ML032960191

From kanterella
Jump to navigation Jump to search
IR 05000400-03-004 on 09/27/03 for Shearon Harris Nuclear Power Plant
ML032960191
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 10/23/2003
From: Fredrickson P
Division of Nuclear Materials Safety II
To: Scarola J
Carolina Power & Light Co
References
IR-03-004
Download: ML032960191 (18)


See also: IR 05000400/2003004

Text

October 23, 2003

Carolina Power and Light Company

ATTN: Mr. James Scarola

Vice President - Harris Plant

Shearon Harris Nuclear Power Plant

P. O. Box 165, Mail Code: Zone 1

New Hill, North Carolina 27562-0165

SUBJECT:

SHEARON HARRIS NUCLEAR POWER PLANT - NRC INTEGRATED

INSPECTION REPORT 050000400/2003004

Dear Mr. Scarola:

On September 27, 2003, the US Nuclear Regulatory Commission (NRC) completed an

inspection at your Shearon Harris reactor facility. The enclosed integrated inspection report

documents the inspection findings, which were discussed on October 6, with you and other

members of your staff.

The inspection examined activities conducted under your license as they relate to safety and

compliance with the Commissions rules and regulations and with the conditions of your license.

The inspectors reviewed selected procedures and records, observed activities, and interviewed

personnel.

Based on the results of this inspection, no findings of significance were identified.

In accordance with 10 CFR 2.790 of the NRC's "Rules of Practice," a copy of this letter and its

enclosure will be available electronically for public inspection in the NRC Public Document

Room or from the Publicly Available Records (PARS) components of NRCs document system

(ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-

rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Paul E. Fredrickson, Chief

Reactor Projects Branch 4

Division of Reactor Projects

Docket No.:

50-400

License No.:

NPF-63

Enclosure:

NRC Inspection Report 050000400/2003004

w/Attachment: Supplemental Information

cc w/encl: (See page 2)

CP&L

2

cc w/encl:

James W. Holt, Manager

Performance Evaluation and

Regulatory Affairs CPB 9

Carolina Power & Light Company

Electronic Mail Distribution

Robert J. Duncan II

Director of Site Operations

Carolina Power & Light Company

Shearon Harris Nuclear Power Plant

Electronic Mail Distribution

Benjamin C. Waldrep

Plant General Manager--Harris Plant

Carolina Power & Light Company

Shearon Harris Nuclear Power Plant

Electronic Mail Distribution

Terry C. Morton, Manager

Support Services

Carolina Power & Light Company

Shearon Harris Nuclear Power Plant

Electronic Mail Distribution

John R. Caves, Supervisor

Licensing/Regulatory Programs

Carolina Power & Light Company

Shearon Harris Nuclear Power Plant

Electronic Mail Distribution

Steven R. Carr

Associate General Counsel - Legal

Department

Progress Energy Service Company, LLC

Electronic Mail Distribution

John H. ONeill, Jr.

Shaw, Pittman, Potts & Trowbridge

2300 N. Street, NW

Washington, DC 20037-1128

Beverly Hall, Acting Director

Division of Radiation Protection

N. C. Department of Environmental

Commerce & Natural Resources

Electronic Mail Distribution

Peggy Force

Assistant Attorney General

State of North Carolina

Electronic Mail Distribution

Public Service Commission

State of South Carolina

P. O. Box 11649

Columbia, SC 29211

Chairman of the North Carolina

Utilities Commission

c/o Sam Watson, Staff Attorney

Electronic Mail Distribution

Robert P. Gruber

Executive Director

Public Staff NCUC

4326 Mail Service Center

Raleigh, NC 27699-4326

Herb Council, Chair

Board of County Commissioners

of Wake County

P. O. Box 550

Raleigh, NC 27602

Tommy Emerson, Chair

Board of County Commissioners

of Chatham County

Electronic Mail Distribution

Distribution w/encl: (See page 3)

CP&L

3

Distribution w/encl:

C. Patel, NRR

L. Slack, RII EICS

RIDSNRRDIPMLIPB

PUBLIC

OFFICE

DRP/RII

DRP/RII

DRP/RII

SIGNATURE

RXM1

RCH2

GTM

NAME

RMusser:aws

RHagar

GMacdonald

DATE

10/22/2003

10/22/2003

10/22/2003

E-MAIL COPY?

