ML033380523

From kanterella
Jump to navigation Jump to search
IR 05000400-03-007, Shearon Harris, on 02/01/03 - 10/21/03, Significance Determination of Fire Protection Findings
ML033380523
Person / Time
Site: Harris 
Issue date: 11/18/2003
From: Ogle C
NRC/RGN-II/DRP/RPB1
To: Scarola J
Carolina Power & Light Co
References
FOIA/PA-2004-0277 IR-03-007
Download: ML033380523 (21)


See also: IR 05000400/2003007

Text

ATTACHMENT 2 CONTAINS PROPRIETARY INFORMATION

November 18, 2003

EA-00-022

EA-01-310

Carolina Power & Light Company

ATTN: Mr. James Scarola

Vice President - Harris Plant

PROPRIETARY INFORMATION

Shearon Harris Nuclear Power Plant

REMOVED

P. O. Box 165, Mail Code: Zone 1

New Hill, North Carolina 27562-0165

SUBJECT:

SHEARON HARRIS NUCLEAR POWER PLANT - NRC FIRE PROTECTION

INSPECTION REPORT NO. 05000400/2003007

Dear Mr. Scarola:

On October 21, 2003, the U.S. Nuclear Regulatory Commission (NRC) completed an in-office

review of the significance of the triennial fire protection inspection findings of inspection report

05000400/2002011 related to your Shearon Harris Nuclear Power Plant. The enclosed report

documents the results of our significance determination, which was discussed on

October 21, 2003, by telephone with Mr. R. Duncan and other members of your staff.

This report documents two NRC-identified findings of very low significance (Green). Both of

these findings were determined to involve violations of NRC requirements. However, because

of the very low safety significance and because they are entered into your corrective action

program, the NRC is treating these two findings as non-cited violations (NCVs) consistent with

Section VI.A. of the NRC Enforcement Policy. If you contest any NCV in this report, you should

provide a response within 30 days of the date of this inspection report, with the basis for your

denial, to the Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington,

DC 20555-0001; with copies to the Regional Administrator, Region II; the Director, Office of

Enforcement, United States Nuclear Regulatory Commission, Washington, DC 20555-0001;

and the NRC Resident Inspector at the Shearon Harris Nuclear Power Plant.

In accordance with 10 CFR 2.790 of the NRCs Rules of Practice, a copy of this letter,

portions of its enclosure and your response (if any) will be available electronically for public

inspection in the NRC Public Document Room or from the Publicly Available Records (PARS)

component of

DOCUMENT TRANSMITTED HEREWITH CONTAINS SENSITIVE UNCLASSIFIED INFORMATION

WHEN SEPARATED FROM ATTACHMENT 2, THIS DOCUMENT IS DECONTROLLED

ATTACHMENT 2 CONTAINS PROPRIETARY INFORMATION

CP&L

2

NRCs document system (ADAMS). However, the NRC is continuing to review the appropriate

classification of the Phase 3 significance determination process analysis (Attachment 2) within

our records management program, considering changes in our practices following the events of

September 11, 2001. Using our interim guidance, the attached analysis has been marked as

Proprietary Information or Sensitive Information in accordance with Section 2.790(d) of Title 10

of the Code of Federal Regulations. Please control the document accordingly (i.e., treat the

document as if you had determined that it contained trade secrets and commercial or financial

information that you considered privileged or confidential). We will inform you if the

classification of these documents change as a result of our ongoing assessments. ADAMS is

accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public

Electronic Reading Room).

Sincerely,

/RA/

Charles R. Ogle, Chief

Engineering Branch 1

Division of Reactor Safety

Docket No.: 50-400

License No.: NPF-63

Enclosure: Inspection Report 05000400/2003007

w/Attachments: 1. Supplemental Information

2. Phase 3 SDP Analysis (Contains Proprietary Information)

cc w/encl and Attachment 1:

James W. Holt, Manager

Performance Evaluation and

Regulatory Affairs CPB 9

Carolina Power & Light Company

Electronic Mail Distribution

Robert J. Duncan II

Director of Site Operations

Carolina Power & Light Company

Shearon Harris Nuclear Power Plant

Electronic Mail Distribution

(cc w/encl and Attachment 1 contd - See page 3)

