ML021010002

From kanterella
Jump to navigation Jump to search
IR 05000285/2002-003 on 02/04-03/01/2002; Omaha Public Power District; Fort Calhoun Station Safety System Design and Performance Capability, Evaluation of Changes, Tests, or Experiments. Violations Identified
ML021010002
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 04/10/2002
From: Marschall C
NRC/RGN-IV/DRS/EMB
To: Ridenoure R
Omaha Public Power District
References
EA-02-059 IR-02-003
Download: ML021010002 (32)


See also: IR 05000285/2002003

Text

April 10, 2002

EA-02-059

R. T. Ridenoure

Division Manager - Nuclear Operations

Omaha Public Power District

Fort Calhoun Station FC-2-4 Adm.

P.O. Box 550

Fort Calhoun, Nebraska 68023-0550

SUBJECT:

FORT CALHOUN STATION - NRC INTEGRATED INSPECTION

REPORT 50-285/02-03

Dear Mr. Ridenoure:

On March 1, 2002, the NRC completed an inspection at your Fort Calhoun Station. The

enclosed report documents the inspection findings, which were discussed on March 1, 2002,

with Mr. D. Bannister and other members of your staff. A supplemental exit meeting was

conducted by telephone on March 11, 2002, with Mr. R. Ridenoure, Division Manager, Nuclear

Operations, and other members of your staff.

This inspection examined activities conducted under your license as they relate to safety and

compliance with the Commissions rules and regulations and with the conditions of your license.

Within these areas, the inspection consisted of selected examination of procedures and

representative records, observations of activities, and interviews with personnel.

Based on the results of this inspection, the NRC has identified six findings that were evaluated

under the risk significance determination process as having very low safety significance

(green). One finding involved the failure to take adequate corrective actions for defective

valves in the emergency diesel air starting system. The second finding involved the failure to

apply an adequate design analysis of emergency diesel generator fuel oil storage requirements.

The third finding involved an inadequate procedure associated with testing of the turbine-driven

auxiliary feedwater pump. The fourth finding involved an inadequate safety evaluation

associated with a change to a surveillance test procedure. The NRC has determined that

violations are associated with these issues. Because of the very low safety significance, the

violations are being treated as noncited violations, consistent with Section VI.A.1 of the

Enforcement Policy. Additionally, two findings were identified pertaining to the diesel-driven

auxiliary feedwater pump, involving day tank inventory and automatic fire suppression, but they

were not identified as violations. If you deny the noncited violations, you should provide a

response within 30 days of the date of this inspection report, with the basis for your denial, to

-2-

the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC

20555-0001, with copies to the Regional Administrator, U.S. Nuclear Regulatory Commission,

Region IV, 611 Ryan Plaza Drive, Suite 400, Arlington, Texas 76011; the Director, Office of

Enforcement, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; and the

NRC Resident Inspector at the Fort Calhoun Station.

In accordance with 10 CFR 2.790 of the NRCs "Rules of Practice," a copy of this letter

and its enclosure will be available electronically for public inspection in the NRC Public

Document Room or from the Publicly Available Records (PARS) component of NRCs

document system (ADAMS). ADAMS is accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Charles S. Marschall, Chief

Engineering and Maintenance Branch

Division of Reactor Safety

Docket: 50-285

License: DPR-40

cc:

Mark T. Frans, Manager

Nuclear Licensing

Omaha Public Power District

Fort Calhoun Station FC-2-4 Adm.

P.O. Box 550

Fort Calhoun, Nebraska 68023-0550

James W. Chase, Division Manager

Nuclear Assessments

Fort Calhoun Station

P.O. Box 550

Fort Calhoun, Nebraska 68023-0550

David J. Bannister, Manager - Fort Calhoun Station

Omaha Public Power District

Fort Calhoun Station FC-1-1 Plant

P.O. Box 550

Fort Calhoun, Nebraska 68023-0550

-3-

James R. Curtiss

Winston & Strawn

1400 L. Street, N.W.

Washington, D.C. 20005-3502

Chairman

Washington County Board of Supervisors

Washington County Courthouse

P.O. Box 466

Blair, Nebraska 68008

Sue Semerena, Section Administrator

Nebraska Health and Human Services System

Division of Public Health Assurance

Consumer Services Section

301 Centennial Mall, South

P.O. Box 95007

Lincoln, Nebraska 68509-5007

-4-

Electronic distribution from ADAMS by RIV:

Regional Administrator (EWM)

DRP Director (KEB)

DRS Director (ATH)

Senior Resident Inspector (WCW)

Branch Chief, DRP/C (KMK)

Senior Project Engineer, DRP/C (vacant)

Staff Chief, DRP/TSS (PHH)

RITS Coordinator (NBH)

Jim Isom, Pilot Plant Program (JAI)

RidsNrrDipmLipb

Scott Morris (SAM1)

FCS Site Secretary (NJC)

SRI:EMB

SRI:EMB

RI:EMB

RI:EMB

PE:PBD

MFRunyan/lmb

LEEllershaw

PAGoldberg

WMMcNeill

JFMelfi

/RA/

/RA/

/RA/

/RA/ T

/RA/ T

03/26/02

03/26/02

03/26/02

03/19/02

03/21/02

RI:EMB

OE:OLB

C:EMB

C:DRPC

C:EMB

CAClark

AASanchez

CSMarschall

CEJohnson

CSMarschall

/RA/

/RA/ E

/RA/

/RA/

/RA/

03/26/02

03/20/02

04/08/02

04/10/02

04/10/02

OFFICIAL RECORD COPY

T=Telephone E=E-mail F=Fax

ENCLOSURE

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

Docket:

50-285

License:

DPR-40

EA No.

EA-02-059

Report No:

50-285/ 02-03

Licensee:

Omaha Public Power District

Facility:

Fort Calhoun Station

Location:

Fort Calhoun Station FC-2-4 Adm

P.O. Box 399, Hwy. 75 - North of Fort Calhoun

Fort Calhoun, Nebraska

Dates:

February 4 through March 1, 2001

Team Leader:

M. F. Runyan, Senior Reactor Inspector, Engineering Maintenance Branch

Inspectors:

L. E. Ellershaw, Senior Reactor Inspector, Engineering Maintenance Branch

P.A. Goldberg, Reactor Inspector, Engineering Maintenance Branch

J .F. Melfi, Reactor Inspector, Engineering Maintenance Branch

W. M. McNeill, Reactor Inspector, Engineering Maintenance Branch

C. A. Clark, Reactor Inspector, Engineering Maintenance Branch

A. A. Sanchez, Operations Engineer, Operator Licensing Branch

Approved By:

Charles S. Marschall, Chief

Engineering Maintenance Branch

Division of Reactor Safety

-2-

SUMMARY OF FINDINGS

IR 05000285-02-03 on 02/04-03/01/20021; Omaha Public Power District; Fort Calhoun Station

safety system design and performance capability, evaluation of changes, tests, or experiments.

The inspections were conducted by six regional inspectors. The inspectors identified six green

findings, four of which were characterized as noncited violations. The significance of most

findings is indicated by their color (Green, White, Yellow, Red) and determined by using

Inspection Manual Chapter 0609, "Significance Determination Process (SDP)." Findings for

which the significance determination process does not apply are indicated by "No Color" or by

the severity level of the applicable violation. The NRCs program for overseeing the safe

operation of commercial nuclear power reactors is described at its Reactor Oversight Process

website at http://www.nrc.gov/NRR/OVERSIGHT/index.html.