YES

NO YES

NO YES

NO

PUBLIC DOCUMENT

YES

NO

OFFICIAL RECORD COPY DOCUMENT NAME: C:\\ORPCheckout\\FileNET\\ML032960191.wpd

Enclosure

U. S. NUCLEAR REGULATORY COMMISSION

REGION II

Docket No:

50-400

License No:

NPF-63

Report No:

050000400/2003004

Licensee:

Carolina Power and Light Company

Facility:

Shearon Harris Nuclear Power Plant, Unit 1

Location:

5413 Shearon Harris Road

New Hill, NC 27562

Dates:

June 29, 2003 - September 27, 2003

Inspectors:

R. Musser, Senior Resident Inspector

R. Hagar, Resident Inspector

G. MacDonald, Senior Project Engineer (Sections 1R05, 1R14,

1R15 & 4OA3)

Approved by:

P. Fredrickson, Chief

Reactor Projects Branch 4

Division of Reactor Projects

SUMMARY OF FINDINGS

IR 05000400/2003-004; 06/29/2003 - 09/27/2003; Shearon Harris Nuclear Power Plant, Unit 1;

Routine Integrated Report.

The report covered a three month period of inspection by resident inspectors and a senior

project engineer. The NRCs program for overseeing the safe operation of commercial nuclear

power reactors is described in NUREG-1649, Reactor Oversight Process, Revision 3, dated

July 2000.

A. Inspector-Identified and Self-Revealing Findings

None.

B. Licensee-Identified Violations

None.

REPORT DETAILS

Summary of Plant Status

The plant operated at or near rated power from the beginning of the inspection period until

August 17, when the reactor was manually tripped following the failure of the A condensate

pump motor. Following replacement of this motor, the plant was returned to power operation on

August 19. On August 27, the A condensate pump motor began to experience an electrical

faulted condition and a rapid downpower was initiated. The plant was stabilized at 45 percent

power and the A condensate pump was secured. The plant was operated at approximately 45

percent power until September 6, when the unit was returned to rated thermal power. The plant

was operated at or near rated power for the remainder of the inspection period.

1.

REACTOR SAFETY

Cornerstones: Initiating Events, Mitigating Systems, Barrier Integrity

1R01

Adverse Weather Protection

a.

Inspection Scope

When Hurricane Isabel was predicted for the site on September 18, the inspectors

reviewed actions taken by the licensee in accordance with Procedure AP-300, Adverse

Weather, prior to the onset of that weather, to ensure that the adverse weather

conditions would neither initiate a plant event nor prevent any system, structure, or

component from performing its design function.

b.

Findings

No findings of significance were identified.

1R04

Equipment Alignment

a.

Inspection Scope

Partial System Walkdowns:

The inspectors performed the following three partial system walkdowns, while the

indicated SSCs were out-of-service for maintenance and testing:

B motor-driven auxiliary feedwater train with the A motor-driven auxiliary feedwater

train out of service on July 23

A emergency diesel generator with the B emergency diesel generator out of service

on August 6

B residual heat removal system with the A residual heat removal system inoperable

on September 17

2

To evaluate the operability of the selected trains or systems under these conditions, the

inspectors reviewed valve and power alignments by comparing observed positions of

valves, switches, and electrical power breakers to the procedures and drawings listed in

the Attachment.

b.

Findings

No findings of significance were identified.

1R05

Fire Protection

a.

Inspection Scope

For the six areas identified below, the inspectors reviewed the licensees control of

transient combustible material and ignition sources, fire detection and suppression

capabilities, fire barriers, and any related compensatory measures, to verify that those

items were consistent with Final Safety Analysis Report (FSAR) Section 9.5.1, Fire

Protection System, and FSAR Appendix 9.5.A, Fire Hazards Analysis. The inspectors

walked down accessible portions of each area and reviewed results from related

surveillance tests, to verify that conditions in the area was consistent with the description

of the area in the FSAR. Documents reviewed are listed in the Attachment.

