-08-24
[Table View] |
Text
January 29, 2004 MEETING NOTICE Organization:
Pacific Gas and Electric Company (PG&E)
Date and Time:
February 12, 2004 8:00 AM (CDT) - 3:00 PM (CDT)
Location:
The Center for Nuclear Waste Regulatory Analyses (CNWRA)
Southwest Research Institute Building 189, Room A-103 6220 Culebra Road San Antonio, TX 78228-5166 This meeting will also have a videoconference connection with:
U.S. Nuclear Regulatory Commission Room O3-B4 11555 Rockville Pike Rockville, MD 20852
Purpose:
Discuss Pacific Gas & Electric Companys (PG&Es) 10 CFR Part 72 license application for an independent spent fuel storage installation at the Humboldt Bay Power Plant.
Participants:
NRC/CNWRA Stephen OConnor Asad Chowdhury (CNWRA), et al.
PG&E Terry Grebel Larry Pulley, et al.
Meeting Category:
This is a Category 1 Meeting: The public is invited to observe this meeting and will have one or more opportunities to communicate with the NRC after the business portion, but before the meeting is adjourned as per Public Meeting Policy, Federal Register Volume 67, Number 102, Pages 36920 - 36924, May 28, 2002.
Contact:
Stephen OConnor, 301-415-2169 Attendance at this meeting by other than those listed above should be made known by February 10, 2004 via phone to the above contact.
Docket Nos. 72-27, 50-133 TAC No. L23683
Attachment:
Agenda
January 29, 2004 MEETING NOTICE Organization:
Pacific Gas and Electric Company (PG&E)
Date and Time:
February 12, 2004 8:00 AM (CDT) - 3:00 PM (CDT)
Location:
The Center for Nuclear Waste Regulatory Analyses (CNWRA)
Southwest Research Institute Building 189, Room A-103 6220 Culebra Road San Antonio, TX 78228-5166 This meeting will also have a videoconference connection with:
U.S. Nuclear Regulatory Commission Room O3-B4 11555 Rockville Pike Rockville, MD 20852
Purpose:
Discuss Pacific Gas & Electric Companys (PG&Es) 10 CFR Part 72 license application for an independent spent fuel storage installation at the Humboldt Bay Power Plant.
Participants:
NRC/CNWRA Stephen OConnor Asad Chowdhury (CNWRA), et al.
PG&E Terry Grebel Larry Pulley, et al.
Meeting Category:
This is a Category 1 Meeting: The public is invited to observe this meeting and will have one or more opportunities to communicate with the NRC after the business portion, but before the meeting is adjourned as per Public Meeting Policy, Federal Register Volume 67, Number 102, Pages 36920 - 36924, May 28, 2002.
Contact:
Stephen OConnor, 301-415-2169 Attendance at this meeting by other than those listed above should be made known by February 10, 2004 via phone to the above contact.
Docket Nos. 72-27, 50-133 TAC No. L23683
Attachment:
Agenda DISTRIBUTION:
NRC File Center SFPO r/f NMSS r/f PUBLIC PMNS (e-mail)
SFPO staff (e-mail)
EWBrach WHodges LCamper WHuffman AChwdhury, CNWRA CManepally, CNWRA C:\\ORPCheckout\\FileNET\\ML040290918.wpd OFC:
SFPO SFPO SFPO NAME:
SOConnor EZiegler JMonninger DATE:
01/27/04 01/28/04 01/29/04 OFFICIAL RECORD COPY
Agenda for February 12, 2004, PG&E Meeting with NRC and CNWRA Introduction 8:00-8:15 (Grebel)
Overview of Humboldt Bay 8:15-8:20 (Pulley)
Overview of Spent Fuel 8:20-8:25 (Pulley)
Licenses and Permits 8:25-8:30 (Grebel)
Siting Issues 8:30-8:45 (Pulley)
Geotechnical Overview 8:45-9:30 (Cluff)
Break 9:30-9:45 Project Description 9:45-10:30 (Pulley)
Site-Specific Technical Aspects
- Seismic / Structural 10:30-11:15 (Pulley / Holtec)
- Tsunami 11:15-11:30 (Pulley)
- Fire Hazards 11:30-11:40 (Soenen)
- Fire Analyses 11:40-12:15 (Holtec)
Lunch 12:15-1:15
- Explosion Hazards 1:15-1:25 (Soenen)
- Explosion Analyses 1:25-1:45 (Holtec)
- Thermal 1:45-2:00 (Holtec)
- Criticality 2:00-2:15 (Holtec)
- Dose 2:15-2:30 (Holtec)
Summary 2:30-2:45 (Grebel)