Cornerstone: Mitigating Systems

Green. The licensee failed to take adequate corrective actions following discovery of a

degraded emergency diesel generator air start system air relay valve in October 2001

and also failed to take adequate corrective actions following the operational failure of

this valve in December 2001. This was identified as a violation of Criterion XVI to

Appendix B of 10 CFR Part 50, Corrective Action.

This finding was of very low safety significance since there was no actual loss of

safety function (the emergency diesel generator started successfully on its backup air

starting system). Because of the low safety significance and the licensees action to

place the issue in their corrective action program (Condition Reports 2001-03772 and

2002-00475), this violation is being treated as a noncited violation in accordance with

Section VI.A.1 of the Enforcement Policy (50-285/0203-01) (Section 1R21.3.b).

Green. The six fire protection sprinklers in the diesel-driven auxiliary feedwater pump

room were located approximately 5 feet below the ceiling and would most likely not

actuate until a fire in the room reached a considerable strength. The delay in actuation

would result from the need for the hot gas layer to descend to the elevation of the

sprinklers, which are normally positioned very close to the ceiling. Because the issue

did not involve NRC regulations, a violation was not identified.

This finding was of very low safety significance because the diesel-driven pump is not

credited in the accident analysis (it is not safety-related, but has high risk significance),

sensors in the room would cause a control room alarm, and manual suppression would

be available. The licensee entered this issue into its corrective action program as

Condition Report 200200498 (Section 1R21.4.b).

Green. The fuel oil inventory in the day tank supplying the diesel-driven auxiliary

feedwater pump was not being directly verified by the licensees surveillance program.

Instrument drift could result in failure to meet the design intent of maintaining the tank

half full to provide a 4-hour run of the pump (which is not safety-related, but has a high

risk significance). Because the issue did not involve NRC regulations, a violation was

not identified.

-3-

This finding was of very low safety significance because there was no actual loss of

safety function and the diesel engine has a integral generator that can power a transfer

pump to replenish the day tank. The licensee entered this issue into its corrective action

program as Condition Report 200200496 (Section 1R21.4.b).

Green. The licensee staff had not accounted for several factors determining the

diesel fuel oil on hand to meet the Technical Specification 2.7(1)m. requirement of

16,000 gallons of fuel oil in FO-1, the diesel generator fuel oil storage tank, and an

additional 8,000 gallons of diesel fuel oil in FO-10, the auxiliary boiler fuel oil storage

tank. The basis for the limit was to maintain a 7-day supply of fuel oil. The factors not

accounted in the analysis were the effect of specific gravity on the loop uncertainties,

the effect of specific gravity on the fuel consumption formula, the effect of the operation

of the diesel driven auxiliary feedwater pump, the effect of errors in estimating volumes,

and other minor errors. This was identified as a violation of Criterion III of Appendix B to

10 CFR Part 50, Design Control, which requires that the design basis be correctly

translated into the technical specifications.

This finding was of very low safety significance as the licensee always maintained

additional inventory that would have provided a full 7-day supply of fuel oil, and the

safety evaluation report credited the sufficiency of a 6-day supply. Because of the very

low safety significance and that the licensee entered this finding into their corrective

action program in Condition Reports 200200464, 200200373, and 200200304, this

violation is being treated as a noncited violation in accordance with Section VI.A.1 of the

Enforcement Policy (50-285/0203-02) (Section 1R21.5.b).

Green. Procedure SE-ST-AFW-3006, "Auxiliary Feedwater Pump FW-10, Steam

Isolation Valve and Check Valve Tests," Revision 5, was inadequate. The procedure

failed to identify that the motor-driven auxiliary feedwater pump was rendered inoperable

during a portion of the test. This was identified as violation of Criterion V to Appendix B

of 10 CFR Part 50, Instruction, Procedures, and Drawings.

The finding was of very low safety significance because there was no actual loss of

safety function as the turbine-driven pump remained operable and the dedicated

operators could be considered to be highly reliable. Because of the very low safety

significance, and because the licensee included the item in their corrective action

program as Condition Report 200200483, this violation is being treated as a noncited

violation in accordance with Section VI.A.1 of the Enforcement Policy (50-285/0203-03)

(Section 1R21.6.b).

Green. The licensee failed to assess Procedure Change Request 42290 to

Procedure SE-ST-AFW-3006, "Auxiliary Feedwater Pump FW-10, Steam Isolation

Valve and Check Valve Tests," under the provisions of 10 CFR 50.59, resulting in a

failure to comply with Technical Specification 2.5. The use of operator actions to

maintain operability was not adequately evaluated. This procedure change should not

have been made without prior NRC approval. This was identified as a violation of

10 CFR 50.59(a)(1)(iii).

This finding was of very low safety significance because the reliability of the operator

actions needed to restore system operability was very high. Because of the very low

-4-

safety significance, and because the licensee included the item in their corrective

action program as Condition Report 200200632, this violation is being treated as a

noncited violation in accordance with Section VI.A.1 of the Enforcement Manual

(50-0203/0203-04) (EA-02-059) (Section 1R21.6.b).

Report Details

1

REACTOR SAFETY

Introduction

A team inspection was performed to verify that facility safety system design and

performance capability were adequate and that the initial design and subsequent

modifications have preserved the current design basis of the systems selected for

review. The scope of the review also included any necessary nonsafety-related

structures, systems, and components that provided functions to support safety

functions. The inspection effort also reviewed the licensees programs and methods for

monitoring the capability of the selected systems to perform the current design basis

functions. This inspection verified aspects of the initiating events, mitigating systems,

and barrier cornerstones.

The probabilistic risk assessment model for Fort Calhoun Station is based on the

capability of the as-built safety systems to perform their intended safety functions

successfully. The area and scope of the inspection were determined by reviewing the

licensees probabilistic risk analysis models to identify the most risk significant systems,

structures, and components according to their ranking and potential contribution to

dominant accident sequences and/or initiators. Deterministic effort was also applied in

the selection process by considering recent inspection history, recent problem area

history, and all modifications developed and implemented. The team reviewed in detail

the emergency diesel generators and the auxiliary feedwater system. The primary

review prompted parallel review and examination of support systems, such as, electrical

power, instrumentation, room cooling systems, and related structures and components.

The objective of this inspection was to assess the adequacy of calculations, analyses,

engineering processes, and engineering and operating practices that were used to

support the performance of the safety systems selected for review and the necessary

support systems during normal, abnormal, and accident conditions. Acceptance criteria

utilized by the NRC inspection team included NRC Regulations, the technical

specifications, applicable sections of the Final Safety Analysis Report, applicable

industry codes and standards, as well as industry initiatives implemented by the

licensees programs.

An inspection to assess the performance of the licensee's program to meet the

regulatory requirements of 10 CFR Part 50.59, "Changes, Tests, And Experiments," was

also conducted by one member of the team, during the first week of the inspection.

-2-

1R02

Evaluation of Changes, Tests, and Experiments (71111.02)

a.

Inspection Scope

The inspectors reviewed a selected sample of 11 safety evaluations to verify that the

licensee had appropriately considered the conditions under which the licensee may

make changes to the facility or procedures or conduct tests or experiments without prior

NRC approval in accordance with 10 CFR 50.59.

