Withdrawn NRC Generic Letter 1989-003: Operator Licensing National Examination Schedule
ML031150236
Person / Time
Site: Beaver Valley, Millstone, Hatch, Monticello, Calvert Cliffs, Dresden, Davis Besse, Peach Bottom, Browns Ferry, Salem, Oconee, Mcguire, Nine Mile Point, Palisades, Palo Verde, Perry, Indian Point, Fermi, Kewaunee, Catawba, Harris, Wolf Creek, Saint Lucie, Point Beach, Oyster Creek, Watts Bar, Hope Creek, Grand Gulf, Cooper, Sequoyah, Byron, Pilgrim, Arkansas Nuclear, Braidwood, Susquehanna, Summer, Prairie Island, Columbia, Seabrook, Brunswick, Surry, Limerick, North Anna, Turkey Point, River Bend, Vermont Yankee, Crystal River, Haddam Neck, Ginna, Diablo Canyon, Callaway, Vogtle, Waterford, Duane Arnold, Farley, Robinson, Clinton, South Texas, San Onofre, Cook, Comanche Peak, Yankee Rowe, Maine Yankee, Quad Cities, Humboldt Bay, La Crosse, Big Rock Point, Rancho Seco, Zion, Midland, Bellefonte, Fort Calhoun, FitzPatrick, McGuire, LaSalle, 05000000, Zimmer, Fort Saint Vrain, Washington Public Power Supply System, Shoreham, Satsop, Trojan, Atlantic Nuclear Power Plant, Clinch River, Crane
Issue date: 03/24/1989
From: Varga S
Office of Nuclear Reactor Regulation
To:
References
GL-89-003, NUDOCS 8903220159
Download: ML031150236 (6)


Text

Withdrawn NRC Generic Letter 1989-03, Operator Licensing National Examination Schedule, dated March 24, 1989, has been withdrawn.

ADAMS Accession Number: ML031150236 See Federal Register notice 81 FR 31969, dated May 20, 2016

UNITED STATES w,

°NUCLEAR REGULATORY COMMISSION WASHINGTON, D. C. 20555 March 24, 1989 TO:

ALL POWER REACTOR LICENSEES AND APPLICANTS FOR AN OPERATING LICENSE

SUBJECT:

OPERATOR LICENSING NATIONAL EXAMINATION SCHEDULE (GENERIC LETTER 89- 03)

Generic Letter (GL) 88-13, dated August 8, 1988, solicited your estimated replacement examination needs for each fiscal year (FY) through 1992 and stated the United States Nuclear Regulatory Commission's (NRC's) intent to implement a national examination schedule beginning in FY 1990 (October 1, 1989). Adopting such a schedule would enable the NRC to more efficiently employ its limited examiner staff while allowing you to plan your training efforts with greater confidence that your licensing examinations will be administered on their designated dates.

The Office of Nuclear Reactor Regulation (NRR) has evaluated your estimated examination needs for FY 1990 and developed the enclosed national examination schedule.

Every attempt was made to schedule examination services at the times you requested; however, if the workload within a region, among facilities of the same vendor type, or nationally was excessive during a particular month, then your designated examination dates were adjusted to eliminate the excessive workload.

Each facility was assigned two examination dates during the fiscal year regardless of how many examinations were indicated in its response to Generic Letter 88-13.

NRR's objective is to administer replacement and/or requalification examinations at each site at approximately 6-month intervals. Although the replacement and requalification examination methodologies are currently too difterent to facilitate concurrent administration of both examinations, NRR is evaluating the potential for adopting portions of the revised requalification methodology in the replacement examination program. When the differences between the two methodologies are reconciled, all normal licensing activities necessary for your facility will be performed during one or both of your designated examination dates.

The NRC regional offices, through direct liaison with your training managers, will schedule examinations within the months assigned on the enclosed national schedule. Every effort should be made to target the assigned examination dates during FY 1990; however, in light of the lead time necessary to revise your training schedules, some deviation from the enclosed schedule will be accommodated. In the absence of documentable, extenuating circumstances, replacement examinations during fiscal years 1991 and beyond will not be rescheduled but will be deferred until the next regularly scheduled site visit. During the period that NRR is evaluating concurrent administration of replacement and requalification examinations, the regions will continue to schedule requalification examinations on a case-by-case basis.

r 80320159 )

9C!53s y

SD 3fDm XDx

hi6b3f

K ) (he same schedule will be used year after year, so your operator licensing examinations should be expected on approximately the same dates every year.

When requalification examinations are added to the schedule, they should be expected with equal regularity.

Your estimates of licensing examination requirements for future fiscal years will be solicited to determine which assigned dates you plan to utilize and the number of candidates to be examined so that NRC may modify its budget and staffing accordingly.

We appreciate your assistance in this matter and invite you to direct any questions concerning the national examination schedule to Mr. Kenneth E.

Perkins, Jr., at (301) 492-1031.

Associate Direct or Projects Office of Nuclear actor Regulation

Enclosure:

National Examination Schedule

K>

Page No.

