Letter Sequence Withdrawal |
|---|
|
|
MONTHYEARML0222003822002-07-31031 July 2002 (Bfn), Units 1, 2, & 3, License Amendment Request, Alternative Source Term Project stage: Request ML0234501432002-12-0909 December 2002 Response to Request for Additional Information (RAI) Related to Technical Specifications (TS) Change TS-405 - Alternative Source Term (AST) Project stage: Response to RAI ML0235203282002-12-0909 December 2002 Response to Request for Additional Information Relating to TS Change No TS-405 - Alternative Source Term Project stage: Response to RAI ML0304403852003-02-12012 February 2003 Units 1, 2 and 3 - Technical Specifications (TS) Change 405 Supplement 1 - Decay Time Project stage: Supplement ML0305501122003-02-12012 February 2003 Technical Specifications (TS) Change 405 Supplement 1 - Decay Time Project stage: Supplement ML0305900912003-02-27027 February 2003 Evaluation of Human Factors Engineering Information Provided by Browns Ferry Nuclear Plant (BFN) - Units 1, 2, & 3 - License Amendment - Alternative Source Term Project stage: Other ML0309204632003-03-26026 March 2003 Response to Request for Additional Information Relating to Technical Specifications (TS) Change TS-405 - Alternative Source Term (AST) Project stage: Response to RAI ML0308507912003-03-26026 March 2003 Response to Request for Additional Information Relating to Technical Specifications (TS) Change No. TS-405 - Alternative Source Term (AST) Project stage: Response to RAI ML0312701552003-05-0707 May 2003 Summary of the drop-in Meeting of 04/23/2003 Regarding the Alternative Source Term with Tim Abney Project stage: Meeting ML0314808412003-05-28028 May 2003 Notice of Meeting with Tennessee Valley Authority (TVA) Regarding Browns Ferry Alternative Source Term Project stage: Request ML0315001742003-05-30030 May 2003 Corrected Meeting Notice, the Correct Date of the Meeting Is Tuesday, June 10, 2003 Not Wednesday, June 11, 2003 for Meeting with Tennessee Valley Authority Regarding Alternative Source Term Project stage: Request ML0316202352003-06-10010 June 2003 Meeting Handouts from 06/10/2003 Meeting with Tennessee Valley Authority Re Alternative Source Term for Browns Ferry Plant Including TVAs Proposed Exemption from GDC 41 for the Standby Liquid Control System Project stage: Meeting ML0318204392003-07-0101 July 2003 Meeting Summary Regarding the Alternative Source Team (AST) for Browns Ferry Plant, Units 1, 2, and 3 Project stage: Meeting ML0318207102003-07-0101 July 2003 Meeting Handouts by Tennessee Valley Authority Browns Ferry Nuclear Plant Exemption Request for the Alternative Source Team Methodlogy - Attachment 2 Project stage: Meeting ML0318207542003-07-0101 July 2003 Meeting Handouts by Tennessee Valley Authority Browns Ferry Nuclear Plant Exemption Request for the Alternative Source Term Methodology - Attachment 3 - Drawing 64908 Piston Check Valve Project stage: Meeting ML0323005192003-07-17017 July 2003 Withdrawal of a Portion of Technical Specification Change (TS-405) - Alternative Source Term (AST) Project stage: Withdrawal ML0321103632003-07-17017 July 2003 Withdrawal of a Portion of Technical Specifications Change (TS-405) - Alternative Source Term (AST) Project stage: Withdrawal ML0411400292004-04-16016 April 2004 Request for Additional Information Regarding the Alternative Source Term Implementation Project stage: RAI ML0412300152004-04-16016 April 2004 Brown Ferry, Units 1 2 & 3, RAI Alternate Source Term Implementation Project stage: RAI L-88-004, Completion of NRC Bulletin 88-04, Potential Safety-Related Pump Loss2004-05-0707 May 2004 Completion of NRC Bulletin 88-04, Potential Safety-Related Pump Loss Project stage: Request ML0413902862004-05-17017 May 2004 Response to Request for Additional Information (RAI) and Unit 1 Analyses Results Related to Technical Specifications (TS) Change No. TS-405 - Alternative Source Term (AST) Project stage: Response to RAI ML0417400192004-06-21021 June 2004 6/21/04, Browns Ferry, Units 1, 2 & 3, RAI, Alternative Source Term Implementation Project stage: RAI ML0420803362004-07-0202 July 2004 Response to Request for Additional Information Related to Technical Specifications Change No. TS-405 Alternative Source Term Project stage: Response to RAI ML0423301302004-08-19019 August 2004 RAI, Alternative Source Term Main Steam Line Indications Project stage: RAI ML0424500562004-08-24024 August 2004 Supplemental Information Associated with Response to Request for Additional Information Related to Technical Specifications Change No. TS-405 - Alternative Source Term Project stage: Supplement ML0425802422004-09-14014 September 2004 RAI, Regarding Alternative Source Term