DOCUMENT TRANSMITTED HEREWITH CONTAINS SENSITIVE UNCLASSIFIED INFORMATION

WHEN SEPARATED FROM ATTACHMENT 2, THIS DOCUMENT IS DECONTROLLED

ATTACHMENT 2 CONTAINS PROPRIETARY INFORMATION

CP&L

3

(cc w/encl and Attachment 1 contd)

Benjamin C. Waldrep

Plant General Manager--Harris Plant

Carolina Power & Light Company

Shearon Harris Nuclear Power Plant

Electronic Mail Distribution

Terry C. Morton, Manager

Support Services

Carolina Power & Light Company

Shearon Harris Nuclear Power Plant

Electronic Mail Distribution

John R. Caves, Supervisor

Licensing/Regulatory Programs

Carolina Power & Light Company

Shearon Harris Nuclear Power Plant

Electronic Mail Distribution

Steven R. Carr

Associate General Counsel - Legal Department

Progress Energy Service Company, LLC

Electronic Mail Distribution

John H. O'Neill, Jr.

Shaw, Pittman, Potts & Trowbridge

2300 N. Street, NW

Washington, DC 20037-1128

Beverly Hall, Acting Director

Division of Radiation Protection

N. C. Department of Environmental

Commerce & Natural Resources

Electronic Mail Distribution

Peggy Force

Assistant Attorney General

State of North Carolina

Electronic Mail Distribution

(cc w/encl and Attachment 1 contd - See page 4)

DOCUMENT TRANSMITTED HEREWITH CONTAINS SENSITIVE UNCLASSIFIED INFORMATION

WHEN SEPARATED FROM ATTACHMENT 2, THIS DOCUMENT IS DECONTROLLED

ATTACHMENT 2 CONTAINS PROPRIETARY INFORMATION

CP&L

4

(cc w/encl and Attachment 1 contd)

Public Service Commission

State of South Carolina

P. O. Box 11649

Columbia, SC 29211

Chairman of the North Carolina

Utilities Commission

c/o Sam Watson, Staff Attorney

Electronic Mail Distribution

Robert P. Gruber

Executive Director

Public Staff NCUC

4326 Mail Service Center

Raleigh, NC 27699-4326

Herb Council, Chair

Board of County Commissioners

of Wake County

P. O. Box 550

Raleigh, NC 27602

Tommy Emerson, Chair

Board of County Commissioners

of Chatham County

Electronic Mail Distribution

Distribution w/encl and Attachment 1:

PUBLIC

RIDSNRRDIPMLIPB

Distribution w/encl and Attachments 1 and 2:

L. Slack, EICS

B. Mozafari, NRR

OEMAIL

(SEE PREVIOUS PAGE FOR CONCURRENCES)

OFFICE

RII:DRS

RII:DRS

RII:DRS

RII:DRP

RII:EICS

SIGNATURE

RA

RA

RA

RA

RA

NAME

RSchin

WRogers

KODonohue

PFredrickson

CEvans

DATE

10/24/2003

10/27/2003

11/18/2003

10/27/2003

11/14/2003

E-MAIL COPY?

YES

NO YES

NO YES

NO YES

NO YES

NO YES

NO YES

NO

PUBLIC

YES

NO

OFFICIAL RECORD COPY DOCUMENT NAME: C:\\ORPCheckout\\FileNET\\ML033380523.wpd

DOCUMENT TRANSMITTED HEREWITH CONTAINS SENSITIVE UNCLASSIFIED INFORMATION

WHEN SEPARATED FROM ATTACHMENT 2, THIS DOCUMENT IS DECONTROLLED

ATTACHMENT 2 CONTAINS PROPRIETARY INFORMATION

Enclosure

U.S. NUCLEAR REGULATORY COMMISSION

REGION II

Docket No.:

50-400

License No.:

NPF-63

Report No.:

05000400/2003007

Licensee:

Carolina Power & Light (CP&L)

Facility:

Shearon Harris Nuclear Power Plant

Location:

5413 Shearon Harris Road

New Hill, NC 27562

Dates:

February 1, 2003 - October 21, 2003

Inspectors:

W. Rogers, Senior Reactor Analyst, Region II

R. Schin, Senior Reactor Inspector, Region II

Approved by:

Charles R. Ogle, Chief

Engineering Branch 1

Division of Reactor Safety

DOCUMENT TRANSMITTED HEREWITH CONTAINS SENSITIVE UNCLASSIFIED INFORMATION

WHEN SEPARATED FROM ATTACHMENT 2, THIS DOCUMENT IS DECONTROLLED

ATTACHMENT 2 CONTAINS PROPRIETARY INFORMATION

SUMMARY OF FINDINGS

IR 05000400/2003-007; 02/01/2003 - 10/21/2003; Shearon Harris Nuclear Power Plant;

Significance Determination of Fire Protection Findings.