1 03/06/89 NATIONAL EXAMINATION SCHEDULE FACILITY OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP NAME ARKANSAS 1

X X

ARKANSAS 2 X

X BEAVER VALLEY 1 X

X BEAVER VALLEY 2 X

X BIG ROCK X

X BRAIDWOOD 1/2 X

X BROWNS FERRY 1/2/3 X

X BRUNSWICK 1/2 X

X BYRON 1/2 X

X CALLAWAY X

X CALVERT CLIFFS 1/2 X

X CATAWBA 1/2 X

X CLINTON X

X COMANCHE PEAK 1/2 X

X COOPER X

X CRYSTAL RIVER 3 X

X DAVIS-BESSE X

X DC COOK 1/2 X

X DIABLO CANYON 1/2 X

X DRESDEN 2/3 X

X DUANE ARNOLD X

X FARLEY 1/2 X

X FERMI 2 X

X FITZPATRICK X

X FORT CALHOUN 1 X

X FORT ST VRAIN X

X GINNA X

X GRAND GULF X

X HADDAM NECK X

X HATCH 1/2 X

X HB ROBINSON X

X HOPE CREEK X

X INDIAN POINT 2 X

X INDIAN POINT 3 X

X KEWAUNEE X

X LACROSSE LASALLE 1/2 X

X LIMERICK 1/2 X

X MAINE YANKEE X

X MCGUIRE 1/2 X

X MILLSTONE 1 X

X MILLSTONE 2 X

X MILLSTONE 3 X

X MONTICELLO 1/2 X

X NINE MILE POINT 1 X

X NINE MILE POINT 2 X

X NORTH ANNA 1/2 X

X OCONEE 1/2/3 X

X OYSTER CREEK X

X PALISADES X

X

Page No.

2 03/06/89 NATIONAL EXAMINATION SCHEDULE FACILITY OCT NOV DEC JAN FEB XAR APR MAY JUN JUL AUG SEP NAME PALO VERDE 1/2/3 X

X PEACH BOTTOM 2/3 X

X PERRY X

X PILGRIM X

X POINT BEACH 1/2 X

X PRAIRIE ISLAND 1/2 X

X QUAD CITIES 1/2 X

X RANCHO SECO X

X RIVER BEND X

X SALEM 1/2 X

X SANONOFRE 1 X

X SAN ONOFRE 2/3 X

X SEABROOK 1/2 X

X SEQUOYAH 1/2 X

X SHEARON HARRIS X

X SHOREHAM X

X SOUTH TEXAS 1/2 X

X ST LUCIE 1/2 X

X SURRY 1/2 X

X SUSQUEHANNA 1/2 X

X TMI 1 X

X TMI 2 TROJAN X

X TURKEY POINT 3/4 X

X VC SUMMER X

X VERMONT YANKEE X

X VOGTLE 1/2 X

X WATERFORD 3 X

X WATTS BAR 1/2 X

X WNP 2 X

X WOLF CREEK X

X YANKEE ROWE X

X ZION 1/2 X

V I'

LIST OF RECENTLY ISSUED GENERIC LETTERS Generic Letter No.

Date of Subject Issuance Issued To 89-02 89-01 88-20 ACTIONS TO IMPROVE THE DETECTION OF COUNTERFEIT AND FRAUDULENTLY MARKETED PRODUCTS IMPLEMENTATION OF PROGRAMMATIC CONTROLS FOR RADIOLOGICAL EFFLUENT TECHNICAL SPECIFICATIONS IN THE ADMINISTRATIVE CONTROLS SECTION OF THE TECHNICAL SPECIFICATIONS AND THE RELOCATION OF PROCEDURAL DETAILS OF RETS TO THE OFFSITE DOSE CALCULATION MANUAL OR TO THE PROCESS CONTROL PROGRAM.

INDIVIDUAL PLANT EXAMINATION FOR SEVERE ACCIDENT VULNERABILITIES -

10 CFR 50.54(f)

USE OF DEADLY FORCE BY LICENSEE GUARDS TO PREVENT THEFT OF SPECIAL NUCLEAR MATERIAL PLANT RECORD STORAGE ON OPTICAL DISKS LOSS OF DECAY HEAT REMOVAL 10 CFR 50.54(f)

REMOVAL OF CYCLE-SPECIFIC PARAMETER LIMITS FROM TECHNICAL SPECIFICATIONS 3/21/89 1/31/89 11/23/88 10/28/88 10/20/88 10/17/88 10/04/88 ALL HOLDERS OF OPERATING LICENSES AND CONSTRUCTION PERMITS FOR NUCLEAR POWER REACTORS ALL LICENSEES HOLDING OPERATING LICENSES AND CONSTRUCTION PERMITS FOR NUCLEAR POWER REACTOR FACILITIES.

ALL LICENSEES HOLDING OPERATING LICENSES AND CONSTRUCTION PERMITS FOR NUCLEAR POWER REACTOR FACILITIES ALL FUEL CYCLE FACILITY LICENSEES WHO POSSESS, USE, IMPORT, EXPORT, OR TRANSPORT FORMULA QUANTITIES OF STRATEGIC SPECIAL NUCLEAR MATERIAL ALL LICENSEES OF OPERATING REACTORS AND HOLDERS OF CONSTRUCTION PERMITS ALL HOLDERS OF OPERATING LICENSES OR CONSTRUCTION PERMITS FOR PRESSURIZED WATER REACTORS ALL POWER REACTOR LICENSEES AND APPLICANTS 88-19 88-18 88-17 88-16