Reactor Auxiliary Building 236 foot elevation Auxiliary Feedwater (AFW) and

Component Cooling Water (CCW) pump area (1-A-3-PB)

Switchgear room A (1-A SWBRA)

Switchgear room B (1-A-SWGRB)

Main control room (12-A-CR)

Computer room, process instrument control cabinets, and control-rod-drive

circuit cabinets (12-A-CRC1)

Vital battery room B (1-A-BATB)

Also, to evaluate the readiness of the licensees personnel to prevent and fight fires, the

inspectors observed fire brigade performance during an unannounced fire drill in the C

CSIP room on August 29.

b.

Findings

No findings of significance were identified.

1R11

Licensed Operator Requalification

a.

Inspection Scope

On August 27, the inspectors observed licensed-operator performance during

requalification simulator training, to verify that operator performance was consistent with

expected operator performance, as described in Exercise Guide EOP-SIM-17.104. This

training tested the operators ability to deal with reactor coolant pump trouble, safety

injection failure, and a main steam line break.

3

The inspectors focused on clarity and formality of communication, use of procedures,

alarm response, control board manipulations, group dynamics and supervisory

oversight.

The inspectors observed the post-exercise critique to verify that the licensee had

identified deficiencies and discrepancies that occurred during the simulator training.

b.

Findings

No findings of significance were identified.

1R12

Maintenance Effectiveness

a.

Inspection Scope

The inspectors reviewed one degraded SSC/function condition to verify the licensees

handling of the condition in accordance with 10CFR50, Appendix B, Criterion XVI,

Corrective Action, and 10CFR50.65, Maintenance Rule. The specific condition involved

multiple failures of 1CP-6, an isolation damper in the containment purge system, as

reported in Action Request (AR) 88929.

The inspectors focused on the following attributes:

Appropriate work practices,

Identifying and addressing common cause failures,

Scoping in accordance with 10 CFR 50,65(b),

Characterizing reliability issues (performance),

Charging unavailability (performance),

Trending key parameters (condition monitoring),

10 CFR 50,65(a)(1) or (a)(2) classification and reclassification, and

Appropriateness of performance criteria for SSCs/functions classified (a)(2)

and/or appropriateness and adequacy of goals and corrective actions for

SSCs/functions classified (a)(1).

b.

Findings

No findings of significance were identified.

1R13

Maintenance Risk Assessments and Emergent Work Evaluation

a.

Inspection Scope

To verify that the licensee performed adequate risk assessments and implemented

appropriate risk management actions when required by 10CFR50.65(a)(4), the

inspectors reviewed the licensees risk assessments and the actions used to manage

risk for the plant configurations associated with the four activities listed below. For

emergent work, the inspectors also verified that any increase in risk was promptly

assessed, and that appropriate risk management actions were promptly implemented.

4

The work week of June 30, including the A emergency chilled water system

outage on July 2

The work week of July 28, including re-evaluation of plant risk for thunderstorm

warnings

The work week of September 8, including the RHR/CS pump room air handler

being out of service

The work week of September 15, including re-evaluation of plant risk for the

approach of Hurricane Isabel

b.

Findings

No findings of significance were identified.

1R14

Operator Performance During Non-Routine Evolutions and Events

a.

Inspection Scope

Following the manual reactor trip of August 17, 2003, the inspectors responded to the

site and observed plant instruments, reviewed plant logs and interviewed operators to

verify that the operators response was in accordance with post-trip procedures, plant

operating procedures and related training. Documents reviewed are listed in the

Attachment.

b.

Findings

No findings of significance were identified.

1R15

Operability Evaluations

a.

Inspection Scope

The inspectors reviewed three operability determinations addressed in response to the

ARs listed below. The inspectors assessed the accuracy of the evaluations, the use

and control of any necessary compensatory measures, and compliance with the

Technical Specifications (TS). The inspectors compared the justification made in the

determination to the requirements from the TS, the FSAR, and the associated design-

basis documents, to verify that operability was properly justified, and that the subject

component remained available, such that no unrecognized increase in risk occurred.

