Correction to References in PSEG Letter LR-N04-0036, Risk-Informed Inservice Inspection Submittal
ML041970376
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 07/07/2004
From: Mannon S
Public Service Enterprise Group
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
LR-N04-0226
Download: ML041970376 (2)


Text

PSEG Nuclear LLC.

P.O. Box 236, Hancocks Bridge, New Jersey 08038-0236 JUL O 7Z004 PSEG LR-N04-0226 NuclearLLC United States Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 CORRECTION TO REFERENCES IN PSEG LETTER LR-N04-0036, RISK-INFORMED INSERVICE INSPECTION SUBMITTAL HOPE CREEK GENERATING STATION DOCKET NO. 50-354 On March 1,2004 (letter LR-N04-0036), PSEG Nuclear LLC submitted a proposed risk-informed alternative to the existing American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code, Section Xl requirements for the selection and examination of Class 1 and 2 piping welds.

This submittal was subsequently updated March 11, 2004 (letter LR-N04-0115).

Inthe Program Plan document, PSEG inadvertently characterized references to four related relief requests as being "submitted." References [6.1] and [6.2]

addressed the proposed synchronization of the ten-year ISI intervals for Salem Units 1 and 2 and Hope Creek, respectively. References [6.3] and [6.4]

addressed a proposal to update the Code of Record for Salem Unit 1 and Hope Creek, respectively, to the 1998 Edition though 2000 Addenda, corresponding to the Code of Record for Salem Unit 2. Infact, three of those letters were still under development at the time of the Risk-informed ISI submittal and only Reference 6.3 had actually been submitted.

The current status of the cited references is as follows:

6.1 Relief Request SC-13-RR-A14 Synchronization of Salem Units 1 and 2 ISI Programs Ten-Year Inservice Inspection Intervals. Not submitted.

6.2 Relief Request HC-12-RR-A20 Synchronization of Hope Creek to Salem Units 1 and 2 ISI Programs Ten-Year Inservice Inspection Intervals. Not submitted.

95-2168 REV. 7/99

Document Control Desk -JUL7 200 LR-N04-0226 6.3 Relief Request S1 RR-Al 3 Consolidation of ASME XI Code of Record. Submitted December 12, 2003 (LR-N03-0499) but withdrawn 3/24/04 (LR-N04-0130), as need for relief was superceded by change made in accordance with 10CFR50.55a.

6.4 Relief Request HC-12-RR-A15 Consolidation of ASME Xl Code of Record. NOT A RELIEF REQUEST - Submitted May 7, 2004 (LR-N04-0161), informing NRC of change made in accordance with 10CFR50.55a.

The overall meaning of Section 1 of the Program Plan where these references occur is not fundamentally altered by these changes. This approach has been previously discussed with the NRC Project Manager.

We apologize for any confusion or inconvenience this may have caused. Should you have any questions, please contact Mr. Michael Mosier at (856) 339-5434.

Sincerely, Steven R. Mannon Manager - Nuclear Safety and Licensing C Mr. H. Miller, Administrator - Region 1 U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Mr. D. Collins, Project Manager - Hope CreeklSalem U.S. Nuclear Regulatory Commission One White Flint North Mail Stop 08C1 Washington, DC 20555-0001 USNRC Resident Inspector Office (X24)

Mr. K. Tosch, Manager IV Bureau of Nuclear Engineering P.O. Box 415 Trenton, NJ 08625