LR-N09-0264, Request for Approval of Cyber Security Plan

From kanterella
Jump to navigation Jump to search

Request for Approval of Cyber Security Plan
ML093350605
Person / Time
Site: Salem, Hope Creek  PSEG icon.png
Issue date: 11/23/2009
From: Neely C
Public Service Enterprise Group
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
LAR H09-07, LAR S09-08, LR-N09-0264
Download: ML093350605 (3)


Text

PSEG Nuclear LLC P.O. Box 236,, Hancocks Bridge, NJ 08038-0236 SECURITY-RELATED INFORMATION - WITHHOLD UNDER 10 CFR 2.390 NOV 3 2009 0 PSEG NuclearL.L. C.

LR-N09-0264 10CFR 50.90 LAR H09-07 10CFR 50.4 LAR S09-08 United States Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 SALEM GENERATING STATION - UNIT 1 and UNIT 2 FACILITY OPERATING LICENSE NOS. DPR 70 and DPR-75 NRC DOCKET NOS. 50-272 and 50-311 HOPE CREEK GENERATING STATION FACILITY OPERATING LICENSE NO. NPF-57 NRC DOCKET NO. 50-354

Subject:

REQUEST FOR APPROVAL OF THE SALEM-HOPE CREEK CYBER SECURITY PLAN In accordance with the provisions of 10 CFR §50.4 and §50.90, PSEG Nuclear is submitting a request for an amendment to the Facility Operating Licenses (FOL) for Salem Nuclear Generating Station Unit 1 and Unit 2 and Hope Creek Generating Station. This proposed amendment requests NRC approval of the Salem-Hope Creek Cyber Security Plan, provides an Implementation Schedule, and adds a sentence to the existing FOL Physical Protection License Condition to require PSEG Nuclear to fully implement and maintain in effect all provisions of the Commission-approved Cyber Security Plan.

This proposed amendment conforms to the model application provided in NEI 08-09 Revision 3 which has been submitted to the NRC for endorsement.

Enclosures 1, 2 and 3 to this letter contain sensitive information. Withhold from public disclosure under 10 CFR 2.390. Upon removal of Enclosures 1, 2 and 3, this letter is uncontrolled.

CBoo SECURITY-RELATED INFORMATION - WITHHOLD UNDER 10 CFR 2.390

SECURITY-RELATED INFORMATION -WITHHOLD UNDER 10 CFR 2.390 Document Control Desk LR-N09-0264 Page 2 provides an evaluation of the proposed change. Enclosure 1 also contains the following attachments:

" Attachment 1 provides the existing FOL pages marked up to show the proposed change.

" Attachment 2 provides a table of deviations PSEG has taken to guidance provided in NEI 08-09 Revision 3. provides a copy of the Salem-Hope Creek Cyber Security Plan Implementation Schedule commitments. provides a copy of the Salem-Hope Creek Cyber Security Plan which is a stand-alone document that will be incorporated by reference into the Salem-Hope Creek Physical Security Plan upon approval. PSEG Nuclear requests that Enclosures 1, 2 and 3, which contains sensitive information, be withheld from public disclosure in accordance with 10 CFR 2.390.

In accordance with 10 CFR 50.91, a copy of this application, with attachments, is being provided to the Designated Official for the State Of New Jersey.

PSEG Nuclear requests an implementation period of 60 days for the FOL changes following NRC approval of the license amendment.

There are, three regulatory commitments contained in this submittal. They are listed in .

If you should have any questions regarding this submittal, please contact Lee Marabella at (856) 339-1208 or James Shank at (856) 339-1834.

I declare under penalty of perjury that the foregoing is true and correct.

Sincerely, Christine T. Neely Director, Regulatory Affairs - Evaluation of Proposed Change Attachment 1 - Proposed Technical Specification Changes (Mark-ups)

Attachment 2 - Evaluation of NEI 08-09 Revision 3 Deviations - Salem-Hope Creek Cyber Security Plan Implementation Schedule Commitments - Salem-Hope Creek Cyber Security Plan SECURITY-RELATED INFORMATION - WITHHOLD UNDER 10 CFR 2.390

SECURITY-RELATED INFORMATION - WITHHOLD UNDER 10 CFR 2.390 Document Control Desk LR-N09-0264 Page 3 C: Mr. S. Collins, Administrator - Region I U. S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 U. S. Nuclear Regulatory Commission Mr. R. Ennis, Project Manager - Salem Unit 1 and Unit 2 and Hope Creek Mail Stop 08C2 Washington, DC 20555-0001 USNRC Senior Resident Inspector - Hope Creek Generating Station USNRC Senior Resident Inspector - Salem Generating Station Mr. P. Mulligan, Manager IV Bureau of Nuclear Engineering P. O. Box 415 Trenton, NJ 08625 Corporate Commitment Tracking Coordinator SECURITY-RELATED INFORMATION - WITHHOLD UNDER 10 CFR 2.390