Summary of Meeting on Licensee'S Modifications to High Pressure Injection Pumps
ML033450292
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 12/16/2003
From: Hopkins J
NRC/NRR/DLPM/LPD3
To:
Hopkins J, NRR/DLPM, 415-3027
Shared Package
ML033450367 List:
References
Download: ML033450292 (6)


Text

December 16, 2003 LICENSEE: FirstEnergy Nuclear Operating Company FACILITY: Davis-Besse Nuclear Power Station, Unit 1

SUBJECT:

SUMMARY

OF MEETING ON JUNE 19, 2003, TO DISCUSS THE LICENSEES MODIFICATIONS TO THE HIGH PRESSURE INJECTION PUMPS On June 19, 2003, members of the U.S. Nuclear Regulatory Commission (NRC) staff met with FirstEnergy Nuclear Operating Company (the licensee), representatives at NRC Headquarters, Two White Flint North, 11545 Rockville Pike, Rockville, MD. The meeting was also video-conferenced with NRC staff at Region III. The purpose of the meeting was to discuss the licensees planned modifications to the Davis-Besse high pressure injection (HPI) pumps to address the issue of possible debris clogging of a cooling port to the hydrostatic bearing. The meeting was a Category 1 public meeting with an audioconference bridge available for those unable to attend in person. The licensees presentation slides are available on the NRC Web site for the meeting. Enclosure 1 is a list of attendees.

The licensees presentation included background information on the HPI pumps, planned modifications to the pumps, and testing planned for the pump modification design. The licensee mentioned that the French had moved the supply port as they were contemplating doing, and that the licensee was trying to obtain information regarding the French pump design and modification. The licensee stated that the first critical operating speed of their pumps was at 3900 rpm and that at a clearance of 2X, the critical operating speed reduced to 3300 rpm.

The licensees contractor was performing analyses concerning the above as the pumps operating speed is 3600 rpm. The licensee stated that the hydraulic performance model would be validated by tests in the plant. The mockup tests are to be performed at Wylie laboratory in Huntsville, Alabama. The licensee expects to complete the self-flushing and clearance tests within the week.

In response to a staff question, the licensee stated that a Failure Modes and Effects Analysis will be available for NRC staff review. In response to another staff question, the licensee stated that the internal strainer would be constructed of austenitic stainless steel and if the strainer were to be destroyed, the debris would flow through the pump. The meeting ended with the staff stating that it would continue to follow the licensees modification design.

/RA/

Jon B. Hopkins, Senior Project Manager, Section 2 Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-346

Enclosures:

1. Attendance List
2. Meeting Slides cc w/encls: See next page

December 16, 2003 In response to a staff question, the licensee stated that a Failure Modes and Effects Analysis will be available for NRC staff review. In response to another staff question, the licensee stated that the internal strainer would be constructed of austenitic stainless steel and if the strainer were to be destroyed, the debris would flow through the pump. The meeting ended with the staff stating that it would continue to follow the licensees modification design.

/RA/

Jon B. Hopkins, Senior Project Manager, Section 2 Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-346

Enclosures:

1. Attendance List
2. Meeting Slides cc w/encls: See next page DISTRIBUTION:

PUBLIC LMarsh/ELeeds JGolla PDIII-2 Reading WRuland AMendiola HNieh JHopkins TScarbrough THarris SUnikewicz OGC AFranovich ACRS/ACNW DTerao CLipa, RIII BJain Package: ML033450367 Attachment - Slides: ML033450382 ADAMS Accession Number: ML033450292 OFFICE PDIII-2/PM PDIII-2/LA PDIII-1/SC NAME JHopkins THarris AMendiola DATE 12/12/03 12/12/03 12/16/03 OFFICIAL RECORD COPY

ATTENDANCE LIST NRC MEETING WITH FIRSTENERGY NUCLEAR OPERATING COMPANY DAVIS-BESSE HPI PUMP MODIFICATIONS JUNE 19, 2003 J. Powers, FENOC R. Franovich, NRC R. Coward, MPR Associates D. Terao, NRC R. Schrauder, FENOC W. Lyon, NRC G. Leidich, FENOC D. Lochbaum, UCS S. Kinsey, MPR Associates D. Horner, McGraw-Hill S. Frantz, Morgan Lewis M. Woods, Pittsburgh Post Gazette A. Mendiola, NRC D. Raleigh, Scientech H. Nieh, NRC B. Jain, NRC W. Ruland, NRC J. Golla, NRC T. Scarbrough, NRC T. Janosi, Hungarian AEA S. Unikewicz, NRC F. Adovjaih, Hungarian AEA J. Hopkins, NRC

Davis-Besse Nuclear Power Station, Unit 1 cc:

Mary E. OReilly Zack A. Clayton FirstEnergy Corporation DERR 76 South Main St. Ohio Environmental Protection Agency Akron, OH 44308 P.O. Box 1049 Columbus, OH 43266-0149 Manager - Regulatory Affairs FirstEnergy Nuclear Operating Company State of Ohio Davis-Besse Nuclear Power Station Public Utilities Commission 5501 North State - Route 2 180 East Broad Street Oak Harbor, OH 43449-9760 Columbus, OH 43266-0573 Director, Ohio Department of Commerce Attorney General Division of Industrial Compliance Department of Attorney General Bureau of Operations & Maintenance 30 East Broad Street 6606 Tussing Road Columbus, OH 43216 P.O. Box 4009 Reynoldsburg, OH 43068-9009 President, Board of County Commissioners of Ottawa County Regional Administrator Port Clinton, OH 43252 U.S. Nuclear Regulatory Commission 801 Warrenville Road President, Board of County Lisle, IL 60523-4351 Commissioners of Lucas County One Government Center, Suite 800 Michael A. Schoppman Toledo, OH 43604-6506 Framatome ANP 1911 N. Ft. Myer Drive David Lochbaum, Nuclear Safety Engineer Rosslyn, VA 22209 Union of Concerned Scientists 1707 H Street NW, Suite 600 Resident Inspector Washington, DC 20006 U.S. Nuclear Regulatory Commission 5503 North State Route 2 The Honorable Dennis J. Kucinich Oak Harbor, OH 43449-9760 United States House of Representatives Washington, D.C. 20515 Randel J. Fast, Plant Manager FirstEnergy Nuclear Operating Company The Honorable Dennis J. Kucinich, Member Davis-Besse Nuclear Power Station United States House of Representatives 5501 North State - Route 2 14400 Detroit Avenue Oak Harbor, OH 43449-9760 Lakewood, OH 44107 Dennis Clum Mr. James P. Riccio Radiological Assistance Section Supervisor Nuclear Policy Analyst Bureau of Radiation Protection Greenpeace Ohio Department of Health 702 H. Street, NW, Suite 300 P.O. Box 118 Washington, DC 20001 Columbus, OH 43266-0118 Paul Gunter Carol OClaire, Chief, Radiological Branch Director Nuclear Watchdog Project Ohio Emergency Management Agency Nuclear Information & Resource Service 2855 West Dublin Granville Road 1424 16th Street NW Suite 401 Columbus, OH 43235-2206 Washington, DC 20009