The in-office review was conducted by a regional inspector, a regional senior reactor analyst,

and NRC Headquarters risk analysts. Two Green findings, each a non-cited violation (NCV),

were identified. The significance of issues is indicated by their color (Green, White, Yellow,

Red) using IMC 0609 Significance Determination Process (SDP). Findings for which the SDP

does not apply may be Green or be assigned a severity level after NRC management review.

The NRC's program for overseeing the safe operation of commercial nuclear power reactors is

described in NUREG-1649, Reactor Oversight Process, Revision 3, dated July 2000.

A.

Inspector Identified Findings

Cornerstones: Mitigating Systems and Initiating Events

Green. The inspectors identified a non-cited violation (NCV) of Operating License

Condition 2.F, the Fire Protection Program, and Technical Specification 6.8.1,

Procedures and Programs, for inadequate implementation of the fire protection

program. Physical and procedural protection for equipment that was relied on for safe

shutdown (SSD) during a fire in fire safe shutdown analysis (SSA) areas 1-A-BAL-B-B1,

1-A-BAL-B-B2, 1-A-BAL-B-B4, 1-A-BAL-B-B5, 1-A-EPA, and 1-A-BAL-C of the reactor

auxiliary building was inadequate. Consequently, a fire in one of these SSA areas

could result in a reactor coolant pump seal loss of coolant accident event, a main steam

power-operated relief valve failed open event, a loss of high pressure safety injection,

and/or a loss of component cooling water to the reactor coolant pump seals. Licensee

corrective action included assigning an additional operator to be available to perform

post-fire SSD actions and performing a complete review of the SSA and related

operating procedures.

This finding was greater than minor because it involved a lack of required fire barriers

for equipment that was relied upon for safe hot shutdown following a fire. The finding

also had more than minor safety significance because it affected the objectives of the

Mitigating Systems and Initiating Events Cornerstones. The finding affected the

availability and reliability of systems that mitigate initiating events to prevent undesirable

consequences and also affected the likelihood of occurrence of initiating events that

challenge critical safety functions. The finding was of very low significance (Green)

because of the low fire ignition frequencies, lack of combustible materials in critical

locations, and the effectiveness of the fire protection features and the unaffected SSD

equipment to mitigate a fire in each of the affected fire zones/areas.

[Section 1R05.1.b.(1)]

DOCUMENT TRANSMITTED HEREWITH CONTAINS SENSITIVE UNCLASSIFIED INFORMATION

WHEN SEPARATED FROM ATTACHMENT 2, THIS DOCUMENT IS DECONTROLLED

ATTACHMENT 2 CONTAINS PROPRIETARY INFORMATION

2

Green. The inspectors identified a non-cited violation (NCV) of Operating License

Condition 2.F, the Fire Protection Program, and Technical Specification 6.8.1,

Procedures and Programs, for inadequate corrective action for previous Violation

50-400/02-08-01. Corrective action for that violation had included creating a new

auxiliary control panel fire area (1-A-ACP) in 2002. However, that corrective action was

not adequate because physical and procedural protection for equipment that was relied

on for safe shutdown (SSD) during a fire in the new fire area was inadequate.

Consequently, a fire in area 1-A-ACP could result in a loss of auxiliary feedwater and a

main steam power-operated relief valve failed open event. Licensee corrective actions

in response to this finding included assigning an additional operator to be available to

perform post-fire SSD actions and performing a complete review of the SSA and related

operating procedures.