The inspectors reviewed 11 screenings pertaining to modifications, and procedure and

calculation revisions, in which the licensee determined that evaluations were not

required, to ensure that the licensees exclusion of a full evaluation was consistent with

the requirements of 10 CFR 50.59.

The inspectors evaluated the effectiveness of the licensees corrective action process to

identify and correct problems concerning their performance associated with

10 CFR 50.59 requirements. In this effort, the inspectors reviewed four condition

reports. Further, the inspectors reviewed the most recent 10 CFR 50.59 program audit.

Additionally, the inspectors reviewed the 10 CFR 50.59 training curriculum and the

qualification records of a sample of independent technical reviewers identified in the

screening and evaluation forms.

b

Findings

No findings of significance were identified.

1R21

Safety System Design and Performance Capability (71111.21)

.1

System Requirements

a.

Inspection Scope

The team reviewed the following attributes for the auxiliary feedwater system and the

emergency diesel generators: (1) process medium (water, steam, and air), (2) energy

sources, (3) control systems, and (4) equipment protection. The team verified that

procedural instructions to operators were consistent with operator actions required to

meet, prevent, and/or mitigate design basis accidents. The review also considered

requirements and commitments identified in the Final Safety Analysis Report, technical

specifications, design basis documents, and plant drawings. These reviews further

verified that required support functions for the emergency diesel generators and the

auxiliary feedwater system would be available.

b.

Findings

No findings of significance were identified.

-3-

.2

System Condition and Capability

a.

Inspection Scope

The team reviewed the periodic testing procedures for the auxiliary feedwater system

and the emergency diesel generators to verify that the design requirements were

adequately demonstrated. The team reviewed the environmental qualification of a

sample of system components to verify the capability to operate under design

environmental conditions and the assumed operating parameters including: voltage,

speed, power, flow, temperature, and pressure.

The team also reviewed the systems operations by conducting system walkdowns;

reviewing normal, abnormal, and emergency operating procedures; and reviewing the

Final Safety Analysis Report, technical specifications, design calculations, drawings, and

procedures.

b.

Findings

No findings of significance were identified.

.3

Identification and Resolution of Problems

a.

Inspection Scope

The team reviewed a sample of problems identified by the licensee in the corrective

action program to evaluate the effectiveness of corrective actions related to design

issues. The sample included open and closed condition reports for the past three years

that identified issues related to or affecting the selected systems.

b.

Findings

Inadequate Corrective Action for Emergency Diesel Generator Air Relay Valves

The team identified two instances of inadequate corrective action related to maintenance

and testing of the air relay valves in the emergency diesel generator air start system.

The air start system for each diesel generator contained two air relay valves, one

designated as primary and the other as secondary. Absent other failures, both of the air

relay valves (primary and secondary) must fail in order for an emergency diesel

generator to fail to start.

On October 17, 2001, a work request was written to address a leaking air relay valve

(SA-196) that was discovered on the Division 2 emergency diesel generator air start

system. Initially given a high priority, the work request was later downgraded, given that

it still functioned, and assigned a completion date of January 28, 2002. The valve

-4-

subsequently failed during a surveillance test on December 12, 2001. The secondary air

start system functioned as designed and successfully started the diesel. There was no

immediate effect on diesel generator operability because it was already declared

inoperable for maintenance. Starting air relay valve SA-196 was replaced on

December 12, 2001.

No condition reports were written following discovery of the leaking air relay valve in

October 2001. Three condition reports were generated concerning the December 2001

air relay valve failure. The cause of the failed valved was classified as an O-ring

aging/wear issue. Although mentioned, the potential for common cause failure was not

addressed in the condition reports. Neither before nor after the events mentioned were

the air relay valves (safety system components) incorporated in any preventative

maintenance or replacement program nor were they addressed from a rigorous

engineering standpoint. It was not until the team inquired into the preventative

maintenance of these valves that a condition report was generated to evaluate these

possible actions.

The team determined that these conditions had a credible impact on safety and that the

issue was more than minor since the air relay valves on the emergency diesel air start

system began to exhibit signs of degradation and one actual failure. The team also

concluded that this issue affected the mitigating system cornerstone since at least one of

the emergency diesel generators is required to mitigate a design basis event, and the

safety function could have been impacted.

Using Phase 1 of the Significance Determination Process, the team determined that only

the mitigation systems cornerstone was affected and that there was no actual loss of

safety function as the emergency diesel generators still started on demand. Therefore,

the problem had a very low safety significance (Green).

Criterion XVI of Appendix B to 10 CFR Part 50 states, in part, that [m]easures shall be

established to assure that conditions adverse to quality . . . are promptly identified and

corrected. In contrast to the above, the team determined that the licensee missed the

opportunity to promptly identify the need for corrective action concerning the leaking air

relay valve (SA-196) in October 2001. The licensee also failed to implement proper

corrective action concerning the failure of that same valve in December 2001. However,

due to the low safety significance and the licensees action to place the issue in their

corrective action program (Condition Reports 200103772 and 200200475), this violation

is being treated as a noncited violation in accordance with Section VI.A.1 of the

Enforcement Policy (50-285/0203-01).

-5-

.4

System Walkdowns

a.

Inspection Scope

The team performed walkdowns of the accessible portions of the auxiliary feedwater

system and the emergency diesel generators as well as the required support systems.

The walkdowns focused on the installation and configuration of power supplies, piping,

components, and instruments. During the walkdowns, the team assessed:

The placement of protective barriers and systems,

The susceptibility to flooding, fire, or environmental conditions,

The physical separation of trains and the provisions for seismic concerns,

Accessibility and lighting for any required local operator action,

The materiel condition and preservation of systems and equipment, and

the conformance of the currently installed system configurations to the current

design and licensing bases.

b.

Findings

Fire Protection of Diesel-Driven Auxiliary Feedwater Pump

The team identified an issue related to the location of fire protection sprinkler heads in

the room that houses the nonsafety-related diesel-driven auxiliary feedwater pump

(FW-54). This pump was included in the scope of the inspection because it has

significant risk importance. Six sprinkler heads were positioned approximately 5 feet

below the ceiling of the room and approximately 4 feet to the side of the pump. A

horizontal 12X12-inch square sheet metal heat collector was located directly above each

sprinkler head .

Fire codes typically require sprinkler heads to be located within 1 or 2 feet of the ceiling

to ensure that they can respond quickly to the formation of a hot gas layer in the room.

Also, some industry testing has shown that heat collectors of the type described above

can retard activation by preventing the free flow of hot gases in the vicinity of the fusible

links in the heads. The team considered the off-ceiling location of the sprinkler heads to

render the diesel-driven auxiliary feedwater pump vulnerable to a small fire that would, in

all likelihood, activate the control room fire alarm sensor, but which could burn for a

considerable time before either manual suppression methods were applied or the hot gas

layer descended to the elevation of the fusible links. This scenario would potentially

extend the length of time needed to recover the pump in case it was needed as a

contingency (if the other auxiliary feedwater pumps were unavailable).

Because the issue did not involve NRC regulations, a violation was not identified.

However, the team determined that this finding was of more than minor significance

because it had a credible impact on safety. That is, the survival or recovery of a risk-

-6-

significant component could be affected. Using Phase I of the significance determination

process, the team determined that the issue affected the mitigating systems cornerstone,

because the pump provides risk mitigation for the auxiliary feedwater system and the

condition potentially impacted the timing at which automatic suppression would

extinguish a fire in the pump room. However, the finding had very low risk significance

(green) because sensors in the room would cause a control room alarm, manual

suppression would be available, and there was not an actual loss of safety function.

