Category:Letter type:L
MONTHYEARL-PI-23-034, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 3.7.8, Cooling Water (Cl) System,2024-01-0202 January 2024 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 3.7.8, Cooling Water (Cl) System, L-PI-23-035, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications Section 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report2023-12-20020 December 2023 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications Section 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report L-PI-23-033, Supplement to License Amendment Request to Revise Technical Specification 3.8.1, Surveillance Requirement 3.8.1.2, Note 32023-12-0505 December 2023 Supplement to License Amendment Request to Revise Technical Specification 3.8.1, Surveillance Requirement 3.8.1.2, Note 3 L-PI-23-025, License Amendment Request to Revise Technical Specification 3.8.1, Surveillance Requirement 3.8.1.2, Note 32023-09-28028 September 2023 License Amendment Request to Revise Technical Specification 3.8.1, Surveillance Requirement 3.8.1.2, Note 3 L-PI-23-023, Baffle Former Bolts Alternate Aging Management Strategy2023-09-11011 September 2023 Baffle Former Bolts Alternate Aging Management Strategy L-PI-23-018, License Amendment Request to Revise ISFSI Technical Specification 4.4 to Allow Use of a Code Alternative to ASME Code, NB-5130, Examination of Weld Edge Preparation Surfaces, for the TN-40HT2023-07-14014 July 2023 License Amendment Request to Revise ISFSI Technical Specification 4.4 to Allow Use of a Code Alternative to ASME Code, NB-5130, Examination of Weld Edge Preparation Surfaces, for the TN-40HT L-PI-23-006, License Amendment Request to Revise Technical Specification 3.7.8 Required Actions2023-06-22022 June 2023 License Amendment Request to Revise Technical Specification 3.7.8 Required Actions L-PI-23-016, 2022 10 CFR 50.46 LOCA Annual Report2023-06-14014 June 2023 2022 10 CFR 50.46 LOCA Annual Report L-PI-23-010, Annual Report of Individual Monitoring2023-04-27027 April 2023 Annual Report of Individual Monitoring L-PI-23-007, Supplement to Application to Revise Technical Specification Section 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR)2023-03-28028 March 2023 Supplement to Application to Revise Technical Specification Section 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR) L-PI-23-005, CFR 50.55a Requests Nos. 1-RR-5-15 and 2-RR-5-15, Proposed Use of Subsequent ASME Code Edition and Addenda in Accordance with 10 CFR 50.55a(g)(4)(iv)2023-03-0303 March 2023 CFR 50.55a Requests Nos. 1-RR-5-15 and 2-RR-5-15, Proposed Use of Subsequent ASME Code Edition and Addenda in Accordance with 10 CFR 50.55a(g)(4)(iv) L-PI-23-001, Day Steam Generator Tube Inspection Report2023-01-30030 January 2023 Day Steam Generator Tube Inspection Report L-PI-22-047, Resubmittal of Prairie Island Nuclear Generating Plant (PINGP) 2018 Unit 1 180-Day Steam Generator Tube Inspection Report2022-12-21021 December 2022 Resubmittal of Prairie Island Nuclear Generating Plant (PINGP) 2018 Unit 1 180-Day Steam Generator Tube Inspection Report L-PI-22-020, Application to Revise Technical Specification Section 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR)2022-12-0202 December 2022 Application to Revise Technical Specification Section 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR) L-PI-22-040, Supplement to Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections2022-10-0606 October 2022 Supplement to Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections L-PI-22-037, Updated Approach for Prairie Island Unit 1 and Unit 2 Baffle Former Bolts2022-09-20020 September 2022 Updated Approach for Prairie Island Unit 1 and Unit 2 Baffle Former Bolts L-PI-22-032, CFR 50.46 LOCA Annual Report2022-06-16016 June 2022 CFR 50.46 LOCA Annual Report L-PI-22-033, Response to Request for Additional Information Prairie Island Nuclear Generating Plant, Units 1 and 2, Amendment to Adopt 24-Month Operating Cycles2022-06-10010 June 2022 Response to Request for Additional Information Prairie Island Nuclear Generating Plant, Units 1 and 2, Amendment to Adopt 24-Month Operating Cycles L-PI-22-003, Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections2022-06-0707 June 2022 Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections L-PI-22-024, Supplement to Application for License Amendment to Implement 24-Month Operating Cycle2022-03-0707 March 2022 Supplement to Application for License Amendment to Implement 24-Month Operating Cycle L-PI-21-047, Response to Request for Additional Information 24-Month Cycle Amendment