This finding was greater than minor because it involved inadequate fire barriers for

equipment that was relied upon for safe hot shutdown following a fire. The finding also

had more than minor safety significance because it affected the objectives of the

Mitigating Systems and Initiating Events Cornerstones. The finding affected the

availability and reliability of systems that mitigate initiating events to prevent undesirable

consequences and also affected the likelihood of occurrence of initiating events that

challenge critical safety functions. The finding was of very low significance (Green)

because of the very low ignition sources in the fire area, manual suppression capability,

and the power conversion system not being affected by a fire in this fire area. [Section

1R05.1.b.(2)]

B.

Licensee-Identified Violations

None

DOCUMENT TRANSMITTED HEREWITH CONTAINS SENSITIVE UNCLASSIFIED INFORMATION

WHEN SEPARATED FROM ATTACHMENT 2, THIS DOCUMENT IS DECONTROLLED

ATTACHMENT 2 CONTAINS PROPRIETARY INFORMATION

REPORT DETAILS

1.

REACTOR SAFETY

Cornerstones: Initiating Events and Mitigating Systems

1R05

FIRE PROTECTION

.1

Significance Determination for Triennial Fire Protection Inspection Findings

a.

Inspection Scope

In Inspection Report (IR) 50-400/02-11, nine findings were identified as unresolved

items (URIs) pending completion of the NRC significance determination process (SDP).

The nine URIs were as follows:

URI 50-400/02-11-01, Failure to Protect Charging System MOV 1CS-165, VCT

Outlet to CSIPs, From Maloperation Due To a Fire

URI 50-400/02-11-02, Failure to Protect Charging System MOVs 1CS-169,

1CS-214, 1CS-218, and 1CS-219 From Maloperation Due To a Fire

URI 50-400/02-11-03, Failure to Protect Charging System MOVs 1CS-166,

1CS-168, and 1CS-217 From Maloperation Due To a Fire

URI 50-400/02-11-04, Failure to Protect Component Cooling MOVs 1CC-251

and 1CC-208, CC for RCP Seals, From Maloperation Due To a Fire

URI 50-400/02-11-05, Reliance on Manual Actions in Place of Required Physical

Separation or Protection From a Fire

URI 50-400/02-11-06, Fire SSD Operator Actions With Excessive Challenges

URI 50-400/02-11-07, Too Many Fire SSD Actions for Operators to Perform

URI 50-400/02-11-08, Using the Boric Acid Tank Without Level Indication

URI 50-400/02-11-09, Failure to Provide Required Emergency Lighting for SSD

Operator Actions

This IR documents the results of the in-office completion of the NRC SDP with respect

to the nine URIs. The significance determination was accomplished as described in

NRC Inspection Manual Chapter (IMC) 0609, Signification Determination Process; IMC

DOCUMENT TRANSMITTED HEREWITH CONTAINS SENSITIVE UNCLASSIFIED INFORMATION

WHEN SEPARATED FROM ATTACHMENT 2, THIS DOCUMENT IS DECONTROLLED

ATTACHMENT 2 CONTAINS PROPRIETARY INFORMATION

2

0609A, Significance Determination of Reactor Inspection Findings for At-Power

Situations; and IMC 0609F, Determining Potential Risk Significance of Fire Protection

and Post-Fire Safe Shutdown Inspection Findings. This involved evaluating the

significance of a potential fire in each of seven affected fire safe shutdown analysis

(SSA) areas using the Phase 2 SDP, considering all examples of the findings that could

be involved in each fire. To better assess the overall significance of all of the

performance deficiencies, they were processed through the SDP as two overall findings:

1) Inadequate Implementation of the Fire Protection Program (FPP) for safe shutdown

(SSD); and 2) Inadequate Corrective Action for a Previous White Fire Protection

Finding.

In addition, the performance deficiencies which could result in the loss of a safety

function were evaluated by NRC Headquarters risk analysts using the Phase 3 portion

of the SDP. Included in this evaluation were extensive walkdowns of the applicable fire

SSA areas by two NRC fire protection contractors to observe ignition sources and

possible fire propagation pathways from these ignition sources that could affect the

unprotected cables of concern. Also, electrical circuit drawings and the latest

information on cable hot short failure mechanisms and probabilities were used to

develop cable failure probabilities that could cause a loss of function for the unprotected

cables of concern.

b.

Findings

(1)

Inadequate Implementation of the FPP for SSD

Introduction: An overall finding was identified in that the implementation of the FPP was

inadequate. Eight of the nine URIs described in IR 50-400/02-11 were considered to

include performance deficiencies related to this overall finding. Based on evaluating

those performance deficiencies for their effects during fires that could occur in each of

six (of the seven total) affected fire SSA areas, this overall finding was determined to

have a very low significance (Green).

