ML043220486
Letter Sequence Other | |
---|---|
Initiation Questions Answers | |
MONTHYEARML0234501432002-12-0909 December 2002
[Table View]Response to Request for Additional Information (RAI) Related to Technical Specifications (TS) Change TS-405 - Alternative Source Term (AST) Project stage: Response to RAI ML0235203282002-12-0909 December 2002 Response to Request for Additional Information Relating to TS Change No TS-405 - Alternative Source Term Project stage: Response to RAI ML0304403852003-02-12012 February 2003 Units 1, 2 and 3 - Technical Specifications (TS) Change 405 Supplement 1 - Decay Time Project stage: Supplement ML0305501122003-02-12012 February 2003 Technical Specifications (TS) Change 405 Supplement 1 - Decay Time Project stage: Supplement ML0305900912003-02-27027 February 2003 Evaluation of Human Factors Engineering Information Provided by Browns Ferry Nuclear Plant (BFN) - Units 1, 2, & 3 - License Amendment - Alternative Source Term Project stage: Other ML0308507912003-03-26026 March 2003 Response to Request for Additional Information Relating to Technical Specifications (TS) Change No. TS-405 - Alternative Source Term (AST) Project stage: Response to RAI ML0309204632003-03-26026 March 2003 Response to Request for Additional Information Relating to Technical Specifications (TS) Change TS-405 - Alternative Source Term (AST) Project stage: Response to RAI ML0312701552003-05-0707 May 2003 Summary of the drop-in Meeting of 04/23/2003 Regarding the Alternative Source Term with Tim Abney Project stage: Meeting ML0314808412003-05-28028 May 2003 Notice of Meeting with Tennessee Valley Authority (TVA) Regarding Browns Ferry Alternative Source Term Project stage: Request ML0315001742003-05-30030 May 2003 Corrected Meeting Notice, the Correct Date of the Meeting Is Tuesday, June 10, 2003 Not Wednesday, June 11, 2003 for Meeting with Tennessee Valley Authority Regarding Alternative Source Term Project stage: Request ML0316202352003-06-10010 June 2003 Meeting Handouts from 06/10/2003 Meeting with Tennessee Valley Authority Re Alternative Source Term for Browns Ferry Plant Including Tva'S Proposed Exemption from GDC 41 for the Standby Liquid Control System Project stage: Meeting ML0318204392003-07-0101 July 2003 Meeting Summary Regarding the Alternative Source Team (AST) for Browns Ferry Plant, Units 1, 2, and 3 Project stage: Meeting ML0318207102003-07-0101 July 2003 Meeting Handouts by Tennessee Valley Authority Browns Ferry Nuclear Plant Exemption Request for the Alternative Source Team Methodlogy - Attachment 2 Project stage: Meeting ML0318207542003-07-0101 July 2003 Meeting Handouts by Tennessee Valley Authority Browns Ferry Nuclear Plant Exemption Request for the Alternative Source Term Methodology - Attachment 3 - Drawing 64908 Piston Check Valve. Project stage: Meeting ML0321103632003-07-17017 July 2003 Withdrawal of a Portion of Technical Specifications Change (TS-405) - Alternative Source Term (AST) Project stage: Withdrawal ML0323005192003-07-17017 July 2003 Withdrawal of a Portion of Technical Specification Change (TS-405) - Alternative Source Term (AST) Project stage: Withdrawal ML0411400292004-04-16016 April 2004 Request for Additional Information Regarding the Alternative Source Term Implementation Project stage: RAI ML0412300152004-04-16016 April 2004 Brown Ferry, Units 1 2 & 3, RAI Alternate Source Term Implementation Project stage: RAI ML0413902862004-05-17017 May 2004 Response to Request for Additional Information (RAI) and Unit 1 Analyses Results Related to Technical Specifications (TS) Change No. TS-405 - Alternative Source Term (AST) Project stage: Response to RAI ML0417400192004-06-21021 June 2004 6/21/04, Browns Ferry, Units 1, 2 & 3, RAI, Alternative Source Term Implementation Project stage: RAI ML0420803362004-07-0202 July 2004 Response to Request for Additional Information Related to Technical Specifications Change No. TS-405 Alternative Source Term Project stage: Response to RAI ML0423301302004-08-19019 