Project stage: RAI ML0427303422004-09-17017 September 2004 Response to Request for Additional Information (RAI) Related to Technical Specifications (TS) Change No. TS-405 - Alternative Source Term (AST) Project stage: Response to RAI ML0427105642004-09-24024 September 2004 Response to NRC Request for Additional Information (RAI) Related to Technical Specification (TS) Change No. TS-405-Alternate Source Term (AST) Project stage: Response to RAI ML0427303492004-09-27027 September 2004 Technical Spec.Pages Re Implementation of Alternative Source Term Project stage: Other ML0427303522004-09-27027 September 2004 Technical Spec. Pages, Re. Implementation of Alternative Source Term Project stage: Other ML0427303642004-09-27027 September 2004 Technical Spec.Pages Re Implementation of Alternative Source Term Project stage: Other ML0427300282004-09-27027 September 2004 9/27/04, Browns Ferry Nuclear Plant - Issuance of Amendments Full-Scope Implementation of Alternative Source Term (TAC Nos. MB5733, MB5734, MB5735, MC0156, MC0157 and MC0158) (TS-405) Project stage: Approval ML0432204832004-11-0808 November 2004 Technical Specifications, Correction to Amendment Nos. 251, 290 & 249 (Enclosure 1) Project stage: Other ML0432204862004-11-0808 November 2004 Technical Specifications, Correction to Amendment Nos. 251, 290 & 249 (Enclosure 2) Project stage: Other ML0431003452004-11-0808 November 2004 Ltr, Correction to Amendment Concerning Alternative Source Term Project stage: Other 2004-11-08
[Table View] |
Text
TVA-BFN-TS-405 10 CFR 50.90 July 17, 2003 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Mail Stop OWFN, P1-35 Washington, D.C. 20555-0001 Gentlemen:
In the Matter of
)
Docket Nos. 50-259 Tennessee Valley Authority
)
50-260 50-296 WITHDRAWAL OF A PORTION OF TECHNICAL SPECIFICATIONS CHANGE (TS-405) - ALTERNATIVE SOURCE TERM (AST) (TAC NOS. MB5733, MB5734, MB5735)
This letter withdraws a portion of proposed Technical Specifications (TS) change 405.
By letter dated July 31, 2002, (Reference 1) TVA submitted a license amendment that supports a full scope application of an Alternative Source Term (AST) following Regulatory Guide 1.183, Alternative Source Terms for Evaluating Design basis Accidents at Nuclear Power Reactors." The AST analysis does not
U.S. Nuclear Regulatory Commission Page 2 July 17, 2003 take credit for the absorption of elemental iodine by the Standby Gas Treatment system and Control Room Emergency Ventilation system charcoal filters. Consequently, as part of the TS change, TVA proposed deletion of TS 5.5.7, Ventilation Filter Testing Program, Sections b and c, and revision of Section d.
To facilitate the NRC review of TS-405, TVA hereby requests that the NRC disregard the discussion describing the changes to TS 5.5.7 on page 2 of the cover letter, and pages E1-3 and E1-14 of Enclosure 1. Accordingly, TVA withdraws the changes proposed to BFN TS pages 5.0-15 and 5.0-16, Unit 1 Amendment 253, Unit 2 Amendment 255, and Unit 3 Amendment 251. The AST analysis will continue to take no credit for the removal of iodine by the charcoal filters. TVA reviewed the No Significant Hazards Consideration Determination and the Environmental Impact Consideration in TS-405 (Reference 1) and determined they remain valid.
Pursuant to 28 U. S. C. § 1746 (1994), I declare under penalty of perjury that the foregoing is true and correct. Executed on this 17 th day of July 2003.
If you have any questions about this request, please telephone me at (256) 729-2636.
Sincerely, Original signed by:
T. E. Abney Manager of Licensing and Industry Affairs cc: See page 3
U.S. Nuclear Regulatory Commission Page 3 July 17, 2003 References 1 TVA letter to NRC, dated July 31, 2002, "Browns Ferry Nuclear Plant (BFN) - Units 1, 2, and 3 - License Amendment - Alternative Source Term."
2 NRC letter from Kahtan N. Jabbour, Senior Project Manager, Section 2, to Allen G.
Howe, Chief, Section 2, dated May 7, 2003, "Summary of The April 23, 2003, Drop-In Meeting With Tim Abney Regarding the Alternative Source Term For Browns Ferry Nuclear Plant, Units 1, 2, and 3."
cc : State Health Officer Alabama Dept. of Public Health RSA Tower - Administration Suite 1552 P.O. Box 303017 Montgomery, AL 36130-3017
U.S. Nuclear Regulatory Commission Page 4 July 17, 2003 DTL:SWA:BAB Enclosure cc: (Enclosure):
A. S. Bhatnagar, PAB 1E-BFN M. J. Burzynski, BR 4X-C J. E. Maddox, LP 6A-C R. G. Jones, NAB 1A-BFN D. C. Olcsvary, LP 6A-C C. M. Root, PAB 1G-BFN J. R. Rupert, NAB 1A-BFN K. W. Singer, LP 6A-C M. D. Skaggs, POB 2C-BFN E. J. Vigluicci, ET 11A-K R. E. Wiggall, SAB 1A-BFN NSRB Support, LP 5M-C EDMS-K s:lic/submit/sub/TechSpec/TS 405 withdraw TS Final