MONTHYEARML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, “Revise Risk Informed Completion Time (RICT) Program” Revision 0 and Revise 10 CFR 50.69 License Condition IR 05000454/20240112024-08-0808 August 2024 Phase 2 Post- Approval License Renewal Report 05000454/2024011 IR 05000454/20240022024-07-26026 July 2024 Integrated Inspection Report 05000454/2024002 and 05000455/2024002, and Exercise of Enforcement Discretion ML24179A3262024-07-23023 July 2024 LTR - Constellation - SG Welds and Nozzles (L-2023-LLR-0053, L-2023-LLR-0054, L-2023-LLR-0055, L-2023-LLR-0056) RS-24-064, Nuclear Radiological Emergency Plan Document Revisions2024-06-28028 June 2024 Nuclear Radiological Emergency Plan Document Revisions RS-24-066, Inservice Testing Interval Extension for Essential Service Water Valves Due to Required Use of Containment Chiller2024-06-25025 June 2024 Inservice Testing Interval Extension for Essential Service Water Valves Due to Required Use of Containment Chiller ML24170A7652024-06-19019 June 2024 Confirmation of Initial License Examination RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations RS-24-044, License Amendment to Transition to Framatome Gaia Fuel and Exemptions to 10 CFR 50.46 and 10 CFR 50 Appendix K. Attachments 1 to 11 Enclosed2024-05-28028 May 2024 License Amendment to Transition to Framatome Gaia Fuel and Exemptions to 10 CFR 50.46 and 10 CFR 50 Appendix K. Attachments 1 to 11 Enclosed RS-24-043, Application to Remove Power Distribution Monitoring System (Pdms) Details from Technical Specifications2024-05-24024 May 2024 Application to Remove Power Distribution Monitoring System (Pdms) Details from Technical Specifications ML24142A3352024-05-21021 May 2024 Quad Cities—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes RS-24-055, 2023 Corporate Regulatory Commitment Change Summary Report2024-05-17017 May 2024 2023 Corporate Regulatory Commitment Change Summary Report BYRON 2024-0031, Completion of License Renewal Activities Prior to Entering the Period of Extended Operation2024-05-16016 May 2024 Completion of License Renewal Activities Prior to Entering the Period of Extended Operation IR 05000454/20240012024-05-10010 May 2024 Integrated Inspection Report 05000454/2024001; 05000455/2024001 and 07200068/2024001 BYRON 2024-0028, Annual Radiological Environmental Operating Report (AREOR)2024-05-0909 May 2024 Annual Radiological Environmental Operating Report (AREOR) BYRON 2024-0022, 2023 Regulatory Commitment Change Summary Report2024-05-0202 May 2024 2023 Regulatory Commitment Change Summary Report RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests RS-24-026, License Amendment to Braidwood Station, Units 1 and 2, and Byron Station, Units 1 and 2, Technical Specifications 5.6.5, Core Operating Limits Report (COLR)2024-04-25025 April 2024 License Amendment to Braidwood Station, Units 1 and 2, and Byron Station, Units 1 and 2, Technical Specifications 5.6.5, Core Operating Limits Report (COLR) ML24116A1192024-04-25025 April 2024 2023 Annual Radioactive Effluent Release Report (ARERR) ML24113A2892024-04-22022 April 2024 Notification of NRC Baseline Inspection and Request for Information ML24113A1272024-04-22022 April 2024 Audit Plan in Support of Review of LAR Revision of TS 3.7.15, 3.7.16, and 4.3.1 (EPID: L-2023-LLA-0136) (Non-Proprietary) BYRON 2024-0020, Annual Dose Report for 20232024-04-18018 April 2024 Annual Dose Report for 2023 IR 05000454/20230042024-02-0202 February 2024 Integrated Inspection Report 05000454/2023004 and 05000455/2023004 ML24022A2722024-01-23023 January 2024 Request for Information for an NRC Post-Approval Site Inspection for License Renewal Inspection Report 05000454/2024011 ML24018A0362024-01-17017 January 2024 Paragon Energy Solutions, Defect with Detroit Diesel/Mtu Fuel Injectors P/N R5229660 Cat Id 0001390618 ML23320A1762023-12-13013 December 2023 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0027 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23277A0032023-12-11011 December 2023 Issuance of Amendments Regarding Adoption of TSTF-370 ML23318A5102023-12-0101 December 2023 Relief from the Requirements of the ASME Code IR 05000454/20233012023-11-27027 November 2023 NRC Initial License Examination Report 05000454/2023301 and 05000455/2023301 BYRON 2023-0065, Unit 2 - Notification of Deviation from Electric Power Research Institute (EPRI) Topical Report MRP-227, Revision 1-A, Materials Reliability Program: Pressurized Water Reactor Internals Inspection and Evaluation Guideline2023-11-17017 November 2023 Unit 2 - Notification of Deviation from Electric Power Research Institute (EPRI) Topical Report MRP-227, Revision 1-A, Materials Reliability Program: Pressurized Water Reactor Internals Inspection and Evaluation Guideline BYRON 2023-0063, Day Inservice Inspection Report for Interval 4, Period 3, (B2R24)2023-11-16016 November 2023 Day Inservice Inspection Report for Interval 4, Period 3, (B2R24) IR 05000454/20230032023-11-13013 November 2023 Integrated Inspection Report 05000454/2023003 and 05000455/2023003 and Exercise of Enforcement Discretion RS-23-117, Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information2023-11-10010 November 2023 Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums ML23313A0852023-11-0909 November 2023 Submittal of 2023-301 Byron Initial License Examination Post-Examination Comments RS-23-114, Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds2023-11-0101 November 2023 Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds ML23297A2352023-10-26026 October 2023 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection RS-23-100, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-10-13013 October 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans RS-23-108, Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles2023-10-11011 October 2023 Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles RS-23-105, Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections2023-10-10010 October 2023 Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections ML23278A0272023-10-0505 October 2023 Operator Licensing Examination Approval - Byron Station, October 2023 RS-23-093, License Amendment to Braidwood Station, Units 1 and 2, and Byron Station, Units 1 and 2, Technical Specifications 3.7.15, Spent Fuel Pool Boron Concentration, 3.7.16, Spent Fuel.2023-09-29029 September 2023 License Amendment to Braidwood Station, Units 1 and 2, and Byron Station, Units 1 and 2, Technical Specifications 3.7.15, Spent Fuel Pool Boron Concentration, 3.7.16, Spent Fuel. ML23251A1622023-09-29029 September 2023 Steam Generator Tube Inspection Reports to Reflect TSTF-577 Reporting Requirements RS-23-094, Relief Request I4R-24, Alternative for Post-Peening Reexamination Frequency for Reactor Pressure Vessel Head Penetration Nozzle Number 752023-09-29029 September 2023 Relief Request I4R-24, Alternative for Post-Peening Reexamination Frequency for Reactor Pressure Vessel Head Penetration Nozzle Number 75 RS-23-091, Relief Request I4R-25, Alternative Requirements for Reactor Pressure Vessel Inservice Inspection Intervals2023-09-26026 September 2023 Relief Request I4R-25, Alternative Requirements for Reactor Pressure Vessel Inservice Inspection Intervals ML23226A0062023-09-19019 September 2023 Review of License Renewal Commitment Number 10 Submittal ML23180A1692023-09-11011 September 2023 Calvert Cliff Units 1 & 2, and R.E. Ginna Plant - Withdrawal of Proposed Alternatives to American Society of Mechanical Engineers (ASME) Requirements (Epids L-2022-LRR-0074, 0076, 0079, 0091, 0092, 0093 and 0094) ML23242A3282023-09-0101 September 2023 Amendment No. 233 Correction IR 05000454/20235012023-08-31031 August 2023 Emergency Preparedness Biennial Exercise Inspection Report 05000454/2023501 and 05000455/2023501 2024-08-09
[Table view] |
Text
May 9, 2014
Mr. Michael Senior VP, Exelon Generation Company, LLC President and CNO, Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555
SUBJECT: BYRON STATION, UNITS 1 AND 2 NRC SECURITY BASELINE INSPECTION REPORT 05000454/2014403; 05000455/2014403
Dear Mr. Pacilio:
On March 28, 2014, the U.S. Nuclear Regulatory Commission (NRC) completed a security baseline inspection at your Byron Station, Units 1 and 2. The inspection covered one or more of the key attributes of the security cornerstone of the NRC's Reactor Oversight Process. The enclosed inspection report documents the inspection results, which were discussed on March 28, 2014, with Mr. Kearney and other members of your staff.
The inspection examined activities conducted under your license as they relate to security and compliance with the Commission's rules and regulations and with the conditions of your license.
The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.
One licensee-identified violation, which was determined to be of very low security significance, (Green) is listed in this report. The NRC is treating this violation as a Non-Cited Violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy. If you contest the violation or significance of this NCV, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; the Director, Office of Enforcement, United States Nuclear Regulatory Commission, Washington, DC 20555-0001; and the NRC Resident Inspector at the Byron Station. In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, "Public Inspections, Exemptions, Requests for Withholding," of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC's Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Enclosure contains Sensitive Unclassified Non-Safeguards Information. When separated from enclosure, this transmittal document is decontrolled. However, the material enclosed herewith contains Security-Related Information in accordance with 10 CFR 2.390(d)(1) and its disclosure to unauthorized individuals could present a security vulnerability. Therefore, the material in the enclosure will not be made available electronically for public inspection in the NRC Public Document Room or from the PARS component of NRC's ADAMS.
If you choose to provide a response and Security-Related Information is necessary to provide an acceptable response, please mark your entire response "Security-Related Information -
Withhold from public disclosure under 10 CFR 2.390" in accordance with 10 CFR 2.390(d)(1)
and follow the instructions for withholding in 10 CFR 2.390 (b)(1). In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response. Should you have any questions concerning this inspection, we will be pleased to discuss them with you.
Sincerely,/RA/ Richard A. Skokowski, Chief Plant Support Branch Division of Reactor Safety Docket Nos. 50-454; 50-455 License Nos. NPF-37; NPF-66 Nonpublic
Enclosure:
IR 05000454/2014403; 05000455/2014403
w/Attachment:
Supplemental Information
cc w/encl: N. Simonian, NSIR/DSO/DDSO/ST E. Wharton, NSIR T. Dimitriadis, RI B. Desai, RII M. Haire, RIV L. Armstrong, Byron Station Security Manager J. Klinger, State Liaison Officer, Illinois Emergency Management Agency cc w/o encl: Distribution via LISTSERV