Description: The licensees implementation of the FPP for ensuring the ability to safely

shut down the plant during a fire was inadequate, in that:

The fire SSA failed to identify several cables that were relied upon for SSD

during a fire. Consequently, those cables were not provided with the required

protection from fire damage. A fire could cause hot shorts in the cables which

would result in maloperation of equipment that was relied upon for SSD during

that fire.

The SSA identified many cables that were relied upon for SSD during a fire, for

which the licensee generally failed to provide the required physical protection

from fire damage. Instead, the SSA designated that operator actions would be

DOCUMENT TRANSMITTED HEREWITH CONTAINS SENSITIVE UNCLASSIFIED INFORMATION

WHEN SEPARATED FROM ATTACHMENT 2, THIS DOCUMENT IS DECONTROLLED

ATTACHMENT 2 CONTAINS PROPRIETARY INFORMATION

3

taken to prevent or mitigate the effects of the fire damage. However, the

licensee did not obtain NRC approval for these deviations from the approved

FPP.

Some of the operator actions that were designated by the SSA were not

incorporated into operating procedures for SSD. Also, the operator actions in

procedures differed in many respects from the operator actions that were

analyzed in the SSA. For example, the operating procedures directed operators

to use some different flowpaths than those analyzed in the SSA.

Some operator actions in the SSD procedures would not work. They were too

challenging, involved entering the area of the fire, were not adequately analyzed,

or were too numerous for the available SSD non-licensed operator to perform.

Detailed examples related to this overall finding were included in the following eight

URIs: 50-400/02-11-01, -02, -03, -04, -05, -07, -08, and -09.

Analysis: The inspectors and analysts evaluated the effects of the multiple examples of

this overall finding during a fire that could occur in each of the six affected fire SSA

areas of the reactor auxiliary building (RAB) using Phase 2 and Phase 3 of the SDP.

Based on that analysis, the inspector and analysts concluded that this finding had more

than minor safety significance because it involved a lack of required fire barriers for

equipment that was relied upon for safe hot shutdown following a fire. The finding also

had more than minor safety significance because it affected the availability and reliability

objectives and the equipment performance attribute of the Mitigating Systems

Cornerstone. In addition, it affected the Initiating Events Cornerstone in that it affected

the objective of limiting the likelihood of occurrence of initiating events that challenge

critical safety functions and also affected the design control attribute. The overall finding

did not have more than very low safety significance (Green) because of the low fire

ignition frequencies that could impact the cables of interest, the lack of combustible

materials in critical locations, and the effectiveness of the fire protection features and

the unaffected SSD equipment to mitigate a fire in each of the affected fire zones/areas.

Enforcement: As described in IR 50-400/02-11, Operating License Condition (OLC) 2.F

requires that the licensee implement and maintain in effect all provisions of the FPP as

described in the Final Safety Analysis Report (FSAR). The Updated FSAR (UFSAR),

Section 9.5.1, FPP, states that outside containment, where cables or equipment

(including associated non-essential circuits that could prevent operation or cause

maloperation due to hot shorts, open circuits, or shorts to ground) of redundant SSD

divisions of systems necessary to achieve and maintain hot shutdown conditions are

located within the same fire area outside of primary containment, one of the redundant

divisions must be ensured to be free of fire damage. Section 9.5.1 further states that if

both divisions are located in the same fire area, then one division is to be physically

DOCUMENT TRANSMITTED HEREWITH CONTAINS SENSITIVE UNCLASSIFIED INFORMATION

WHEN SEPARATED FROM ATTACHMENT 2, THIS DOCUMENT IS DECONTROLLED

ATTACHMENT 2 CONTAINS PROPRIETARY INFORMATION

4

protected from fire damage by one of three methods: 1) a three-hour fire barrier, 2) a

one-hour fire barrier plus automatic detection and suppression, or 3) a 20-foot

separation with no intervening combustibles and with automatic detection and

suppression. The licensee had not received NRC approval for deviating from these

requirements.