August 2004 RAI, Alternative Source Term Main Steam Line Indications Project stage: RAI ML0424500562004-08-24024 August 2004 Supplemental Information Associated with Response to Request for Additional Information Related to Technical Specifications Change No. TS-405 - Alternative Source Term Project stage: Supplement ML0425802422004-09-14014 September 2004 RAI, Regarding Alternative Source Term Project stage: RAI ML0427303422004-09-17017 September 2004 Response to Request for Additional Information (RAI) Related to Technical Specifications (TS) Change No. TS-405 - Alternative Source Term (AST) Project stage: Response to RAI ML0427105642004-09-24024 September 2004 Response to NRC Request for Additional Information (RAI) Related to Technical Specification (TS) Change No. TS-405-Alternate Source Term (AST) Project stage: Response to RAI ML0427300282004-09-27027 September 2004 9/27/04, Browns Ferry Nuclear Plant - Issuance of Amendments Full-Scope Implementation of Alternative Source Term (TAC Nos. MB5733, MB5734, MB5735, MC0156, MC0157 and MC0158) (TS-405) Project stage: Approval ML0427303492004-09-27027 September 2004 Technical Spec.Pages Re Implementation of Alternative Source Term Project stage: Other ML0427303522004-09-27027 September 2004 Technical Spec. Pages, Re. Implementation of Alternative Source Term Project stage: Other ML0427303642004-09-27027 September 2004 Technical Spec.Pages Re Implementation of Alternative Source Term Project stage: Other ML0432204832004-11-0808 November 2004 Technical Specifications, Correction to Amendment Nos. 251, 290 & 249 (Enclosure 1) Project stage: Other ML0432204862004-11-0808 November 2004 Technical Specifications, Correction to Amendment Nos. 251, 290 & 249 (Enclosure 2) Project stage: Other ML0431003452004-11-0808 November 2004 Ltr, Correction to Amendment Concerning Alternative Source Term Project stage: Acceptance Review 2004-11-08 |
ML043220486 | |
Person / Time | |
---|---|
Site: | Browns Ferry ![]() |
Issue date: | 11/08/2004 |
From: | NRC/NRR/DLPM/LPD2 |
To: | |
Brown Eva, NRR/DLPM, 415-2315 | |
Shared Package | |
ML043200588 | List: |
References | |
TAC MB5733, TAC MB5734, TAC MB5735 | |
Download: ML043220486 (1) | |
Similar Documents at Browns Ferry | |
---|---|
Category:Technical Specifications
MONTHYEARML22348A0052023-01-25025 January 2023
[Table view]Issuance of Amendment Nos. 326, 349, and 309; 363 and 35; 159 and 67 Regarding Adoption of TSTF-554, Revise Reactor Coolant Leakage Requirements ML22349A6472023-01-20020 January 2023 Issuance of Amendment Nos. 325, 348, and 308; 362 and 356; and 158 and 66 Regarding Adoption of TSTF-529, Rev. 4, Clarify Use and Application Rules ML22348A0662023-01-13013 January 2023 Issuance of Amendment Nos. 325, 348, & 308 Regarding Application of Advanced Framatome Methodologies, & Adoption of TSTF Traveler TSTF-564-A, Rev. 2, in Support of Atrium 11 Fuel Use (EPID L-2021-LLA-0132) - Nonproprietary CNL-22-039, Application to Revise Technical Specifications to Adopt TSTF-554-A, Revision 1, Revise Reactor Coolant Leakage Requirements (BFN TS-537) (SQN-21-05) (WBN-TS-21-04)2022-07-13013 July 2022 Application to Revise Technical Specifications to Adopt TSTF-554-A, Revision 1, Revise Reactor Coolant Leakage Requirements (BFN TS-537) (SQN-21-05) (WBN-TS-21-04) ML21285A0682021-10-28028 October 2021 Issuance of Amendment Nos. 319, 342, and 302 Regarding the Adoption of Technical Specification Task Force Traveler TSTF-582, Revision 2 ML21214A1392021-08-30030 August 2021 Issuance of Amendment Nos. 318, 341, and 301 Regarding Changes to Technical Specification 3.8.6, Battery Cell Parameters ML21075A0762021-04-30030 April 2021 Issuance of Amendment Nos. 316, 339, and 299 Regarding the Incorporation of the Tornado Missile Risk Evaluator Into the Licensing Basis ML21041A4892021-04-0808 April 2021 Issuance of Amendment Nos. 315, 338, and 298 Regarding the Adoption of Technical Specifications Task Force Traveler, TSTF-425, Revision 3 ML20282A3452020-11-19019 