Prairie Island Nuclear Generating Plant, Units 1 and 22021-12-0707 December 2021 Response to Request for Additional Information 24-Month Cycle Amendment Prairie Island Nuclear Generating Plant, Units 1 and 2 L-PI-21-045, Response to Request for Additional Information Cooling Water System License Amendment Request2021-11-0404 November 2021 Response to Request for Additional Information Cooling Water System License Amendment Request L-PI-21-029, Exigent License Amendment Request to Revise Technical Specification 3.7.8 to Allow a One-Time Extension of the Completion Time of Required Action B.12021-10-0707 October 2021 Exigent License Amendment Request to Revise Technical Specification 3.7.8 to Allow a One-Time Extension of the Completion Time of Required Action B.1 L-PI-21-006, License Amendment Request to Revise Technical Specification 3.3.1, Reactor Trip System (RTS) Instrumentation, to Incorporate Installed Bypass Test Capability for the Power Range RTS Functions2021-10-0202 October 2021 License Amendment Request to Revise Technical Specification 3.3.1, Reactor Trip System (RTS) Instrumentation, to Incorporate Installed Bypass Test Capability for the Power Range RTS Functions L-PI-21-032, Response to Request for Additional Information Amendment Request to Adopt TSTF-471 and 571-T for Prairie Island2021-09-30030 September 2021 Response to Request for Additional Information Amendment Request to Adopt TSTF-471 and 571-T for Prairie Island L-PI-21-016, Application for License Amendment to Implement 24-Month Operating Cycle2021-08-0606 August 2021 Application for License Amendment to Implement 24-Month Operating Cycle L-PI-21-027, 2020 10 CFR 50.46 LOCA Annual Report2021-06-28028 June 2021 2020 10 CFR 50.46 LOCA Annual Report L-PI-21-023, Independent Spent Fuel Storage Installation - 2020 Annual Radiological Environmental Monitoring Program Report2021-05-14014 May 2021 Independent Spent Fuel Storage Installation - 2020 Annual Radiological Environmental Monitoring Program Report L-PI-21-007, Application to Revise Technical Specifications to Adopt TSTF-471, Eliminate Use of the Term Core Alterations in Actions and Notes2021-04-19019 April 2021 Application to Revise Technical Specifications to Adopt TSTF-471, Eliminate Use of the Term Core Alterations in Actions and Notes L-PI-20-050, Request for a One-Time Exemption from 10 CFR 50, Appendix E, Biennial Emergency Preparedness Exercise Requirements, Due to COVID-19 Pandemic2020-10-0707 October 2020 Request for a One-Time Exemption from 10 CFR 50, Appendix E, Biennial Emergency Preparedness Exercise Requirements, Due to COVID-19 Pandemic L-PI-20-051, Supplement to Application to Revise Technical Specifications to Adopt TSTF-547, Clarification of Rod Position Requirements2020-09-28028 September 2020 Supplement to Application to Revise Technical Specifications to Adopt TSTF-547, Clarification of Rod Position Requirements L-PI-20-026, Response to Request for Additional Information: License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiativ2020-09-0101 September 2020 Response to Request for Additional Information: License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4 L-PI-20-035, = Request for Revision to Reactor Vessel Material Surveillance Capsule Removal Schedule2020-07-28028 July 2020 = Request for Revision to Reactor Vessel Material Surveillance Capsule Removal Schedule L-PI-20-023, Independent Spent Fuel Storage Installation, Response to Request for Additional Information: License Amendment Request to Expand the Storage Capacity of the Independent Spent Fuel Storage Installation (ISFSI)2020-06-10010 June 2020 Independent Spent Fuel Storage Installation, Response to Request for Additional Information: License Amendment Request to Expand the Storage Capacity of the Independent Spent Fuel Storage Installation (ISFSI) L-PI-20-014, Supplement to License Amendment Request: Expand the Storage Capacity of the Independent Spent Fuel Storage Installation (ISFSI2020-04-29029 April 2020 Supplement to License Amendment Request: Expand the Storage Capacity of the Independent Spent Fuel Storage Installation (ISFSI L-PI-20-004, License Amendment Request to Revise Technical Specifications (TS) to Remove Note I from Limiting Condition for Operating (LCO) 3.4.12 and LCO 3.4.132020-03-30030 March 2020 License Amendment Request to Revise Technical Specifications (TS) to Remove Note I from Limiting Condition for Operating (LCO) 3.4.12 and LCO 3.4.13 L-PI-20-001, License Amendment Request to Address Issues Identified in Westinghouse Nuclear Safety Advisory Letter NSAL-09-5, Revision 1, and NSAL-15-12020-01-29029 