Because the issue did not involve NRC regulations, a violation was not identified. The

licensee initiated Condition Report 200200498 to examine this concern.

Inventory of Diesel-Driven Auxiliary Feedwater Pump Fuel Oil Day Tank

The 150-gallon fuel oil day tank for the diesel-driven auxiliary feedwater pump had three

level instruments: level sensors LS-2120 and LS-2121 which control (start and stop) the

transfer pump used to refill the day tank and cause a low level alarm in the control room,

respectively; and LI-2120, which is a local dial indicator of tank level. The tank was kept

by procedure at least half full to ensure the capability of the pump to run for at least 4

hours. This run time was provided, in part, for a station blackout situation, where the

diesel-driven pump functions as a backup to the turbine-driven pump. The level

instruments were not calibrated but were functionally tested every two years under

Preventive Maintenance Procedure IC-PM-FW-0900, Operational Verification of FW-54

Fuel Oil Day Tank FO-38 Controls, Revision 1. This test procedure did not require that

the actual level in the tank be verified. Therefore, instrument drift over a long period of

time could result in tank levels deviating from the design objective.

The team postulated the following scenario: the level sensors and level indicator drift in

tandem over time to a lower setpoint, but still appear to be functioning normally during

the preventive maintenance functional tests. The drift continues following a test to a

point where the tank is actually less than half full and the low-level sensor of LI-2120

does not come in when the pump is started and expends the available fuel (in response

to an event). The pump runs for less than 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> and then runs out of fuel oil as the

transfer pump fails to start and replenish the inventory.

Because the issue did not involve NRC regulations, a violation was not identified.

However, the team determined that this finding was of more than minor significance

because it had a credible impact on safety. That is, the design function of a risk-

significant component could be affected. Using Phase I of the significance determination

process, the team determined that the issue affected the mitigating systems cornerstone,

because it potentially impacted core decay heat removal. However, the finding had very

low risk significance (green) because there was not an actual loss of safety function and

the diesel engine powering the pump has a generator that can power a transfer pump to

replenish the day tank inventory. Because the issue did not involve NRC regulations, a

violation was not identified. The licensee initiated Condition Report 200200496 to review

this concern.

-7-

.5

Design Review

a.

Inspection Scope

The team reviewed the current as-built instrument and control, electrical, and mechanical

design of the auxiliary feedwater system and the emergency diesel generators. These

reviews included a review of design assumptions, calculations, required system thermal-

hydraulic performance, electrical power system performance, protective relaying, and

instrument setpoints and uncertainties. The team also performed a single failure review

of individual components to determine the effects of such failures on the capability of the

systems to perform their design safety functions.

The team reviewed calculations, drawings, specifications, vendor documents, Final

Safety Analysis Report, technical specifications, emergency operating procedures, and

temporary and permanent modifications.

b.

Findings

Failure to Account Adequately for Diesel Generator Fuel Oil Inventory

The team found that licensee staff had not accounted for several factors in the

determination of the diesel fuel oil on hand to meet the Technical Specification 2.7(1)m.

limit of 16,000 gallons of fuel oil in FO-1, the diesel generator fuel oil storage tank, and

an additional 8,000 gallons of diesel fuel oil in FO-10, the auxiliary boiler fuel oil storage

tank. The basis for the limit was to maintain a 7-day supply of fuel oil.

Calculation FC03382, Diesel Generator LOCA Loads ETS-2.08N-L1, Revision 15,

established 24,280 gallons as the required inventory of fuel oil. The design calculations,

combined with the technical specification limits, assured a minimum fuel oil inventory of

25,220 gallons (940 gallon margin). This information was detailed in a licensee

application for "Amendment of the Operating License," dated September 17, 1993. The

amendment was approved by a safety evaluation report, dated March 29, 1994. The

NRC staff found that the proposed fuel oil inventory was actually below a seven-day

supply, but above a six-day supply and that this situation was acceptable because

replacement oil could be obtained with high confidence within a period of 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br />.

The team reviewed Calculation FC06289, Diesel Generator Fuel Oil Storage Tanks

Level TLU Calculation, Revision 0. The team found that the licensee had not assessed

possible variations in specific gravity in the total loop uncertainty calculation. The

licensee can accept diesel fuel with a range of specific gravities between 0.8762 and

0.8156 or 30 to 42 American Petroleum Institute (API) units, a variation of a little more

than 7 percent. The level indicators assumed a specific gravity of 0.8550. Use of the

densest permissible fuel oil would result in a measured volume discrepancy of

approximately 2.5 percent. The team considered the total loop uncertainty calculation

(FC06289) to be inadequate. The licensee staff documented this concern in Condition

Report 200200464.

-8-

The level indicators for the main and auxiliary boiler tank were mechanically scribed with

an indication ranging from 250 -18130 gallons. The licensees calculation for the volume

of the fuel oil tanks, FC06289, calculated a volume of 240 -18050 gallons. This resulted

in a non-conservative zero shift of the indication. The licensee identified this as

Condition Report 200200373.

The team reviewed Engineering Analysis92-047, Diesel Generator Fuel Oil

Requirements, Revision 0. This calculation established a formula relating fuel

consumption to load demand on the diesel generator based on some test runs. The

formula was used in subsequent calculations, such as Calculation FC03382. The team

found that specific gravity had not been used as a variable in establishing the formula for

fuel consumption. Text book data (Diesel Engine Reference Book by L. R. C. Lilly,

published by Butterworths in 1984) indicated that the energy level of the fuel oil could

vary across the permissible range of American Petroleum Institute units by 2.34 percent.

The licensee staff documented the failure to consider this within the analysis in Condition

Report 200200464.

The team found that the licensee staff had not considered the consumption of fuel oil by

the diesel-driven auxiliary feedwater pump (FW-54) in the depletion of oil reserves. The

fuel oil transfer pump (FO-37) on the diesel-driven auxiliary feedwater pump was used

under certain conditions to transfer fuel oil from the auxiliary boiler tank to the fuel oil

tank. The team estimated the effect of operation of Pump FW-54 for the time to transfer

8,000 gallons to be 286 gallons, or 1.18 percent of 24,280 gallons. Procedure EPIP-RR-

17A, TSC Administrative Logistics Coordinator Actions, Revision 19, did not identify the

impact of Pump FW-54 consumption on the fuel oil inventory. The licensee staff

documented this analytical oversight in Condition Report 200200464.

The team questioned the volume used in calculations for the diesel generator engine

tank. The team measured and calculated the volume of the tank to be a maximum of

520 gallons per diesel generator, not the 550 gallons assumed. The licensee staff did

not have documentation of the unusable volume below the suction pipe of the fuel pumps

in the diesel engine base tank. The licensee estimated the unusable volume in the diesel

generator engine tank to be 30 gallons per tank. Together, the two errors were

120 gallons, or 0.50 percent of 24,280 gallons. The licensee staff documented this

concern in Condition Report 200200304.

In summation, the errors identified (only the major sources are discussed above)

amounted to a negative 5.23 percent or 1,271 gallons (well in excess of the analyzed

margin). Therefore, the team concluded that the technical specification limits for the

storage of emergency diesel generator fuel oil were not adequately supported by the

design calculations.