Documents reviewed are listed in the Attachment.

AR 96373, HNP Action Plan for containment sump level transmitter LT-7161A

AR 103527103527 Relay Failure on the 1B emergency safeguards sequencer

AR 95977, Through wall leak on service water line near valve 1SW-118

b.

Findings

No findings of significance were identified.

5

1R19

Post Maintenance Testing

a.

Inspection Scope

For the five post-maintenance tests listed below, the inspectors witnessed the test

and/or reviewed the test data, to verify that test results adequately demonstrated

restoration of the affected safety functions described in the FSAR and TS.

OP-155, Diesel Generator Emergency Power System, following repair of a fuel

line leak on July 1

ORT-1512, Essential Chilled Water Turbopak Units Quarterly Inspection/Checks

Modes 1-6, following routine maintenance on the train A essential chilled water

chiller on July 16

OST-1008, 1A-SA RHR Pump Operability Quarterly Interval Modes 1-2-3,

following maintenance on 1-RH-31, A RHR Pump Mini Flow Valve

OST-1073, 1B-SB Emergency Diesel Generator Operability Test Monthly Interval

Modes 1-2-3-4-5-6, following routine maintenance on the train B emergency

diesel generator on August 6

OPT-1014, Turbine Valve Test Quarterly Interval Modes 1-5, following a

firmware modification to the digital electro-hydraulic system

b.

Findings

No findings of significance were identified.

1R22

Surveillance Testing

a.

Inspection Scope

For the four surveillance tests identified below, the inspectors witnessed testing and/or

reviewed test data to verify that the systems, structures, and components involved in

these tests satisfied the requirements described in the TS and the FSAR, and that the

tests demonstrated that the SSCs were capable of performing their intended safety

functions.

MST-I0207, Refueling Water Storage Tank Level (L-0993) Operational Test

OST-1211*, Auxiliary Feedwater Pump 1A-SA Operability Test Quarterly Interval

Modes 1-4

MST-I0151, Steam Generator C Narrow Range Level Loop (L-0496) Operational

Test

OST-1122, Train A 6.9 kV Emergency Bus Undervoltage Trip Actuating Device

Operational Test and Contact Check Modes 1-6

  • This procedure included inservice testing requirements.

b.

Findings

No findings of significance were identified.

6

1EP6

Drill Evaluation

a.

Inspection Scope

The inspectors observed an operator training evolution conducted on August 27, to

verify licensee self-assessment of classification, notification, and protective action

recommendation development in accordance with NEI 99-02, Regulatory Assessment

Indicator Guideline, Rev. 2.

b.

Findings

No findings of significance were identified.

4.

OTHER ACTIVITIES

August 17 Reactor Trip

a.

Inspection Scope

Following a manual reactor trip that occurred on August 17, 2003 from 100 percent

power, due to a loss of the A condensate pump; the inspectors reviewed the licensees

actions, observed plant parameters for mitigating systems and fission product barriers,

and assessed licensee event classification and reporting. The inspectors later reviewed

the post-trip/safeguards actuation report to verify that plant response was as expected

and to verify that plant equipment abnormalities were identified and corrected prior to

plant startup. Refer to Section 1R14 for additional information. ocuments reviewed are

listed in the Attachment.

b.

Findings

No findings of significance were identified.

4OA6 Meetings, Including Exit

On October 6, 2003, the resident inspectors presented the inspection results to

Mr. James Scarola and other members of his staff. The inspectors confirmed that

proprietary information was not provided or examined during the inspection.

Attachment

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee personnel

D. Braund, Security Superintendent

J. Briggs, Superintendent, Environmental and Chemical

J. Caves, Licensing Supervisor

F. Diya, Superintendent, System Engineering (Acting Engineering Support Services

Mgr.)