January 2020 License Amendment Request to Address Issues Identified in Westinghouse Nuclear Safety Advisory Letter NSAL-09-5, Revision 1, and NSAL-15-1 L-PI-19-041, Application to Revise Technical Specifications to Adopt TSTF-547, Clarification of Rod Position Requirements2019-12-23023 December 2019 Application to Revise Technical Specifications to Adopt TSTF-547, Clarification of Rod Position Requirements L-PI-19-031, License Amendment Request: Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2019-12-16016 December 2019 License Amendment Request: Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b L-PI-19-040, License Amendment Request: Revise Technical Specification 5.5.14 to Permanently Extend Containment Leakage Rate Test Frequency2019-10-0707 October 2019 License Amendment Request: Revise Technical Specification 5.5.14 to Permanently Extend Containment Leakage Rate Test Frequency L-PI-19-038, Submittal of Revised Pressure and Temperature Limits Report2019-09-19019 September 2019 Submittal of Revised Pressure and Temperature Limits Report L-PI-19-037, Response to Request for Additional Information: 10 CFR 50.55a Requests Nos. 1-RR-5-10 and 2-RR-5-10, Proposed Alternative to Reactor Vessel Inservice Inspection (ISI) Intervals2019-09-16016 September 2019 Response to Request for Additional Information: 10 CFR 50.55a Requests Nos. 1-RR-5-10 and 2-RR-5-10, Proposed Alternative to Reactor Vessel Inservice Inspection (ISI) Intervals L-PI-19-025, Request to Approve Site-Specific Probabilistic Risk Assessment (PRA) Model for Flowserve N-Seal Abeyance Seal and Dynamic Testing for the Prairie Island Nuclear Generating Plant (PINGP)2019-08-27027 August 2019 Request to Approve Site-Specific Probabilistic Risk Assessment (PRA) Model for Flowserve N-Seal Abeyance Seal and Dynamic Testing for the Prairie Island Nuclear Generating Plant (PINGP) L-PI-19-029, Supplement to Response to Request for Additional Information: Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components For...2019-08-0505 August 2019 Supplement to Response to Request for Additional Information: Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components For... L-PI-19-002, 10 CFR 50.55a Requests Nos. 1-RR-5-10 and 2-RR-5-10, Proposed Alternative to Reactor Vessel Inservice Inspection (ISI) Intervals for Prairie Island, Unit 1 and Unit 22019-06-13013 June 2019 10 CFR 50.55a Requests Nos. 1-RR-5-10 and 2-RR-5-10, Proposed Alternative to Reactor Vessel Inservice Inspection (ISI) Intervals for Prairie Island, Unit 1 and Unit 2 L-PI-19-014, Response to Request for Additional Information: Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors2019-04-29029 April 2019 Response to Request for Additional Information: Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors L-PI-19-003, Request for Revision to Reactor Vessel Material Surveillance Capsule Removal Schedule for Prairie Island Nuclear Generating Plant (PINGP)2019-02-0404 February 2019 Request for Revision to Reactor Vessel Material Surveillance Capsule Removal Schedule for Prairie Island Nuclear Generating Plant (PINGP) L-PI-19-006, Emergency License Amendment Request Regarding One-Time Extension for Technical Specification Completion Time Requirements2019-01-29029 January 2019 Emergency License Amendment Request Regarding One-Time Extension for Technical Specification Completion Time Requirements L-PI-19-005, Online Reference Portal for NRC Review of License Amendment Request to Implement 10 CFR 50.692019-01-15015 January 2019 Online Reference Portal for NRC Review of License Amendment Request to Implement 10 CFR 50.69 L-PI-18-063, Response to Request for Additional Information: Revise License Condition Associated with Implementation of NFPA 8052018-12-0606 December 2018 Response to Request for Additional Information: Revise License Condition Associated with Implementation of NFPA 805 2024-01-02
[Table view] |
Text
ý& XcelEnergy-NOV 2 9 2011 L-PI-1 1-094 10 CFR 50 Appendix E U S Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Prairie Island Nuclear Generating Plant Units 1 and 2 Dockets 50-282 and 50-306 Renewed License Nos. DPR-42 and DPR-60 Notification of Changes to Prairie Island Nuclear Generating Plant (PINGP) Emergqency Response Data System (ERDS) and PINGP Data Point Library (DPL)
In accordance with the requirements of 10CFR 50, Appendix E, Section VI.3.b, Northern States Power Company, a Minnesota corporation, doing business as Xcel Energy (hereafter "NSPM") is submitting this letter to provide notification of changes to the PINGP ERDS link software targeted to be implemented by December 31, 2011.