The team evaluated this finding using the significance determination process. The

finding did not have a credible impact on safety because the technical specification

storage limits provided more than a six-day supply of fuel oil, which was a sufficient

amount according to the safety evaluation report. However, inadequate design control

resulted in a technical specification limit that failed to assure that the assumed

operational requirement was met. This is important, because both the licensee and the

NRC depend on accurate technical specifications to ensure that operation of the plant is

-9-

consistent with design assumptions. The safety significance of the finding was found to

be very low (Green) because the 6-day requirement accepted in the safety evaluation

report was met.

The team identified this finding as a violation of Criterion III of Appendix B to

10 CFR Part 50, Design Control, which requires that the design basis be correctly

translated into the technical specifications. Because of the very low safety significance

and the licensees documentation of this issue into their corrective action program

(Condition Reports 200200464, 200200373, and 200200304), this violation is being

treated as a noncited violation in accordance with Section VI.A.1 of the Enforcement

Policy (50-285/0203-02).

.6

Safety System Inspection and Testing

a.

Inspection Scope

The team reviewed the program and procedures for testing and inspecting selected

components in the auxiliary feedwater system and the emergency diesel generators.

The review included the results of surveillance tests required by the technical

specifications.

During the week of February 25, 2002, the team observed the quarterly performance test

of the turbine-driven auxiliary feedwater pump, using Procedure SE-ST-AFW-3006,

"Auxiliary Feedwater Pump FW-10, Steam Isolation Valve, and Check Valve Tests,"

Revision 26.

b.

Findings

Issues Related to Testing of Turbine-Driven Auxiliary Feedwater Pump

The team identified two green noncited violations related to periodic testing of the

turbine-driven auxiliary feedwater pumps. Both of these issues involved crediting

operator actions in lieu of automatic actions or realigning equipment that normally only

maintains its standby configuration in response to an accident condition. These issues

may apply to additional testing or maintenance conducted at Fort Calhoun Station.

The NRC issued guidance concerning operator actions in Information Notice (IN) 97-28,

Crediting of Operator Actions in Place of Automatic Actions and Modifications of

Operator Actions, Including Response Times. The following is an excerpt from this

Notice:

"The original design of nuclear power plant safety systems and their ability to

respond to design-basis accidents were described in licensees' FSARs and were

reviewed and approved by the NRC. Most safety systems were designed to rely

on automatic system actuation to ensure that the safety systems were capable of

carrying out their intended functions. In a few cases, limited operator actions,

when appropriately justified, were approved. Proposed changes that substitute

manual action for automatic system actuation or modify existing operator actions,

including operator response times, previously reviewed and approved during the

-10-

original licensing review of the plant will, in all likelihood, raise the possibility of a

USQ. Such changes must be evaluated under the criteria of 10 CFR 50.59 to

determine whether a USQ is involved and whether NRC review and approval is

required before implementation. A licensee may not make such changes before it

receives approval from the NRC when the change, test, or experiment may

(1) increase the probability of occurrence or the consequences of an accident or a

malfunction of equipment important to safety previously analyzed in the FSAR,

(2) create the possibility of an accident or a malfunction of a different type than

any previously evaluated in the FSAR, or (3) reduce the margin of safety as

defined in the basis for any TS. In the NRC staffs experience, many of the

changes of the type described above proposed by licensees do involve a USQ."

In the two examples that follow, the licensee failed to determine properly whether

changes involving the substitution of manual for automatic actions created an inoperable

condition or a licensing issue requiring NRC approval.

Inadequate Test Procedure

While observing the quarterly performance test of the turbine-driven auxiliary feedwater

pump, FW-10, in accordance with Procedure SE-ST-AFW-3006, "Auxiliary Feedwater

Pump FW-10, Steam Isolation Valve and Check Valve Tests," Revision 5, the team noted

that, in Steps 7.16 through 7.23 of the procedure, the normally locked-open manual

suction valve, FW-350, of the motor-driven auxiliary feedwater pump was closed by an

operator and the control room switch for this pump was placed in pull-to-lock. While in

this configuration, the turbine-driven auxiliary feedwater pump, FW-6, as well as the

motor-driven pump discharge check valve were tested. The test procedure prescribed

that dedicated operators be stationed at the closed motor-driven pump suction valve and

at the pump switch in the control room ready to restore the normal configuration if so

directed. The procedure considered the motor-driven pump to be operable in this

configuration as long as the operators were stationed and ready to perform actions as

prescribed. The team disagreed and stated that the motor-driven pump should have

been declared inoperable while in this configuration and that the licensee should have

entered Technical Specification 2.5(1) limiting condition for operation, which permits up

to 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> operation with one of the two safety-related auxiliary feedwater pumps

inoperable. The basis for the teams position was that the technical specifications and

the Final Safety Analysis Report, as well as any other regulatory document, did not

permit operator actions to be used as a condition to establish equipment operability

during surveillance testing. The team considered the cause of this problem to be an

inadequate test procedure, for failing to identify an instance of inoperability.

This finding was determined to have a credible impact on safety, in that, the failure to

open the suction valve or restore the switch position of the motor-driven pump could

potentially cause damage to the pump or preclude the flow of auxiliary feedwater to the

steam generators.

-11-

Using Phase 1 of the Significance Determination Process, the team determined that only

the mitigation systems cornerstone was affected and there was no actual loss of safety

function as the turbine-driven pump remained operable and the dedicated operators

could be considered to be highly reliable. Therefore, the problem had a very low safety

significance (Green).

The team determined that the test procedure was inadequate and identified this as a

violation of 10 CFR Part 50, Appendix B, Criterion V, "Instructions, Procedures, and

Drawings. Because of the very low safety significance, and because the licensee

included the finding in their corrective action program as Condition Report 200200483,

this violation is being treated as a noncited violation (50-285/0203-03) in accordance with

Section VI.A.1 of the Enforcement Policy.

Inadequate Safety Evaluation for Change to Surveillance Test Procedure

The team noted that, during a portion of Procedure SE-ST-AFW-3006, both of the safety-

related auxiliary feedwater pumps (the turbine-driven and the motor-driven) were

rendered inoperable at the same time. Step 7.29 of the procedure declared the turbine-

driven pump inoperable since pump discharge flow was about to be directed to the

emergency feedwater storage tank and operators were to take control of the pump speed

control loop. In Step 7.34, the locked-open manual feedwater valve, FW-170, was

closed and normally-closed motor-operated valve, HCV-1384, the main and auxiliary

feedwater cross-connect valve, was opened. In step 7.36, the normally locked-closed

discharge valve to the emergency feedwater storage tank, FW-1049, was opened. The

effect of changing the positions of these three valves was to direct flow to the emergency

feedwater storage tank and block the alternate auxiliary feedwater flow path to the steam

generator feed rings (where normal feedwater enters the steam generators). The normal

auxiliary feedwater discharge path to the steam generators remained open, but the flow

from both the turbine-driven pump and the motor-driven pump was diverted to the

auxiliary feedwater storage tank. At this time, the licensee did not declare the motor-

driven feedwater pump inoperable even though the flow from this pump would take the

same path as the turbine pump to the emergency feedwater storage tank. The team

noted that the non-safety-related diesel-driven feedwater pump, FW-54, would be

inoperable as well, since its flow would also go to the emergency feedwater storage tank

instead of the steam generator. With flowpaths open both to the steam generators and

to the storage tank, it was uncertain (the licensee had not performed an evaluation) if

sufficient flow would be available to the steam generators in this configuration (even if all

pumps were running). The licensee credited operator actions in the control room to

restore Motor-Operated Valve HCV-1384 to its normal closed position, which would

permit the motor-driven pump to deliver its entire flow to the steam generators. The

team concluded that the use of operator actions as a condition for operability was not

permitted for surveillance testing.

