Information Notice 2005-14, Fire Protection Findings on Loss of Seal Cooling to Westinghouse Reactor Coolant Pumps
ML051080499 | |
Person / Time | |
---|---|
Issue date: | 06/01/2005 |
From: | Hiland P NRC/NRR/DIPM/IROB |
To: | |
Franovich M, NRR/DSSA/SPSB, 415-3361 | |
References | |
IN-05-014 | |
Download: ML051080499 (7) | |
UNITED STATES
NUCLEAR REGULATORY COMMISSION
OFFICE OF NUCLEAR REACTOR REGULATION
WASHINGTON, D.C. 20555-0001 June 1, 2005 NRC INFORMATION NOTICE 2005-14: FIRE PROTECTION FINDINGS ON LOSS OF
SEAL COOLING TO WESTINGHOUSE
REACTOR COOLANT PUMPS
ADDRESSEES
All holders of operating licenses for pressurized water reactors, except those who have
permanently ceased operations and have certified that fuel has been permanently removed
from the reactor vessel.
PURPOSE
The U.S. Nuclear Regulatory Commission is issuing this information notice (IN) to inform
addressees about recent inspection findings on post-fire procedural requirements related to
loss of cooling to reactor coolant pump (RCP) seals. NRC anticipates that recipients will review
the information for applicability to their facilities and consider taking actions, as appropriate, to
avoid similar issues. However, no specific action or written response is required.
BACKGROUND
Assuming a fire results in loss of cooling to the RCP seals, licensees may comply with 10 CFR
Part 50, Appendix R, Fire Protection Program for Nuclear Power Facilities Operating Prior to
January 1, 1979, by protecting the cooling to the seals or by demonstrating that the plant can
cope with RCP seal leakoff flow rates. Many licensees have installed RCP seal packages using
high-temperature O-rings that will not result in uncontrolled leakage from RCP seals for
conditions with loss of all RCP seal cooling. Licensees also ensure adequate makeup
capability to compensate for any RCP seal leakoff and maintain reactor coolant system (RCS)
inventory according to requirements of Appendix R, Sections III.G.2, III.G.3, and III.L.1 and
performance goals of Appendix R,Section III.L.2. Note that a plant licensed before January 1,
1979, must meet the provisions of Appendix R,Section III.G and III.L and a plant licensed after
January 1, 1979, must implement the fire protection provisions of its operating license.
DESCRIPTION OF CIRCUMSTANCES
At Surry, NRC inspectors found that certain postulated fires could result in the loss of cooling to
the RCP seals. The inspectors noted that the RCP seal vendor, Westinghouse, advised that
increased seal leakage, to around 21 gpm, could occur if seal cooling is lost and not restored
before hot RCS fluid reaches the RCP seals. Additionally, the Westinghouse Owners Group
(WOG) revised their generic emergency response guidelines for the station blackout event to
recommend that RCP seal cooling not be restored following a prolonged loss of seal cooling in
which the seal temperature exceeds the RCP seal vendors recommendations. The licensee
incorporated this guidance into its emergency operating procedures for the response to a loss
of all alternating current (AC) power event but not in its procedures for safe shutdown of the
reactor after a fire. Restoration of seal injection after the seals become hot could lead to
increased leakage beyond the RCS makeup capability needed to satisfy the performance goals
in Appendix R,Section III.L.2 (NRC Inspection Reports 50-280/03-07 and 50-281/03-07).
Similar findings were made at other nuclear power plants. At Turkey Point, NRC inspectors
found that the post-fire procedures did not provide timely operator action to restore seal
injection and could result in increased RCP seal leakage beyond the capacity of equipment
dedicated to achieve and maintain post-fire safe shutdown according to Appendix R, Section
III.G.2 (NRC Inspection Reports 50-250/04-07 and 50-251/04-07). At North Anna, NRC
inspectors found, similar to the Surry finding, that certain fires could result in a loss of seal
cooling. Seal cooling could be restored after the seal had heated up, thereby potentially
resulting in increased seal leakage beyond the RCS makeup capability required to satisfy
Appendix R,Section III.L.2 (NRC Inspection Reports 50-338/03-06 and 50-339/03-06). At
Summer, the inspectors were concerned that the licensees fire emergency procedure did not
direct personnel to reestablish seal cooling flow in a timely manner, potentially leading to
increased seal leakage beyond the RCS makeup capability needed to satisfy Appendix R,
Section III.L.2 (NRC Inspection Report 50-395/01-10).