R. Duncan, Director Site Operations

W. Gurganious, Nuclear Assessment Manager

E. McCartney, Training Manager

G. Miller, Maintenance Manager

T. Morton, Manager Support Services

T. Natale, Outage and Scheduling Manager

G. Olive, Lead Nuclear Security Specialist

T. Pilo, Emergency Preparedness Supervisor

J. Scarola, Harris Plant Vice President

G. Simmons, Superintendent, Radiation Control

B. Waldrep, Harris Plant General Manager

M. Wallace, Senior Specialist, Licensing

E. Wills, Operations Manager

NRC personnel

P. Fredrickson, Chief, Reactor Projects Branch 4

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

None

LIST OF DOCUMENTS REVIEWED

1R04

Equipment Alignment

Partial System Walkdown

Emergency diesel generator system

Procedure OP-155, Diesel Generator Emergency Power System

Drawing 2165-S-563, Simplified Flow Diagram Diesel Fuel Oil System, Unit 1

Drawing 2165-S-633S01, Simplified Flow Diagram Emergency Diesel Generator

Lube Oil and Air Intake & Exhaust System - Unit 1.

Drawing 2165-S-0633S02, Simplified Flow Diagram Emergency Diesel Generator

1A-SA & 1B-SB Jacket Water System Unit 1

2

Drawing 2165-S-0633S03, Simplified Flow Diagram Emergency Diesel Generator

1A-SA & 1B-SB Fuel Oil and Drainage Systems Unit 1

Drawing 2165-S-0633S04, Simplified Flow Diagram Emergency Diesel Generator

1A-SA & 1B-SB Starting Air System Unit 1

Auxiliary Feedwater System

Procedure OP-137, Auxiliary Feedwater System

Drawing 2165-S-0544, Simplified Flow Diagram Feedwater System Unit 1"

Residual Heat Removal System

Procedure OP-111, RHR System

Drawing 2165-S-LATER, Simplified Flow Diagram Residual Heat Removal System

Unit 1"

1R05

Fire Protection

Results from recent completions of the following procedures:

FPT-1301, Hose Rack Inspection Auxiliary Building - Quarterly Interval Modes All

FPT-3204, Fire Detector Functional Test Local Fire Detector Panel 4 -12 Month

Interval

FPT-3151, Fire Protection Periodic Test Fire Extinguisher Inspection Auxiliary

Building - Monthly Interval

FPT-3426, Fire Damper Inspection 18 Month Interval RAB 236 Elevation

Other Documents

Fire Preplan FPP-012-02-RAB A09-4

Fire Preplan FPP-012-02-RAB A34-6

Fire Preplan FPP-012-02-RAB A35-6

Fire Preplan FPP-012-02-RAB A38-6

Fire Preplan FPP-012-02-RAB A51-7

Fire Preplan FPP-012-02-RAB A52-7

Fire Preplan FPP-012-02-RAB A53-7

Fire Preplan FPP-012-02-RAB A55-7

1R13

Maintenance Risk Assessments and Emergent Work Evaluation

Procedures

Operations Work Procedure (OWP), OWP-HVAC, Emergency Ventilation

Other Documents

Calculation 9-TMC-1

Calculation HNP-F/PSA-0058

3

1R14

Personnel Performance During Nonroutine Plant Evolutions and Events and Section

4OA3: Event Follow-up

Procedures

Emergency Operating Procedure (EOP), EOP-PATH-1, Path -1

Abnormal Operating Procedure (AOP), AOP-10, Feedwater Malfunctions

EOP-EPP-004, Reactor Trip Response

Other Documents

OMM-4 Post-trip/Safeguards Review Package for August 17, 2003 Manual Reactor Trip

1R15

Operability Evaluations

Procedures

Operations Surveillance Test (OST), OST-1021, Daily Surveillance Requirements,

Daily Surveillance Log of containment sump level transmitter LIT-01CT-7161ASA

Maintenance Surveillance Test (MST), MST-I0198, Containment Reactor Cavity

Sump NR Level Loop (LM-7161A) Calibration

Operating Procedure (OP), OP-163, Plant Computer

Other Documents

FSAR Section 5.2.5.3.1

AR 96373, HNP Action Plan for LT7161A

DBD-141, Plumbing and Drainage System

Data Results of containment sump level transmitter compensatory actions July 3

through September 20, 2003