Technical Specification 2.5, "Steam and Feedwater Systems," states, "(1) during

Modes 1 and 2, one auxiliary feedwater pump may be inoperable for up to 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />,

provided that the redundant component shall be tested to demonstrate operability", and

"(3) All valves, interlocks and piping associated with the above components required to

function during accident conditions are operable. Manual valves that could interrupt

auxiliary feedwater flow to the steam generators shall be locked in the required position

-12-

to ensure a flow path to the steam generators." The team determined that the failure of

the licensee to maintain the motor-driven auxiliary feedwater pump operable while the

turbine-driven pump was declared inoperable during the test and, in addition, the failure

to maintain the manual valves in the required locked position to ensure a flow path to the

steam generators was contrary to Technical Specification 2.5.

The team reviewed Procedure Change Request 42290, dated April 21, 1994. This

procedure change revised the auxiliary feedwater pump test procedure to permit a

full-flow test of the turbine-driven pump and included credit for operator actions to

manipulate valves and change lineups to maintain the operability of the motor-driven

pump.

The team reviewed the 10 CFR 50.59 screening associated with Procedure Change

Request 42290. Question 9.4 of the screening, asking whether the change involved a

change to the technical specifications, was answered no, stating that Technical Specification 2.5 had been reviewed and needed no changes. The team noted that the

screening failed to demonstrate that operator actions prescribed by the procedure

change would be sufficient to ensure that the motor-driven pump could still meet its

design function, in terms of both reliability and timing and, thus, maintain compliance with

Technical Specification 2.5 (1). Also, the screening failed to identify that Technical Specification 2.5 (3) was affected by the unlocking and movement of locked valves that

would need to be manually re-positioned.

10 CFR 50.59(a)(1)(iii) [as the regulation existed at the time of this violation] allowed a

licensee to conduct tests or experiments not described in the Final Safety Analysis

Report without prior Commission unless the proposed test or experiment involved a

change in the technical specifications or an unreviewed safety question. The team

concluded that the licensees' failure to recognize that Technical Specifications 2.5(1) and

2.5(3) were not being met by relying on operator action, and that therefore prior

Commission approval was needed, was a violation of 10 CFR 50.59(a)(1)(iii).

This finding was determined to have a credible impact on safety, in that, it involved a

flawed analysis that ultimately led to operation of the plant in a manner not anticipated in

the original license.

Using Phase 1 of the Significance Determination Process, the team determined that only

the mitigation systems cornerstone was affected and that the reliability of the operator

actions needed to restore system operability was very high. Also the plant was in this

configuration for only approximately 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> per month. Therefore, this finding was

determined to have a very low safety significance (Green).

Because of the low safety significance, and because the licensee included the item in

their corrective action program as Condition Report 200200632, this violation is being

treated as a noncited violation (50-285/0203-04) (EA 02-059) in accordance with Section

VI.A.1 of the Enforcement Manual.

-13-

4

OTHER ACTIVITIES (ZA)

4OA6 Management Meetings

Exit Meeting Summary

The team leader presented the inspection results to Mr. D. Bannister, Plant Manager,

and other members of licensee management at the conclusion of the onsite inspection

on March 1, 2002.

At the conclusion of this meeting, the team leader asked the licensees management

whether any materials examined during the inspection should be considered proprietary.

No proprietary information was identified.

A supplemental exit meeting was conducted by telephone on March 11, 2002, with

Mr. R. Ridenoure, Division Manager, Nuclear Operations, and other members of licensee

management.

ATTACHMENT

Licensee Contacts :

D. Bannister, Plant Manager

G. Cavanaugh, Supervisor, Station Licensing

M. Frans, Manager, Nuclear Licensing

S. Gebers, Corporate Health Physicist

R. Haug, Manager, Chemistry

R. Lentz, Licensing Engineer

E. Matzke, Station Licensing Engineer

J. McManis, Manager, Design Engineering

G. Miller, Inservice Testing Coordinator

M. Puckett, Manager, Radiation Protection

J. Ressler, Mechanical Design Engineer

R. Ridenoure, Division Manager, Nuclear Operations

NRC:

W. Walker, Senior Resident Inspector

L. Willoughby, Resident Inspector

ITEMS OPENED AND CLOSED

Opened and Closed

50-285/0203-01

NCV

Inadequate Corrective Action for Defective Emergency Diesel

Generator Air Starting System Air Relay Valves (Section 1R21.3.b)

50-285/0203-02

NCV

Inadequate Design Control of Emergency Diesel Generator Fuel

Oil Inventory (Section 1R21.5.b)

50-285/0203-03

NCV

Inadequate Procedure for Testing Auxiliary Feedwater Pumps

(Section 1R21.6.b )

50-285/0203-04

NCV

Inadequate 10 CFR 50.59 Safety Evaluation Associated with

Change to Auxiliary Feedwater Pump Test Procedure

(Section 1R21.6.b)

-2-

Documents Reviewed

Condition Reports:

199601064

199700434

199700523

199701063

199701248

199800133

199800495

199801246

199801563

199801642

199900170

199900611

199901062

199901558

199901600

199901608

200000708

200000723

200000866

200000870

200000931

200001124

200001194

200001758

200100008

200100399

200100407

200100407

200100407

200100623

200101064

200101108

200101108

200101265

200101265

200101398

200101472

200101515

200101515

200101854

200101906

200101907

200101907

200102254

200102254

200102256

200102256

200102383

200102407

200102419

200102419

200102437

200102437

200102573

200103112

200103112

200103141

200103319

200103419

200103557

200103692

200103716

200103736

200103772

200103837

200200126

200200126

200200160

200200184

200200275

200200283

200200286

200200304

200200322

200200464

200200475

200200476

200200496

200200498

200200632

Calculations:

FC03382, Diesel Generator LOCA Loads ETS-2.08N-L1, Revision 15

FC03519, Analysis Summary for Loss of all Auxiliary Feedwater Equipment due to FW-10

Steam Line Break, Revision 0

FC05007, Usable Capacity of Emergency Feedwater Storage Tank FW-19, Revision 0

FC05040, Calculation of the Flowrate for the Auxiliary Feedwater Pump (FW-6), During Last

Startup, Revision 0

FC05045, FW-10 Steam Line HELB, Revision 01

FC05072, Auxiliary Feedwater Maximum Operating Temperature and Pressure Calculation,

Revision 0

FC05073, Auxiliary Feedwater Pumps Design Calculation, Revision 0

FC05361, Auxiliary Feedwater System Calculation (Pump Design and Turbine Drive

Controller), Revision 5

FC05365, Auxiliary Feedwater Flow and Head Requirements, Revision 0

FC05467, Fuel Oil Transfer Pump FO-4A-1 and 2 and FO-4B-1 and 2 Discharge Pressure and

Motor Horsepower, Revision 0

FC05492, Diesel and Operating Conditions for the Diesel Generator Fuel Oil System,

Revision 1

-3-

FC05587, Emergency Diesel Generator Instrument/Relief Valve Setpoint Calculation,