Also, OLC 2. F. and UFSAR Section 9.5.1 state that Branch Technical Position (BTP)

9.5-1 was used in the design of the FPP for safety-related systems and equipment and

for other plant areas containing fire hazards that could adversely affect safety-related

systems. BTP 9.5-1, Section C.5.g, Lighting and Communication, paragraph (1),

requires that fixed self-contained lighting consisting of fluorescent or sealed-beam units

with individual eight-hour-minimum battery power supplies should be provided in areas

that must be manned for SSD and for access and egress routes to and from all fire

areas.

In addition, Technical Specification 6.8.1, Procedures and Programs, requires

procedures as recommended by Regulatory Guide 1.33 and procedures for FPP

implementation. Regulatory Guide 1.33 recommends procedures for combating

emergencies, including fires. The licensees interpretation of the FPP was that they

could and would rely on proceduralized operator actions in place of physically protecting

electrical cables for SSD equipment from fire damage. The operator actions were

contained in Procedure AOP-36, Safe Shutdown Following a Fire, Rev. 21.

Contrary to the above requirements, the licensee failed to adequately implement and

maintain in effect all of the provisions of the approved FPP. The licensee failed to

ensure that one of the redundant SSD divisions of systems necessary to achieve and

maintain cold shutdown conditions was protected from fire damage; failed to have

adequate procedures for combating fire emergencies; and failed to provide the required

emergency lighting in areas that must be manned for SSD; as described above in the

eight examples of this overall finding. These conditions were identified by the NRC in

December 2002 and had been in place for years. Because the identified examples of

this failure to adequately implement and maintain in effect all of the provisions of the

approved FPP are of very low safety significance and have been entered into the

corrective action program [Action Requests (ARs) 76260, 80212, 80089, 69721, 80215,

75065, and 79047], this violation is being treated as a NCV, consistent with Section VI.A

of the NRC Enforcement Policy: NCV 50-400/03-07-01; Inadequate Implementation of

the Fire Protection Program for Safe Shutdown.

(2)

Inadequate Corrective Action for a Previous White Fire Protection Finding

Introduction: In IR 50-400/02-08, the NRC left Violation 50-400/02-08-01 open for

further NRC review of the new manual operator actions that were added for the new

1-A-ACP fire area, as part of the licensees corrective action for the violation. In IR

50-400/02-11, the NRC documented the review of those new manual operator actions

DOCUMENT TRANSMITTED HEREWITH CONTAINS SENSITIVE UNCLASSIFIED INFORMATION

WHEN SEPARATED FROM ATTACHMENT 2, THIS DOCUMENT IS DECONTROLLED

ATTACHMENT 2 CONTAINS PROPRIETARY INFORMATION

5

and identified that the licensees corrective actions contributed to four new findings. For

this significance determination, those findings were grouped into one overall finding of

inadequate corrective action for a previous White fire protection finding. Based on

evaluating the multiple examples of this overall finding for their effects during a fire that

could occur in the new 1-A-ACP fire area, this overall finding was determined to have a

very low significance (Green).

Description: The licensees corrective actions for a previous White fire protection finding

(Violation 50-400/02-08-01), associated with a Thermo-Lag fire barrier assembly

between the B train switchgear room / auxiliary control panel and the A train cable

spreading room, were inadequate. The corrective actions were inadequate because

they failed to rectify deficiencies in design, construction, and operation related to SSD

from a fire in the new 1-A-ACP fire area. Consequently, a fire in area 1-A-ACP could

result in a loss of auxiliary feedwater and a main steam power-operated relief valve

failed open event. The licensees corrective actions contributed to four new findings that

are now grouped into the overall finding of inadequate corrective action:

The corrective actions created a new fire area (1-A-ACP) and many new manual

operator actions for a fire in the new fire area instead of providing the required

physical protection of cables. This finding was described in URI 50-400/02-11-

05, Reliance on Manual Actions in Place of Required Physical Separation or

Protection From a Fire.

The corrective actions also created a manual operator action with excessive

challenges such that there was not reasonable assurance that all non-licensed

operators (NLOs) would be able to perform the action during a fire event. This

finding was described in URI 50-400/02-11-06, Fire SSD Operator Actions With

Excessive Challenges.

In addition, the corrective actions created too many local manual operator

actions for the new fire area for the one SSD NLO to perform. This finding was

described in URI 50-400/02-11-07, Too Many Fire SSD Actions for Operators to

Perform.