November 2020 Issuance of Amendment Nos. 313, 336, 296, 350, 344, 138, and 44 Revise Emergency Plan On-Shift Emergency Medical Technician & Onsite Ambulance Requirements ML20190A1052020-08-11011 August 2020 Correction to Amendment No. 319 Regarding Revisions to Technical Specification 3.3.6.1, Primary Containment Isolation Instrumentation ML20085G8962020-06-26026 June 2020 Issuance of Amendment Nos. 312, 335, and 295 Regarding Request to Revise Emergency Plan Staff Augmentation Times CNL-20-003, Application for Technical Specifications Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program (BFN-TS-516)2020-03-27027 March 2020 Application for Technical Specifications Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program (BFN-TS-516) ML18277A1102019-08-27027 August 2019 Units, 1 & 2 Issuance of Amendment Nos. 309, 332, 292, 345, 339, 128, and 31 Regarding Unbalanced Voltage Protection ML18283A8972018-10-10010 October 2018 Enclosure 1: Proposed Changes to Browns Ferry Nuclear Plant Unit 1 Technical Specifications, Attachments 1, 2, & 3 ML18251A0032018-09-27027 September 2018 Issuance of Amendment Nos. 305, 328, and 288 to Revise Technical Specification 5.5.12, Primary Containment Leakage Rate Testing Program (CAC Nos. MG0113, MG0114, and MG0115; EPID L-2017-LLA-0292) ML17215A2432017-10-0202 October 2017 Browns Ferry Nuclear Plant, Units 1, 2, and 3; Watts Bar Nuclear Plant, Units 1 and 2 - Issuance of Amendments to Change Technical Specifications to Adopt Technical Specifications Task Force Traveler-522 (CAC No. MF9562-MF9566) CNL-17-015, Transmittal of Response to Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 36, Transmission System Update -Safety Aspects2017-01-20020 January 2017 Transmittal of Response to Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 36, Transmission System Update -Safety Aspects NL-17-015, Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Transmittal of Response to Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 36, Transmission System Update -Saf2017-01-20020 January 2017 Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Transmittal of Response to Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 36, Transmission System Update -Safe ML16330A1582017-01-17017 January 2017 Issuance of Amendments Regarding Revisions to Technical Specification 4.3.1.2, Fuel Storage Criticality ML16028A4142016-04-26026 April 2016 Issuance of Amendment to Revise Technical Specifications Related to Cycle 18 Safety Limit Minimum Critical Power Ratio ML15317A4782016-02-0909 February 2016 Issuance of Amendment to Revise Technical Specifications Related to Cycle 18 Safety Limit Minimum Critical Power Ratio ML15344A3212016-01-0707 January 2016 Issuance of Amendment Regarding Modification of Technical Specification 3.4.9, RCS Pressure and Temperature (P/T) Limits ML15321A4722015-12-23023 December 2015 Issuance of Amendments Regarding Revision to Table 3.3.6.1-1, Primary Containment Isolation Instrumentation ML15287A2132015-12-16016 December 2015 Issuance of Amendments Regarding Technical Specification Changes to Reactor Core Safety Limits ML15324A2472015-12-14014 December 2015 Issuance of Amendment to Adopt TSTF-501, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Valves to Licensee Control ML15287A3712015-12-0404 December 2015 Issuance of Amendments for the Adoption of Technical Specifications Task Force Standard Technical Specifications Change Traveler TSTF-535 (CNL-15-029) ML15212A7962015-10-28028 October 2015 Issuance of Amendments to Transition to Fire Protection Program NFPA-805 ML15251A5402015-09-29029 September 2015 Issuance of Amendment Regarding Control Rod Scram Time Testing Frequency Per TSTF-460, Revision 0 CNL-15-056, Application to Modify Technical Specification 2.1.1.2, Reactor Core Minimum Critical Power Ratio Safety Limits (TS-506)2015-09-25025 September 2015 Application to Modify Technical Specification 2.1.1.2, Reactor Core Minimum Critical Power Ratio Safety Limits (TS-506) CNL-15-073, Application to Modify the Technical Specifications by Adding New Specification TS 3.3.8.3, Emergency Core Cooling System Preferred Pump Logic, Common Accident Signal (CAS) Logic, and Unit Priority Re-Trip Logic, And.2015-09-16016 September 2015 Application to Modify the Technical Specifications by Adding New Specification TS 3.3.8.3, Emergency Core Cooling System Preferred Pump Logic, Common Accident Signal (CAS) Logic, and Unit Priority Re-Trip Logic, And. ML15065A0492015-06-0202 June 2015 Issuance of Amendment Revising Pressure and Temperature Limit Curves CNL-15-070, Withdrawal of Proposed Technical Specification Change to Revise the Leakage Rate Through MSIVs - TS-4852015-05-29029 May 2015 Withdrawal of Proposed Technical Specification Change to Revise the Leakage Rate Through MSIVs - TS-485 CNL-15-019, License Amendment Request for the Adoption of Technical Specifications Task Force (TSTF) Traveler TSTF-460-A, Revision 0, Control Rod Scram Time Testing Frequency (TS-501)2015-03-0909 March 2015 License Amendment Request for the Adoption of Technical Specifications Task Force (TSTF) Traveler TSTF-460-A, Revision 0, Control Rod Scram Time Testing Frequency (TS-501) CNL-15-029, License Amendment Request for the Adoption of Technical Specifications Task Force (TSTF) Traveler TSTF-535, Revision 0, Revise Shutdown Margin Definition to Address Advanced Fuel Designs (TS-502)2015-03-0909 March 2015 License Amendment Request for the Adoption of Technical Specifications Task Force (TSTF) Traveler TSTF-535, Revision 0, Revise Shutdown Margin Definition to Address Advanced Fuel Designs (TS-502) CNL-15-033, License Amendment Request Under Exigent Circumstances for the Change to Add a Reference to the ATRIUM-10 Xm NRC Safety Evaluation Approval in Technical Specification 5.6.5.b in Support of ATRIUM-10 Xm Fuel Use2015-02-12012 February 2015 License Amendment Request Under Exigent Circumstances for the Change to Add a Reference to the ATRIUM-10 Xm NRC Safety Evaluation Approval in Technical Specification 5.6.5.b in Support of ATRIUM-10 Xm Fuel Use CNL-14-156, Technical Specifications (TS) Changes TS-431 and TS-418 - Extended Power Uprate (EPU) - Withdrawal of Requests and Update to EPU Plans and Schedules2014-09-18018 September 2014 Technical Specifications (TS) Changes TS-431 and TS-418 - Extended Power Uprate (EPU) - Withdrawal of Requests and Update to EPU Plans and Schedules NL-14-081, Browns Ferry, Units, 1, 2 & 3, Revised Pages to Technical Specification Change TS-478-Addition of Analytical Methodologies to Technical Specification 5.6.5 and Revision of Tech Spec 2.1.1.2 in Support of ATRIUM-10 Xm Fuel Use at Browns Fer2014-05-16016 May 2014 Browns Ferry, Units, 1, 2 & 3, Revised Pages to Technical Specification Change TS-478-Addition of Analytical Methodologies to Technical Specification 5.6.5 and Revision of Tech Spec 2.1.1.2 in Support of ATRIUM-10 Xm Fuel Use at Browns Ferr CNL-14-081, Units, 1, 2 & 3, Revised Pages to Technical Specification Change TS-478-Addition of Analytical Methodologies to Technical Specification 5.6.5 and Revision of Tech Spec 2.1.1.2 in Support of ATRIUM-10 Xm Fuel Use at Browns Ferry2014-05-16016 May 2014 Units, 1, 2 & 3, Revised Pages to Technical Specification Change TS-478-Addition of Analytical Methodologies to Technical Specification 5.6.5 and Revision of Tech Spec 2.1.1.2 in Support of ATRIUM-10 Xm Fuel Use at Browns Ferry NL-13-148, Browns Ferry, Unit 1, Application to Modify Technical Specification 3.4.9, RCS Pressure and Temperature Limits (BFN TS 484)2013-12-18018 December 2013 Browns Ferry, Unit 1, Application to Modify Technical Specification 3.4.9, RCS Pressure and Temperature Limits (BFN TS 484) CNL-13-148, Application to Modify Technical Specification 3.4.9, RCS Pressure and Temperature Limits (BFN TS 484)2013-12-18018 December 2013 Application to Modify Technical Specification 3.4.9, RCS Pressure and Temperature Limits (BFN TS 484) CNL-13-126, Proposed Technical Specification Change to