Revision 1

FC05829, MOV Degraded Voltage Calculation, Revision 8

FC05916, Operating Temperature Limits for DG-1 and DG-2, Revision 3

FC06148, Auxiliary Feedwater Storage Requirements, Revision 3

FC06181, Auxiliary Feedwater System Flow Rates with SE-ST-AFW-3005 Recirculation Path to

EFWST in Service, Revision 0

FC06289, Diesel Generator Fuel Oil Storage Tanks Level TLU Calculation, Revision 0

FC06638, Capacity of Fuel Oil Tank FO-38, Revision 0

Engineering Analyses:

EA-FC-029, "IST Review of Surveillance Test Pump Procedures," Revision 0

EA-FC-90-028, "Effect of Single Failure of FW-10 Overspeed Limiting Governor," Revision 2

EA-FC-91-010, No Title, Revision 0

EA-FC-91-084, Breaker/Fuse Coordination Study, Revision 4

EA-FC-92-047, Diesel Generator Fuel Oil Requirements, Revision 0

EA-FC-92-072, Diesel Generator Loading Transient Analysis ETS-2.08N-MS1, Revision 2

EA-FC-92-080, Resolution of MOV Operating Conditions Design Basis Discrepancies, Revision 5

EA-FC-92-082, Provide Test Conditions for MOVs Covered by GL 89-10, Revision 4

EA-FC-93-010, "Steam Leak Through FW-1314 in Room 19," Revision 0

EA-FC-95-022, NFPA 13 Code Compliance Verification Checklist - Diesel Generator Rooms Dry-

Pipe System, Revision 2

EA-FC-95-048, Evaluation of Susceptibility of Safety Related Power Operated Gate Valves to

Pressure Locking or Thermal Binding, Revision 2

EA-FC-96-12, Safety Significance of the MFIVs and Their Ability to Open,

Revision 0EA-FC-96-134, Evaluation of Hydraulic Snubber Inspection Results, Revision 0

EA-FC-97-012, "Evaluation of Reduced Auxiliary Feedwater Flow," Revision 0

-4-

IC-PM-FW-0900, "Operational Verification of FW-54 Fuel Oil Day Tank FO-38 Level Controls,"

Revision 1

OP-ST-AFW-0004, Auxiliary Feedwater Pump FW-10 Operability Test, Revision 21

Design Basis Document

SDBD-DG-112, Emergency Diesel Generators, Revision18

Drawings:

B120D06002, Sheet 1, Auxiliary Fuel Oil Day Tank, Revision 5

B120F14501, Sheet 2, Schematic Engine Control, Revision 15

D-4665, DG-1 Diesel Generator One Line Diagram, Revision 5

D-4666, DG-2 Diesel Generator One Line Diagram, Revision 5

11405-E-1, Main One Line Diagram, Revision 36

11405-E-3, 4.16 KV. Auxiliary Power One Line Diagram, Revision 19

11405-E-7, Sheet 2, 480 Volt Primary Plant Motor Control Center One Line Diagram, Revision 17

11405-M-282, Sheet 1, Fuel Oil Flow Diagram, Revision 54

13229, Fuel Oil Tank FO-1, Revision 5

17016, DG-1 and DG-2 Diesel Generator Assembly, Revision 5

17396, Sheet 16, Schematic Engine Control, Revision 6

17398, Sheet 18, Schematic, Engine Control, Revision 8

Fig. 8.1-1, Simplified One Line Diagram Plant Electrical System, Revision 117

11405-M-252, Cover Sheet, Composite Flow Diagram Main Steam P & ID, Revision 24

11405-M-252, Sheet 1, Flow Diagram Steam P & ID, Revision 92

11405-M-253, Cover Sheet, Composite Flow Diagram Steam Generator Feedwater and

Blowdown P & ID, Revision 26

11405-M-253, Sheet 4, Flow Diagram Steam Generator Feedwater and Blowdown P & ID,

Revision 29

11405-M-254, Cover Sheet, Composite Flow Diagram Condensate P & ID, Revision 31

-5-

11405-M-262, Sheet 1, Fuel Oil Flow Diagram P & ID, Revision 54

Miscellaneous:

OPPD Letter Dated September 17, 1993

NRC Safety Evaluation Date March 29, 1994

System Training Manual, Volume 16, Emergency Diesel Generators, Revision 19

Nuclear Procurement Manual NPM-260, Revision 1

Material Discrepancy Report [PO. S042950], December 2, 1999

EPRI Report NP-6608, Shelf Life of Elastomeric Components, May 1994

Self Assessment LIM-01-0024, an assessment of the 10 CFR 50.59 process, report dated

December 28, 2001

Report LIC-01-0076, 10 CFR 50.59 Twenty Four Month Report to NRC, October 5, 2001

Safety Audit Review Committee Report (Meeting Minutes) 02-QUA-011, January 23, 2002

Procedure PED-QP-3, Calculation Preparation, Review, and Approval, Revision 7 dated June 14,

2001

10 CFR 50.59 Continuing Training Plan

SDBD-FW-AFW-117, "Design basis document auxiliary feedwater," Revision 23

TM C438.0010, Technical Manual for Coffin Turbo Pump Auxiliary Feed Pump, Revision 10

Procedures:

AOP-06, "Fire Emergency," Revision 9AOP-07, "Evacuation of Control Room," Revision 7

AOP-17, "Loss of Instrument Air," Revision 4

AOP-23, "Reset of Engineered Safeguards," Revision 6

AOP-31, "161 KV Grid Malfunctions," Revision 5

AOP-32, "Loss of 4160 Volt or 480 Volt Bus Power," Revision 6

EM-ST-DG-0001, "Diesel Generator and Emergency 4.16 kV Bus Protective Relays," Revision 7

-6-

EM-ST-ESF-0001, "Quarterly Engineered Safety Features Offsite Power Low Signal (OPLS)

Sensor Check," Revision 7

EOP-00, "Standard Post Trip Actions," Revision 15

EOP-01, "Reactor Trip Recovery," Revision 8

EOP-02, "Loss of Offsite Power, Loss of Forced Circulation," Revision 10

EOP-03, "Loss of Coolant Accident," Revision 18

EOP-07, "Station Blackout," Revision 8

EPIP-RR-17A, TSC Administrative Logistics Coordinator Actions, Revision 19

FCSG-23, 10 CFR 50.59 Resource Manual, Revision 1

NOD-QP-3, 10 CFR 50.59 Reviews, Revision 23

OI-AFW-4, Auxiliary Feedwater Startup and System Operation, Revision 42

OI-AWF-1-CL-A, "Operating Instruction Auxiliary Feedwater," Revision 49

OI-DG-1, Diesel Generator No. 1, Revision 31

OI-DG-2, Diesel Generator No. 2, Revision 36

OP-FT-DG-0002, "Function Test: Emergency Diesel Generator Endurance Functional Test,"

Revision 9

OP-PM-AFW-0004, "Third Auxiliary Feedwater Pump Operability Verification," Revision 23

OP-ST-AFW-0001, "Auxiliary Feedwater System Valve Alignment Check," Revision12

OP-ST-AFW-0004, Auxiliary Feedwater Pump FW-10 Operability Test, Revision 21

OP-ST-DG-0001, "Surveillance Test: Diesel Generator 1 Check," Revision 35

OP-ST-DG-0002, "Surveillance Test: Diesel Generator 2 Check," Revision 36

OP-ST-ESF-0001, "Surveillance Test: Diesel Auto Start Initiating Circuit Test," Revision 18