Further, the corrective actions failed to provide the required emergency lighting

for the new manual actions. This finding was described in URI 50-400/02-11-09,

Failure to Provide Required Emergency Lighting for SSD Operator Actions.

Analysis: The inspectors and analysts evaluated the effects of the multiple examples of

the overall finding of inadequate corrective action during a fire that could occur in the

1-A-ACP fire area of the RAB, using Phase 2 of the SDP. Based on that evaluation,

the inspectors and analysts concluded that the overall finding had more than minor

safety significance because it involved inadequate fire barriers for equipment that was

relied upon for safe hot shutdown following a fire. The finding also had more than minor

DOCUMENT TRANSMITTED HEREWITH CONTAINS SENSITIVE UNCLASSIFIED INFORMATION

WHEN SEPARATED FROM ATTACHMENT 2, THIS DOCUMENT IS DECONTROLLED

ATTACHMENT 2 CONTAINS PROPRIETARY INFORMATION

6

safety significance because it affected the availability and reliability objectives and the

equipment performance attribute of the Mitigating Systems Cornerstone. In addition, it

affected the Initiating Events Cornerstone in that it affected the objective of limiting the

likelihood of occurrence of initiating events that challenge critical safety functions and

also affected the design control attribute. The finding did not have more than very low

safety significance (Green) because of the very low ignition sources in the fire area,

manual suppression capability, and the power conversion system not being affected by

a fire in this fire area. The Green significance determination was also confirmed by a

walkdown of the fire area by two contractors.

Enforcement: Operating License Condition 2.F and the UFSAR, Section 9.5.1, FPP,

includes quality assurance requirements for fire protection. The FPP states that a

quality assurance program is being used to identify and rectify any possible deficiencies

in design, construction, and operation of the fire protection systems. Operating License

Condition 2.F requires that one of the redundant divisions be free of fire damage.

Further, if both divisions were located in the same area, OLC 2.F requires that one of

the divisions be physically protected from fire damage by one of three specified

methods. Also, OLC.2.F requires that battery-backed emergency lights be provided in

locations where operators are required to perform actions for SSD from a fire. In

addition, Technical Specification 6.8.1, Procedures and Programs, requires procedures

for implementing the FPP and for combating fires. The licensees procedure for safe

shutdown following a fire in the new ACP room fire area was AOP-36, Safe Shutdown

Following a Fire, Rev. 24.

Contrary to the above requirements, the licensees corrective actions for previous

Violation 50-400/02-08-01 were inadequate because the actions failed to rectify

deficiencies in design, construction, and operation related to SSD from a fire in the area

of the ACP room. The licensee failed to protect various equipment either physically or

procedurally from the effects of a fire where that equipment was relied on for SSD. The

new ACP room effectively became part of the licensees FPP when AOP-36 was revised

(Revision 24) in November 2002 to include new operator actions for a fire in the new

ACP room. Consequently, the conditions included in this violation were effectively in

place for more than three days but less than thirty days when they were identified by the

NRC in December 2002 during the triennial fire protection inspection. Because the

identified examples of this inadequate corrective action are of very low safety

significance and have been entered into the corrective action program (AR 80215), this

violation is being treated as an NCV, consistent with Section VI.A of the NRC

Enforcement Policy: NCV 50-400/03-07-02; Inadequate Corrective Action for a

Previous White Fire Protection Finding.

.2

(Closed) VIO 50-400/02-08-01, Failure to Implement and Maintain NRC Approved FPP

SSD System Separation Requirements

DOCUMENT TRANSMITTED HEREWITH CONTAINS SENSITIVE UNCLASSIFIED INFORMATION

WHEN SEPARATED FROM ATTACHMENT 2, THIS DOCUMENT IS DECONTROLLED

ATTACHMENT 2 CONTAINS PROPRIETARY INFORMATION

7

This Violation was closed with a new corrective action NCV opened as discussed in

Section 1R05.1.b.(2).

.3

(Closed) URIs 50-400/02-11-01, -02, -03, -04, -05, -06, -07, -08, and -09

These URIs were resolved in two new NVCs as discussed in Sections 1R05.1.b.(1) and

(2). Consequently, these URIs are closed.

4.