Notification is required 30 days prior to any hardware or software changes that could affect the transmission format or computer communication protocol to the ERDS.
These changes will involve a conversion from a dial-up modem-based system to a more reliable internet-based system using a plant information server and NRC-supplied Virtual Private Network (VPN) appliance. During implementation of this change, the existing ERDS link will remain available and will not affect the plant's ability to activate the existing ERDS link, if required.
Concurrent with the implementation of the above changes, several data points will be deleted and several new points will be added. Enclosure 1 contains a summary of the DPL changes, along with the DPL for PINGP Unit 1 and Unit 2. This notification satisfies the reporting criteria for 10CFR 50, Appendix E, Section VI.3.a.
Summary of Commitments This letter contains no new commitments and no revisions to existing commitments.
Mark A. Schimmel Site Vice President, Prairie Island Nuclear Generating Plant Northern States Power Company - Minnesota 1717 Wakonade Drive East 9 Welch, Minnesota 55089-9642 Telephone: 651.388.1121
Document Control Desk Page 2 Enclosures (1) cc: Administrator, Region Ill, USNRC NRR Project Manager, USNRC Resident Inspector, USNRC, PINGP Bezakulu Alemu, USNRC ERDS Project Manager Steve Sage, ERDS System Engineer
ENCLOSURE I Prairie Island Nuclear Generating Plant Unit 1 and Unit 2 Emergency Response Data System (ERDS) Data Point Library 4 pages follow
<1 Prairie Island Nuclear Plant - Unit 2 ERDS Data Point Library 11/28/2011 PROCESS DESCRIPTIONS DEFINITIONS AVG The average of 2 values with rejection of bad quality inputs.
CV-AVG The average of 3 or more values with Chauvenet rejection of out of range or bad inputs.
MAVG 15 The 15 minute moving average over time of a single value.
SUM The sum of 2 or more inputs DIFF The Difference of 2 inputs QV Quality validation of a single value. ( i.e. Range checking applied).
STABFUNC Atmospheric Stability function of (60 Meter - 10 meter temperature)
MAX Maximum value of 2 or more inputs.
OR Logical OR of 2 or more digital inputs ABBREVIATIONS WR WIDE RANGE SENSORS NR NARROW RANGE SENSORS FR FULL RANGE SENSORS BWST / RWST REFUELING WATER STORAGE TANK CNTMT CONTAINMENT COND CONDENSER DIR DIRECTION HP/LP HIGH / LOW PRESSURE LVL LEVEL MU REACTOR MAKEUP N/A NOT APPLICABLE P/S "Process or Sensor" column heading NIS / NI NUCLEAR INSTRUMENTATION SYSTEM PRZR PRESSURIZER RAD RADIATION RCS REACTOR COOLANT SYSTEM RNG RANGE SAS SAFETY ASSESSMENT SYSTEM (SPDS)
SG STEAM GENERATOR SI SAFETY INJECTION STM STEAM TIC or TC THERMOCOUPLE Other Notes
- 1) The "Generic Description" field is the same as the ERCS point description for all points in this document.
- 2) The "Analog / Digital" field is omitted because all points in this document are analogs (except Y1057D).
- 3) There are no trip setpoints, but we have provided high and low alarm limits If any.
tIyelthe spraheet.!
Change summary: New point column shows the new point we will be using.
Old point column shows the point that will be deleted.
Quality codes sent will be GOOD and BAD. SUSPECT will show up as GOOD.
New Added point Old deleted New description Reason points 2U4143WSSEL 2U4105A MET WIND SPEED 15MAVG SEL Same value we use on our Eplan Displays. Single 2U4106A value replaces A and B met tower. Selected value reduces confusion on which of 5 inputs to use.
2U4143WDSEL 2U4109A MET WIND DIR 15MAVG SEL Same value we use on our Eplan Displays. Single 2U41 1OA value replaces A and B met tower. Selected value reduces confusion on which of 5 inputs to use.
2U4143STSEL 2U4135A MET DELTAT STABILITY 15MAVG Same value we use on our Eplan Displays. Single 2U4136A SEL value replaces A and B met tower. Selected value reduces confusion on which of 2 inputs to use.
2UO780A 2U5032A WR SG A LVL Wide range more appropriate to use during accident conditions than narrow range.
2U0781A 2U5034A WR SG B LVL Wide range more appropriate to use during accident conditions than narrow range.
SERVERID n/a Point deleted. Not required since simulator has different VPN IP address.