OP-ST-ESF-0002, "Surveillance Test: Diesel Generator No. 1 and No. 2 Auto Operation,"

Revision 24

OP-ST-ESF-0006, "Engineered Safety Features Off-site Power Low Signal (OPLS) Functional

Test," Revision 17

-7-

OP-ST-ESF-0022, "S1-2 Automatic Load Sequencer Test," Revision 18

OP-ST-ESF-0023, "S2-2 Automatic Load Sequencer Test," Revision 19

PED-SEI-12, "Guidelines for FCS lube oil test results and action parameters," Revision 7

SO-M-11, Maintenance Work Control, Revision 54

SO-R-01, Reportability Determination, Revision 08

SO-R-02, Condition Reporting and Corrective Action, Revision 19

SS-PFT-TX- 1002, "Performance functional test valve monitoring program," Revision 2

Modifications Packages

DCN 2796 (MR-FC-96-013), Snubber Upgrades

EC 11239 (MR-FC-95-003), Replace Bad Actor Relays for DG-1& DG-2"

EC 11260 (MR-FC-95-024), Steam Trap on FW-10 Steam Chest

EC 11296 (MR-FC-97-021), Diesel Generator Tach. Loop Isolation

EC 13583 (ECN-96-048), Diesel Generator Lube Oil Low Temperature Alarm

EC 13584 (ECN-96-049), Diesel Generator Starting Air Relief Valves

EC 13915 (ECN-97-135), Remove Expanded Metal Cage Around FW-10"

EC 13953 (ECN-97-196), Revise Engine Mounting on Diesel Engine FW-56"

EC 14002 (ECN-97-321), Replacement of FW-56 Fuel Shutoff Solenoid

EC 14994, (DCN 10282), FW-10 Reliability Enhancements

EC 14992, FW-10 Reliability Enhancements, Revision 10

ECN 93214, SGBP System Isolation Mechanical, Revision 0

EC 14994, FW-10 Reliability Enhancements, Revision 0

Temporary Modification Package

EC 15045 (DCP 10375/ DCN 10333), Place FW-10 throttle valve positioner YC-1039-2 in bypass

so it can be removed and rebuilt without taking FW-10 out of service, Approved June, 12, 2000

Surveillance Tests:

IC-ST-DG-0017, Calibration of Emergency Diesel No. 1 Auxiliary Fuel Oil Day Tank Level Control

and Alarm, dated December 27, 2001

IC-ST-DG-0057, Calibration of Emergency Diesel No. 2 Auxiliary Fuel Oil Day Tank Level Control

and Alarm, dated February 6, 2002

OP-PM-AFW-0004,Third Auxiliary Feedwater Pump Operability Verification, Revision 12,

Performed January 21, 1998

-8-

OP-ST-ESF-0002, Diesel Generator No. 1 and No. 2 Auto Operation, dated April 16, 2001,

October 27, 1999, and May 3, 1998

OP-ST-ESF-0006, Engineered Safety Features Off-Site Power Low Signal (OPLS) Function Test,

dated April 7, 2001, October 28, 1999, and May 4, 1998

OP-ST-ESF-0022, S1-2 Automatic Load Sequencer Test, dated December 27, 2001, October 4,

2001, July 12, 2001 and April 23, 2001

OP-ST-ESF-0023, S2-2 Automatic Load Sequencer Test, dated February 25, 2002, November 29,

2001, September 5, 2001, and June 13, 2001

OP-ST-SHIFT-0001, Operations Technical Specification Shift Surveillance, for December 2001,

January 2002, and February 2002

10 CFR 50.59 Evaluations Associated with the Following Documents

Design Change Notice DCN-10235, RC-3A L. O. Cooler CCW Supply Piping Replacement,

April 25, 2000

Design Change Notice DCN-10271, M22 Penetration Inside Containment Manual Valve, July 24,

2000

Design Change Notice DCN-10282, FW-10 Reliability Enhancements, July 27, 2000

Engineering Change EC-14643, CCWA Corrosion Monitor, February 18, 1998

Engineering Change EC-25423, Temporary Air Supply to FCV-1904 A/B/C, September 6, 2000

Engineering Change EC-25851, Pressurizer Temperature Nozzle Leak Repair, October 26, 2000

Engineering Change EC-25898, Pressurizer TE-107 Mechanical Nozzle Seal Assembly,

October 30, 2000

Engineering Change EC-26581, Component Cooling Water System Drain Down and Refill,

March 8, 2001

Engineering Change EC-27317, Install a Second Isolation Valve on the Sample Line of Each

Safety Injection Tank, April 26, 2001

Engineering Change EC-27083, UT Void Detection for LPSI Injection Lines, April 12, 2001

Engineering Change EC-28349, Install Restraint on IA Piping to HCV-1041A Actuator,

August 28, 2001

-9-

10 CFR 5.59 Screenings Associated with the Following Documents

Procedure OP-ST-FO-3001 (EC-28451), Diesel Generator 1 Fuel Oil System Pump Inservice

Test, September 20, 2001

Procedure OP-ST-AFW-0001 (EC-29137), Aux FW System Valve Alignment Check, January 17,

2002

Procedure OI-EE-3 (EC-28171), 125 VDC System Normal Operation, August 30, 2001

Procedure OI-AFW-4 (EC-28785), Aux FW Startup and System Operation, November 15, 2001

Procedure EOP-00 (EC-25657), Standard Post Trip Actions, September 20, 2001

Procedure PE-ST-VX-3001 (EC-27830), ASME Section XI Code Relief Valve Test for the CCW

System, June 26, 2001

Procedure OI-CH-3 (EC-28724), Chemical and Volume Control System Normal Operation of

VCT, November 15, 2001

Procedure OI-MS-1A (EC-27987), Main Steam System Operation, July 31, 2001

Procedure OI-RM-1 (EC-14940), Radiation Monitoring, December 7, 2001

Procedure IC-ST-RPS-0010 (EC-27565), Quarterly Function Test of Low Flow Reactor Coolant

Trip Units, June 7, 2001

Calculation FC 03382, Diesel Generator LOCA Loads ETS-2.08N-L1, January 16, 2002

Purchase Order

PO S042950: From Morrison Kundsen Co. Inc., 1989 (Air relay valves)

Work Orders

19232, completed May 21, 1999

70415, completed October 6, 2000

83895, competed May 30, 2001

103960, completed December 13, 2001

Work Request 39332, Troubleshoot D2 air relay valve, leaks during engine start, October 17, 2001

-10-

Licensee Event Reports

1997-004, Diesel Generator Outside of Design Basic Due to a Violation of Appendix R,

Revision 1

1998-005, Emergency Diesel Generator Start Due to Failure of one of the Off Site Power

Sources, Revision 0

1998-008, Over Pressurization of Auxiliary Feedwater Piping Due to Misadjustment of Governor,

Revision 0

1999-001,Shutdown Technical Specification Entry Due to Auxiliary Feedwater Inoperability,

Revision 0

Quality Surveillance Observations

070, 03/08/01

083, 03/15/01

184, 04/27/01

194, 04/29/01

254, 06/21/01

342, 09/13/01

414, 10/29/01

472, 11/29/01

475, 11/29/01

604, 12/27/01