OTHER ACTIVITIES

4OA3 Event Followup

(Closed) LER 50-400/02-04-00, Unanalyzed Condition Due to Inadequate Separation of

Associated Circuits

This LER describes conditions that were previously identified by the NRC in IR

50-500/02-11 and that were evaluated and resolved in a new NCV in Section

1R05.1.b.(1) above. This LER was reviewed by the inspectors and no additional

findings were identified. This LER is closed.

4OA6 Meetings, including Exit

The team presented the inspection results to Mr. R. Duncan and other members of his

staff at the conclusion of the inspection on October 21, 2003. The licensee

acknowledged the findings presented. Proprietary information is not included in this

inspection report.

DOCUMENT TRANSMITTED HEREWITH CONTAINS SENSITIVE UNCLASSIFIED INFORMATION

WHEN SEPARATED FROM ATTACHMENT 2, THIS DOCUMENT IS DECONTROLLED

ATTACHMENT 2 CONTAINS PROPRIETARY INFORMATION

Attachment 1

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee personnel

J. Caves, Licensing Supervisor

F. Diya, Acting Manager, Engineering

R. Duncan, Director of Site Operations

M. Fletcher, Manager, Fire Protection Program

T. Morton, Manager, Support Services

NRC personnel

G. MacDonald, Senior Project Engineer, Division of Reactor Projects, Region II

R. Musser, Senior Resident Inspector, Shearon Harris

P. OBryan, Resident Inspector, Shearon Harris

C. Ogle, Chief, Engineering Branch 1, Division of Reactor Safety, Region II

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

Opened and Closed

50-400/03-07-01

NCV

Inadequate Implementation of the FPP for SSD

[Section 1R05.1.b.(1)]

50-400/03-07-02

NCV

Inadequate Corrective Action for a Previous White Fire

Protection Finding [Section 1R05.1.b.(2)]

Closed

50-400/02-08-01

VIO

Failure to Implement and Maintain NRC Approved FPP

SSD System Separation Requirements (Section 1R05.2)

50-400/02-11-01

URI

Failure to Protect Charging System MOV 1CS-165, VCT

Outlet to CSIPs, From Maloperation Due To a Fire

(Section 1R05.3)

DOCUMENT TRANSMITTED HEREWITH CONTAINS SENSITIVE UNCLASSIFIED INFORMATION

WHEN SEPARATED FROM ATTACHMENT 2, THIS DOCUMENT IS DECONTROLLED

ATTACHMENT 2 CONTAINS PROPRIETARY INFORMATION

2

Attachment 1

50-400/02-11-02

URI

Failure to Protect Charging System MOVs 1CS-169, 1CS-

214, 1CS-218, and 1CS-219 From Maloperation Due To a

Fire (Section 1R05.3)

50-400/02-11-03

URI

Failure to Protect Charging System MOVs 1CS-166, 1CS-

168, and 1CS-217 From Maloperation Due To a Fire

(Section 1R05.3)

50-400/02-11-04

URI

Failure to Protect Component Cooling MOVs 1CC-251 and

1CC-208, CC for RCP Seals, From Maloperation Due To a

Fire (Section 1R05.3)

50-400/02-11-05

URI

Reliance on Manual Actions in Place of Required Physical

Separation or Protection From a Fire (Section 1R05.3)

50-400/02-11-06

URI

Fire SSD Operator Actions With Excessive Challenges

(Section 1R05.3)

50-400/02-11-07

URI

Too Many Fire SSD Actions for Operators to Perform

(Section 1R05.3)

50-400/02-11-08

URI

Using the Boric Acid Tank Without Level Indication

(Section 1R05.3)

50-400/02-11-09

URI

Failure to Provide Required Emergency Lighting for SSD

Operator Actions (Section 1R05.3)

50-400/02-04-00

LER

Unanalyzed Condition Due to Inadequate Separation of

Associated Circuits (Section 4OA3)

DOCUMENT TRANSMITTED HEREWITH CONTAINS SENSITIVE UNCLASSIFIED INFORMATION

WHEN SEPARATED FROM ATTACHMENT 2, THIS DOCUMENT IS DECONTROLLED

ATTACHMENT 2 CONTAINS PROPRIETARY INFORMATION

3

PROPRIETARY INFORMATION

REMOVED

Attachment 2