Revise the Leakage Rate Through MSIVs-TS-4852013-11-22022 November 2013 Proposed Technical Specification Change to Revise the Leakage Rate Through MSIVs-TS-485 ML13199A2212013-08-30030 August 2013 Issuance of Amendments Re. Deletion of References to Section XI of the ASME Code and Incorporate References to the ASME OM Code and Allow Application of 25% Extension of Surveillance Intervals ML13092A3932013-03-27027 March 2013 License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants (2001 Edition) (Technical Specification Change TS-480) ML13070A3072013-02-28028 February 2013 Technical Specification Change TS-478 - Addition of Analytical Methodologies to Technical Specification 5.6.5 for Browns Ferry 1, 2, & 3, & Revision of Technical Specification 2.1.1.2 for Browns Ferry Unit 2, in Support of ATRIUM-10 Xm Fuel ML11189A2172012-07-30030 July 2012 Issuance of Amendments Regarding Request to Add Technical Specification 3.7.3, Control Room Emergency Ventilation System, Action to Address Two Crev Subsystems Inoperable ML12114A0042012-04-18018 April 2012 Supplement to License Amendment Request to Transition to Areva Fuel ML1011601532010-04-16016 April 2010 Supplemental Information for Technical Specification Change TS-473 - Areva Fuel Transition Amendment Request ML0923700452009-11-19019 November 2009 Issuance of Amendments Regarding Technical Specification Improvement to Adopt Technical Specification Task Force (TSTF) TSTF-476, Revision 1 ML0931001212009-10-31031 October 2009 Attachment 19, Browns Ferry Unit 1 -Technical Specification Change 467, ANP-2638NP, Revision 2, Applicability of Areva Np BWR Methods to Extend Power Uprate Conditions ML0931402652009-10-31031 October 2009 Attachment 13, Browns Ferry Unit 1 - Technical Specification Change 467, ANP-2864(NP), Revision 2, Reload Safety Analysis Report 2023-01-25 |
Text
(3) The licensee is authorized to relocate certain requirements included in Appendix A and the former Appendix B to licensee-controlled documents. Implementation of this amendment shall include the relocation of these requirements to the appropriate documents, as described in the licensee's application dated September 6, 1996, as supplemented May 1, August 14, November 5 and 14, December 3,4,11, 22, 23, 29, and 30, 1997, January 23, March 12, April 16, 20, and 28, May 7, 14, 19, and 27, and June 2, 5, 10 and 19, 1998, evaluated in the NRC staff s Safety Evaluation enclosed with this amendment. This amendment is effective immediately and shall be implemented within 90 days of the date of this amendment.
(4) Deleted.
(5) Classroom and simulator training on all power uprate related changes that affect operator performance will be conducted prior to operating at uprated conditions.
Simulator changes that are consistent with power uprate conditions will be made and simulator fidelity will be validated in accordance with ANSIIANS 3.5-1985.
Training and the plant simulator will be modified, as necessary, to incorporate changes identified during startup testing. This amendment is effective immediately.
(6) The licensee shall fully implement and maintain in effect all provisions of the Commission-approved physical security, guard training and qualification, and safeguards contingency plans including amendments made pursuant to provisions of the Miscellaneous Amendments and Search Requirements revisions to 10 CFR 73.55 (51 FR 27817 and 27822) and to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The plans, which contain Safeguards Information protected under 10 CFR 73.21, are entitled: "Browns Ferry Physical Security Plan", with revisions submitted through May 24,1988; "Browns Ferry Security Personnel Training and Qualification Plan", with revisions submitted through April 16,1987; and "Browns Ferry Safeguards Contingency Plan", with revisions submitted through June 27,1986. Changes made in accordance with 10 CFR 73.55 shall be implemented in accordance with the schedule set forth therein.
BFN-UNIT 3 4 Amendment No. '2 49