DISCUSSION
The NRC uses deterministic information to determine the existence of performance
deficiencies. The risk significance of an identified performance deficiency is evaluated using
probabilistic risk assessment (PRA) models.
In each case cited above, the NRC inspectors attributed the performance deficiency to
inconsistent recovery procedures. They observed that the plant emergency procedures for a
loss of all AC power did not agree with the plant procedures for mitigating the effects of a
postulated fire. The post-fire procedures failed to direct plant personnel to restore RCP seal
cooling before the seal temperature exceeds the vendor-specified limit. The inspection findings
from Turkey Point also indicate that the fire mitigation procedures fail to consider that
restoration of seal cooling is a time-critical operator action. For seal packages in general, the makeup capability must exceed the seal leakoff to ensure
that a hot standby condition can be achieved (according to the requirements in Appendix R,
Section III. L.1. (c) and that the pressurizer level is maintained in the indicating range
(according to the performance goals in Appendix R,Section III L.2.b). Furthermore, protecting
seal integrity would be assisted if procedures for operating equipment needed for post-fire
shutdown are consistent with vendor recommendations. For the Westinghouse RCP seals, as
discussed in a recently submitted document on RCP seal performance (Reference 3), a
leakage rate of 21 gpm per RCP may be assumed in the licensees safe shutdown assessment
following the loss of all RCP seal cooling. Assumed leakage rates greater than 21 gpm are
only warranted if increased seal leakage is postulated as a result of deviations from seal vendor
recommendations. Test or operating experience may be used to justify other RCP seal leakage
rates.
Licensees with Westinghouse RCP seals have developed fire emergency procedures to cope
with a loss of all RCP seal cooling by either reestablishing seal cooling to the RCPs before
increased seal leakage occurs (to prevent increased leakage) or by providing sufficient RCS
makeup to achieve and maintain post-fire safe shutdown.
Performance deficiencies and violations of regulatory requirements can result from all of the
following: (1) procedural deviations from the manufacturers recommendations without a
documented basis, (2) inadequate procedures, and (3) inadequate documented analysis to
show that Appendix R,Section III.L requirements are met.
If a performance deficiency exists, it is evaluated in the significance determination process
(SDP) using PRA models. The loss of RCP seal cooling has been extensively modeled in PRA
applications. In particular, the NRC used PRA information from its closure of a generic safety
issue involving RCP seal failure (Reference 1) and from its safety evaluation of an industry
model of RCP seal leakage (Reference 2) as the SDP framework to evaluate the risk
significance of certain fire protection inspection findings. In the Surry case, the NRC estimated
that the increase in the core damage frequency was between 1E-6 and 1E-5 per year (a white
inspection finding). This finding is highly dependent on the plant-specific electrical switchgear
room arrangement and the fire mitigation strategy.
In the recently submitted document on RCP seal performance (Reference 3), the NRC has not
found sufficient new information to improve PRA models from previously issued industry models
(Reference 4) or safety evaluation reports (Reference 2).
The PRA modeling considers two cases. In case 1 (plants with Westinghouse high- temperature O-rings and seals), Westinghouse, the RCP seal vendor, states that after loss of
seal cooling, the seals with high-temperature O-rings will leak at about 21 gpm per pump. If the
licensee implements vendor guidelines, this condition is not expected to proceed to failures
resulting in leak rates greater than 21 gpm per pump. Even if seal cooling is not reestablished, degradation of the seals for leakage rate to significantly increase is not expected for an indefinite period of time if the RCPs are secured before the seal temperature exceeds 235 degrees F. Restoration of seal cooling may result in cold thermal shock of the seal and
possibly cause increased seal leakage. If seal cooling is restored using component cooling
water (CCW) to the thermal barrier cooler, water hammer may occur and possibly compromise
the integrity of the CCW system. As discussed in the recently submitted document on RCP
seal performance (Reference 3), if the CCW system is damaged, then plant shutdown after a
fire accident may not be possible in all scenarios.
To be consistent with 10 CFR Part 50, Appendix B, Quality Assurance Criteria for Nuclear
Power Plants and Fuel Reprocessing Plants, protection of seal integrity depends on fire
protection and RCP recovery procedures being consistent with the manufacturers
recommendations and that the associated instrumentation, alarms, and recovery procedures
are available after a fire.
