Attachment 7, St. Lucie License Amendment Request Extended Power Uprate, Summary of Regulatory Commitments
ML101160207
Person / Time
Site: Saint Lucie NextEra Energy icon.png
Issue date: 04/16/2010
From:
Florida Power & Light Co
To:
Office of Nuclear Reactor Regulation
Shared Package
ML101160214 List:
References
L-2010-078
Download: ML101160207 (2)


Text

St. Lucie Unit 1 EPUAtt. 7-1 Summary of Regulatory CommitmentsSt. Lucie Unit 1L-2010-078Docket No. 50-335Attachment 7ATTACHMENT7 LICENSE AMENDMENT REQUESTEXTENDED POWER UPRATE

SUMMARY

OF REGULATORY COMMITMENTSFLORIDA POWER AND LIGHTST. LUCIE NUCLEAR PLANT, UNIT1This coversheet plus 1 pages St. Lucie Unit 1 EPUAtt. 7-2 Summary of Regulatory CommitmentsSt. Lucie Unit 1L-2010-078Docket No. 50-335Attachment 7ATTACHMENT7

SUMMARY

OF REGULATORY COMMITMENTSIntroductionThe regulatory commitments listed below are intended to maintain compliance with regulatory requirements during preparation for and upon EPU implementation. The commitments are based upon the plant changes summarized in license amendment request (LAR) Attachment5, EPU Licensing Report. These commitments will be completed prior to the final implementation of EPU, which is currently scheduled for the conclusion of Fall2011 refueling outage.REGULATORY COMMITMENTS1.Update the Inservice Testing Program to reflect changes to plant pumps and valves under EPU conditions.2.Provide operator training to account for increased EPU power level and resultant plant changes.3.Perform additional reactor auxiliary building HVAC motor environmental qualification or modification of the components identified in LR Section2.3.1, Environmental Qualification of Electrical Equipment.4.Implement modification(s) to increase safety injection tank design pressure for EPU conditions described in LR Section2.8.5.6.3, Emergency Core Cooling System and Loss-of-Coolant Accidents.5.Implement modification(s) necessary to accommodate the simultaneous hot and cold leg injection requirements for EPU conditions as described in LR Section2.8.5.6.3, Emergency Core Cooling System and Loss-of-Coolant Accidents.6.Implement modification(s) to install a leading edge flow meter (LEFM) as described in LR Section2.4.4, Measurement Uncertainty Recapture Power Uprate, and update UFSAR Section13.8, Licensee-Controlled Technical Specification Requirements, to include Limiting Conditions for Operation (LCO) and Action Statements for the LEFM system.7.Implement modification(s) to the ac electrical busses as described in LR Section2.3.3, AC Onsite Power System.8.Revise the administrative controls for the main containment purge isolation valves such that they are maintained closed in MODES1, 2, 3 and4.9.Implement modification(s) to pipe supports for systems impacted by loads due to EPU conditions, as described in LR Section2.2.2.2, Balance of Plant Piping, Components, and Supports.10.Revise applicable procedures to accommodate operator actions during station blackout at EPU conditions, as described in LR Section2.11, Human Factors.