IR 05000528/2013501

From kanterella
Jump to navigation Jump to search
IR 05000528-13-501, IR 05000529-13-501 and 05000530-13-501, 12/31/2013, Palo Verde, Units 1, 2 & 3, NRC Emergency Preparedness Annual Inspection
ML14059A534
Person / Time
Site: Palo Verde  
Issue date: 02/27/2014
From: Mark Haire
Plant Support Branch-1
To: Edington R
Arizona Public Service Co
M. Haire
References
IR-13-501
Download: ML14059A534 (2)


Text

February 27, 2014

SUBJECT:

PALO VERDE NUCLEAR GENERATING STATION, UNITS 1, 2, AND 3 NRC EMERGENCY PREPAREDNESS ANNUAL INSPECTION REPORT 05000528/2013501, 05000529/2013501, AND 05000530/2013501

Dear Mr. Edington:

On December 31, 2013, the Nuclear Regulatory Commission (NRC) staff completed its annual inspection of the Emergency Preparedness Program at the Palo Verde Nuclear Generating Station, Units 1, 2 and 3. This inspection began on January 1, 2013. Issuance of this letter closes NRC Inspection Report 05000528/2013501, 05000529/2013501, and 05000530/2013501. The inspection results associated with the 2013-501 reports are documented in integrated Resident Inspector Reports 2013-002, 2013-003, 2013-004, and 2013-005.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Mark S. Haire, Chief

Plant Support Branch 1

Division of Reactor Safety

Dockets: 50-528; 50-529; 50-530 Licenses: NPF-41; NPF-51; NPF-74

Electronic Distribution to Palo Verde Nuclear Generating Station

UNITED STATES NUCLEAR REGULATORY COMMISSION

REGION IV

1600 E. LAMAR BLVD.

ARLINGTON, TX 76011-4511 Electronic distribution by RIV:

Regional Administrator (Marc.Dapas@nrc.gov)

Deputy Regional Administrator (Steven.Reynolds@nrc.gov)

DRP Director (Kriss.Kennedy@nrc.gov)

DRP Deputy Director (Troy.Pruett@nrc.gov)

Acting DRS Director (Jeff.Clark@nrc.gov)

Acting DRS Deputy Director (Geoffrey.Miller@nrc.gov)

Senior Resident Inspector (Tony.Brown@nrc.gov)

Resident Inspector (Mica.Baquera@nrc.gov)

Resident Inspector (Dustin.Reinert@nrc.gov)

Administrative Assistant (Revonna.Stuart@nrc.gov)

Branch Chief, DRP/A (Ryan.Lantz@nrc.gov)

Senior Project Engineer, DRP/A (Bob.Hagar@nrc.gov)

Project Engineer, DRP/A (Brian.Parks@nrc.gov)

Public Affairs Officer (Victor.Dricks@nrc.gov)

Public Affairs Officer (Lara.Uselding@nrc.gov)

Project Manager (Balwant.Singal@nrc.gov)

Branch Chief, DRS/TSB (Ray.Kellar@nrc.gov)

RITS Coordinator (Marisa.Herrera@nrc.gov)

ACES (R4Enforcement.Resource@nrc.gov)

Regional Counsel (Karla.Fuller@nrc.gov)

Technical Support Assistant (Loretta.Williams@nrc.gov)

Congressional Affairs Officer (Jenny.Weil@nrc.gov)

RIV/ETA: OEDO (Ernesto.Quinones@nrc.gov)

S:\\DRS\\PSB 1\\MID-CYCLE & END-OF-CYCLE\\EOC 501 Letters\\EOC 2013501 Letters\\PV2013501-EOC-LTR-dch.docx ML ADAMS: No x Yes x SUNSI Review Complete Reviewer Initials: MSH

x Publicly Available x Non-Sensitive

Non-publicly Available Sensitive C:PSB-1

MSHaire

/RA/

2/27/14

OFFICIAL COPY