IR 05000498/1980028

From kanterella
Jump to navigation Jump to search
IE Insp Repts 50-498/80-28 & 50-499/80-28 on 801006-10 & 14-17.No Noncompliance Noted.Major Areas Inspected:Const Activities Pertaining to Resumption of Aws Welding
ML19351E971
Person / Time
Site: South Texas  STP Nuclear Operating Company icon.png
Issue date: 11/06/1980
From: Crossman W, Randy Hall, Tomlinson D
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML19351E970 List:
References
50-498-80-28, 50-499-80-28, NUDOCS 8012190623
Download: ML19351E971 (4)


Text

.

O'

U. S. NUCLEAR REGULATORY COMMISSION OFFICE OF INSPECTION AND ENFORCEMENT

REGION IV

Report No. 50-498/80-28; 50-499/80-28 Docket No. 50-498; 50-499 Category A2 Licensee:

Houston Lighting & Power Company Post Office Box 1700 Houston, Texas 77001 Facility Name:

South Texas Project, Units 1 & 2 Inspection at:

South Texas Project, Matagorda County, Texas Inspection Conducted:

October 6-10 and October 14-17, 1980 Inspector:

-

//

lb p. P. Tomlinson, Reactor Inspector, Engineering Bat 4 Support Section Other Accompanying Personnel:

R. E. Hall, Chief, Engineering Support Section (October 9-10,1980)

// d 8d Approved:

%

W. A. Crossman, Chief, Projects Section Date

//

R. E. Hall, Chief, Engineering Support Section D' ate

Inspection Summary:

Inspection on October 6-10 and 14-17, 1980 (Report No. 50-498/80-28; 50-499/80-28)

Areas Inspected:

Unannounced follow-up inspection of construction activities pertaining to the resumption of AWS welding, re-examination and repair of existing AWS welds, and review of responses to NRC Inspection Report No. 50-498/79-19; 50-499/79-19 findings.

The inspection involved fifty-three inspector-hours by one NRC inspector.

Results:

No items of noncompliance or deviations were identified.

l bN 8012190

...

..

.

._

-

_

'

.

DETAILS 1.

Persons Contacted Principal Licensee Employees

  • R. A. Frazar, Manager, Quality Assurance
  • L, D. Wilson, Project QA Supervisor T. J. Jordan, Supervisor, Quality Systems J. W. Soward, QC Supervisor Other eersonnel D. Muscente, Welding Project Manager, B&R The IE inspector also contacted other licensee and contractor employees including members of the QA/QC and engineering staffs.
  • Denotes those attending the exit interview.

2.

Licensee Action on Previous Inspection Findings (Closed) Unresolved Item (50-498/79-19-36; 50-499/79-19-36):

No Code Inspection by ANI on Weld Now Embedded in Concrete on the Fuel Transfer Tube.

The IE inspector interviewed cognizant engineering personnel and reviewed the inspection reports and other correspondence relative to the fuel transfee tube.

The transfer tube was delivered to the site as two pieces which were welded together by site welders and inspected by the

-

ANI.

The bellows were then welded to the tube assembly.

The required NDE of the welds was performed and the entire assembly was hydrostatically tested and the results documented on October 9, 1978.

The ANI was not I

notified of the hydro test, did not witness the test and did not code stamp the final fuel transfer tube assembly.

Brown and Root engineering redefined the code jurisdictional boundaries and removed the code stamp requirements for the fuel transfer tube making it consistent with the other containment mechanical penetrations.

NCR S-M 1513-A, with attach-ments, removes the code stamp requirements thus relieving the ANI of responsibility for witnessing the hydro-test.

The ANI issued a memo

.

dated December 7, 1978, which stated, "All previous and future ANI involve-l ment with the subject assembly is no longer applicable for Units 1 and 2."

!

This item is no longer unresolved as the assembly classification has been clarified, the code stamp requirement removed and ANI involvement deleted.

This item is closed.

-2-

.

-,

., -,,,

- -.

,

. - - - - -

,

-

w-

+,*

m

- - < -

-

.

l 3.

Site Tour The IE inspector walked through various areas of the site to observe construction activities and to inspect housekeeping.

The tour included Reactor Building No. 1, MEAB No. 1 and several storage areas.

No items of noncompliance or deviations were noted.

4.

Resumotion of AWS Welding The IE inspector reviewed the Brown and' Root (B&R) plan for the restart of welding activities in the area of AWS Category 1 structural steel welds.

A review of associated procedures was conducted including Procedures MECP-1 for requalifying welders, WEI-6 for t.he re-examination and repair of AWS Category 1 welds and MECP-2 for new AWS Category 1 welds.

Records were reviewed for each of the first six welders requalified and a thorough examination of the attendant radiographs was made to assure that film quality and weld quality requirements were met.

Film identification, density, penetrameter placement, penetrameter designation and defect evaluation were among the items checked.

The IE inspector was present for the welding and inspection of the first two hundred joints and performed an over-check evaluation of approxi-mately one-half of these.

All welds inspected appeared to be of adequate size and contour.

None exhibited unacceptable undercut, porosity, spatter or laps.

The IE inspector interviewed three of the requalified welders, two welding supervisors, the area general foreman, a welding engineer and the Level III inspector assigned to the restart program.

All appeared knowledgeable of the restart and procedural requirements.

Also inter-viewed were the three members of re-examination / repair Team 1 who were

,

documenting deficient welds in MEA 8 No. 1, cubicle 2-F.

Current plans l

involve three of these teams to inspect 100% of all existing AWS structural l

welds and perform repairs on all that do not conform with visual inspection requirements.

i There are presently thirty-five welders qualified to work on new and repair welds in cubicles 2A, 28 and 2F as well as shop produced welds for embeds.

Seven inspectors have been requalified to examine and document both the new AWS welds and those under the re examination / repair program.

Qualifi-cation records of these personnel will be reviewed during subsequent

IE inspections.

No items of noncompliance or deviations were noted.

t

!

!

!

-3-

-

__

.

.

. -

-

_

_=

1

.:

,

.

.

,

.

t j

5.

Exit Interview

l l

The IE inspector met with licensee representatives (denoted in paragraph 1)

'

at the conclusion of the inspection on October 17, 1980. -The findings of this inspection were discussed.

i

,'

t f

!

i i

l

!

i

.i j

i

1, j

l

!

!

!

i l

i

1

1

4-4-

,

-

, -

_. -,..... -,. -. -. ~. - -,..,,,,,, - -,,.... - - _, -. -......, _.

....-~~-.,__,,......,_....-,r.

~. -,.,, _,,. - -

.. - -. - - - -,,.

.