In case 1 (plants with Westinghouse high-temperature O-rings and seals), the NRC PRA
modeling accounts for two failure scenarios, given a loss of seal cooling with no RCPs
operating. In failure scenario 1 (hot shock), during initial heating of the seals, hydraulic
instability caused by fluid flashing can potentially open (pop) the second-stage seal faces
(Reference 2). For this scenario, the NRC PRA model assumes that the popping failure of the
second-stage seal occurs at 13 minutes after loss of RCP seal cooling.
In case 1, failure scenario 2 (cold shock), if RCP seal cooling is restored after the seal
temperature exceeds the vendor-specified limit, given survival from the initial hot shock of the
seals, the NRC uses seal failure probabilities and consequential seal leakage sizes similar to
those used in failure scenario 1.
In case 2 of the NRC PRA model (Westinghouse plants with old, pre-high-temperature RCP
seals), Westinghouse, the RCP seal vendor, states that after loss of seal cooling, the old
seals could fail after about 30 minutes. Therefore, protection of seal integrity requires the
restoration of seal cooling within the appropriate time limit. However, this time limit is
approximate. Plant-specific vendor guidance may differ based on (1) commitments made with
respect to the station blackout analysis and (2) licensee-specific vendor recommendations.
CONTACT
This information notice requires no specific action or written response. Please direct any
questions about this matter to the technical contact(s) listed below or the appropriate NRR
project manager.
/RA/
Patrick L. Hiland, Chief
Reactor Operations Branch
Division of Inspection Program Management
Office of Nuclear Reactor Regulation
Technical Contacts: Phil Qualls, NRR Michael Franovich, NRR
301-415-1849 301-415-3361 E-mail: pmq@nrc.gov E-mail: mxf1@nrc.gov
Albert Wong, NMSS
301-415-7843 E-mail: axw2@nrc.gov
Attachment: References
Note: NRC generic communications may be found on the NRC public Web site, http://www.nrc.gov, under Electronic Reading Room/Document Collections.
CONTACT
This information notice requires no specific action or written response. Please direct any
questions about this matter to the technical contact(s) listed below or the appropriate NRR
project manager.
/RA/
Patrick L. Hiland, Chief
Reactor Operations Branch
Division of Inspection Program Management
Office of Nuclear Reactor Regulation
Technical Contacts: Phil Qualls, NRR Michael Franovich, NRR
301-415-1849 301-415-3361 E-mail: pmq@nrc.gov E-mail: mxf1@nrc.gov
Albert Wong, NMSS
301-415-7843 E-mail: axw2@nrc.gov
Attachment: References
Note: NRC generic communications may be found on the NRC public Web site, http://www.nrc.gov, under Electronic Reading Room/Document Collections.
DISTRIBUTION:
IN File
ADAMS ACCESSION #: ML051080499 DOCUMENT NAME: E:\Filenet\ML051080499.wpd
OFFICE DSSA:SPLB Tech Editor DSSA:SPLB ADPT:DLPM ADPT:DLPM
NAME CVHodge PKleene SWeerakkody CGratton EABrown
DATE 05/12/2005 04/06/2005 04/08/2005 05/12/2005 05/16/2005 OFFICE ADPT:DIPM ADPT:DIPM ADPT:DIPM A:SC:OES:IROB:DIPM C:IROB:DIPM
NAME SRMonarque KRCotton GSShukla EJBenner PLHiland
DATE 05/12/2005 05/12/2005 05/12/2005 05/16/2005 06/01/2005 OFFICIAL RECORD COPY Attachment
REFERENCES
1. NRC Regulatory Information Summary 2000-002, Closure of Generic Safety Issue 23, Reactor Coolant Pump Seal Failure, February 15, 2000 (ADAMS ML003680402)
2. NRC Office of Nuclear Reactor Regulation, Safety Evaluation of WCAP-15603, Revision 1, WOG 2000 Reactor Coolant Pump Seal Leakage Model for Westinghouse
PWRs, Westinghouse Owners Group Project No. 694, May 2003 (ADAMS
3. Westinghouse Owners Group, Reactor Coolant Pump Seal Performance for Appendix R
Assessments, WCAP-16396-NP, Revision 0, January 2005 (ADAMS ML050320187)
4. Westinghouse Electric Company, LLC, WOG 2000 Reactor Coolant Pump Seal Leakage
Model for Westinghouse PWRs, WCAP-15603, Revision 1, May 2002 (ADAMS